Project 400kV SWITCHYARD


SRI DAMODARAM SANJEEVAIAH THERMAL POWER PLANT NEAR KRISHNAPATNAM
ANDHRA PRADESH POWER DEVELOPMENT COMPANY LTD
Title Compliance Report for SCADA Process Displays Date: 11.10.11

Sl.No APPDCL COMMENTS ABB’ Reply

1. Figures 1, 2 &3 are not legible. Drawings in bigger size and


legible shall be submitted Complied.

2.
Breakers designation shall be 401-CB,402-CB etc. instead Complied.
of 401 Q52, 402 Q52 etc.
3. Earth switches for line isolators shall be indicated on line
side.
Complied.

4. Bus-1 & Bus-2 voltage & frequency values shall be


Complied.
displayed
5. Soft LED indication for synchronization in limit and Incoming
We will check the specification and revert before 14th Oct.
& Running voltage values shall be displayed

Page 1 of 2
Sl.No APPDCL COMMENTS ABB’ Reply

Measurement boxes are given for Active and Reactive power(+/-) and Line
Indicator will show the direction of Active Power dynamically (Import/Export)

6. Display of Active and Reactive power shall be for both


Import/Export shall be included

7. Figure-3 shall be replaced with latest revision of Architectural


drawing
Complied

Popup windows/ dialogue boxes with description shall be


8. included for a) selection of 402 Breaker from DDCMIS &
We will check and revert before 14th Oct.
SCADA. B) Control selection of switchyard equipment from
DDCMIS, SCADA and remote SRLDC.
All the features mentioned in FDS shall be available in
9.
SCADA, in addition to the features mentioned in the above All the comments except 5, 8 are complied
document.
10. Tap position, OTI and WTI status of the respective
Transformers also to be included for Display.
Complied.