CNOOC UGANDA LIMITED

CONSULTANCY SERVICES FOR RESETTLEMENT HOUSES,


DESIGN REVIEW AND CONSTRUCTION SUPERVISION

DAILY PROGRESS REPORT

REPORT DATE: 1st-09-2018

REPORT TO: CNOOC Team

PREPARED BY: Omar Hassan (Resident Engineer )


Table of Contents

1 WORK DONE TODAY ............................................................................................................................... 2


1.1 Activities executed today. ...................................................................................................................... 2
1.2 Problems / challenges faced today: ....................................................................................................... 2
1.3 Workers on Construction Site Today ..................................................................................................... 2
2 SITE PROGRESS...................................................................................................................................... 3
2.1 Overall site progress .............................................................................................................................. 3
2.2 Site progress breakdown ....................................................................................................................... 3
2.2.1 Substructure ................................................................................................................................. 3
2.2.2 Superstructure .............................................................................................................................. 4
2.2.3 Finishes, Doors and Windows ...................................................................................................... 5
3 MATERIAL REQUIREMENT ...................................................................................................................... 5
4 EQUIPMENT ON SITE .............................................................................................................................. 5
5 SEPTEMBER RAINFALL RECORD........................................................................................................... 6
5.1 General site activities: ........................................................................................................................... 7
6 MAJOR QHSE ISSUES ON SITE: ............................................................................................................. 7
6.1 Quality Issues ........................................................................................................................................ 7
6.2 Health Issues ......................................................................................................................................... 7
6.3 Safety Issues ......................................................................................................................................... 7
6.4 Environment Issues ............................................................................................................................... 7
7 SOCIAL ISSUES ON SITE ........................................................................................................................ 7
APPENDIX A: Daily cold work permits from CNOOC supervision team. ................................................................ 8

1
1 WORK DONE TODAY
1.1 Activities executed today.
Activity Location Quantity
General works Offloading of roofing materials. Site A
-60x40Hollow sections. 47 pcs.
-G28 iron sheets. 69pcs.
-Z –purlin 100x50 30pcs

 Landscaping was the main activity Site A block 2 main


on site house.
Main works  Shuttering for kitchen soffits for Site A block 3 and 4 1.1m2
ring beam. kitchens.

1.2 Problems / challenges faced today:


Problem Location/Description Remedy
Inclement Slippery roads due to heavy Contractor should ensure proper planning
weather downpour the previous day and timely delivery of construction
hampered the transportation of materials to site.
materials to site thus leading to late
delivery of construction materials.
Insufficient Construction materials like cement The contractor should ensure continued
construction and reinforcement required for the availability of construction materials on site.
materials day’s works were insufficient thus
leading to closure of work at midday.

1.3 Workers on Construction Site Today


Company Personnel Nationality Comment
CNOOC 1 Ugandan Safety officer(Mr Tom Okrut)
KKATT Consult 0 Uganda Resident Engineer, Omar Hassan
X Team Leader Paul Mwirumubi
X Project
0 Patrick B Haines
Manager
Senior
X Joseline Byambandwa
foreman.
Site
 1 Musana David
Engineer.
X 2 Foremen. Owino and John
 1 Driver. Alex.
Uganda
 13 13 Helpers. Helpers
Network civil
25 Safety
engineering  1 Ndyahwerwa Aclleus
contractors. Personnel.
Byamukama Denis,Kamanyire
 3 Security.
David and Chombe John Mary
George Tibemanya and 2
 3 Carpenter
others.
X 0 Masons
 1 Store Keeper Collins
26 (26 personnel on site)
.

2
2 SITE PROGRESS
2.1 Overall site progress
Physical progress to date stands at 48.04%. The revised planned progress for September is 100.00%.
Time progress to the 1st of September, 2018 is 90.96%.
100.00% 100.00%

90.00%
84.28%
80.00%

70.00%
67.24%
Percentage progress

60.00%
48.04%
55.42%
50.00%
45.30%
48.04%
40.00%

36.21%
30.00%

20.00% 20.78%
15.55% 15.22%
10.00%
0.00% 3.91%
0.00% 0.00%
Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18

2.2 Site progress breakdown

2.2.1 Substructure
Block type Activities Block 1 Block 2 Block 3 Block 4 Block 5
Main house All 100% 100% 100% 100% 100%
Kitchen All 100% 100% 100% 100% 100%
Re-Excavations 100% 100% 100% 0% 100%
strip foundations 100% 0% 100% 0% 100%
starter bar reinforcements 100% 0% 100% 0% 100%
Hollow blocks concrete 100% 0% 100% 0% 100%
plinth walls 100% 0% 100% 0% 100%
Latrine boxing of pit hole 0% 0% 0% 0% 0%
Over site slab formwork 90% 0% 0% 0% 100%
slab concrete 0% 0% 0% 0% 0%
back filling into foundations 100% 0% 100% 0% 60%
casting over site slab 0% 0% 0% 0% 0%
Percentage Completion 69% 10% 60% 0% 66%
Final percentage completion per block 89.6% 70% 86.6% 67% 88.67%

3
2.2.2 Superstructure
Block type Activities Block 1 Block 2 Block 3 Block 4 Block 5
Block work for super
100% 100% 100% 100% 100%
structure
Ring beam formwork 100% 100% 100% 0% 0%
Ring Beam reinforcements 100% 100% 100% 0% 0%
Ring beam concrete 100% 100% 100% 0% 0%
columns form work 100% 100% 100% 100% 50%
Reinforcements for
100% 100% 100% 100% 0%
columns
Columns concrete 100% 100% 100% 100% 0%
Vertical bands concrete 100% 100% 100% 100% 100%
Tile work 0% 0% 0% 0% 0%
Main House
Skirting 0% 0% 0% 0% 0%
Plaster 0% 0% 0% 0% 0%
Paint 0% 0% 0% 0% 0%
External pointing 0% 0% 0% 0% 0%
Ceiling joists 0% 0% 0% 0% 0%
Ceiling boards 0% 0% 0% 0% 0%
Access door 0% 0% 0% 0% 0%
Roof construction 0% 0% 0% 0% 0%
Rain water disposal 0% 0% 0% 0% 0%
Rain water storage. 0% 0% 0% 0% 0%
splash apron 30% 30% 10% 5% 0%
Final percentage
42% 41.5% 40.5% 25% 13%
completion per block
Block work for super
100% 100% 100% 100% 90%
structure
Ring beam formwork 0% 0% 0% 0% 0%
Ring Beam reinforcements 0% 0% 0% 0% 0%
Ring beam concrete 0% 0% 0% 0% 0%
columns form work 100% 100% 100% 100% 0%
Reinforcements for
100% 100% 100% 100% 0%
columns
Columns concrete 100% 100% 100% 100% 0%
Vertical bands concrete 100% 100% 100% 100% 100%
Kitchen
Tile work 0% 0% 0% 0% 0%
Skirting 0% 0% 0% 0% 0%
Plaster 0% 0% 0% 0% 0%
Paint 0% 0% 0% 0% 0%
External pointing 0% 0% 0% 0% 0%
Ceiling joists 0% 0% 0% 0% 0%
Ceiling boards 0% 0% 0% 0% 0%
Access door 0% 0% 0% 0% 0%
Pompei openings 0% 0% 0% 0% 0%
splash apron 0% 0% 10% 10% 0%
Final percentage
34.36% 34.36% 28.33% 28.33% 12.60%
completion per block
Latrine All 0% 0% 0% 0% 0%
Final percentage
24.79% 24.79% 19.82% 16.87% 8.03%
completion per block

4
2.2.3 Finishes, Doors and Windows
Block type Activities Block 1 Block 2 Block 3 Block 4 Block 5
House All 0% 0% 0% 0% 0%
Kitchen All 0% 0% 0% 0% 0%
Latrine All 0% 0% 0% 0% 0%
Final percentage completion per block 0% 0% 0% 0% 0%

3 MATERIAL REQUIREMENT
Material requirement for foundation completion
Block type Activities Block 1 Block 2 Block 3 Block 4 Block 5
Main
House All 0 0 0 0 0

Kitchen
All 0 0 0 0 0
sand (m3) 0.5 2 0.5 2 2
cement (bags) 10 50 10 50 20
Latrine. Hollow blocks 0 300 0 300 0
formwork (m2) 1 4 4 4 4
T10 reinforcement (pcs) 10 30 10 30 18

4 EQUIPMENT ON SITE
S/N Item Qty on site No. Working today Remark
Concrete Mixer machine ,Lister
1 1 0 No concrete mixing
Engine India
No compaction works
2 Poker and vibrator Robin type 1 0
for concrete.
No compaction works
3 Jumping compactor Honda type 1 0 for splash apron
excavations.
Elf truck 1.55 cubic meters
4 1 Moving of materials.
capacity and Reg No.UBA 242J 1
5 Super custom (UAP 142L) 1 0 Broke down.
6 Plate compactor (Robin type ) 1 0 No compaction works.

5
5 SEPTEMBER RAINFALL RECORD
Month September 2018
Date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Rainfall(mm) 0
Temp (0C) 22

Date 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Rainfall(mm)
Temp (0C)

6
PHOTOS OF “WORK PROGRESS AND ISSUES ON SITE” TODAY

5.1 General site activities:

Figure 1: Shuttering of kitchen soffits for ring beam Figure 2: Landscaping for block 1 and 2 main house at
block 3 and 4 at site A. site A.

6 MAJOR QHSE ISSUES ON SITE:


Issue Present Situation Comment
6.1 Quality Issues
 None observed  None observed  None observed
6.2 Health Issues
 None observed  None observed.  None observed.
6.3 Safety Issues
 None observed  None observed  None observed
6.4 Environment Issues
 None observed  None observed.  None observed.

7 SOCIAL ISSUES ON SITE


Social Issue Present Situation Comment
 None observed  None observed.  None observed.

7
APPENDIX A: Daily cold work permits from CNOOC supervision team.