sr2018 CCl Engingering (Web Course), IT Guwahati Module : Estimation and Rate Analysis(Rat ‘Analysis & Prime Gost) Print this page ‘<< Previous| First] Last| Next >> Rate Analysis ‘At various stages in the project management, we need to know + how much is cost of executing unit amount of the work ‘+ how many equipment or labour are required to execute unit amount of an item of work. ‘These things are required for the purpose of eliminating cost of construction, material planning, labour and equipment allocation in the scheduling etc. Obtaining the cost of unit amount of an item is called rate analysis, To obtain the rate of an item, generally following cost are considered. cost of material + cost of labour * cost of equipments, plant tools etc. + overhead cost + profit ‘<< Previous| First] Last] Next>> ntps:inptl ac invcourses/105103030/15 "