PROVINSI : ACEH
PEKERJAAN : Pembangunan Rumah Type 36
LOKASI : Kota Subulussalam
TAHUN : 2014
UPAH
1 Mandor 72,000.00
2 Kepala Tukang 90,000.00
3 Tukang Kayu 55,000.00
4 Tukang Batu 55,000.00
5 Tukang Besi 60,000.00
6 Tukang Gali 55,000.00
7 Tukang Las 55,000.00
8 Tukang Cat 55,000.00
9 Pekerja 50,000.00
BAHAN
1 Allumnium Foil 50,000.00
2 Atap Bittumen Cellulose 3,00 mm 95,000.00
3 Baut Khusus 2" - 5 " 1,100.00
4 Baja Profil 23,400.00
5 Baja RinganProfil O 80X80X4 8,000.00
6 Baja RinganProfil C 80X80X4 8,000.00
7 Frame Baja Ringan 27,000.00
8 Batten Baja Ringan 19,000.00
9 Batu apung 97,000.00
10 Batu belah 15/20 118,800.00
11 Batu Andesit hitam 154,000.00
12 Batu bata 600.00
13 Bata berongga/Bataco 3,800.00
14 Bathtub 1,749,600.00
15 Bubungan Bitumen Cellulose 3,00 mm 62,000.00
16 Bubung Genteng Keramik palentong 12,500.00
17 Besi beton polos 7,300.00
18 Besi Plat Strip 9,800.00
19 Bak stainless steel 505,500.00
20 Bubung palentong 11,800.00
21 Cat dasar 22,500.00
22 Cat penutup 21,400.00
23 Cat meni 20,000.00
24 Cat meni besi 20,000.00
25 Cat minyak 32,400.00
26 Capsule Baja Ringan 18,000.00
27 Dempul 14,600.00
28 Dolken kayu ø 8 - 10/400 cm 30,000.00
29 Door holder 98,000.00
30 Engsel pintu 10,700.00
31 Engsel jendela 8,050.00
32 Engsel angin 11,300.00
33 Floor drain 27,000.00
34 Genteng Keramik 11,900.00
35 Genteng metal 48,000.00
36 Gypsum board (120 x 240 x 9) mm 62,000.00
37 Super Panel 9x1220x2420mm 215,000.00
38 Ijuk 10,700.00
39 Jendela Nako 222,600.00
40 Kaca Polos tebal 5 mm 86,400.00
41 Kaca Polos tebal 10 mm 100,000.00
42 Kaca buram 12 mm 148,800.00
43 Kaca patri 132,000.00
44 Koral beton/Kerikil 108,000.00
45 Kayu 5/7 2,000,000.00
46 Kayu Klas I (Seumantok/Ulin/dll) 3,996,000.00
47 Kayu Klas II (Kamper/Kruing/dll) 3,100,000.00
48 Kayu Klas III (Borneo dll) 2,700,000.00
49 Kayu bekisting 2,650,000.00
50 Kayu papan bouwplank 2,000,000.00
51 Kayu Bulat Bekisting 24,000.00
52 Kayu profil 5,000.00
53 Kayu cetakan 2,650,000.00
54 Kawat beton 9,500.00
55 Kawat harmonika 13,000.00
56 Kunci tanam 2 slaag 96,300.00
57 Kunci tanam antik 110,000.00
58 Kunci tanam biasa 75,000.00
59 Kunci tanam kamar mandi 68,000.00
60 Kunci selot/grendel 9,800.00
61 Kuas 8,500.00
62 Kloset duduk Keramik Setara KIA 1,263,600.00
63 Kloset jongkok Keramik setara KIA 97,200.00
64 Kran ¾" atau ½" 30,000.00
65 Kait angin 11,700.00
66 Keramik Lantai 40 x 40 cm 8,333.33
67 Keramik Lantai 30 x 30 cm 4,363.64
68 Keramik Lantai 20 x 20 cm Anti Slip 1,072.00
69 Keramik Lantai 10 x 10 cm Anti Slip 1,500.00
70 Keramik Dinding 20 x 25 cm 2,000.00
71 Kerikil Beton 120,000.00
72 List kayu 2/4 2,500,000.00
73 Lem kayu 15,000.00
74 Minyak bekisting (Melamin) 17,000.00
75 Minyak cat 15,600.00
76 Nok genteng metal 30,000.00
77 Pipa galvanis ø½" 10,383.33
78 Pipa galvanis ø¾" 16,666.67
79 Pipa galvanis ø1" 18,483.33
80 Pipa galvanis ø1¼" 22,500.00
81 Pipa hawa 24,500.00
82 Pipa Penguras Bak 10,000.00
83 Pipa PVC ø 2" 11,500.00
84 Pipa PVC ø 3" 16,200.00
85 Pipa PVC ø 4" 27,000.00
86 Pipa PVC ø 5" 40,000.00
87 Paku biasa 2" - 5" 11,600.00
88 Paku biasa 1/2" - 1" 11,000.00
89 Paku asbes 9,800.00
90 Paku skrup 3,5" 19,000.00
91 Paku hak panjang 15 cm 21,400.00
92 Pasir urug 90,800.00
93 Pasir beton 108,800.00
94 Pasir pasang 97,200.00
95 Plamir 10,700.00
96 Plywood 4 mm 59,400.00
97 Plywood 9 mm 124,200.00
98 Residu 6,000.00
99 Roster/terawang 3,800.00
100 Screw 350.00
101 Semen portland 40 Kg 35,700.00
102 Semen warna 40 Kg 73,440.00
103 Seng gelombang 3" - 5" 38,000.00
104 Seng Plat bjls 28 53,000.00
105 Seng Plat bjls 24 49,600.00
106 Seng gelombang BJLS 32 48,200.00
107 Seng gelombang BJLS 28 38,450.00
108 Seal Teap 7,500.00
109 Sealent/perekat 50,000.00
110 Shower 350,000.00
111 Sirtu 135,000.00
112 Tanah Timbun 43,200.00
113 T 01 s/d T10 14,000.00
114 Urinoir 810,000.00
115 Vertikals blinds 125,000.00
116 Wastafel 427,000.00
117 Water drain + asesories 35,000.00
SATUAN
Hari
Hari
Hari
Hari
Hari
Hari
Hari
Hari
Hari
M2
M2
Bh
Kg
m'
m'
m'
m'
M3
M3
M2
Bh
Bh
Bh
lbr
Bh
Kg
Kg
Bh
Bh
kg
kg
kg
kg
kg
M'
Kg
Btg
Bh
Bh
Bh
Bh
Bh
Bh
Lbr
Lbr
Lbr
Kg
Bh
M2
M2
M2
M2
M3
M3
M3
M3
M3
M3
M3
Lbr
M¹
M³
Kg
M²
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
M3
M3
Lt
Lt
Lt
Lbr
M¹
M¹
M¹
M¹
Bh
Bh
M¹
M¹
M¹
M¹
Kg
Kg
Kg
Kg
Kg
M3
M3
M3
Kg
Lbr
Lbr
Ltr
Bh
Bh
Zak
Zak
Lbr
Lbr
Lbr
Lbr
Lbr
Set
Kg
Set
M3
M3
M'
Bh
M²
Bh
Bh
ACEH, 2014
ANALISA RENCANA ANGGARAN BIAYA
Tenaga
- Pekerja 0.200 Oh x Rp. 50,000.00 = Rp.
- Tukang Batu 0.150 Oh x Rp. 55,000.00 = Rp.
- Kepala Tukang 0.015 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.010 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
SNI 03-2837-2002 - 2- d 1 M 2 Plesteran 1 Pc : 4 Ps, tebal 15 mm
Bahan
- Semen portland 5.200 Kg x Rp. 892.50 = Rp.
- Pasir pasang 0.02 M3 x Rp. 97,200.00 = Rp.
Jumlah (1) = Rp.
Tenaga
- Pekerja 0.200 Oh x Rp. 50,000.00 = Rp.
- Tukang Batu 0.150 Oh x Rp. 55,000.00 = Rp.
- Kepala Tukang 0.015 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.010 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
SNI 03-3434-2002 - b 1 M³ Pasang kusen pintu dan jendela kayu Klas II
Bahan
- Kayu Klas II, balok 1.200 M3 x Rp. 3,100,000.00 = Rp.
Jumlah (1) = Rp.
Tenaga
- Pekerja 6.000 Oh x Rp. 50,000.00
= Rp.
- Tukang Kayu 18.000 Oh x Rp. 55,000.00
= Rp.
- Kepala Tukang 2.000 Oh x Rp. 90,000.00
= Rp.
- Mandor 0.300 Oh x Rp. 72,000.00
= Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
Anl. Al2 1 M 2 Pasang konstruksi kuda-kuda baja ringan rangka atap
Bahan
- Baja Ringan Profil O 80x50x4 1.300 M' x Rp. 8,000.00 = Rp.
- Baja Ringan Profil C 80x50x4 0.600 M' x Rp. 8,000.00 = Rp.
- Baut Khusus 2" - 5" 6.000 Bh x Rp. 1,100.00 = Rp.
Jumlah (1) = Rp.
Tenaga
- Pekerja 0.100 Oh x Rp. 50,000.00 = Rp.
- Tukang 0.200 Oh x Rp. 55,000.00 = Rp.
- Kepala Tukang 0.032 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.032 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
Tenaga
- Pekerja 0.150 Oh x Rp. 50,000.00= Rp.
- Tukang Kayu 0.250 Oh x Rp. 55,000.00= Rp.
- Kepala Tukang 0.025 Oh x Rp. 90,000.00= Rp.
- Mandor 0.075 Oh x Rp. 72,000.00= Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
SNI 03-3434-2002 - av 1 M² Pasang lisplang ukuran (3 x 20) cm, kayu klas II
Bahan
- Kayu klas II, balok 0.0072 M3 x Rp. 3,100,000.00 = Rp.
- Paku biasa 2" - 5" 0.050 Kg x Rp. 11,600.00 = Rp.
Jumlah (1) = Rp.
Tenaga
- Pekerja 0.100 Oh x Rp. 50,000.00 = Rp.
- Tukang Kayu 0.200 Oh x Rp. 55,000.00 = Rp.
- Kepala Tukang 0.025 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.0050 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
Analisa biaya konstruksi pekerjaan beton
SNI 03-3435-2002 - a 1 M³ Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr
Bahan
- Semen portland 218.000 Kg x Rp. 892.50 = Rp.
- Pasir beton 0.520 M³ x Rp. 108,800.00 = Rp.
- Koral beton 0.870 M³ x Rp. 108,000.00 = Rp.
Jumlah (1) = Rp.
Tenaga
- Pekerja 1.650 Oh x Rp. 50,000.00 = Rp.
- Tukang Batu 0.250 Oh x Rp. 55,000.00 = Rp.
- Kepala Tukang 0.025 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.080 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
Tenaga
- Pekerja 6.000 Oh x Rp. 50,000.00 = Rp.
- Tukang Batu 1.000 Oh x Rp. 55,000.00 = Rp.
- Kepala tukang 0.100 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.300 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
Tenaga
- Pekerja 0.300 Oh x Rp. 50,000.00 = Rp.
- Tukang Kayu 0.260 Oh x Rp. 55,000.00 = Rp.
- Kepala tukang 0.026 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.005 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
Tenaga
- Pekerja 0.300 Oh x Rp. 50,000.00 = Rp.
- Tukang Kayu 0.330 Oh x Rp. 55,000.00 = Rp.
- Kepala tukang 0.033 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.006 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
Tenaga
- Pekerja 0.300 Oh x Rp. 50,000.00 = Rp.
- Tukang Kayu 0.330 Oh x Rp. 55,000.00 = Rp.
- Kepala tukang 0.033 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.006 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
Pekerjaan lain-lain Untuk membongkar cetakan dan menyiram beton diperlukan
- Pekerja 4.000 Oh x Rp. 50,000.00 = Rp.
Jumlah (1) = Rp.
SUPLEMEN SNI 03-3435-2002 a Pondasi Tapak P1 100 x 100 x 20 cm
Beton Cor K225 1.000 M³ x Rp. 872,810.00 = Rp.
Pekerjaan Besi 56.102 Kg x Rp. 8,662.10 = Rp.
Cetakan Beton 9.825 M2
x Rp. 143,180.00 = Rp.
Pekerjan lain-lain 1.000 Oh x Rp. 200,000.00 = Rp.
= Rp.
Tenaga
- Pekerja 0.060 Oh x Rp. 50,000.00 = Rp.
- Tukang Kayu 0.600 Oh x Rp. 55,000.00 = Rp.
- Kepala tukang 0.060 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.003 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
Tenaga
- Pekerja 0.010 Oh x Rp. 50,000.00 = Rp.
- Tukang Kayu 0.500 Oh x Rp. 55,000.00 = Rp.
- Kepala tukang 0.010 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.005 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
SNI 03-2838-2002- 4 - e 1 buah pasang engsel pintu
Bahan
- Engsel pintu 1.000 Bh x Rp. 10,700.00 = Rp.
Jumlah (1) = Rp.
Tenaga
- Pekerja 0.015 Oh x Rp. 50,000.00 = Rp.
- Tukang Kayu 0.150 Oh x Rp. 55,000.00 = Rp.
- Kepala tukang 0.015 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.00075 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
Tenaga
- Pekerja 0.050 Oh x Rp. 50,000.00 = Rp.
- Tukang Kayu 0.500 Oh x Rp. 55,000.00 = Rp.
- Kepala tukang 0.050 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.0025 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
SNI 03-2838-2002- 4 - q 1 M² pasang kaca, tebal 5 mm
Bahan
- Kaca t = 5 mm 1.100 M² x Rp. 86,400.00 = Rp.
Jumlah (1) = Rp.
Tenaga
- Pekerja 0.015 Oh x Rp. 50,000.00 = Rp.
- Tukang Kayu 0.150 Oh x Rp. 55,000.00 = Rp.
- Kepala tukang 0.015 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.00075 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
SNI 03-2838-2002- 5 - at1 1 M 2 Pasang lantai keramik 30 x 30 cm
Bahan
- Keramik 30x30 cm 11.000 Bh x Rp. 4,363.64 = Rp.
- Semen portland 11.380 Kg x Rp. 892.50 = Rp.
- Pasir pasang 0.042 M3 x Rp. 97,200.00 = Rp.
- Semen warna 1.500 Kg x Rp. 1,836.00 = Rp.
Jumlah (1) = Rp.
Tenaga
- Pekerja 0.620 Oh x Rp. 50,000.00 = Rp.
- Tukang Batu 0.350 Oh x Rp. 55,000.00 = Rp.
- Kepala tukang 0.035 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.030 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
SNI 03-2838-2002- 5 - at2 1 M 2 Pasang lantai keramik 40 x 40 cm
Bahan
- Keramik 40x40 cm 7.000 Bh x Rp. 8,333.33 = Rp.
- Semen portland 11.380 Kg x Rp. 892.50 = Rp.
- Pasir pasang 0.042 M3 x Rp. 97,200.00 = Rp.
- Semen warna 1.500 Kg x Rp. 1,836.00 = Rp.
Jumlah (1) = Rp.
Tenaga
- Pekerja 0.620 Oh x Rp. 50,000.00 = Rp.
- Tukang Batu 0.350 Oh x Rp. 55,000.00 = Rp.
- Kepala tukang 0.035 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.030 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
SNI 03-2838-2002- 6 - h 1 M² Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis penutup
Bahan
- Cat meni 0.200 Kg x Rp. 20,000.00 = Rp.
- Plamir 0.150 Kg x Rp. 10,700.00 = Rp.
- Cat dasar 0.170 Kg x Rp. 22,500.00 = Rp.
- Cat penutup 0.260 Kg x Rp. 21,400.00 = Rp.
Jumlah (1) = Rp.
Tenaga
- Pekerja 0.070 Oh x Rp. 50,000.00 = Rp.
- Tukang Cat 0.009 Oh x Rp. 55,000.00 = Rp.
- Kepala tukang 0.006 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.003 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
SNI 03-2838-2002- 6 - i 1 M² Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis penutup
Bahan
- Cat meni 0.200 Kg x Rp. 20,000.00 = Rp.
- Plamir 0.150 Kg x Rp. 10,700.00 = Rp.
- Cat dasar 0.170 Kg x Rp. 22,500.00 = Rp.
- Cat penutup 0.350 Kg x Rp. 21,400.00 = Rp.
Jumlah (1) = Rp.
Tenaga
- Pekerja 0.070 Oh x Rp. 50,000.00 = Rp.
- Tukang Cat 0.105 Oh x Rp. 55,000.00 = Rp.
- Kepala tukang 0.004 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.003 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
SNI 03-2838-2002- 6 - l 1 M² Pelaburan bidang kayu dengan cat residu dan ter
Bahan
- Residu atau ter 0.350 Ltr x Rp. 6,000.00 = Rp.
Jumlah (1) = Rp.
Tenaga
- Pekerja 0.100 Oh x Rp. 50,000.00 = Rp.
- Tukang Cat 0.000 Oh x Rp. 55,000.00 = Rp.
- Kepala tukang 0.000 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.006 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
SNI 03-2838-2002- 6 - n 1 M² Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
Bahan
- Plamir 0.100 Kg x Rp. 10,700.00 = Rp.
- Cat dasar 0.100 Kg x Rp. 22,500.00 = Rp.
- Cat penutup 0.260 Kg x Rp. 21,400.00 = Rp.
Jumlah (1) = Rp.
Tenaga
- Pekerja 0.020 Oh x Rp. 50,000.00 = Rp.
- Tukang Cat 0.063 Oh x Rp. 55,000.00 = Rp.
- Kepala tukang 0.006 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.003 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
Tenaga
- Pekerja 0.020 Oh x Rp. 50,000.00 = Rp.
- Tukang Cat 0.200 Oh x Rp. 55,000.00 = Rp.
- Kepala tukang 0.020 Oh x Rp. 90,000.00 = Rp.
- Mandor 0.010 Oh x Rp. 72,000.00 = Rp.
Jumlah (2) = Rp.
Jumlah (1) + (2) = Rp.
24,000.00
232.00
14,000.00
38,232.00
5,000.00
5,500.00
900.00
360.00
6,760.00
44,992.00
Rekap Bahan
5,000.00
3,600.00
8,600.00
Rekap Bahan
20,000.00
0.00
0.00
2,880.00
22,880.00
Rekap Bahan
26,300.00
0.00
0.00
3,744.00
30,044.00
Rekap Bahan
9,600.00
0.00
0.00
1,368.00
10,968.00
Rekap Bahan
51,840.00
51,840.00
25,000.00
0.00
0.00
3,600.00
28,600.00
80,440.00
108,960.00
108,960.00
15,000.00
0.00
0.00
720.00
15,720.00
124,680.00
Rekap Bahan
130,680.00
180,285.00
47,142.00
358,107.00
75,000.00
33,000.00
5,400.00
5,400.00
118,800.00
476,907.00
Rekap Bahan
142,560.00
27,240.00
169,800.00
39,000.00
21,450.00
3,510.00
2,808.00
66,768.00
236,568.00
Rekap Bahan
84,000.00
38,823.75
7,776.00
130,599.75
32,500.00
11,000.00
1,800.00
2,160.00
47,460.00
178,059.75
42,000.00
16,912.88
3,693.60
62,606.48
16,000.00
5,500.00
900.00
1,080.00
23,480.00
86,086.48
42,000.00
10,263.75
4,179.60
56,443.35
16,000.00
5,500.00
900.00
1,080.00
23,480.00
79,923.35
7,604.10
1,652.40
9,256.50
10,000.00
8,250.00
1,350.00
720.00
20,320.00
29,576.50
4,641.00
1,944.00
6,585.00
10,000.00
8,250.00
1,350.00
720.00
20,320.00
26,905.00
3,720,000.00
3,720,000.00
300,000.00
990,000.00
180,000.00
21,600.00
1,491,600.00
5,211,600.00
10,400.00
4,800.00
6,600.00
21,800.00
5,000.00
11,000.00
2,880.00
2,304.00
21,184.00
42,984.00
Rekap Bahan
m, kayu Klas II
37,200.00
1,160.00
38,360.00
7,500.00
13,750.00
2,250.00
5,400.00
28,900.00
67,260.00
22,320.00
580.00
22,900.00
5,000.00
11,000.00
2,250.00
360.00
18,610.00
41,510.00
Rekap Bahan
194,565.00
56,576.00
93,960.00
345,101.00
82,500.00
13,750.00
2,250.00
5,760.00
104,260.00
449,361.00
Rekap Bahan
8,925.00
2,828.80
4,752.00
16,505.80
57,500.00
1,100.00
180.00
432.00
59,212.00
75,717.80
346,290.00
70,720.00
70,200.00
487,210.00
300,000.00
55,000.00
9,000.00
21,600.00
385,600.00
872,810.00
Rekap Bahan
7,665.00
142.50
7,807.50
350.00
420.00
63.00
21.60
854.60
8,662.10
106,000.00
3,480.00
1,700.00
111,180.00
15,000.00
14,300.00
2,340.00
360.00
32,000.00
143,180.00
119,250.00
3,480.00
1,700.00
124,430.00
15,000.00
14,300.00
2,340.00
360.00
32,000.00
156,430.00
Rekap Bahan
106,000.00
4,640.00
3,400.00
40,500.00
43,470.00
60,000.00
258,010.00
15,000.00
18,150.00
2,970.00
432.00
36,552.00
294,562.00
Rekap Bahan
106,000.00
4,640.00
3,400.00
48,600.00
43,470.00
60,000.00
266,110.00
15,000.00
18,150.00
2,970.00
432.00
36,552.00
302,662.00
Rekap Bahan
200,000.00
200,000.00
872,810.00
485,958.54
1,406,680.70
200,000.00
2,965,449.24
Rekap Bahan
872,810.00
1,098,977.27
547,505.00
200,000.00
2,719,292.27
Rekap Bahan
872,810.00
2,284,010.77
1,746,126.92
200,000.00
5,102,947.69
872,810.00
1,423,376.46
1,387,200.83
200,000.00
3,883,387.29
Rekap Bahan
872,810.00
1,113,788.28
1,178,248.00
200,000.00
3,364,846.28
872,810.00
2,337,942.55
2,265,861.54
200,000.00
5,676,614.09
872,810.00
945,170.58
1,059,317.00
200,000.00
3,077,297.58
872,810.00
2,026,216.87
1,668,521.28
200,000.00
4,767,548.16
Rekap Bahan
57,142.86
232.00
57,374.86
6,000.00
3,300.00
540.00
432.00
10,272.00
67,646.86
35,294.12
440.00
35,734.12
5,000.00
3,850.00
720.00
432.00
10,002.00
45,736.12
59,375.00
6,600.00
65,975.00
6,000.00
3,300.00
540.00
432.00
4,272.00
70,247.00
Rekap Bahan
73,160.00
4,400.00
77,560.00
7,500.00
3,850.00
720.00
432.00
5,002.00
82,562.00
Rekap Bahan
21,621.60
570.00
22,191.60
3,500.00
5,500.00
900.00
252.00
10,152.00
32,343.60
Rekap Bahan
110,000.00
110,000.00
3,000.00
33,000.00
5,400.00
216.00
41,616.00
151,616.00
Rekap Bahan
75,000.00
75,000.00
500.00
27,500.00
900.00
360.00
29,260.00
104,260.00
10,700.00
10,700.00
750.00
8,250.00
1,350.00
54.00
10,404.00
21,104.00
Rekap Bahan
8,050.00
8,050.00
500.00
5,500.00
900.00
36.00
6,936.00
14,986.00
11,700.00
11,700.00
750.00
8,250.00
1,350.00
54.00
10,404.00
22,104.00
9,800.00
9,800.00
1,000.00
11,000.00
1,800.00
72.00
13,872.00
23,672.00
98,000.00
98,000.00
2,500.00
27,500.00
4,500.00
180.00
34,680.00
132,680.00
95,040.00
95,040.00
750.00
8,250.00
1,350.00
54.00
10,404.00
105,444.00
48,000.00
10,156.65
4,082.40
2,754.00
64,993.05
31,000.00
19,250.00
3,150.00
2,160.00
55,560.00
120,553.05
58,333.33
10,156.65
4,082.40
2,754.00
75,326.38
31,000.00
19,250.00
3,150.00
2,160.00
55,560.00
130,886.38
Rekap Bahan
26,800.00
10,156.65
4,082.40
2,754.00
43,793.05
31,000.00
19,250.00
3,150.00
2,160.00
55,560.00
99,353.05
Rekap Bahan
mir), 1 lapis cat dasar, 2 lapis penutup
4,000.00
1,605.00
3,825.00
5,564.00
14,994.00
3,500.00
495.00
540.00
180.00
4,715.00
19,709.00
mir), 1 lapis cat dasar, 3 lapis penutup
4,000.00
1,605.00
3,825.00
7,490.00
16,920.00
3,500.00
5,775.00
360.00
180.00
9,815.00
26,735.00
2,100.00
2,100.00
5,000.00
0.00
0.00
432.00
5,432.00
7,532.00
Rekap Bahan
1 lapis cat dasar, 2 lapis cat penutup)
1,070.00
2,250.00
5,564.00
8,884.00
1,000.00
3,465.00
567.00
180.00
5,212.00
14,096.00
Rekap Bahan
2,000.00
85.00
2,085.00
1,000.00
11,000.00
1,800.00
720.00
14,520.00
16,605.00
+ Rangka Furing
6000.00
830.00
7705.00
41572.20
0.00
41572.20
RENCANA ANGGARAN BIAYA
1 2 3 5
I PEKERJAAN PERSIAPAN
1 Bouwplank 46.000 M' SNI 03-2835-2002 - 1 - d
2 Pembersihan Lahan dan Lean Clearing 130.000 M2 SNI 03-2835-2002 - 1 - h
IV PEKERJAAN LANTAI
1 Lantai Kerja T = 5 cm Camp. 1Pc : 3 Ps : : 5 Kr 1.703 M3 SNI 03-2838-2002- 5 - at1 - a
SNI 03-3435-2002
2 Lantai Keramik 40/40 33.067 M2 SNI 03-2838-2002- 5 - au1
3 Lantai Keramik KM. 30/30 2.228 M2 SNI 03-2838-2002- 5 - au1
4 Dinding Keramik KM. 30/30 4.752 M2
V PEKERJAAN DINDING
1 Pas. Dinding 1/2 Bata 1 Pc : 2 Ps 4.100 M2 SNI 03-2837-2002 - 1 - i
2 Pas. Dinding 1/2 Bata 1 Pc : 4 Ps 114.800 M2 SNI 03-2837-2002 - 1 - k
3 Plesteran Dinding 1 Pc : 2 Ps 4.100 M2 SNI 03-2837-2002 - 2- b
4 Plesteran Dinding 1 Pc : 4 Ps 114.800 M2 SNI 03-2837-2002 - 2- d
5 Plesteran Kolom dan Rigkbalk 8.860 M2 SNI 03-2837-2002 - 2- d
VI PEKERJAAN PLAFOND
1 Plafond Gypsum 4 mm + Rangka Furing 33.067 M2 Anl. X.4
2 List Pofil Gypsum 25.730 M' Taksir
1 2 3 5
1 2 3 5
IX PEKERJAAN ELEKTRIKAL
1 Pemasukan Arus Listrik 1.000 Ls Taksir
2 Lampu Hemat Energi 8 Watt 6.000 Bh Taksir
3 Stop Kontak Daya + Instalasi 4.000 Bh Taksir
4 Saklar Tunggal Terpasang 2.000 Bh Taksir
5 Saklar Ganda Terpasang 2.000 Bh Taksir
6 MCB 1.000 Bh Taksir
7 1300 KVA 1.000 Bh Taksir
No
44,992.00 2,069,632.00 ###
8,600.00 1,118,000.00 ###
Sub Jumlah 3,187,632.00 ###
###
22,880.00 455,071.80 ###
10,968.00 54,537.01 ###
124,680.00 182,191.08 ###
124,680.00 533,735.94 ###
80,440.00 1,251,896.92 ###
Sub Jumlah 2,477,432.76 ###
###
###
236,568.00 672,174.24 ###
476,907.00 4,716,753.21 ###
449,361.00 56,054.42 ###
3,883,387.29 4,776,566.37 ###
5,676,614.09 5,392,783.38 ###
5,102,947.69 4,898,829.79 ###
5,102,947.69 714,412.68
Sub Jumlah 20,513,161.40 ###
###
449,361.00 765,187.37 ###
120,553.05 3,986,287.68 ###
99,353.05 221,313.39 ###
99,353.05 472,135.23 ###
Sub Jumlah 5,444,923.67 ###
###
86,086.48 352,954.55 ###
79,923.35 9,175,200.58 ###
29,576.50 121,263.65 ###
28,016.50 3,216,294.200 ###
28,016.50 248,212.418 ###
Sub Jumlah 13,113,925.40 ###
###
41,572.20 1,374,654.14 ###
12,000.00 308,760.000 ###
Sub Jumlah 1,683,414.14 ###
###
5,211,600.00 2,814,264.000 ###
600,000.00 1,800,000.000 ###
520,000.00 520,000.000 ###
375,000.00 375,000.000
400,000.00 2,800,000.000 ###
300,000.00 300,000.000 ###
HARGA SATUAN JUMLAH HARGA
(Rp) (Rp)
6 7
Sub Jumlah 8,609,264.00 ###
###
14,096.00 1,618,220.80 ###
26,735.00 884,037.37 ###
Sub Jumlah 2,502,258.17
HARGA SATUAN JUMLAH HARGA
(Rp) (Rp)
6 7
1,000,000.00 1,000,000.000
27,000.00 162,000.000
44,000.00 176,000.000
18,000.00 36,000.000
21,000.00 42,000.000
1,000,000.00 1,000,000.000
2,000,000.00 2,000,000.000
Sub Jumlah 4,416,000.00
120,000.00 120,000.000
600,000.00 600,000.000
35,000.00 70,000.000
30,000.00 30,000.000
2,500,000.00 2,500,000.000
Sub Jumlah 3,320,000.00
PT. Alegerhan
RE KAPITULAS I
ENGINEER ESTIMATE
PROPINSI : ACEH
PEKERJAAN : Pembangunan Rumah Type 36
LOKASI : Kota Subulussalam
TAHUN : 2014
NO URAIAN PEKERJAAN
1 2
I PEKERJAAN PERSIAPAN
II PEKERJAAN TANAH DASAR DAN PASIR
III PEKERJAAN STRUKTUR BETON BERTULANG
IV PEKERJAAN LANTAI
V PEKERJAAN DINDING
VI PEKERJAAN PLAFOND
VII PEKERJAAN KUSEN PINTU DAN JENDELA
VIII PEKERJAAN PENGECETAN
IX PEKERJAAN ELEKTRIKAL
X PEKERJAAN KUNCI dan PENGANTUNG
XI PEKERJAAN SANITER DAN FIXTURE
XII PEKERJAAN ATAP DAN RANGKA BAJA
JUMLAH
DIBULATKAN
Terbilang : Tujuh Puluh Empat juta Lima Ratus Enam Puluh Satu Ribu Rupiah
PT. Alegerhan
ASI
IMATE
TOTAL JUMLAH
(Rp)
3
3,187,632.00
2,477,432.76
20,513,161.40
5,444,923.67
13,113,925.40
1,683,414.14
8,609,264.00
2,502,258.17
4,416,000.00
1,576,356.00
3,320,000.00
7,717,560.41
74,561,927.94
74,561,927.94
74,561,000.00
PT. Alegerhan