LAPORAN HARIAN PRODUKSI No.

Dokumen 0073/DOC-PROD/ARU/IX/13

PT ARU MI Tgl Terbit 12-Sep-14

Revisi -

TGL : 9 Oktober 2018 Halaman 1

KONTROL PRODUKSI
Waktu
NO Mesin NAMA OPERATOR JUMLAH
GANTI ASAH
Bakalan Bakalan Finish Finish Finish Step KET NG KETERANGAN PROSES
Mulai Selesai Potong NG QC FG PAHAT PAHAT
Luar Dalam Luar Dalam Proses Shingane
Saepul 6:00 12:00 87 12x
1 CNC TC 30
Agus 12:00 18:00 67 8x K2-B3

Pajar 8:00 17:00 60 6x K2-C (Training CNC)


2 CNC SL 40
Aji 12:00 18:00

Fahmi 6:00 12:00 22 3x Dalam 2 x Proses


3 Moriseiki 1
Reza 12:00 18:00 70 55 : K2C, 15 : 92/80

Mesin Yusuf 6:00 12:00 6 45 1x 1x K1-C


4
Panjang Yadin 12:00 18:00 70 Shingane

Rahmat 6:00 12:00 100 Step Sebelah (Shingane)


5 Chubu Koki
P Entang 12:00 18:00 75 Step Shingane

Dede 6:00 12:00 50 Shingane


6 Moriseiki 2
Ramdan 12:00 18:00 10 52 Shingane 92/80

P Yuyu 6:00 12:00 80 Step Sebelah (Shingane)


7 Wasino
P Mul 12:00 18:00 24 K2-C (Trouble Mesin)

Ade 6:00 12:00 2 35 3x K2-B3


8 Turret
P Ahmad 12:00 18:00 36 2x K2-C

DISETUJUI DIPERIKSA

TGL: TGL: