1. a.

Joint Survey of Constructed Crosshead


b. Setting Out Position of
- Concrete Pedestals

- LRB block out according to LRB Schedule


and LRB Drawing manufactures

CROSS VIEW SIDE VIEW

Void former Ø 120 mm @ 280 (Depth)


Form Work

2. a. Scabble concrete surface


(by Main Contractor)
b. Install formwork and void former 120 mm
dia form work (by Main Conctractor)

CROSS VIEW SIDE VIEW


Void former Ø 120 mm @ 280 (Depth)
Form Work

3. Pouring Concrete pedestal ( By Main Contractor)

CROSS VIEW SIDE VIEW

CONCRETE PEDESTAL
TEMPORARY BEARING ( For details refer separate drawings)
PEDESTAL

4. Curing Concrete and remove formwork,


prepare top surface of pedestal to receive
grout. ( By Main Contractor)
5. Joint Survey to fit the inclination,
level,position,etc.
6. Install temporary bearings to line and level

CROSS VIEW SIDE VIEW


STABILITY PROP

7.a. Install steel box girder to line and level,


install stability prop to keep stability.

CROSS VIEW SIDE VIEW

STABILITY PROP

7.b. Install steel box girder to line and


level, install stability prop to keep
stability.

CROSS VIEW SIDE VIEW


8. Install Diafragma and remove stability
props
9. Joint survey steel box girder before install
the slab formwork

CROSS VIEW SIDE VIEW

10. Install form work for deck slab, after


than install reinforcement bar and than
concreting deck slab. sequence
concreting deck slab follow requirement
bridge engineer. ( By Main Contractor)

CROSS VIEW SIDE VIEW


Hydraulic Jack 150 ton and shim plate

CROSS VIEW 11. Curing concrete


12. Remove formwork
13. Handover span to Bukaka
14. Insert hydraulic Jacks and shim plates ( 2 no.
per girder) each end

Hydraulic Jack 150 ton and shim plate

SIDE VIEW
HYDRAULIC POWER PACK
GENERATOR

Hydraulic Jack 150 ton and shim plate

Pallet trolley- 500 kg ( to


move LRB)

15. Syncronised lifting of both girder + 10 mm


CROSS VIEW (max) at pierhead
16. Remove temporary bearing
17. Clean out blockouts and Pedestal
18. Insert dowel of LRB ( 4 no. per LRB)

HYDRAULIC POWER PACK

SIDE VIEW
HYDRAULIC POWER PACK
GENERATOR
Grout mixing

Hydraulic Jack 150 ton


and shim plate

Pallet trolley- 500 kg ( to


move LRB)

CROSS VIEW
19 a. Insert LRB Bearing and taper plate to (line and level)
b. Secure Fastenes at top and bottom plates
20. Lower steel box girder to design level.
21. Install formwork for grout pad.
22. Grouting use sika grout 215 (or similiar product).

HYDRAULIC POWER PACK

SIDE VIEW
HYDRAULIC POWER PACK
GENERATOR

Hydraulic Jack 150 ton

Pallet trolley- 500 kg ( to


move LRB)

CROSS VIEW
23. Curing 1 day/ remove form work

24. Release Jack, and transfer load to


permanent LRB.

HYDRAULIC POWER PACK

Hydraulic Jack 150 ton

SIDE VIEW
25. Remove hydraulik Jacks & shim plates
26. Final tightening all fasteners.

CROSS VIEW

LRB BEARING

SIDE VIEW
STEEL BOX GIRDER

NUT CL BEARINGS
WASHER
TAPER PLATE

BEARING HEIGHT "H"

PLATE 5mm
GROUTING

DEPTH VARIES TO SUIT DESIGN

PIER HEAD