Course Outline
The training program deals with
fundamentals, designing, drafting, erection,
estimation, maintenance & detail engineering
of Central HVAC systems including Central Air
Systems & Chilled Water Systems
Systems. The
dedicated training sessions covers detailed
applications & usage of codes & standards
ASHRAE, ISHRAE, SMACNA, ASME, ARI, DW
142 and more.

How Trainee benefits


The participants enrolling for the training
programme at IPEBS can look forward for a
challenging position in Engineering Consulting
& Construction Companies.

The participants can work can as Design


Engrs, Project/Procurement ( Site
ite Engrs ),
Estimation, Testing & Commissioning, Sales &
Maintenance Engrs for different residential,
“Attendees will gain real world experience
commercial and industrial projects including
which they can utilise it at their work.”
work.
commercial malls, towers, hospitals, clean
rooms, cold stores, universities, and other
facilities.

Course Material
The most extensive material as per the
current industrial standards which covers all
Design & Detail Engineering, Erection,
Maintenance Standards of HVAC Systems.
Training programme objective:
We go great lengths to provide you with the highest quality training available
& we promise a wealth of practical and valuable information in a short
period of time. We guarantee the superior training in India, with 100%
Become a HVAC,
learning, knowledge transfer and training satisfaction.
Specialist at IPEBS
Combine theoretical knowledge & practical experience to gain a total picture
Target
of system design & operational requirements.

“ The fast paced program will cover fundamentals, drafting, design


• Engg Consultants , calculations, equipment selection, problem solving, erection & maintenance
• HVAC Equipment requirements, routing of ducts / pipes, usage of codes and standards, project
Cos. work, HVAC softwares like pipe sizer, duct sizer, Elite RHVAC, CHVAC,
• Contractors, Carrier’s Block Load, HAP ( Hourly Analysis Program).”
• Construction Co’s
• O/M Companies
Course Speaker:
Our experienced & polished trainers are hand-picked to present our sessions
based in their dynamic public speaking skills and their industrial expertise.

These professionals have hands on experience in the MEP, HVAC, Plumbing &
“IPEBS - India’s No-1 Fire Fighting, Electrical, Industrial Piping & Pipeline industries and provided
Technical Training thousands of hours of training sessions.
provider in Plant
Engineering & Building
Services”.
Trainee’s Feedback:
Excellent experience of the training sessions which covers all the detailing &
designing concepts of Mechanical Services and HVAC system design.

Well structured training programme to understand the different phases of


design, erection, maintenance & operation of the systems.

A very informative and must do course for anyone who is involved or going
to be involved in the HVAC / Construction or related industries.

Totally power packed course to enhance engineering skills & empower the
engineers.

Enrol for the Training programme at IPEBS & avail the Video Training.
Institute of Piping Engineering & Building Services

Program Description
Our corporate
clients includes: This certificate program introduces the participants to the following modules:

Introduction to HVAC Documents Approvals


Refrigerants. Project Procurement works
Cooling Load estimation Preparation of Drawings.
Heating Loss estimation Clean Rooms/ Cold Stores
Air Distribution System.
Ventilation system.
Chilled Water system
Equipment Selection
Erection of Equipments.
Maintenance
Estimation of Projects.

I) Introduction to HVAC

• Scope of HVAC Industry with overview of Consulting & Construction


industry.

• Concepts of Air conditioning systems.

o Codes & Standards

o Principles of air conditioning

 Vapour compression cycle

 Absorption Chilling system

o Air conditioning systems

 Local cooling comfort System

— Window Air conditioning

— Split Air conditioning

— Multi Split Air conditioning

— Chilled water Fan coil unit

And many more.......

IPEBS – INSTITUTE OF PIPING ENGG. & BUILDING SERVICES


Tel: 040-30623249, 0091 – 9885946711,
E-MAIL: info@ipebs.in WEBSITE: www.ipebs.in
Institute of Piping Engineering & Building Services

 Centrally air conditioned system

— Central Air Conditioning System

— Chilled water system.

o Psychometric chart

— Properties of Air (DBT, %RH, WBT, HR, DPT, ENTHALPY.)

• Components of AHU & its functioning

o Cooling

o Heating

o Humidification Methods

o Dehumidification Methods

o Filtration

II) Refrigerant
Experience knowledge rich &
• Types of refrigerant Comprehensive Short Professional
• Evaporating & Condensing properties
Training courses in Piping
of refrigerant. Engineering/ Pipeline Engg. &
Building Services.
• Refrigerant Pipe sizing methods
( HVAC/Electrical/Plumbing/Fire
III) Cooling & Heating load estimation. Fighting) courses IPEBS
• Basics of Heat transfer in a building
envelop.

• Understanding of Outdoor & Indoor


Conditions.

o Correction to Outdoor temperature & Indoor temperature requirements

o Exposure of Wall, Latitude of Location, Yearly Range, Daily Range etc

o Factors effecting the loads estimate.

• Sources of Heat Gain

o External- Sun Gain through Glass/Window, Sun Gain through Roof/Wall,


Partition gain

o Internal - People, Lights, Electrical Equipments, Motors, Kitchen Appliances,


Heat gain through Infiltration air, Heat gain thorough Ventilation & By-pass air,
Heat gain through ducts. Calculating ESHF, GTH, ADP, Dehumidified CFM.

IPEBS – INSTITUTE OF PIPING ENGG. & BUILDING SERVICES


Tel: 040-30623249, 0091 – 9885946711,
E-MAIL: info@ipebs.in WEBSITE: www.ipebs.in
Institute of Piping Engineering & Building Services

• Heat loss calculations

o Basics of Heat loss in a building envelop.

o Sources of Heat loss –

 Heat loss through Glass/window, Heat loss through Roof/Wall

 Heat loss through Partition Glass/wall/Floor/slab, Heat loss through


Infiltration air/Ventilation air & Bypass air

 Heat loss through slab on Grade

IV) Design of Air Distribution System.

• Components of Air distribution system.

o Types of Ducts, Duct Fittings, Dampers, Types of Diffusers, RAG, Flexible Duct,
Flexible Connector, End Cap, Sound Attenuator etc.

o Duct Elbows selections (Long radius, Short radius- No throat, Throat elbows,
with heel radius, throat radius & radius of elbow).

o Vanes location & number of vanes required

o Duct Material Calculation- GI sheet, Total sheet required in kgs. Gauge of duct &
Thickness of Gauge. Hanger Spacing, Hanger Rod Diameter and Angle support
Size.

o Duct designing methods.

 Velocity reduction method.

 Equal friction Method.

 Static regain method.

o Fan selection & Static pressure calculation.

o Supply & Return Duct configuration, Assigning Velocity of Air (FPM) to each
Section of Supply and Return Duct Low Velocity system, Medium Velocity
System and High Velocity System.

o Components of Air Distribution System, Supply and Return Duct configurations


(Extended Plenum Systems, Radial System, Trunk and Branch system)

o Stair Well Pressurization System Designing

V) Design of Ventilation system.

• Introduction to Ventilation system,

o Components of Ventilation system.

IPEBS – INSTITUTE OF PIPING ENGG. & BUILDING SERVICES


Tel: 040-30623249, 0091 – 9885946711,
E-MAIL: info@ipebs.in WEBSITE: www.ipebs.in
Institute of Piping Engineering & Building Services

• Restaurant and Residence Kitchen Ventilation System Design

o Sizing of Hood, Number of filters required & Duct designing.

VI) Chilled Water system design.

• Introduction to Chilled water system, Hot water system.

• Classification of chillers

o As per Evaporator.

o As per Condenser.

o As per compressor.

• Chiller arrangements, Cooling tower arrangement, Types of cooling tower &


Expansion tank connections.

• Pumps required in Chilled water system

o Production Pumps

o Distribution Pumps

o Pump Classifications.

• Chilled water system pipe designing

o Piping fundamentals

 Pipe designators, Piping standards.

 Piping fittings and Components.

 Valves used in Chilled water system

o Chilled water and Hot water GPM calculation.

o Calculation of Water Velocity FPS on Suction and Discharge side of Pump.

o Hydraulic Design for Sizing the Pipe for Amount of Flow.( Open & Closed Piping
Systems).

o District Cooling System.

o Friction loss calculation for the piping system

 Friction Loss in Straight Pipes.

 Friction Loss in Straight Pipes. Friction Loss in Fittings. Valves used in


Chilled Water System.

 Friction Loss in Valves & Special components.

o Calculating TDH for Pump (Open Piping System and Closed Piping System).
IPEBS – INSTITUTE OF PIPING ENGG. & BUILDING SERVICES
Tel: 040-30623249, 0091 – 9885946711,
E-MAIL: info@ipebs.in WEBSITE: www.ipebs.in
Institute of Piping Engineering & Building Services

o Pipe Sizing Manual Method Hazen-Williams Equation for Calculating Friction


Loss.

o Pump Cavitations & NPSH Calculation for Pump.

VII) Equipment Selection

• AHU & FCU classification and selection.

• Package Unit Selection DX- Chiller Selection.

• Condenser Selection (Air cooled, Water Cooled, Evaporative).

• Cooling Tower Selection Mixed Air Temperature Calculation.

• HRF for Open and Closed Compressor.

• Expansion Tank Selection

VIII) Erection of Equipments

• Detailing & Installation of Chillers

• Detailing & Installation of Air handling units.

• Detailing & Installation of Package units.

• Detailing & Installation of Fan coil units.

• Detailing & Installation of Condensing units

IX) Estimation of Project

• Understanding the tendering requirements

• Quantity take off

• Preparing Inquiry for Suppliers & Finalizing the suppliers.

• Final Billing & Quotations finalization

X) Documents Approvals
• Preparation of Material submittals,

• Shop drawing submittals,

• Types of approval.

• Preparation of BOQ and design documents,

• Specifications.
IPEBS – INSTITUTE OF PIPING ENGG. & BUILDING SERVICES
Tel: 040-30623249, 0091 – 9885946711,
E-MAIL: info@ipebs.in WEBSITE: www.ipebs.in
Institute of Piping Engineering & Building Services

XI) Project Procurement works


• Identifying the critical equipments
• preparation of purchase orders
• Letter of Intent
• Letter of credit
• Minutes of meeting

XII) Drafting of HVAC Systems-


• Introduction to Drafting,
• Types of Drawings used in the industry,
• Study & Preparation of Floor Drawings,
o Roof Drawings,
o Sectional Drawings
o Builders Work Drawings,
o Co- ordination Drawings &
o Riser Diagram,
o Abbreviations & Symbols used.

Project work- Load calculations, duct designing & Equipment selection

.
Software’s: Commercial HVAC/Residential HVAC, Duct Sizing / Pipe Sizing software. Carrier
Block Load & Hap(Hourly analysis programme)

IPEBS – INSTITUTE OF PIPING ENGG. & BUILDING SERVICES


Tel: 040-30623249, 0091 – 9885946711,
E-MAIL: info@ipebs.in WEBSITE: www.ipebs.in

Anda mungkin juga menyukai