1 WORK DONE TODAY
1.1 Activities executed today.
Activity Location Quantity
General works Offloading of roofing materials. Site A
-60x40Hollow sections. 47 pcs.
-G28 iron sheets. 69pcs.
-Z –purlin 100x50 30pcs
2
2 SITE PROGRESS
2.1 Overall site progress
Physical progress to date stands at 48.04%. The revised planned progress for September is 100.00%.
Time progress to the 1st of September, 2018 is 90.96%.
100.00% 100.00%
90.00%
84.28%
80.00%
70.00%
67.24%
Percentage progress
60.00%
48.04%
55.42%
50.00%
45.30%
48.04%
40.00%
36.21%
30.00%
20.00% 20.78%
15.55% 15.22%
10.00%
0.00% 3.91%
0.00% 0.00%
Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18
2.2.1 Substructure
Block type Activities Block 1 Block 2 Block 3 Block 4 Block 5
Main house All 100% 100% 100% 100% 100%
Kitchen All 100% 100% 100% 100% 100%
Re-Excavations 100% 100% 100% 0% 100%
strip foundations 100% 0% 100% 0% 100%
starter bar reinforcements 100% 0% 100% 0% 100%
Hollow blocks concrete 100% 0% 100% 0% 100%
plinth walls 100% 0% 100% 0% 100%
Latrine boxing of pit hole 0% 0% 0% 0% 0%
Over site slab formwork 90% 0% 0% 0% 100%
slab concrete 0% 0% 0% 0% 0%
back filling into foundations 100% 0% 100% 0% 60%
casting over site slab 0% 0% 0% 0% 0%
Percentage Completion 69% 10% 60% 0% 66%
Final percentage completion per block 89.6% 70% 86.6% 67% 88.67%
3
2.2.2 Superstructure
Block type Activities Block 1 Block 2 Block 3 Block 4 Block 5
Block work for super
100% 100% 100% 100% 100%
structure
Ring beam formwork 100% 100% 100% 0% 0%
Ring Beam reinforcements 100% 100% 100% 0% 0%
Ring beam concrete 100% 100% 100% 0% 0%
columns form work 100% 100% 100% 100% 50%
Reinforcements for
100% 100% 100% 100% 0%
columns
Columns concrete 100% 100% 100% 100% 0%
Vertical bands concrete 100% 100% 100% 100% 100%
Tile work 0% 0% 0% 0% 0%
Main House
Skirting 0% 0% 0% 0% 0%
Plaster 0% 0% 0% 0% 0%
Paint 0% 0% 0% 0% 0%
External pointing 0% 0% 0% 0% 0%
Ceiling joists 0% 0% 0% 0% 0%
Ceiling boards 0% 0% 0% 0% 0%
Access door 0% 0% 0% 0% 0%
Roof construction 0% 0% 0% 0% 0%
Rain water disposal 0% 0% 0% 0% 0%
Rain water storage. 0% 0% 0% 0% 0%
splash apron 30% 30% 10% 5% 0%
Final percentage
42% 41.5% 40.5% 25% 13%
completion per block
Block work for super
100% 100% 100% 100% 90%
structure
Ring beam formwork 0% 0% 0% 0% 0%
Ring Beam reinforcements 0% 0% 0% 0% 0%
Ring beam concrete 0% 0% 0% 0% 0%
columns form work 100% 100% 100% 100% 0%
Reinforcements for
100% 100% 100% 100% 0%
columns
Columns concrete 100% 100% 100% 100% 0%
Vertical bands concrete 100% 100% 100% 100% 100%
Kitchen
Tile work 0% 0% 0% 0% 0%
Skirting 0% 0% 0% 0% 0%
Plaster 0% 0% 0% 0% 0%
Paint 0% 0% 0% 0% 0%
External pointing 0% 0% 0% 0% 0%
Ceiling joists 0% 0% 0% 0% 0%
Ceiling boards 0% 0% 0% 0% 0%
Access door 0% 0% 0% 0% 0%
Pompei openings 0% 0% 0% 0% 0%
splash apron 0% 0% 10% 10% 0%
Final percentage
34.36% 34.36% 28.33% 28.33% 12.60%
completion per block
Latrine All 0% 0% 0% 0% 0%
Final percentage
24.79% 24.79% 19.82% 16.87% 8.03%
completion per block
4
2.2.3 Finishes, Doors and Windows
Block type Activities Block 1 Block 2 Block 3 Block 4 Block 5
House All 0% 0% 0% 0% 0%
Kitchen All 0% 0% 0% 0% 0%
Latrine All 0% 0% 0% 0% 0%
Final percentage completion per block 0% 0% 0% 0% 0%
3 MATERIAL REQUIREMENT
Material requirement for foundation completion
Block type Activities Block 1 Block 2 Block 3 Block 4 Block 5
Main
House All 0 0 0 0 0
Kitchen
All 0 0 0 0 0
sand (m3) 0.5 2 0.5 2 2
cement (bags) 10 50 10 50 20
Latrine. Hollow blocks 0 300 0 300 0
formwork (m2) 1 4 4 4 4
T10 reinforcement (pcs) 10 30 10 30 18
4 EQUIPMENT ON SITE
S/N Item Qty on site No. Working today Remark
Concrete Mixer machine ,Lister
1 1 0 No concrete mixing
Engine India
No compaction works
2 Poker and vibrator Robin type 1 0
for concrete.
No compaction works
3 Jumping compactor Honda type 1 0 for splash apron
excavations.
Elf truck 1.55 cubic meters
4 1 Moving of materials.
capacity and Reg No.UBA 242J 1
5 Super custom (UAP 142L) 1 0 Broke down.
6 Plate compactor (Robin type ) 1 0 No compaction works.
5
5 SEPTEMBER RAINFALL RECORD
Month September 2018
Date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Rainfall(mm) 0
Temp (0C) 22
Date 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Rainfall(mm)
Temp (0C)
6
PHOTOS OF “WORK PROGRESS AND ISSUES ON SITE” TODAY
Figure 1: Shuttering of kitchen soffits for ring beam Figure 2: Landscaping for block 1 and 2 main house at
block 3 and 4 at site A. site A.
7
APPENDIX A: Daily cold work permits from CNOOC supervision team.