Document
Title: LOAD DOWN PROCEDURE to P-MIN

A. LOAD- DOWN to P-Min (60MW) PROCEDURE

Operating Limits Responsible Status


Equipment/Procedure Tag no.
Normal Alarm Trip SS/SV CRO AO WTP MH
1. Initial Condition: Unit Load is at P-Max (1500MW and at “CCS mode”) √ √
2. Request Clearance to NGCP-SO and record the time of confirmation √
and name of the officer on duty
3. Call or text the SMC Trader for the Load down √
4. Notify the Water Treatment for load down for chemical dosing/stroke √
adjustment.
5. Set the Ramp Rate of 1MW/Min HIC-MWRL √
6. Set on ULD Setter the target load of 90MW ULD Setter Target MW √
7. Monitor Boiler and Turbine parameters while loading down. Furnace √
Bed Temp Gradient max of -2°C/min
8. If the 90MW achieve, set the ff: √
a. ULD Setter HIC-ULD from Auto to Man
a. Turbine Master EIC-TM from Auto to Man
Note: this will change the mode from CCS to Boiler Follow
9. Manually adjust the load from 90MW to 72MW using Turbine Master √
EIC-TM
10. Gradually adjust the desuperheater to maintain the Main Steam Temp TICMS1004/TICBR1150/ √
and pressure TICBR1130/TICBR1140
11. If the 72MW achieve, change the boiler mode from “Boiler Follow” to HIC-BM / PIC-COBM √
“Base”. Set the Boiler Master (HIC-BM) and Boiler Pressure Control
(PIC-COBM) to Man.
12. Adjust the MW load on the TCS until it reaches 60MW. Maintain ramp TCE194_A1 √
rate of 1MW/min
13. Gradually adjust the MV (speed of Limestone Roto Feeder). Maintain AICFG10571 √
the SOx level while minimizing the Limestone consumption.
14. Adjust the Coal Master set value/ Desuperheater/O2/PAF Bias/and FIC-CM /HS-O2 √
staging Air to sustain the boiler at 60MW. TICMS1004/TICBR1150/T
Maintain the ff: ICBR1130/TICBR1140/
a. MSP at 117-118ksc (based on actual, differ from the design) HIC-TADBS
b. MST at 538°C (based on actual, differ from the design)
c. Furnace Bed Temp Gradient max of 2°C/min
d. Bed Temp 850 to 920°C (depend on the coal HV)
e. RHT 507 to 510 °C (based on actual, differ from the design)
f. RHP 14 to 15ksc (based on actual, differ from the design)
15. Call the NGCP-SO if the P-min(60MW) was achieve and record the time √
of call and the officer on duty
Note: In-case there will be abnormal situation occurred while loading-up, hold the
load-up. Informed NGCP-SO and SMC Trader for Load Profile adjustment. Informed
Operations Manager and Plant Manager for the details.
16. Informed the SMC Trader on the status √

Page 1 of 1