General Description
The umbilicals are separated in 2 types: 4-off Production Umbilicals (PROD) and 1-off Subsea
Isolation Valve/Riser Integrity Monitoring System (SIV/RIMS) Umbilical. The umbilical data sheets are
available in Ref [9] and [10]. Each umbilical is pulled into a dedicated I-tube.
Each umbilical is composed of a BS connected to the bottom of I-tube and a Pulling head secured
topside on top of an I-tube.
See below typical view of the umbilical between the FPSO and sea bed (and over the subsea arch).
Pulling Head
Umbilical
I-tube
Lower spool
BSC Female
BSC Male
Bend Stiffener
Pulling Head - General
The pulling head is composed of a padeye, a resin spool and a removable forging split body.
Resin spool
– stay in
The functional components for the 1-off Dynamic SIV-RIMS Umbilical are detailed in below table 2.2
Table 2.2: SIV/RIMS umbilical functional components
SUMMARY OF THE SCOPE OF WORK AND SERVICES
The Scope of Work for the performance of the activities in this CONTRACT includes:
• Management and Project Control;
• Review of precommissioning certificates (e.g.: insulation, continuity, fiber optic Time Domain Comment [RG4]: Verification of initial status
Reflectometry…) before to start the Hook up activities; and line identification (tag)
Cable / lines / JB visual inspection (discoloration
• Offshore Hook Up activities: electrical cable, instrument cable and Fiber optic, hydraulic on tubes, cable outer sheath damaged...) to be
part of Vendor scope
connection; Removal of upstream tubing protection (blind
• Mechanical completion activities; flange or cap) to be part of Vendor scope
Comment [AQ5]: Which works? The ones
• Cleaning of the working area; forming part of the CONTRACT?
• Technical assistance during full system tests on FPSO after final termination and hydraulic
connection (if specially requested)
Provided manpower is requested to be reasonably flexible to adapt to the various task throughout the
project phases.
Marine Spread will be provided by CONTRACTOR and is not included in SUBCONTRACTOR’S
Scope of Work. Marine Spread will include Floatel and Supply Vessels.
SUBCONTRACTOR shall adhere to the provisions set forth by the applicable laws and decrees within
the force of law.
SUBCONTRACTOR shall meet the prescriptions and obligations of environmental legislation, and
execute the operations in such a way to mitigate the impact on the environment. Strict attention shall
be given to the equipment & tools complying with environmental requirements.
SUBCONTRACTOR shall be working in accordance to offshore Hook-Up schedule in conjunction with
CONTRACT drawings and comply with Codes, specifications as well as Safety at Work.
Detailed responsibilities of SUBCONTRACTOR and CONTRACTOR are described in document the
Responsibility Matrix.
Working shifts are as follows:
• Offshore onboard the FPSO: 24 hrs divided into 12-hr day and night shifts, 7 days a week
Cable Connections in
Umbilical Description Pulling Scope
qty JB
Electrical
Electrical quad cables 4 16 wires 10 mtrs
cable
PROCUREMENT
As Base Case, all incorporated materials and equipment are to be provided by CONTRACTOR
excpect for the following material that have to be procured by SUBCONTRACTOR:
1. Fiber optic splicing kit;
2. 16mm2 armoured quad connection materials;
3. Labeling and other small consumables.
• Verification of initial status and line identification (tag) of cables, lines, JB, tube.
• Visual inspection (discoloration on tubes, cable outer sheath damaged...).
• Removal of upstream tubing protection (blind flange or cap).
• Electrical cable Activities;
• Instrument cable and fiber optic Activities;
• Hydraulic tubing activities;
• Mechanical completion;
• Any other services And /Or facilities required to complete the WORK.
Provided manpower is requested to be reasonably flexible to adapt to the various tasks throughout
the project phases.
Scaffolding
Scaffolding will be provided and is under the responsibility of FPSO CONTRACTOR.