UNIT COST
QUANTITY UNIT DESCRIPTION MATERIALSLABOR (35%)
3 GAL FLAT LATEX 700 245
1 L FLAT LATEX 175 61.25
1 KG PATCHING COMPOUND 70 24.5
4 PCS SAND PAPER #120 20 7
6 GAL SEMI-GLOSS LATEX 700 245
UNIT COST
QUANTITY UNIT DESCRIPTION MATERIALSLABOR (35%)
10 GAL FLAT LATEX 700 245
2 L FLAT LATEX 175 61.25
3 KG PATCHING COMPOUND 70 24.5
10 PCS SAND PAPER #120 20 7
20 GAL SEMI-GLOSS LATEX 700 245
TOTAL COST
MATERIALS LABOR (35%) COST
7000 2450 9450
225 78.75 303.75
200 70 270
14000 4900 18900
120 42 162
200 70 270
375 131.25 506.25
TOTAL 29862
TOTAL COST
MATERIALS LABOR (35%) COST
2100 735 2835
175 61.25 236.25
70 24.5 94.5
80 28 108
4200 1470 5670
TOTAL 8943.75
TOTAL COST
MATERIALS LABOR (35%) COST
7000 2450 9450
350 122.5 472.5
210 73.5 283.5
200 70 270
14000 4900 18900
TOTAL 29376