Anda di halaman 1dari 66

MENAI

KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
Routine Maintenance (RM)
DARI
Oct-18
SUNGA
I 1 Patching
10/1/2018 RM/470 MAF/KPZ CH 21+000 - CH 23+000
pothole
BULOH
KE 2 MAF/KPZ
ASSAM
3 MAF/KPZ
JAWA,
4 MAF/KPZ
KUALA
5 MAF/KPZ
SELAN
Survey (SV)
GOR,
Oct-18
SELAN
GOR Joint survey
SECAR
1 12/10/18 SV/325 Joint Survey CH 3+600 - CH 4+800 RHS surcharge
A level
REKA
DAN Joint survey
2 12/10/18 SV/326 Joint Survey CH 2+800 - CH 2+900 RHS excavation
BINA USM

Joint survey
3 22/10/18 SV/327 Joint Survey CH 2+450 - CH 2+900 LHS excavation
USM

Joint survey
4 22/10/18 SV/328 Joint Survey CH 0+300 - CH 0+800 LHS excavation
USM

Joint survey
5 22/10/18 SV/329 Joint Survey CH 18+500 - CH 19+000 RHS excavation
rock
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
Joint survey
DARI6 10/24/2018 SV/330 Joint Survey CH 15+675 - CH 16+300 LHS
sand fill
SUNGA
I 7 Joint Survey
8
BULOH Joint Survey
KE 9 Joint Survey
ASSAM
10 Joint Survey
JAWA,
11 Joint Survey
KUALA
12 Joint Survey
SELAN
13 Joint Survey
GOR,
14
SELAN Joint Survey
GOR15 Joint Survey
SECAR
16 Joint Survey
A 17 Joint Survey
REKA
18 Joint Survey
DAN
19 Joint Survey
BINA
20 Joint Survey

21 Joint Survey

22 Joint Survey

23 Joint Survey
Earthwork (GKE)
Oct-18
Embankment
1 02/10/18 GKE/2112 Gankee Earthwork S/B CH 15+626 - CH 16+350 LHS
fill

Prepared
2 02/10/18 GKE/2113 Gankee Earthwork S/B CH 19+900 - CH 20+600 RHS
subgred level

3 02/10/18 GKE/2114 Gankee Earthwork S/B CH 19+700 - CH 19+800 RHS Cutting slope
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI Fill
4 02/10/18 GKE/2115 Gankee Earthwork S/B CH 23+300 - CH 23+500 RHS
SUNGA embankment
I
Close turfing
BULOH
5 02/10/18 GKE/2116 Gankee Earthwork S/B CH 19+200 - CH 19+450 BS
at slope
KE 6 02/10/18 GKE/2117 Gankee Earthwork S/B CH 18+000 - CH 18+700 RHS
Excavated &
ASSAM trim slope
Excavation
7
JAWA, 04/10/18 GKE/2118 Gankee Earthwork S/B CH 11+900 - CH 12+200 LHS
USM
Excavation
KUALA
8 04/10/18 GKE/2119 Gankee Earthwork S/B CH 10+050 - CH 10+350 LHS
USM
SELAN
9 04/10/18 GKE/2120 Gankee Earthwork S/B CH 10+900 - CH 10+700 RHS
Excavation
GOR, USM
8
SELAN 04/10/18 GKE/2121 Gankee Earthwork S/B CH 10+550 - CH 10+900 LHS Earth backfill
GOR 9 04/10/18 GKE/2122 Gankee Earthwork S/B CH 10+200 - CH 10+425 RHS Earth backfill
SECAR
A 10 04/10/18 GKE/2123 Gankee Earthwork S/B Earth backfill
CH 9+925 - CH 10+050 LHS
REKA
DAN11 04/10/18 GKE/2124 Gankee Earthwork S/B CH 9+425 - CH 9+575 LHS Earth backfill
BINA
12 04/10/18 GKE/2125 Gankee Earthwork S/B CH 4+650 - CH 4+800 RHS Earth backfill
Excavation
13 04/10/18 GKE/2126 Gankee Earthwork S/B CH 7+500 - CH 7+650 LHS
surcharge
Excavation
14 04/10/18 GKE/2127 Gankee Earthwork S/B CH 6+575 - CH 6+850 LHS
surcharge

Backfilling
sand laying
15 05/10/18 GKE/2128 Gankee Earthwork S/B CH 16+325 - CH 16+115 LHS
300mm under
subgred

2nd trial
16 05/10/18 GKE/2129 Gankee Earthwork S/B CH 18+600 LHS
blasting

Excavation of
17 08/10/18 GKE/2130 Gankee Earthwork S/B CH 9+800 - CH 10+500
road kerb
18 10/10/18 GKE/2131 Gankee Earthwork S/B CH 2+800 - CH 2+950 RHS Sand backfill
Excavation
19 10/10/18 GKE/2132 Gankee Earthwork S/B CH 5+600 - CH 6+000 LHS
centre line
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
Excavation
SUNGA 300mm under
I 20 10/10/18 GKE/2133 Gankee Earthwork S/B CH 15+525 - Ch 15+200 LHS
subgrade
BULOH level (RNR)
Sand laying
KE
300mm under
ASSAM
21 10/10/18 GKE/2134 Gankee Earthwork S/B CH 16+115 - CH 15+340 LHS subgrade
JAWA, (subgred
KUALA Excavation of
level)
Fill
22 10/10/18 GKE/2135 Gankee Earthwork S/B CH 2+450 - CH 2+850 LHS
USM
embankment
SELAN
suitable earth
GOR,
23 10/10/18 GKE/2136 Gankee Earthwork S/B CH 15+525 - Ch 15+200 LHS
material for
SELAN RNR to
GOR Excavation
subgred level
work to
SECAR
24 13/10/18 GKE/2137 Gankee Earthwork S/B CH 18+000 - CH 18+150 RHS
subgrade
A level
REKA Excavation
DAN25 13/10/18 GKE/2138 Gankee Earthwork S/B CH 18+000 - CH 18+150 RHS work to
Normal
remove USM
BINA
26 15/10/18 GKE/2139 Gankee Earthwork S/B CH 10+500 - CH 10+350 LHS excavation
subgrade
Excavation of
27 15/10/18 GKE/2140 Gankee Earthwork S/B CH 7+850 - CH 7+900 LHS
surcharge
Subgrade
28 15/10/18 GKE/2141 Gankee Earthwork S/B CH 6+075 - CH 6+300 LHS
preparation
29 15/10/18 GKE/2142 Gankee Earthwork S/B CH 2+700 - CH 2+850 RHS Earth backfill
Excavation of
30 15/10/18 GKE/2143 Gankee Earthwork S/B CH 3+300 - CH 3+600 RHS
USM
Excavation
31 15/10/18 GKE/2144 Gankee Earthwork S/B CH 2+450 - CH 2+700 LHS
USM
Excavation of
32 15/10/18 GKE/2145 Gankee Earthwork S/B CH 0+300 - CH 0+850 LHS
USM
Excavation
33 17/10/18 GKE/2146 Gankee Earthwork S/B CH 11+000 - CH 11+200 LHS
USM
34 17/10/18 GKE/2147 Gankee Earthwork S/B CH 11+900 - CH 12+250 LHS Sand backfill
35 17/10/18 GKE/2148 Gankee Earthwork S/B CH 10+550 - CH 10+900 LHS Earth backfill

36 GKE/2149 Gankee Earthwork S/B

37 GKE/2150 Gankee Earthwork S/B


Embankment
38 18/10/18 GKE/2151 Gankee Earthwork S/B CH 4+950 - CH 5+375 LHS
fill
39 24/10/18 GKE/2152 Gankee Earthwork S/B CH 2+450 - CH 2+700 LHS Sand backfill
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
40 24/10/18 GKE/2153 Gankee Earthwork S/B CH 12+000 - CH 12+200 LHS Sand backfill
DARI
SUNGA
I Embankment
BULOH fill (soil
KE41 26/10/18 GKE/2154 Gankee Earthwork S/B CH 15+000 - CH 15+450 LHS filling) 300mm
under
ASSAM subgrade
JAWA,
Sand backfill
KUALA for "RnR" to
42
SELAN 26/10/18 GKE/2155 Gankee Earthwork S/B CH 15+450 - Ch 15+870 LHS
subgrade
GOR, level
SELAN
GOR Excavated
600mm under
SECAR
43 26/10/18 GKE/2156 Gankee Earthwork S/B CH 15+450 - Ch 15+870 LHS
subgrade
A level for "RnR"
REKA
DAN
BINA
44 26/10/18 GKE/2157 Gankee Earthwork S/B CH 11+900 - CH 12+300 LHS Sand backfill

Excavation
45 26/10/18 GKE/2158 Gankee Earthwork S/B CH 11+200 - CH 12+300 LHS
USM

Excavation
46 26/10/18 GKE/2159 Gankee Earthwork S/B CH 6+500 - CH 6+875 LHS surcharge to
subgrade
Embankment
47 26/10/18 GKE/2160 Gankee Earthwork S/B CH 4+950 - CH 5+375 LHS
filling
48 26/10/18 GKE/2161 Gankee Earthwork S/B CH 2+450 - CH 2+700 LHS Sand backfill
Excavation
49 26/10/18 GKE/2162 Gankee Earthwork S/B CH 2+450 - CH 2+900 LHS
USM
Excavation
50 26/10/18 GKE/2163 Gankee Earthwork S/B CH 0+875 - CH 0+950 LHS
USM
51 26/10/18 GKE/2164 Gankee Earthwork S/B CH 0+300 - CH 0+850 LHS Sand backfill
Excavation
52 26/10/18 GKE/2165 Gankee Earthwork S/B CH 0+000 - CH 0+300 LHS
USM
53 GKE/2166 Gankee Earthwork S/B
54 GKE/2167 Gankee Earthwork S/B
55 Gankee Earthwork S/B
56 Gankee Earthwork S/B
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
57 Gankee Earthwork S/B
DARI
58
SUNGA Gankee Earthwork S/B
I 59 Gankee Earthwork S/B
BULOH
60 Gankee Earthwork S/B
KE
ASSAM
61 Gankee Earthwork S/B
JAWA,
62 Gankee Earthwork S/B
KUALA
63 Gankee Earthwork S/B
SELAN
GOR,
64 Gankee Earthwork S/B
SELAN
65 Gankee Earthwork S/B
GOR
SECAR
66 Gankee Earthwork S/B
A 67 Gankee Earthwork S/B
REKA
DAN68 Gankee Earthwork S/B
BINA
69 Gankee Earthwork S/B
70 Gankee Earthwork S/B
71 Gankee Earthwork S/B
72 Gankee Earthwork S/B
Laboratory (QAQC)
Oct-18 Collect 1st
Collect
panel deck
1 01/10/18 QC/1314 AUSB CH 9+800 sample s/base
slab at bridge
(sand)
No.1 for
Collect
2 01/10/18 QC/1315 AUSB CH 19+180 - CH 19+400 BS
treatment
sample
3 01/10/18 QC/1316 AUSB CH 5+500 - CH 6+000 LHS filing & &
R/base test
test
sieve
sieving
(Routine test)
FDT test
embankment
4 02/10/18 QC/1317 AUSB CH 15+625 - CH 16+350 LHS fill (subgrade
level) final
layer
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FDT test
FT54 embankment
5 02/10/18 QC/1318 AUSB CH 23+300 - CH 23+500 RHS Delivery
DARI fill 1st layer -
material
6 02/10/18 QC/1319 AUSB CH 5+000 LHS 3rd layer PVD
SUNGA 110rolls Nylex
I MW310
BULOH
Inspection for
KE delivery
ASSAM material u-
7 02/10/18 QC/1320 AUSB CH 23+800 - CH 23+900
JAWA, drain size
KUALA 900x900 GSG
concrete
SELAN
GOR,
SELAN
GOR
Test cube
SECAR 28day for
A 8 02/10/18 QC/1321 AUSB PE Mix Selayang Plant precast
REKA parapet
DAN (No.1-No.25)
BINA

Sonic loging
test at bridge
No.2: Point P1
9 04/10/18 QC/1322 AUSB CH 23+750
(Abut-A),
Point P7
(Abut-B)

Pavement
10 04/10/18 QC/1323 AUSB CH 5+790 - CH 5+400 works- FDT
for subbase
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
Inspection for
SUNGA delivery
I material u-
BULOH
11 04/10/18 QC/1324 ASUB CH 19+900 - CH 20+500
drain size
KE 1500x1500
(UTAMA
ASSAM CONCRETE)
JAWA, 380units
KUALA
SELAN FAT for TNB
GOR, Federal Power Sdn. Bhd., Shah Alam,
12 04/10/18 QC/1325 ASUB cable ABC LV
Selangor
SELAN 3Cx185mm2
GOR FDT earth
13 04/10/18 QC/1326 ASUB CH 2+400 - CH 2+800 RHS
filling
SECAR Collect
A 14 04/10/18 QC/1327 ASUB CH 6+500 - CH 7+000 LHS
sample
FDT earth
REKA
15 04/10/18 QC/1328 ASUB CH 9+425 - CH 9+575 LHS
filling
DAN16 04/10/18 QC/1329 ASUB CH 10+200 - CH 10+425 RHS
FDT sand
BINA backfilling
FDT sand
17 04/10/18 QC/1330 ASUB CH 9+900 - CH 10+125 RHS
backfill
FDT sand
18 04/10/18 QC/1331 ASUB CH 10+350 - CH 10+600 LHS
backfill
FDT sand
19 04/10/18 QC/1332 ASUB CH 9+925 - CH 10+050 LHS
backfill
FDT earth
Test cube
20 04/10/18 QC/1333 ASUB CH 4+300 - CH 4+800 RHS
filling
7day for pile
21 10/4/2018 QC/1334 ASUB PE Mix Selayang Plant Test cube
cap (LHS)
7day for
pedestrian
22 10/4/2018 QC/1335 ASUB PE Mix Selayang Plant Test
bored cube
pile
bridgefor
7day No.2
point
Test P11
cube
23 10/4/2018 QC/1336 ASUB PE Mix Selayang Plant precast
(Abut-B)
7day
parapetfor BR2
24 10/4/2018 QC/1337 ASUB PE Mix Selayang Plant bored
G40NS pile
point P9
Mackintosh
(Abut-B)
25 10/5/2018 QC/1338 ASUB CH 0+000 - CH 0+750 LHS
Probe

To carry out
FDT for
26 10/5/2018 QC/1339 ASUB CH 19+181 BS
200mm
subbase layer
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian
FDT test Kerja
sand
FT54 filling
27 10/5/2018 QC/1340 ASUB CH 16+000 - CH 15+450 LHS replacement
DARI FDT
600mm testunder
sand
SUNGA
28 10/5/2018 QC/1341 ASUB CH 16+325 - CH 16+115 LHS laying
subgred below
level
I subgred level
29 QC/1342 ASUB
BULOH
KE
ASSAM Test cube
7day for
JAWA,
30 10/8/2018 QC/1343 ASUB PE Mix Selayang Plant bored pile
KUALA BR2 point P8
SELAN (Abut-B)
GOR,
SELAN
GOR Test cube
SECAR 7day fordeck
A 31 10/8/2018 QC/1344 ASUB PE Mix Selayang Plant slab (1st
penel) Abut-A
REKA Bridge 1
DAN
BINA
Test cube
7day for
32 10/8/2018 QC/1345 ASUB PE Mix Selayang Plant bored pile
BR2 point P10
(Abut-B)
Test cube
7day cube
Test for pile
33 10/8/2018 QC/1346 ASUB PE Mix Selayang Plant cap
28day(RHS)
for
pedestrian
precast
34 10/8/2018 QC/1347 ASUB PE Mix Selayang Plant Bridge No.2
parapet (2nd
cast/No.26 to
Take soil
50 NOS)
35 10/5/2018 QC/1348 ASUB CH 8+700 sample for
test
Test &
witness for
36 10/8/2018 QC/1349 ASUB CH 8+700 double
hydrometer &
pin hole test
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
Mackintosh
SUNGA
Probe- ML3
I 37 10/9/2018 QC/1350 ASUB CH 0+847 RHS, ML4 LHS,
BULOH Jalan Kelab
KE (ML6A) LHS
ASSAM
JAWA,
KUALA Machinery
SELAN testing
38 10/9/2018 QC/1351 ASUB Cheras Quarry
GOR, (Weight &
SELAN pressure test)
GOR
SECAR
A
REKA
Collect sand
DAN sample &
BINA test- filling
for subgrade
(change soil
39 10/9/2018 QC/1352 ASUB CH 15+800 - CH 16+325 LHS to
sand),soaked
CBR test &
test
MDD/OMC
4.5kg

Pavement
works-
Machineries
inspection
40 10/9/2018 QC/1353 ASUB Pulau Indah (Timbang &
pressure)
(Tyre
roller,Tandem
roller)
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
Inspection for
SUNGA delivery
I material u-
BULOH
41 10/10/2018 QC/1354 ASUB CH 19+900 - CH 20+500
drain size
KE 1500x1500
(UTAMA
ASSAM CONCRETE)
JAWA, 30pc
KUALA
SELAN
GOR,
SELAN Inspection for
GOR delivery
material u-
SECAR drain size
A 42 10/10/2018 QC/1355 ASUB CH 19+900 - CH 20+500
1500x1500
REKA (UTAMA
DAN CONCRETE)
30pc
BINA

Inspection for
delivery
material u-
drain size
43 10/10/2018 QC/1356 ASUB CH 19+900 - CH 20+500
1500x1500
(UTAMA
CONCRETE)
30pc

Inspection for
delivery
material u-
drain size
44 10/10/2018 QC/1357 ASUB CH 19+900 - CH 20+500
1500x1500
(UTAMA
CONCRETE)
30pc
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI Test cube
SUNGA 28day for
I 45 pile-plug
10/10/2018 QC/1358 ASUB PE Mix Selayang Plant
(RHS)
BULOH
pedestrian
KE bridge No.2
ASSAM
JAWA,
KUALA
Material
SELAN received
GOR,
46 10/10/2018 QC/1359 ASUB Stor Abadi Ria 240mm cable
SELAN ABC LV (TNB)
GOR 23drums
SECAR
A
REKA
DAN
BINA Material
delivery
arrieved on
47 10/10/2018 QC/1360 ASUB CH 1+650 LHS site- u0drain
1000x1000
(SVC), u-drain
750x750 (SVC)

FDT sand
laying 300mm
FDT
48 10/11/2018 QC/1361 ASUB CH 16+115 - CH 15+340 LHS under
embankment
subgrade
fill suitable
49 10/11/2018 QC/1362 ASUB CH 15+525 - Ch 15+200 LHS levelfor
FDT
material
subgrade
(earth) &
50 10/10/2018 QC/1363 ASUB CH 5+400 - CH 6+000 LHS
subbase 2m
subgred level
fromfor
FDT CL
51 10/11/2018 QC/1364 ASUB CH 5+400 - CH 6+000 LHS Inspection for
roadbase
delivery
material u-
52 10/11/2018 QC/1365 ASUB CH 23+100 - CH 23+300
drain size
600x600 GSG
(119Nos)
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI Test cube
SUNGA 28day for
I 53 bored pile
10/12/2018 QC/1366 ASUB PE Mix Selayang Plant
point P6
BULOH
(Abut-A)
KE Bridge No.2
ASSAM
JAWA,
KUALA Delivery
SELAN material PVD
54 10/11/2018 QC/1367 ASUB CH 2+600 RHS
GOR, Nylex MW310
SELAN 150rolls
GOR
SECAR
A Inspection for
REKA delivery
DAN55 10/4/2018 QC/1368 ASUB CH 23+800 - CH 23+900 material u-
BINA drain size
900x900 GSG

Inspection for
delivery
CH 23+100 - CH 23+300 material u-
drain size
600x600 GSG

Test cube
7day concrete
56 10/12/2018 QC/1369 ASUB CH 19+600 RHS gred 25 JKR
concrete toe
drain
Test cube
7day concrete
gred 25 JKR
57 10/12/2018 QC/1370 ASUB CH 17+720
concrete slab
for sump at
ML12
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA Test cube
I 7day concrete
BULOH gred 25 JKR
concrete
KE58 10/12/2018 QC/1371 ASUB CH 17+720
surround for
ASSAM crossing
JAWA, culvert at
KUALA ML12
SELAN
GOR,
SELAN
GOR Test cube
SECAR 28day
concrete gred
A
25 JKR
REKA
59 10/12/2018 QC/1372 ASUB CH 20+250 RHS
concrete
DAN headwall &
BINA wingwall at
ML15A

Test cube
28day
concrete gred
60 10/12/2018 QC/1373 ASUB CH 20+250 RHS 25 JKR
concrete slab
wingwall at
ML15A
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
Test cube
SUNGA 28day
I concrete gred
BULOH
61 10/12/2018 QC/1374 ASUB CH 20+500
25 JKR
KE concrete
headwall &
ASSAM wingwall at
JAWA, ML16
KUALA Test cube
28day
SELAN concrete gred
62
GOR, 10/12/2018 QC/1375 ASUB CH 23+500 LHS
25 JKR
SELAN concrete
GOR roadside drain
FDT
SECAR embankment
A fill suitable
63 10/15/2018 QC/1376 ASUB CH 15+525 - Ch 15+200 LHS
REKA material
DAN (earth)
subgred level
BINA

FDT subgrade
64 10/16/2018 QC/1377 ASUB CH 18+000 - CH 18+150 RHS
level

Marshall test
65 10/15/2018 QC/1378 ASUB CH 5+400 - CH 5+580 LHS of trial lay
ACBC 28

Test cube
21day for
bored pile
66 10/15/2018 QC/1379 ASUB point P2
(Abut-A)
Bridge No.2
(for MLT test)
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA MLT test
I bored pile
BULOH
67 10/15/2018 QC/1380 ASUB
point P2 at
KE bridge No.2
(MLT working
ASSAM load 1400 KN)
JAWA,
KUALA
SELAN
GOR, FDT test sand
68 10/15/2018 QC/1381 ASUB CH 2+800 - CH 2+950 RHS
backfill
SELAN
GOR Pavement
SECAR
69 10/15/2018 QC/1382 ASUB CH 5+490 - CH 5+580 LHS works -
A Sponge test
REKA
DAN Pavement
BINA
70 10/15/2018 QC/1383 ASUB CH 5+400 - CH 5+480 LHS works - Retest
roadbase

Inspection
delivery
material u-
71 10/16/2018 QC/1384 ASUB CH 19+900 - CH 20+500 drain Utama
Concrete size
1500x1500
30Nos

Material
delivery
72 10/16/2018 QC/1385 ASUB CH 21+300 - CH 22+000
manhole JC9C
8nos
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA Inspection for
I delivery
BULOH material
crossing
KE73 10/17/2018 QC/1386 ASUB
culvert G-cast
ASSAM size 600m
JAWA, (26pcs) &
KUALA 1500m (1pc)
SELAN
GOR,
SELAN
GOR Delivery
SECAR material PVD
74 10/14/2018 QC/1387 ASUB CH 2+500 RHS
Nylex MW310
A 100rolls
REKA
Delivery
DAN material PVD
75
BINA 10/16/2018 QC/1388 ASUB CH 2+500 RHS
Nylex MW310
76 10/17/2018 QC/1389 ASUB CH 5+570 - CH 5+800 LHS 80rolls
FDT roadbase
Coring for
77 10/18/2018 QC/1390 ASUB CH 5+580 - CH 5+490 LHS trial lay
ACB28
Sponge test -
78 10/18/2018 QC/1391 ASUB CH 5+590 - CH 5+800 LHS Collect c/run
prime coat
sample (Road
79 10/18/2018 QC/1392 ASUB CH 19+200 - CH 19+400 BS
base) & test -
sieving
Test cube
28day for
80 10/16/2018 QC/1393 ASUB PE Mix Selayang Plant parapet
(No.51 to 75
Nos)

Test cube
28day for
81 10/16/2018 QC/1394 ASUB PE Mix Selayang Plant bored pile
point P03
(Abutment A)
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA Test cube
I 82 28days bored
10/17/2018 QC/1395 ASUB PE Mix Selayang Plant
pile point P01
BULOH
(Abutment A)
KE
ASSAM
JAWA,
KUALA
Test cube
SELAN 28days for
GOR,
83 10/17/2018 QC/1396 ASUB PE Mix Selayang Plant bored pile
SELAN point P04
GOR (Abutment A)
SECAR
A
REKA
Material
DAN receive - High
BINA
84 10/18/2018 QC/1397 ASUB CH 6+000 strength
woven
geotextile

Pavement
85 10/18/2018 QC/1398 ASUB CH 5+800 - CH 6+000 (LHS) works- FDT
road base

Pavement
works-
86 10/18/2018 QC/1399 ASUB CH 5+580 - CH 5+780 LHS
Marshall test
for ACB28
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA Collect soil
sample & test
I to determine
87
BULOH 10/18/2018 QC/1400 ASUB CH 6+000 - CH 7+000 LHS
MDD/OMC
KE 4.5kg for
ASSAM subgrade
JAWA,
KUALA
SELAN Pavement
88 10/19/2018 QC/1401 ASUB CH 5+400 - CH 5+480 LHS works - Retest
GOR,
FDT
SELAN
GOR
SECAR Pavement
works -
A 89 10/19/2018 QC/1402 ASUB CH 5+400 - CH 5+480 LHS Emution test
REKA SSIK (Prime
DAN coat)
BINA
Pavement
works -
90 10/19/2018 QC/1403 ASUB CH 5+800 - CH 6+000 (LHS)
Emution test
SSIK

Pavement
works -
91 10/19/2018 QC/1404 ASUB CH 5+400 - CH 5+480 LHS
Martial test
AC28

Test cube
7day for
92 10/19/2018 QC/1405 ASUB PE Mix Selayang Plant diaphragmn &
wingwall
(Abutment B)
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
Test cube
SUNGA
28day for
I 93 10/19/2018 QC/1406 ASUB PE Mix Selayang Plant diaphragmn &
BULOH wingwall
KE (Abutment A)
ASSAM
JAWA,
KUALA
Test cube
SELAN 28days for
GOR,
94 10/19/2018 QC/1407 ASUB PE Mix Selayang Plant bored pile
SELAN point P07
GOR (Abutment B)
SECAR
A
REKA
DAN FDT-
BINA Embankment
fill for
transition slab
95 10/15/2018 QC/1408 ASUB CH 19+135
at abutment A
for bridge
No.1 (1st - 9th
layer)

FDT-
Embankment
fill for
transition slab
96 10/19/2018 QC/1409 ASUB CH 19+135
at abutment A
for bridge
No.1 (1st - 9th
layer)
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA To determine
calibrate
I mould
BULOH
97 10/20/2018 QC/1410 ASUB compaction
KE 105mmØ &
ASSAM 152mmØ
JAWA,
KUALA
SELAN Test cube
GOR, 7day for
SELAN
98 10/12/2018 QC/1411 ASUB PE Mix Selayang Plant parapet
GOR No.101 to 125
Nos
SECAR
A
REKA
DAN Test cube
28day for
BINA
99 10/15/2018 QC/1412 ASUB PE Mix Selayang Plant bored pile
point P5
(Abutment-A)

Pavement
100 10/22/2018 QC/1413 ASUB CH 6+000 - CH 6+300 LHS work - FDT
subgrade

Pavement
101 10/22/2018 QC/1414 ASUB CH 5+770 - CH 5+930 LHS work - Martial
test
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
Inspection for
SUNGA delivery
I material u-
BULOH
102 10/22/2018 QC/1415 ASUB CH 19+900 - CH 20+500
drain size
KE 1500x1500m
Utama
ASSAM Concrete
JAWA, (28Nos)
KUALA
SELAN
GOR,
SELAN To carry out
FDT test for
GOR
103 10/22/2018 QC/1416 ASUB CH 19+187.50 - CH 19+450 BS
road base
SECAR layer
A Test cube
REKA 7day for deck
104 10/22/2018 QC/1417 ASUB PE Mix Selayang Plant slab (Panel 2)
DAN & wingwall
BINA (Abutment-B)
Test cube
28day for
105 10/22/2018 QC/1418 ASUB PE Mix Selayang Plant bored pile
point P2
(Abutment A)

Test cube
7day for
106 10/22/2018 QC/1419 ASUB PE Mix Selayang Plant precast
parapet
(No.126 - 150)
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
Test cube
SUNGA
28day for
I 107 10/22/2018 QC/1420 ASUB PE Mix Selayang Plant bored pile
BULOH point P12
KE (Abutment B)
ASSAM
JAWA,
KUALA
SELAN
GOR, Grounting
SELAN cement works
GOR bridge No.2
108 10/23/2018 QC/1421 ASUB CH 23+750 (bored pile)
SECAR P1 (Abutment
A A), P7
REKA (Abutment B)
DAN
BINA

Pavement
109 10/24/2018 QC/1422 ASUB CH 5+480 - CH 5+930 LHS works- Coring
test

To carry out
emulsion
sponge test
110 10/23/2018 QC/1423 ASUB CH 19+187.50 - CH 19+450 LHS
for
bituminous
prime coat

CH 19+187.50 - CH 19+350 RHS


MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA
I To carry out
BULOH joint sampling
KE for asphatic
111 10/23/2018 QC/1424 ASUB CH 19+187.50 - CH 19+450 (LHS & RHS) concrete
ASSAM binder course
JAWA, ACB 28 for
KUALA Marshall test
SELAN
GOR,
SELAN
GOR
SECAR Collect sand
A 112 10/23/2018 QC/1425 ASUB CH 12+000 sample & test
- sieving test
REKA
DAN
BINA Pavement
113 10/24/2018 QC/1426 ASUB CH 6+150 - CH 6+300 LHS works- FDT
subgrade

Delivery
114 10/26/2018 QC/1427 ASUB CH 6+000 woven high
strength

Inspection for
delivery
material u-
115 10/26/2018 QC/1428 ASUB CH 19+900 - CH 20+500 drain size
1500mX1500m
UTAMA
concrete

Ready for
inspection to
116 10/26/2018 QC/1429 ASUB CH 23+450 - CH 23+650
close NCR
No.051
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI Pavement
117 10/26/2018 QC/1430 ASUB CH 6+000 - CH 6+800 LHS works - FDT
SUNGA Test cube
for subbase
I 28day for
pile-cap (LHS)
BULOH
118 10/25/2018 QC/1431 ASUB PE Mix Selayang Plant
pedestrian
KE bridge No.2
ASSAM (PB2)
Test cube
JAWA, 28day for
bored pile
KUALA
119 10/25/2018 QC/1432 ASUB PE Mix Selayang Plant
point P9
SELAN (Abutment B)
GOR, BR2
SELAN
GOR
SECAR Test cube
A 28day for
REKA
120 10/26/2018 QC/1433 ASUB PE Mix Selayang Plant precast
DAN parapet No.76
to No.100
BINA

Test cube
28day for
bored pile
121 10/26/2018 QC/1434 ASUB PE Mix Selayang Plant
point P11
(Abutment B)
BR2

Test cube
28day for
122 10/27/2018 QC/1435 ASUB PE Mix Selayang Plant bored pile
point P8
(Abutment-B)
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI Test cube
SUNGA 7day for
I 123 10/29/2018 QC/1436 ASUB PE Mix Selayang Plant diaphragmn
Pier1 Bridge
BULOH No.1 (BR1)
KE
ASSAM
JAWA,
Test cube
KUALA 28day for
SELAN
124 10/29/2018 QC/1437 ASUB PE Mix Selayang Plant point bored
GOR, pile P10
SELAN (Abutment B)
GOR
SECAR
A Test cube
REKA 28day for
deck slab
DAN
125 10/29/2018 QC/1438 ASUB PE Mix Selayang Plant
(Panel 1)
BINA bridge No.1
(BR1)
To carry out
joint sampling
126 10/25/2018 QC/1439 ASUB CH 15+980 - CH 16+350 & testing for
subgrade
layer (sand)
To carry out
FDT test for
127 10/26/2018 QC/1440 ASUB CH 15+900 - CH 16+350
subgrade
layer (sand)

To carry out
joint sampling
& testing for
128 10/26/2018 QC/1441 ASUB CH 15+900 - CH 16+300
subbase layer
(crushed
aggregate)
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA To carry out
I FDT test for
129
BULOH 10/27/2018 QC/1442 ASUB CH 15+900 - CH 16+300 subbase layer
(crushed
KE aggregate)
ASSAM
JAWA,
KUALA
SELAN
Test cube
GOR, 28day for
SELAN pile-cap (RHS
GOR
130 10/29/2018 QC/1443 ASUB PE Mix Selayang Plant area)
SECAR pedestrian
bridge No.2
A (PB2)
REKA
DAN
BINA Non woven
geotextile -
131 10/29/2018 QC/1444 ASUB CH 6+000
Material
receive

To carry out
core sampling
test for
132 10/29/2018 QC/1445 ASUB CH 19+187.5 - CH 19+450
asphaltic
concrete
binder AC28

Environment (CSK)
Oct-18
1 CSK Murni Sdn Bhd
2 CSK Murni Sdn Bhd
3 CSK Murni Sdn Bhd
4 CSK Murni Sdn Bhd
Drainage Section A (KMN)
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
Oct-18
DARI
SUNGA
I
Inlet & outlet
BULOH structure
KE apron slab
1 10/3/2018 KMN/683 KMN Tech Services CH 11+320 LHS & CH 11+390 LHS
ASSAM installation
JAWA, works ACL54
& ACL55
KUALA
SELAN Inlet & outlet
structure
GOR, head/wing
SELAN
2 10/3/2018 KMN/684 KMN Tech Services CH 11+320 LHS & CH 11+390 LHS wall
GOR installation
SECAR works ACL54
& ACL55
A
Inlet & outlet
REKA structure
DAN concreting
3 10/3/2018 KMN/685 KMN Tech Services CH 11+036 RHS & CH 11+320 LHS
BINA works wall ML
9 & apron slab
ACL54

ML7
construction
works:
formwork
4 10/3/2018 KMN/686 KMN Tech Services CH 3+355 RHS installation,re
bar
installation &
concreting
works
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA
I U-drain
BULOH capping beam
construction:
KE formwork
ASSAM
5 10/3/2018 KMN/687 KMN Tech Services CH 2+500 - CH 3+000 RHS installation,re
JAWA, bar
KUALA installation &
concreting
SELAN works
GOR,
SELAN
GOR
SECAR
A Construction
REKA of earth
DAN scupper drain
6 10/4/2018 KMN/688 KMN Tech Services CH 6+600 - CH 9+000 BS size
BINA 300mmx300m
m from toeML5
Construct
slope
installation
works:
Excavation
7 10/9/2018 KMN/689 KMN Tech Services CH 1+650 LHS works,formwo
rk & rebar
installation,co
ncreting
works
Inlet & outket
structure
installation &
8 10/9/2018 KMN/690 KMN Tech Services CH 12+980 LHS
concreting
works: Apron
slab ACL53

Head/wing
CH 13+070 LHS
wall ACL55
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
Apron slab
DARI CH 13+250 LHS
ACL60
SUNGA
I
BULOH
KE U-drain
ASSAM capping beam
JAWA, construction:
KUALA formwork
9 10/9/2018 KMN/691 KMN Tech Services CH 2+500 - CH 2+300 RHS installation,re
SELAN bar
GOR, installation &
SELAN concreting
GOR works
SECAR
A
REKA
DAN
BINA
Construct ML6
installation
works:
Excavation
10 10/9/2018 KMN/692 KMN Tech Services CH 1+655 RHS works,formwo
rk & rebar
installation,co
ncreting
works

U-drain
750x750
11 10/9/2018 KMN/693 KMN Tech Services CH 1+650 - CH 1+750 LHS
installation
works
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA
I Inlet & outlet
BULOH structure
KE sump
ASSAM construction
works (ML5):
JAWA,
12 10/16/2018 KMN/694 KMN Tech Services CH 1+650 LHS Excavation,fo
KUALA rmwork &
SELAN rebar
GOR, installation,co
ncreting
SELAN works
GOR
SECAR
A
REKA
DAN
BINA
Inlet & outlet
structure
sump
construction
works (ML6):
13 10/16/2018 KMN/695 KMN Tech Services CH 1+655 RHS Excavation,fo
rmwork &
rebar
installation,co
ncreting
works
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA
I Inlet & outlet
BULOH structure
KE sump
ASSAM construction
works (ML7):
JAWA,
14 10/16/2018 KMN/696 KMN Tech Services CH 3+355 RHS Excavation,fo
KUALA rmwork &
SELAN rebar
GOR, installation,co
ncreting
SELAN works
GOR
SECAR
A
REKA
DAN
BINA
U-drain
capping beam
construction:
formwork
15 10/16/2018 KMN/697 KMN Tech Services CH 2+500 - CH 2+800 RHS installation,re
bar
installation &
concreting
works
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA Inelt & outlet
I structure
BULOH head/wing
CH 12+980 (LHS),CH 13+170 (LHS) CH wall
KE16 10/18/2018 KMN/698 KMN Tech Services
12+670 (RHS) installation
ASSAM works
JAWA, ACL53,ACL57,
KUALA ACR69
SELAN
GOR,
SELAN
GOR
SECAR Inelt & outlet
A structure
head/wing
REKA
17 10/18/2018 KMN/699 KMN Tech Services CH 12+980 (LHS), CH 13+170 (LHS) wall
DAN concreting
BINA works
ACL53,ACL57

U-drain
capping beam
construction:
formwork
18 10/18/2018 KMN/700 KMN Tech Services CH 2+500 - CH 2+700 RHS installation,re
bar
installation &
concreting
works
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA
I Inlet & outlet
structure
BULOH sump
KE CH 1+650 (LHS),CH 16+55 (RHS), CH construction
19 10/18/2018 KMN/701 KMN Tech Services
ASSAM 3+355 (RHS) installation
JAWA, works:
ML5,ML6 &
KUALA ML7
SELAN
GOR,
SELAN
GOR
SECAR
A
REKA Inlet & outlet
DAN median drain
BINA M5
installation
works:
Excavation
20 10/20/2018 KMN/702 KMN Tech Services CH 7+400 LHS
works, rebar
& formwork
installation
work,
concreting
works
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA Inlet & outlet
I structure
BULOH sump
installation
KE21 10/20/2018 KMN/703 KMN Tech Services CH 3+355 RHS
works ML7 -
ASSAM rebar
JAWA, installation
KUALA works
SELAN
GOR,
SELAN
GOR
SECAR
A Inlet & outlet
structure
REKA head/wing
DAN wall
22 10/20/2018 KMN/704 KMN Tech Services CH 13+170 LHS, CH 12+670 RHS
BINA installation &
concreting
works ACL57,
ACR69

23 KMN Tech Services


24 KMN Tech Services
25 KMN Tech Services
26 KMN Tech Services
27 KMN Tech Services
28 KMN Tech Services

29 KMN Tech Services

30 KMN Tech Services

31 KMN Tech Services


MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
32 KMN Tech Services
DARI
33 KMN Tech Services
SUNGA
I 34 KMN Tech Services
BULOH
35 KMN Tech Services
KE
ASSAM
36 KMN Tech Services
JAWA,
KUALA
37 KMN Tech Services
SELAN
38
GOR, KMN Tech Services
SELAN
39 KMN Tech Services
GOR
SECAR
Drainage - Section B (PHL)
A
REKA
Oct-18 Install rebar &
DAN formwork for
1 10/1/2018 PHL/335 PHL Suria CH 17+720 slab sump at
BINA ML12-
2 10/1/2018 PHL/336 PHL Suria CH 18+100 - CH 18+200 RHS Concrete
Install
concreteBRCwork
A6 f
work
& concrete
3 10/1/2018 PHL/337 PHL Suria CH 19+900 - CH 19+000 RHS Install BRC A6
work for
& concrete
bench drain
4 10/1/2018 PHL/338 PHL Suria CH 19+600 - CH 19+900 LHS
work for toe
5 10/1/2018 PHL/339 PHL Suria CH 20+250 LHS drain
Install rebar

Lay crusher
run & install
rebar &
6 10/3/2018 PHL/340 PHL Suria CH 20+500 LHS formwork for
slab wingwall
at ML16-
concrete work

Install rebar &


formwork for
7 10/3/2018 PHL/341 PHL Suria CH 12+271 RHS
sump ML12-
conrete work
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA Install BRC A6
I & concrete
BULOH work for
cascading
KE 8 10/3/2018 PHL/342 PHL Suria CH 18+100 - CH 18+200
interceptor
ASSAM drain-
JAWA, Excavation
KUALA work
SELAN Excavate
GOR, work for
bench
SELAN
9 10/3/2018 PHL/343 PHL Suria CH 18+900 - CH 19+000 RHS
drain,Install
GOR BRC A6 &
SECAR concrete work
A Excavate
REKA work for toe
DAN10 10/3/2018 PHL/344 PHL Suria CH 19+600 - CH 19+900 LHS drain, Install
BRC A6 &
BINA concrete work

Concrete
work for
11 10/3/2018 PHL/345 PHL Suria CH 20+250 headwall &
wingwall at
ML15A
Excavate
work & lay
12 10/4/2018 PHL/346 PHL Suria CH 23+800 - CH 23+900 crusher run
for u-drain &
install u-drain

Install rebar &


formwork for
sump at
13 10/4/2018 PHL/347 PHL Suria CH 17+720
ML12-
Concrete
work
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA Excavate
I work & lay
crusher run
BULOH
14 10/4/2018 PHL/348 PHL Suria CH 19+900 - CH 20+500 RHS for u-drain
KE size
ASSAM 1500x1500 &
JAWA, install u-drain
KUALA
Install rebar &
SELAN formwork slab
15
GOR, 10/8/2018 PHL/349 PHL Suria CH 20+500 LHS
wingwall at
SELAN
16 10/8/2018 PHL/350 PHL Suria CH 17+720 ML16
Install rebar
GOR17 10/8/2018 PHL/351 PHL Suria CH 18+100 - CH 18+200 RHS Concrete work
SECAR
A
REKA Excavate
DAN work for toe
18
BINA 10/8/2018 PHL/352 PHL Suria CH 19+600 - CH 19+900 drain, Install
BRC A6 &
concrete work

Concrete
work for
19 10/8/2018 PHL/353 PHL Suria CH 20+250 LHS headwall &
wingwall at
ML15A

Excavate
work for u-
20 10/8/2018 PHL/354 PHL Suria CH 23+800 - CH 23+900 drain & lay
crusher run,
Install U-drain
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA Excavate
I work for toe
BULOH
21 10/8/2018 PHL/355 PHL Suria CH 19+200 - CH 19+300
drain, Install
KE BRC A6 &
concrete work
ASSAM for toe drain
JAWA,
KUALA Excavate
work & lay
SELAN crusher run
22
GOR, 10/10/2018 PHL/356 PHL Suria CH 18+350
for median
SELAN culvert at
GOR MM22
Install
SECAR formwork &
BRC A6 for
A median
REKA culvert at
DAN MM22
BINA

Excavate
work & lay
crusher run
23 10/10/2018 PHL/357 PHL Suria CH 19+080
for median
culvert at
MM24

Install
formwork &
BRC A6 for
slab
Excavate
24 10/11/2018 PHL/358 PHL Suria CH 19+200 - CH 19+300 work for toe
drain

Install BRC A6
& concrete
work for toe
drain
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI Excavate
25 10/11/2018 PHL/359 PHL Suria CH 19+600 - CH 19+700 work for toe
SUNGA drain
I
BULOH
KE Install BRC A6
ASSAM & formwork
work for toe
JAWA, drain
KUALA
SELAN
26 10/11/2018 PHL/360 PHL Suria CH 19+900 - CH 20+500 Excavate work &
GOR,
SELAN Install u-drain
GOR27 10/11/2018 PHL/361 PHL Suria CH 23+800 - CH 23+900 LHS Excavate work &
SECAR Install u-drain
A 28 10/11/2018 PHL/362 PHL Suria CH 23+500 Concrete work
REKA
DAN Excavate
BINA work & lay
crusher run
29 10/11/2018 PHL/363 PHL Suria CH 23+370
for crossing
culvert at
ML23

Install BRC A6
& formwork
slab for
crossing
culvert at
ML23

30 PHL/364 PHL Suria


MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA Excavate
work & lay
I crusher run
31
BULOH 10/15/2018 PHL/365 PHL Suria CH 18+400
for median
KE crossing
ASSAM culvert at M22
JAWA,
KUALA
SELAN Install BRC A6
GOR, & concrete
SELAN work at M22
GOR
SECAR
A
Excavate
REKA work & lay
DAN crusher run
32 10/15/2018 PHL/366 PHL Suria CH 19+100
BINA for median
crossing
culvert at M24

Install BRC A6
& concrete
slab at M24

Excavate
work & install
BRC A6 for
33 10/15/2018 PHL/367 PHL Suria CH 19+200 - CH 19+300 RHS toe drain,
Concrete
work for toe
drain

Concrete
work & Install
34 10/15/2018 PHL/368 PHL Suria CH 19+600 - CH 19+900 LHS
BRC A6 for
toe drain
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA Excavated
I work & lay
crusher run
BULOH
35 10/15/2018 PHL/369 PHL Suria CH 19+900 - CH 20+500 for u-drain,
KE Install u-drain
ASSAM size
JAWA, 1500x1500mm
KUALA
SELAN
GOR,
SELAN Excavated
work & lay
GOR crusher run
SECAR
36 10/15/2018 PHL/370 PHL Suria CH 23+100 - CH 23+300 for u-drain,
A Install u-drain
REKA size
600x600mm
DAN
BINA
37 10/15/2018 PHL/371 PHL Suria CH 23+370 Excavate work &

Excavate
work & lay
crsuher run
38 10/15/2018 PHL/372 PHL Suria CH 23+800 - CH 23+900
for u-drain,
Install u-drain
size 900x900

Install culvert
39 10/15/2018 PHL/373 PHL Suria CH 23+500 LHS size 600mm
Repair & concre
for median
crossing
40 10/17/2018 PHL/374 PHL Suria CH 18+400
culvert at
M22, Install
formwork &
BRC A6
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA
Install culvert
I size 600mm
BULOH for median
KE crossing
ASSAM culvert at
41 10/17/2018 PHL/375 PHL Suria CH 19+100
M24, Install
JAWA, formwork &
KUALA BRC A6,
SELAN Concrete
GOR, surround
SELAN
GOR
SECAR
A
REKA Excavate
DAN work for toe
BINA drain, Install
42 10/18/2018 PHL/376 PHL Suria CH 19+200 - CH 19+300 RHS
BRC A6 &
concrete work
for toe drain

43 10/18/2018 PHL/377 PHL Suria CH 19+600 - CH 19+900 LHS Install BRC A6

Excavate
work & lay
crusher run
44 10/18/2018 PHL/378 PHL Suria CH 19+900 - CH 20+500 RHS for u-drain,
Install u-drain
size
1500mx1500m
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI Excavate
SUNGA work & lay
I crusher run
45
BULOH 10/18/2018 PHL/379 PHL Suria CH 23+100 - CH 23+300 LHS for u-drain,
Install u-drain
KE size
ASSAM 600mx600m
JAWA,
KUALA
46 10/18/2018 PHL/380 PHL Suria CH 23+370 Excavate work &
SELAN
GOR, Install BRC A6
SELAN
47 10/18/2018 PHL/381 PHL Suria CH 21+740 RHS Backfilling wor
GOR48 10/18/2018 PHL/382 PHL Suria CH 23+500 - CH 23+600 Hacking & concr
SECAR
49 10/20/2018 PHL/383 PHL Suria CH 22+045 RHS Backfilling wor
A
REKA
DAN
BINA
Install
formwork &
Install BRC A6
for median
crossing
culvert at
50 10/20/2018 PHL/384 PHL Suria CH 18+400 M22,
Concrete
work for
median
crossing
culvert at M22
& backfilling
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA
I Install culvert
BULOH size 600mm
KE for median
ASSAM crossing
culvert at
JAWA,
M24,Install
KUALA formwork &
SELAN
51 10/20/2018 PHL/385 PHL Suria Ch 19+100 BRC A6,
GOR, Concrete
SELAN work for
median
GOR crossing
SECAR culvert at
A M24,
REKA Backfilling
DAN
BINA

Excavate
work for toe
52 10/22/2018 PHL/386 PHL Suria CH 19+200 - CH 19+300 RHS drain, Install
BRCA6 &
concrete work

Excavate
work & lay
crusher run
53 10/22/2018 PHL/387 PHL Suria CH 19+900 - CH 20+500 for u-drain,
Install u-drain
size
1500x1500
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA Excavate
work & lay
I crusher run
54
BULOH 10/22/2018 PHL/388 PHL Suria CH 23+100 - CH 23+300
for u-drain,
KE Install u-drain
ASSAM size 600x600
JAWA,
KUALA
Backfilling at
SELAN
55 10/22/2018 PHL/389 PHL Suria CH 21+740
ML19
GOR,
SELAN
Lay crusher
GOR run ,Install
SECAR
56 10/22/2018 PHL/390 PHL Suria CH 23+390 formwork &
A install BRC A6
REKA at ML23
DAN
BINA
Concrete
work for
57 10/22/2018 PHL/391 PHL Suria CH 23+500 - CH 23+600
roadside drain
(repair)

Install culvert
size 600mm
58 10/24/2018 PHL/392 PHL Suria CH 19+900 for median
crossing
culvert at M24
Install BRC A6
& formwork,
Concrete
work for
concrete
surround
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
Backfilling for
SUNGA median
I 59 10/24/2018 PHL/393 PHL Suria CH 18+400
crossing
BULOH culvert at M22
KE
ASSAM
JAWA, Backfilling for
crossing
KUALA
60 10/24/2018 PHL/394 PHL Suria CH 22+050
culvert at
SELAN ML20
GOR,
SELAN
GOR
SECAR Excavate
work for toe
A 61 10/25/2018 PHL/395 PHL Suria CH 19+200 - CH 19+300 RHS drain, Install
REKA BRC A6 &
DAN concrete work
BINA

Excavate
work for u-
62 10/25/2018 PHL/396 PHL Suria CH 19+900 - CH 20+500 drain, Install
u-drain size
1500x1500

Excavate
work for u-
63 10/25/2018 PHL/397 PHL Suria CH 23+100 - CH 23+300 drain, Install
u-drain size
600x600
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA Install
I formwork &
BULOH BRC A6 for
KE crossing
64 10/25/2018 PHL/398 PHL Suria CH 23+090 culvert at
ASSAM ML23,
JAWA, Concrete
KUALA work for
SELAN concrete slab
GOR,
SELAN
GOR
Backfilling for
SECAR crossing
A 65 10/25/2018 PHL/399 PHL Suria CH 21+740
culvert at
REKA ML19
DAN
BINA Backfilling for
crossing
66 10/27/2018 PHL/400 PHL Suria CH 22+050
culvert at
ML20

Excavation
work & lay
crusher run
for medium
67 10/27/2018 PHL/401 PHL Suria crossing
culvert at
M27, Install
BRC A6 &
concrete work
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
Backfilling for
SUNGA median
I 68 10/27/2018 PHL/402 PHL Suria CH 10+100
crossing
BULOH culvert at M24
KE
ASSAM
SYABAS Work (BWSB)
JAWA,
Oct-18
KUALA
1 10/1/2018 BWSB/333 Bina Water Sdn Bhd CH 15+200 - CH 15+700 Connection pi
SELAN
2
GOR, 10/1/2018 BWSB/334 Bina Water Sdn Bhd CH 15+200 Standby connec
SELAN
3 10/4/2018 BWSB/335 Bina Water Sdn Bhd CH 21+800 - CH 21+900 Excavated & la
GOR4 10/5/2018 BWSB/336 Bina Water Sdn Bhd CH 15+200 Standby connec
SECAR
5 10/11/2018 BWSB/337 Bina Water Sdn Bhd CH 0+000 - Ch 1+000 Remove existin
A 6 10/13/2018 BWSB/338 Bina Water Sdn Bhd CH 10+000 - CH 10+100 Excavated & la
REKA
7 10/15/2018 BWSB/339 Bina Water Sdn Bhd CH 10+000 Standby connec
DAN
8
BINA 10/15/2018 BWSB/340 Bina Water Sdn Bhd CH 10+000 Connection nig
10 10/15/2018 BWSB/341 Bina Water Sdn Bhd CH 1+000 - CH 2+000 Remove existin
11 10/22/2018 BWSB/342 Bina Water Sdn Bhd CH 1+000 - CH 1+500 Remove existin
12 10/23/2018 BWSB/343 Bina Water Sdn Bhd CH 21+000 - CH 22+000 Connection pi
13 Bina Water Sdn Bhd
14 Bina Water Sdn Bhd
15 Bina Water Sdn Bhd
16 Bina Water Sdn Bhd
17 Bina Water Sdn Bhd

18 Bina Water Sdn Bhd


19 Bina Water Sdn Bhd
TNB Work (ARSB)
Oct-18 Open tren &
lay cable
1 06/10/18 ARSB/212 Abadi Ria Sdn Bhd CH 1+600 Open tren &
185mm
lay cableTNB
LV(U/G)
CH 2+000
185mm
LV(U/G) TNB
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
Kerja-kerja
FT54 overhead by
2 06/10/18 ARSB/213 Abadi Ria Sdn Bhd CH 12+200 - CH 12+350 RHS
DARI short line ABC
Tanam
cable stuck
SUNGA CH 11+500
pole
Lay U/G cable
I 3 10/10/18 ARSB/214 Abadi Ria Sdn Bhd CH 3+000 300mm LV
BULOH TNB
KE
ASSAM Lay overhead
4
JAWA, 10/10/18 ARSB/215 Abadi Ria Sdn Bhd CH 12+300 RHS cable 240mm
HT TNB
KUALA
SELAN
GOR,
SELAN Shutdown &
GOR termination
5 10/10/18 ARSB/216 Abadi Ria Sdn Bhd CH 0+000
SECAR cable 240mm
A HT TNB
REKA
DAN
BINA Rectify
185mm U/G
6 12/10/18 ARSB/217 Abadi Ria Sdn Bhd CH 6+400
LV TNB cable
crossing

Shutdown &
termination
240mm cable
HT TNB P/E
Assam Jawa
7 12/10/18 ARSB/218 Abadi Ria Sdn Bhd Assam Jawa - Ladang Kuala Selangor to Taman
Mulia & P/E
Taman Belibis
to P/E Ladang
Kuala
Selangor
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
Shutdown
SUNGA
240mm
I 8 15/10/18 ARSB/219 Abadi Ria Sdn Bhd Taman Belibis
BULOH to PPV CB12
KE termination
Termination
ASSAM cable 185mm
JAWA, overhead,ter
9
KUALA 22/10/18 ARSB/220 Abadi Ria Sdn Bhd CH 0+000 - CH 3+000 mination
cable 300mm
SELAN overhead LV
GOR, Lay cable
(TNB)
SELAN 240mm HT
10 22/10/18 ARSB/221 Abadi Ria Sdn Bhd CH 10+900
(TNB) (P/E to
GOR Tiang)
SECAR
A
REKA Lay cable
DAN CH 12+400 Kilang besi
cable 240mm
BINA

Shutdown &
termination
11 29/10/18 ARSB/222 Abadi Ria Sdn Bhd CH 10+900 - CH 12+400 RHS
240mm HT
cable (TNB)

Utilities : Telekom (SNB)

Oct-18

Pulling cable
1 10/2/2018 NBSB/182 Syarikat Niaga Bumidan CH 1+800 - CH 2+300
cooper

Transfer cable
cooper

Recover cable
cooper

Transfer fibre
2 10/8/2018 NBSB/183 Syarikat Niaga Bumidan
cable F2
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI Recover fibre
SUNGA cable exefuse
I
BULOH Recover pole
KE exefuse
ASSAM
JAWA,
3 10/15/2018 NBSB/184 Syarikat Niaga Bumidan CH 21+000 - CH 22+000
Install
KUALA manhole JC9C
SELAN
GOR, CH 21+000 - CH 22+000 Lay PVC pipe
Lay PVC pipe
SELAN
4 10/22/2018 NBSB/185 Syarikat Niaga Bumidan CH 21+000 - CH 24+000
100mm
GOR CH 21+000 - CH 24+000
Lay PVC pipe
SECAR 110mm
CH 21+000 - CH 24+000 Test ducting
A
REKA CH 21+000 - CH 22+000 Verify cabinet
DAN Lay PVC pipe
5 10/18/2018 NBSB/186 Syarikat Niaga Bumidan CH 21+000 - CH 24+000
100mm
BINA Lay PVC pipe
CH 21+000 - CH 24+000
110mm
Lay PVC pipe
6 10/25/2015 NBSB/187 Syarikat Niaga Bumidan CH 21+000 - CH 24+000
100mm
Recover FOC
CH 0+000 - CH 23+000
& pole
Utilities : Maxis (FSB/M)
Oct-18
Install pole &
1 10/16/2018 FSB/110 Fibertell CH 22+000 - CH 23+400 RHS lay cable FOC
Maxis
Remove
CH 16+500 - CH 17+500 LHS
existing pole

Utilities : Gas Malaysia (AIT)


Oct-18

1 AI TOTAL

2 AI TOTAL

3 AI TOTAL
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT544 AI TOTAL
DARI
Bridge
SUNGA (PML)
I Oct-18
BULOH
KE
ASSAM
JAWA,
Inspection of
KUALA reinforcement
SELAN rebar &
GOR, formwork for
1
SELAN 10/1/2018 PML/264 Pembinaa Melima CH 19+135 1st panel slab
abutment A to
GOR Pier1 (7.0m
SECAR long) before
A concreting
REKA
DAN
BINA Casting 1st
panel deck
2 10/1/2018 PML/265 Pembinaa Melima CH 19+135
slab at bridge
No.1

Inspection of
reinforcement
& formwork
pile-cap (RHS)
3 10/1/2018 PML/266 Pembinaa Melima CH 11+787.600
pedestrian
bridge No.2
before
concreting

Casting pile-
cap (RHS)
4 10/1/2018 PML/267 Pembinaa Melima CH 11+787.600
pedestrian
bridge No.2
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA
I Ø600mm
BULOH bored pile
KE works at
ASSAM bridge No.2:
Boring into
JAWA, soil, curing
KUALA into
5 10/4/2018 PML/268 Pembinaa Melima CH 23+750
SELAN soil,install
GOR, steel
cage,concreti
SELAN ng
GOR G40T2(s),testi
SECAR ng works &
A survey works
REKA
DAN
BINA

Bridge No.1
works for:
Install rebar
wingwall
(Abut-
B),install
rebar
6 10/4/2018 PML/269 Pembinaa Melima CH 19+135 diaphragmn
(Abut-
B),Install
rebar deck
slab (Abut-B)
& dismantle
formwork
(Abut-A)
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
Backfill works
SUNGA
& install rebar
I 7 10/4/2018 PML/270 Pembinaa Melima CH 11+787.600 column at
BULOH pedestrian
KE bridge No.2
ASSAM
Launching
JAWA,
8 PML/271 Pembinaa Melima span 2 (P1-P2)
KUALA BM2.1 to
9 10/10/2018 PML/272 Pembinaa Melima CH 19+135
SELAN BM2.11(11
GOR, NOS) at
Bridge No.1
SELAN
GOR Inspection of
SECAR reinforcement
A rebar
REKA diaphragmn,w
ingwall &
DAN10 10/10/2018 PML/273 Pembinaa Melima CH 19+135 deck slab
BINA (6.700m) at
Abutment B
for bridge
No.1 before
concreting

Concreting
diaphragmn &
11 10/11/2018 PML/274 Pembinaa Melima CH 19+135 wingwall
(Abut-B) at
Bridge No.1
Concreting
deck slab
12 10/15/2018 PML/275 Pembinaa Melima CH 19+135 (Abut-B) at
Bridge No.1
Casting
(Panel 2)
precast
parapet at
13 10/16/2018 PML/276 Pembinaa Melima CH 19+135 Embankment
site office
fill works
melima for
Ijok
14 10/15/2018 PML/277 Pembinaa Melima CH 19+135 transition
No. 126+ slab
at Abutment
150Nos
A
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA Inspection of
I reinforcement
BULOH rebar &
KE formwork
15 10/19/2018 PML/278 Pembinaa Melima CH 19+135 diaphragmn
ASSAM at Pier1
JAWA, before
KUALA concreting
SELAN (Bridge 1)
GOR,
SELAN
GOR
Casting
SECAR diaphragmn
A 16 10/19/2018 PML/279 Pembinaa Melima CH 19+135
Pier 1 at
REKA bridge No.1
DAN
BINA
Inspection of
reinforcement
rebar
17 10/23/2018 PML/280 Pembinaa Melima CH 19+135
diaphragmn
at Pier 2
Bridge No.1
Excavation
works pile-
18 10/24/2018 PML/281 Pembinaa Melima CH 13+793 cap at
pedestrian
bridge No.1
Preparation
rebar column
19 10/24/2018 PML/282 Pembinaa Melima CH 13+793 & formwork
pedestrian
bridge No.2
Inspection of
reinforcement
rebar &
formwork
20 10/24/2018 PML/283 Pembinaa Melima CH 19+135
approach slab
at Abutment
A & B for
bridge No.1
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
Casting
SUNGA
approach slab
I 21 10/25/2018 PML/284 Pembinaa Melima CH 19+135 Abutment A &
BULOH B for bridge
KE No.1
ASSAM
JAWA,
KUALA Concreting
diaphragmn
SELAN
22 10/25/2018 PML/285 Pembinaa Melima CH 19+135
Pier 2 at
GOR, Bridge No.1
SELAN
GOR
SECAR
A
REKA Inspection of
DAN reinforcement
& formwork
BINA column P3
23 10/26/2018 PML/286 Pembinaa Melima CH 11+787.00
(LHS) & P4,P5
(RHS) for
pedestrian
bridge No.2

Casting half
column
pedestrian
24 10/26/2018 PML/287 Pembinaa Melima CH 11+787.600 bridge No.2
for P3 (LHS
area) & P4,P5
(RHS area)
Installation
formwork &
25 10/27/2018 PML/288 Pembinaa Melima CH 11+787.600 rebar column
at pedestrian
bridge No.2
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
Excavation
SUNGA
pile-cap & cut
I 26 10/27/2018 PML/289 Pembinaa Melima CH 13+793 off pile at
BULOH pedestrian
KE bridge No.1
ASSAM
JAWA,
KUALA
27 Pembinaa Melima
SELAN
GOR,
28 Pembinaa Melima
SELAN
GOR
29
SECAR Pembinaa Melima
A
30 Pembinaa Melima
REKA
DAN31 Pembinaa Melima
BINA
32 Pembinaa Melima
Geotextile (MTS)
Oct-18

Installation of
1 10/3/2018 MTS/143 MTS Fibromat CH 5+235 - CH 5+375 LHS
PVD
Lay &
stitching
2 10/11/2018 MTS/144 MTS Fibromat CH 15+340 - CH 16+135 LHS
woven high
3 MTS/145 MTS Fibromat strength

4 10/11/2018 MTS/146 MTS Fibromat CH 10+600 - CH 11+000 LHS Lay & stitching
5 10/11/2018 MTS/147 MTS Fibromat CH 2+450 - Ch 2+600 RHS Installation of
6 10/15/2018 MTS/148 MTS Fibromat CH 2+600 - CH 2+700 RHS Installation of
7 10/12/2018 MTS/149 MTS Fibromat CH 12+000 - CH 12+230 Lay & stitching
8 10/17/2018 MTS/150 MTS Fibromat CH 2+625 - CH 2+700 RHS Installation of
9 10/18/2018 MTS/151 MTS Fibromat CH 2+770 - CH 2+900 RHS Installation of
10 10/18/2018 MTS/152 MTS Fibromat CH 4+875 - CH 5+375 Lay & stitching
11 10/22/2018 MTS/153 MTS Fibromat CH 0+320 - CH 0+750 Lay & stitching
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
12 10/24/2018 MTS/154 MTS Fibromat CH 2+500 - CH 2+700 LHS Geotextile inst
DARI
13 10/26/2018 MTS/155 MTS Fibromat CH 15+655 - CH 15+450 LHS Lay & stitching
SUNGA
14 10/27/2018 MTS/156 MTS Fibromat CH 2+450 - CH 2+900 RHS Lay & stitching
I
BULOH
Traffic Management (PT)
KEOct-18
ASSAM
1 Pakatan Trafik Sdn Bhd
JAWA,
KUALA
2 Pakatan Trafik Sdn Bhd
SELAN
3 Pakatan Trafik Sdn Bhd
GOR,
4 Pakatan Trafik Sdn Bhd
SELAN
GOR 5 Pakatan Trafik Sdn Bhd
SECAR
6 Pakatan Trafik Sdn Bhd
A
REKA7 Pakatan Trafik Sdn Bhd
DAN 8 Pakatan Trafik Sdn Bhd
BINA
9 Pakatan Trafik Sdn Bhd

10 Pakatan Trafik Sdn Bhd

11 Pakatan Trafik Sdn Bhd

12 Pakatan Trafik Sdn Bhd


13 Pakatan Trafik Sdn Bhd
Road Marking (LZ)
Oct-18
Milling
1 10/2/2018 LZ/024 LZ Teraju CH 5+400 - CH 6+000 LHS existing
Laying of
pavement
subbase to
CH 5+680 - CH 5+400 LHS
formation
Painting new
2 LZ Teraju level
temporary
road marking,
3 10/6/2018 LZ/026 LZ Teraju CH 13+500 - CH 10+000 BS
remove
Pavement
4 10/8/2018 LZ/027 LZ Teraju CH 5+400 - CH 5+800 LHS existingLaying
works- road
marking
of roadbase
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI Excavate
CH 5+400 - CH 5+800 LHS subgrade 2m
SUNGA for CL
I
BULOH Milling
KE CH 6+000 - CH 6+300 LHS existing
ASSAM premix
JAWA,
KUALA Premix
SELAN remove
5 10/11/2018 LZ/028 LZ Teraju CH 5+800 - CH 6+000 LHS roadkerb,Layi
GOR,
ng of
SELAN roadbase
GOR
SECAR
A
REKA
DAN Excavate
subgrade,layi
BINA ng of subbase
CH 5+800 - CH 6+000 LHS
& laying of
roadbase 2m
for CL

Milling
CH 6+300 - CH 6+600 LHS existing
premix
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
SUNGA
I Pavement
BULOH works - Joint
dipping,grandi
KE ng roadbase
ASSAM
6 10/15/2018 LZ/029 LZ Teraju CH 5+400 - CH 6+500 LHS to
JAWA, formation,spr
KUALA ay SSIK to
receive BC28
SELAN & Trial lay
GOR,
SELAN
GOR
SECAR
A Lay 200mm
REKA crusher run
7 10/15/2018 LZ/030 LZ Teraju CH 19+187.50 - CH 19+450
DAN for roadbase
layer
BINA

CH 19+187.50 - CH 19+335 RHS


Spray prime
8 10/15/2018 LZ/031 LZ Teraju CH 5+490 - CH 5+580 LHS
coat

Trial lay ACBC


9 10/15/2018 LZ/032 LZ Teraju CH 5+490 - CH 5+580 LHS
28
10 LZ/033 LZ Teraju
Coring test
11 10/17/2018 LZ/034 LZ Teraju CH 5+580 - CH 5+490
for trial lay

CH 5+590 - CH 5+800 LHS Joint dipping

CH 5+590 - CH 5+000 LHS Spray SSIT

Pavement
12 10/19/2018 LZ/035 LZ Teraju CH 5+570 works- Laying
AC28
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI Joint dipping
SUNGA CH 5+400 - CH 5+480 LHS & spray prime
I coat
BULOH
KE CH 5+400 - CH 5+480 LHS Laying AC28
ASSAM CH 6+000 - CH 6+200 LHS Subgrade
JAWA,
13 10/20/2018 LZ/036 LZ Teraju CH 5+770 - CH 5+930 LHS Laying AC28
KUALA
Laying
SELAN CH 6+000 - CH 6+300 LHS
subbase
GOR,
SELAN CH 6+000 - CH 6+300 LHS Joint dipping
GOR
SECAR
Pavement
A 14 10/24/2018 LZ/037 LZ Teraju CH 6+140 - CH 6+500 LHS works -
REKA Subgrade
DAN
BINA Laying of
CH 6+000 - CH 6+140 LHS
subbase

CH 6+140 - CH 6+500 LHS Joint dipping

Instrumentation (YC)
Oct-18

CH4900 RHS,CH5200 RHS,CH6625


1 10/6/2018 YC/186 Yeyeh Cons RHS,CH6625 LHS,CH8100 LHS,CH8700 Take reading fo
LHS

CH6250 RHS,6425 RHS,6625 RHS,6625


LHS,6800 RHS,6800 LHS,6850 RHS,
6925 RHS, 6975 RHS,7025 RHS,7200
2 10/6/2018 YC/187 Yeyeh Cons RHS,7400 RHS,7500 RHS,7600 RHS, Take reading f
7700 RHS,7800 RHS,7875 RHS,8450
LHS,8525 LHS,8700 LHS,9100 LHS,9150
RHS,9175 LHS
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI
CH3775 RHS,3900 RHS,4025 RHS,4100
SUNGA RHS,4325 RHS,4475 RHS,4575 RHS,
I 3 10/6/2018 YC/188 Yeyeh Cons
4725 RHS,4825 RHS,4900 RHS,4925
Take reading f
BULOH RHS,5100 RHS,5350 RHS
KE
ASSAM
JAWA,
KUALA
SELAN
4 10/6/2018 YC/189 Yeyeh Cons CH8450 LHS,CH8525 LHS,CH8700 LHS Take reading f
GOR,
SELAN
GOR
SECAR
A
REKA
CH4900 RHS,CH5200 RHS,CH6625
DAN5 10/13/2018 YC/190 Yeyeh Cons RHS,CH6625 LHS,CH8100 LHS,CH8700 Take reading fo
BINA LHS

CH6250 RHS,6425 RHS,6625 RHS,6625


LHS,6800 RHS,6800 LHS,6850 RHS,
6925 RHS, 6975 RHS,7025 RHS,7200
6 10/13/2018 YC/191 Yeyeh Cons RHS,7400 RHS,7500 RHS,7600 RHS, Take reading f
7700 RHS,7800 RHS,7875 RHS,8450
LHS,8525 LHS,8700 LHS,9100 LHS,9150
RHS,9175 LHS

CH3775 RHS,3900 RHS,4025 RHS,4100


RHS,4325 RHS,4475 RHS,4575 RHS,
7 10/13/2018 YC/192 Yeyeh Cons Take reading f
4725 RHS,4825 RHS,4900 RHS,4925
RHS,5100 RHS,5350 RHS

8 10/13/2018 YC/193 Yeyeh Cons CH8450 LHS,CH8525 LHS,CH8700 LHS Take reading f
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
DARI CH4900 RHS,CH5200 RHS,CH6625
9 10/20/2018 YC/194 Yeyeh Cons RHS,CH6625 LHS,CH8100 LHS,CH8700 Take reading fo
SUNGA LHS
I
BULOH
KE CH6425 RHS,6625 RHS,6625 LHS,6800
ASSAM RHS,6800 LHS,6850 RHS, 6925 RHS,
6975 RHS,7025 RHS,7200 RHS,7400
JAWA,
10 10/20/2018 YC/195 Yeyeh Cons RHS,7500 RHS,7600 RHS, 7700 Take reading f
KUALA RHS,7800 RHS,7875 RHS,8450 LHS,8525
SELAN LHS,8700 LHS,9100 LHS,9150 RHS,9175
GOR, LHS
SELAN
GOR
SECAR CH3775 RHS,3900 RHS,4025 RHS,4100
A 11 10/20/2018 YC/196 Yeyeh Cons
RHS,4325 RHS,4475 RHS,4575 RHS,
Take reading f
REKA 4725 RHS,4825 RHS,4900 RHS,4925
RHS,5100 RHS,5350 RHS
DAN
BINA
12 10/20/2018 YC/197 Yeyeh Cons CH8450 LHS,CH8525 LHS,CH8700 LHS Take reading f

CH4900 RHS,CH5200 RHS,CH6625


13 10/27/2018 YC/198 Yeyeh Cons RHS,CH6625 LHS,CH8100 LHS,CH8700 Take reading fo
LHS

CH6425 RHS,6625 RHS,6625 LHS,6800


RHS,6800 LHS,6850 RHS, 6925 RHS,
6975 RHS,7025 RHS,7200 RHS,7400
14 10/27/2018 YC/199 Yeyeh Cons RHS,7500 RHS,7600 RHS, 7700 Take reading f
RHS,7800 RHS,7875 RHS,8450 LHS,8525
LHS,8700 LHS,9100 LHS,9150 RHS,9175
LHS

CH3775 RHS,3900 RHS,4025 RHS,4100


RHS,4325 RHS,4475 RHS,4575 RHS,
14 10/27/2018 YC/200 Yeyeh Cons Take reading f
4725 RHS,4825 RHS,4900 RHS,4925
RHS,5100 RHS,5350 RHS
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
FT54
15 10/27/2018 YC/201 Yeyeh Cons CH8450 LHS,CH8525 LHS,CH8700 LHS Take reading f
DARI
SUNGA
16 Yeyeh Cons
I 17 Yeyeh Cons
BULOH
KE18 Yeyeh Cons
ASSAM
19 Yeyeh Cons
JAWA,
KUALA
20 Yeyeh Cons
SELAN
21
GOR, Yeyeh Cons
SELAN
22 Yeyeh Cons
GOR
SECAR
23 Yeyeh Cons
A
REKA
DAN
BINA

24 Yeyeh Cons

Pavement (SGL)
Oct-18 Lay 200mm
thick crusher
1 10/5/2018 SGL/032 Sungai Long CH 19+181 BS
run for
Lay 200mmroad
base
thick layer
sand for
2 10/5/2018 SGL/033 Sungai Long CH 19+181 BS
road base
layer

Lay 200mm
thick crusher
3 10/9/2018 SGL/034 Sungai Long CH 19+181 BS
run for road
base layer
MENAI
KTARA
F
JALAN
5.1 Senarai Permintaan Bagi Pemeriksaan (RFI)
PERSE
KUTUA
Lay 200mm
N No. Tarikh keluar No. RFI Sub- Con Lokasi Huraian Kerja
crusher run
FT54 for road base
4 10/11/2018 SGL/035 Sungai Long CH 19+187 - Ch 19+450
DARI layer &
SUNGA compaction
work
To carry out
I 5 10/19/2018 SGL/036 Sungai Long CH 19+187.50 - CH 19+450 BS
Power
dipping test
BULOH brooming
KE 6 10/19/2018 SGL/037 Sungai Long CH 19+187.50 - CH 19+450
work & to
ASSAM apply/ layer
of bituminous
JAWA, prime coat
KUALA Lay 200mm
thick
SELAN
7 25/10/18 SGL/037 Sungai Long CH 19+187.50 - CH 19+450 LHS & RHS asphaltic
GOR, concrete
SELAN binder AC 28
GOR Lay 200mm
SECAR thick crushed
A 8 29/10/18 SGL/038 Sungai Long CH 15+900 - CH 16+300
aggregate for
REKA subbase layer
DAN
BINA

Anda mungkin juga menyukai