D21a P-8e0
D21a P-8e0
BIAYA
TOTAL
NO. PEKERJAAN HARGA
( IDR )
TERBILANG :
A. PEKERJAAN PERSIAPAN
1. Pemasangan Bouwplank m1 48.00 SNI-03-02-P-6.4 26,587.92 1,276,220.16
1,276,220.16
C. PEKERJAAN PONDASI
1. Beton Tumbuk Di Bawah Pondasi m3 1.37 SNI-03-02-B-6.2 355,878.40 487,553.41
2. Pondasi Batu Gunung m3 11.06 SNI-03-02-PO-6.5 453,066.04 5,012,722.67
3. Aan Stamping m3 4.61 SNI-03-02-PO-6.14 224,015.40 1,032,710.99
4.
6,532,987.07
K. PEKERJAAN PENGECATAN
1. Cat Dinding Tembok Exterior ( Polimex ) M2 75.29 SNI-03-02-PC-6.14.A 18,240.38 1,373,268.96
2. Cat Dinding Tembok Interior ( Polimex ) M2 75.29 SNI-03-02-PC-6.14.B 28,240.38 2,126,141.96
3. Cat Kusen, Pintu, Jendela dan Ventilasi ( Kuda Terbang ) M2 9.70 SNI-03-02-PC-6.8 31,885.52 309,280.87
4. Cat Daun Pintu Panel ( Kuda Terbang ) M2 9.94 SNI-03-02-PC-6.8 31,885.52 316,814.53
5. Cat Daun Jendela ( Kuda Terbang ) M2 7.31 SNI-03-02-PC-6.8 31,885.52 233,019.38
6. Cat Daun Ventilasi ( Kuda Terbang ) M2 0.45 SNI-03-02-PC-6.8 31,885.52 14,233.70
7. Cat Plafond Gypsum ( Polimex ) M2 45.00 SNI-03-02-PC-6.14.C 28,704.90 1,291,720.50
8. Cat Lisplank GRC ( Kuda Terbang ) M2 17.00 SNI-03-02-PC-6.14.C 28,704.90 487,983.30
6,152,463.20
G. PEKERJAAN SANITASI
1. Pipa PVC Ø 1/2" , Vinilon m1 10.00 SNI-03-02-SN-6.25.A 16,683.60 166,836.00
2. Floor Drain, SAN EI pcs 1.00 SNI-03-02-SN-6.36 34,820.00 34,820.00
3. Kloset, AMERICAN STANDART pcs 1.00 SNI-03-02-SN-6.2.A 306,115.76 306,115.76
4. Septic Tank unit 1.00 Taksir 10,000,000.00 10,000,000.00
5. Sumur Resapan unit 1.00 Taksir 800,000.00 800,000.00
6. Tempat Sabun, KIA unit 1.00 Taksir 250,000.00 250,000.00
7. Wastafel, TOTO L 38 V1, Puith unit 1.00 Taksir 600,000.00 600,000.00
8. Cermin Dinding Pada Wastafel unit 1.00 Taksir 200,000.00 200,000.00
12,357,771.76
H. PEKERJAAN DAPUR
1. Pasangan Batu Bata, Tebal 1 Bata 1 : 2 m2 0.45 SNI-03-02-D-6.2 169,324.09 76,195.84
2. Plat Meja Dapur m3 0.10 Taksir 2,000,000.00 200,000.00
3. Keramik Untuk Dapur (20x25), IKAD KW 1 m2 5.00 SNI 03-2838-2002- 5 - a 109,083.90 545,419.50
4. Stainlees Steel tempat Cuci Piring + Asesoris unit 1.00 Taksir 500,000.00 500,000.00
5. Stopnoshing m1 3.60 Taksir 50,000.00 180,000.00
1,501,615.34
PEKERJAAN PERSIAPAN
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
I. SNI-03-02-P-6.4
1 M' Pengukuran Dan Pemasangan Bouwplank
- Bahan
- Kayu 5/7 cm ( Kelas IIII ) M3 0.0050 2,200,000.00 11,000.00
- Paku Biasa 2" - 5" Kg 0.0200 9,396.00 187.92
- Kayu Papan 3/20 cm ( Kelas III ) M3 0.0070 2,200,000.00 15,400.00
a. Sub. Jumlah 26,587.92
- Upah
- Tukang Org/Hri 0.0100 45,000.00 450.00
- Pekerja Org/Hri 0.1000 36,000.00 3,600.00
- Kepala Tukang Org/Hri 0.0080 55,000.00 440.00
- Mandor Org/Hri 0.0050 50,000.00 250.00
b. Sub. Jumlah 4,740.00
Jumlah ( a + b ) 31,327.92
II. SNI-03-02-P-6.8
1 M2 Membersihkan Lapangan Dan Perataan
- Upah
- Pekerja Org/Hri 0.1500 36,000.00 5,400.00
- Mandor Org/Hri 0.0500 50,000.00 2,500.00
Jumlah 7,900.00
DAFTAR
ANALISA HARGA SATUAN
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
I. SNI-03-2835-202-2-A
1 M3 Galian Tanah Biasa Sedalam 1 Meter
- Upah
- Pekerja org/hri 0.4000 36,000.00 14,400.00
- Mandor org/hri 0.0400 50,000.00 2,000.00
Jumlah 16,400.00
I. SNI-03-2835-202-2-C
1 M3 Galian Tanah Biasa Sedalam 3 Meter
- Upah
- Pekerja org/hri 0.7350 36,000.00 26,460.00
- Mandor org/hri 0.0730 50,000.00 3,650.00
Jumlah 30,110.00
II. SNI-03-02-T-6.9
1 M3 Urugan Kembali
- Upah
- Pekerja org/hri 0.2120 36,000.00 7,632.00
- Mandor org/hri 0.0190 50,000.00 950.00
Jumlah 8,582.00
III. SNI-03-02-T-6.12A
1 M3 Timbunan Tanah
- Bahan
- Tanah Timbun M3 1.3000 46,656.00 60,652.80
a. Sub. Jumlah 60,652.80
- Upah
- Pekerja Org/Hri 0.3500 36,000.00 12,600.00
- Mandor Org/Hri 0.0150 50,000.00 750.00
b. Sub. Jumlah 13,350.00
Jumlah ( a + b ) 74,002.80
IV. SNI-03-02-T-6.12
1 M3 Urugan Pasir
- Bahan
- Pasir Urug M3 1.2000 98,064.00 117,676.80
a. Sub. Jumlah 117,676.80
- Upah
- Pekerja Org/Hri 0.3500 36,000.00 12,600.00
- Mandor Org/Hri 0.0150 50,000.00 750.00
b. Sub. Jumlah 13,350.00
Jumlah ( a + b ) 131,026.80
V. SNI-03-02-T-6.12.A
1 M3 Urugan Kerikil
- Bahan
- Kerikil M3 1.2000 116,640.00 139,968.00
a. Sub. Jumlah 139,968.00
- Upah
- Pekerja Org/Hri 0.3500 36,000.00 12,600.00
- Mandor Org/Hri 0.0150 50,000.00 750.00
b. Sub. Jumlah 13,350.00
Jumlah ( a + b ) 153,318.00
PEKERJAAN PONDASI
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
I. SNI-03-02-PO-6.5
1 M3 Pasang Pondasi Batu Kali, 1 PC : 4 PS
- Bahan
- Batu Belah / Kali 15/20 cm M3 1.1300 128,304.00 144,983.52
- Semen Padang @ 40 Kg Zak 4.0750 40,600.00 165,445.00
- Pasir Pasang M3 0.5200 104,976.00 54,587.52
a. Sub. Jumlah 365,016.04
- Upah
- Tukang Batu Org/Hri 0.6000 45,000.00 27,000.00
- Pekerja Org/Hri 1.5000 36,000.00 54,000.00
- Kepala Tukang Org/Hri 0.0600 55,000.00 3,300.00
- Mandor Org/Hri 0.0750 50,000.00 3,750.00
b. Sub. Jumlah 88,050.00
Jumlah ( a + b ) 453,066.04
II. SNI-03-02-PO-6.14
1 M3 Pasang Pondasi Batu Kosong
- Bahan
- Batu Belah / Kali 15/20 cm M3 1.2000 116,640.00 139,968.00
- Pasir Urug M3 0.3500 98,064.00 34,322.40
a. Sub. Jumlah 174,290.40
- Upah
- Tukang Batu Org/Hri 0.3900 45,000.00 17,550.00
- Pekerja Org/Hri 0.7800 36,000.00 28,080.00
- Kepala Tukang Org/Hri 0.0390 55,000.00 2,145.00
- Mandor Org/Hri 0.0390 50,000.00 1,950.00
b. Sub. Jumlah 49,725.00
Jumlah ( a + b ) 224,015.40
PEKERJAAN BETON DAN BETON BERTULANG
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
PEKERJAAN BETON
I. SNI-03-02-B-6.2
1 M3 Membuat Beton Cor/Tumbuk , 1 Pc : 3 Ps : 6 Kr
- Bahan
- Semen Padang @ 40 Kg Zak 4.9250 40,600.00 199,955.00
- Pasir Beton M3 0.5700 116,640.00 66,484.80
- Koral / Kerikil Beton M3 0.1150 116,640.00 13,413.60
a. Sub. Jumlah 279,853.40
- Upah
- Tukang Batu Org/Hri 0.2500 45,000.00 11,250.00
- Pekerja Org/Hri 1.6500 36,000.00 59,400.00
- Kepala Tukang Org/Hri 0.0250 55,000.00 1,375.00
- Mandor Org/Hri 0.0800 50,000.00 4,000.00
b. Sub. Jumlah 76,025.00
Jumlah ( a + b ) 355,878.40
II. SNI-03-02-B-6.13
1 M3 Membuat Beton Bertulang Mutu K-225
- Bahan
- Semen Padang @ 40 Kg Zak 9.7000 40,600.00 393,820.00
- Pasir Beton M3 0.9200 116,640.00 107,308.80
- Koral / Kerikil Beton M3 0.7800 116,640.00 90,979.20
a. Sub. Jumlah 592,108.00
- Upah
- Tukang Batu Org/Hri 0.4500 45,000.00 20,250.00
- Pekerja Org/Hri 1.6500 36,000.00 59,400.00
- Kepala Tukang Org/Hri 0.0450 55,000.00 2,475.00
- Mandor Org/Hri 0.0060 50,000.00 300.00
b. Sub. Jumlah 82,425.00
Jumlah ( a + b ) 674,533.00
I. SNI-03-02-B-6.25
1 KG Pembesian Dengan besi Ulir
- Bahan
- Besi Beton Kg 1.0500 9,000.00 9,450.00
- Kawat Beton Kg 0.0150 9,396.00 140.94
a. Sub. Jumlah 9,590.94
- Upah
- Tukang Besi Org/Hri 0.0070 45,000.00 315.00
- Pekerja Org/Hri 0.0070 36,000.00 252.00
- Kepala Tukang Org/Hri 0.0010 55,000.00 55.00
- Mandor Org/Hri 0.0003 50,000.00 15.00
b. Sub. Jumlah 637.00
Jumlah ( a + b ) 10,227.94
I. SNI-03-02-B-6.25
1 KG Pembesian Dengan besi polos
- Bahan
- Besi Beton Kg 1.0500 8,500.00 8,925.00
- Kawat Beton Kg 0.0150 9,396.00 140.94
a. Sub. Jumlah 9,065.94
- Upah
- Tukang Besi Org/Hri 0.0070 45,000.00 315.00
- Pekerja Org/Hri 0.0070 36,000.00 252.00
- Kepala Tukang Org/Hri 0.0010 55,000.00 55.00
- Mandor Org/Hri 0.0003 50,000.00 15.00
b. Sub. Jumlah 637.00
Jumlah ( a + b ) 9,702.94
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
- Upah
- Tukang Kayu Org/Hri 0.2600 45,000.00 11,700.00
- Pekerja Org/Hri 0.3000 36,000.00 10,800.00
- Kepala Tukang Org/Hri 0.0260 55,000.00 1,430.00
- Mandor Org/Hri 0.0050 50,000.00 250.00
b. Sub. Jumlah 24,180.00
Jumlah ( a + b ) 35,700.92
Dibulatkan 35,700.92
I. SNI-03-02-B-6.31
1 M2 Pasang Bekisting Untuk Balok Sloof
- Bahan
- Kayu Terentang ( Kelas III ) M3 0.0450 2,200,000.00 99,000.00
- Paku Biasa 2" - 5" Kg 0.3000 9,396.00 2,818.80
- Minyak Bekisting Ltr 0.1000 10,000.00 1,000.00
- Balok Kayu ( Kelas III ) M3 0.0180 2,200,000.00 39,600.00
- Multiplek 6 mm Lbr 0.3500 87,480.00 30,618.00
a. Sub. Jumlah 173,036.80
- Upah
- Tukang Kayu Org/Hri 0.2600 45,000.00 11,700.00
- Pekerja Org/Hri 0.3000 36,000.00 10,800.00
- Kepala Tukang Org/Hri 0.0260 55,000.00 1,430.00
- Mandor Org/Hri 0.0050 50,000.00 250.00
b. Sub. Jumlah 24,180.00
Jumlah ( a + b ) 197,216.80
Dibulatkan 197,216.80
II. SNI-03-02-B-6.32
1 M2 Pasang Bekisting Untuk Kolom
- Bahan
- Kayu Terentang ( Kelas III ) M3 0.0400 2,200,000.00 88,000.00
- Paku Biasa 2" - 5" Kg 0.4000 9,396.00 3,758.40
- Minyak Bekisting Ltr 0.2000 10,000.00 2,000.00
- Balok Kayu ( Kelas III ) M3 0.0150 2,200,000.00 33,000.00
- Multiplek 6 mm Lbr 0.3500 87,480.00 30,618.00
a. Sub. Jumlah 157,376.40
- Upah
- Tukang Kayu Org/Hri 0.3300 45,000.00 14,850.00
- Pekerja Org/Hri 0.3000 36,000.00 10,800.00
- Kepala Tukang Org/Hri 0.0330 55,000.00 1,815.00
- Mandor Org/Hri 0.0060 50,000.00 300.00
b. Sub. Jumlah 27,765.00
Jumlah ( a + b ) 185,141.40
Dibulatkan 185,141.40
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
III. SNI-03-02-B-6.33
1 M2 Pasang Bekisting Untuk Balok
- Bahan
- Kayu Terentang ( Kelas III ) M3 0.0400 2,200,000.00 88,000.00
- Paku Biasa 2" - 5" Kg 0.4000 9,396.00 3,758.40
- Minyak Bekisting Ltr 0.2000 10,000.00 2,000.00
- Balok Kayu ( Kelas III ) M3 0.0180 2,200,000.00 39,600.00
- Multiplek 6 mm Lbr 0.3500 87,480.00 30,618.00
a. Sub. Jumlah 163,976.40
- Upah
- Tukang Kayu Org/Hri 0.3300 45,000.00 14,850.00
- Pekerja Org/Hri 0.3200 36,000.00 11,520.00
- Kepala Tukang Org/Hri 0.0330 55,000.00 1,815.00
- Mandor Org/Hri 0.0060 50,000.00 300.00
b. Sub. Jumlah 28,485.00
Jumlah ( a + b ) 192,461.40
Dibulatkan 192,461.40
IV. SNI-03-02-B-6.34
1 M2 Pasang Bekisting Untuk Plat Lantai
- Bahan
- Kayu Terentang ( Kelas IIII ) M3 0.0400 2,200,000.00 88,000.00
- Paku Biasa 2" - 5" Kg 0.4000 9,396.00 3,758.40
- Minyak Bekisting Ltr 0.2000 10,000.00 2,000.00
- Balok Kayu ( Kelas III ) M3 0.0150 2,200,000.00 33,000.00
- Multiplek 6 mm Lbr 0.3500 87,480.00 30,618.00
a. Sub. Jumlah 157,376.40
- Upah
- Tukang Kayu Org/Hri 0.3300 45,000.00 14,850.00
- Pekerja Org/Hri 0.3200 36,000.00 11,520.00
- Kepala Tukang Org/Hri 0.0330 55,000.00 1,815.00
- Mandor Org/Hri 0.0060 50,000.00 300.00
b. Sub. Jumlah 28,485.00
Jumlah ( a + b ) 185,861.40
Dibulatkan 185,861.40
VI. SNI-03-02-B-6.39
1 Membongkar Bekisting Dan Merawat Beton ( Curring )
- Upah
- Pekerja Org/Hri 4.0000 36,000.00 144,000.00
b. Sub. Jumlah 144,000.00
Jumlah ( a ) 144,000.00
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
I. SNI-03-02-B-6.38.SA
1 M3 Beton Balok Sloof 15/20 cm
- Besi Beton Ulir Kg 0.0000 10,227.94 0.00
- Besi Beton polos Kg 65.0000 9,702.94 630,691.10
- Bekisting / Mal + Perancah M2 7.0000 197,216.80 1,380,517.60
- Beton M3 1.0100 674,533.00 681,278.33
- Membongkar Bekisting Dan Merawat Beton Unit 1.0000 144,000.00 144,000.00
Jumlah 2,836,487.03
I. SNI-03-02-B-6.38.SB
1 M3 Beton Balok Sloof 25/40 cm
- Besi Beton Ulir Kg 78.9120 10,227.94 807,107.20
- Besi Beton polos Kg 94.3492 9,702.94 915,464.63
- Bekisting / Mal + Perancah M2 7.0000 197,216.80 1,380,517.60
- Beton M3 1.0100 674,533.00 681,278.33
- Membongkar Bekisting Dan Merawat Beton Unit 1.0000 144,000.00 144,000.00
Jumlah 3,928,367.76
I. SNI-03-02-B-6.38.Bla
1 M3 Beton Balok Lantai 40/80 cm
- Besi Beton Ulir Kg 62.5940 10,227.94 640,207.68
- Besi Beton polos Kg 51.7860 9,702.94 502,476.45
- Bekisting / Mal + Perancah M2 13.7143 197,216.80 2,704,687.54
- Beton M3 1.0100 674,533.00 681,278.33
- Membongkar Bekisting Dan Merawat Beton Unit 1.0000 144,000.00 144,000.00
Jumlah 4,672,650.00
I. SNI-03-02-B-6.38.Blb
1 M3 Beton Balok Lantai 25/50 cm
- Besi Beton Ulir Kg 124.6316 10,227.94 1,274,724.53
- Besi Beton polos Kg 88.1842 9,702.94 855,646.00
- Bekisting / Mal + Perancah M2 7.0000 197,216.80 1,380,517.60
- Beton M3 1.0100 674,533.00 681,278.33
- Membongkar Bekisting Dan Merawat Beton Unit 1.0000 144,000.00 144,000.00
Jumlah 4,336,166.46
II. SNI-03-02-B-6.38.Blc
1 M3 Beton Balok Lantai 25/40 cm
- Besi Beton Ulir Kg 72.0000 10,227.94 736,411.68
- Besi Beton polos Kg 35.0000 9,702.94 339,602.90
- Bekisting / Mal + Perancah M2 13.3333 197,216.80 2,629,550.76
- Beton Cor K-200 M3 1.0100 674,533.00 681,278.33
- Membongkar Bekisting Dan Merawat Beton Unit 1.0000 144,000.00 144,000.00
Jumlah 4,530,843.67
II. SNI-03-02-B-6.38.RB
1 M3 Beton Ring Balok 11/15 cm
- Besi Beton Ulir Kg 0.0000 10,227.94 0.00
- Besi Beton polos Kg 60.0000 9,702.94 582,176.40
- Bekisting / Mal + Perancah M2 7.0000 192,461.40 1,347,229.80
- Beton Cor K-200 M3 1.0100 674,533.00 681,278.33
- Membongkar Bekisting Dan Merawat Beton Unit 1.0000 144,000.00 144,000.00
Jumlah 2,754,684.53
III. SNI-03-02-B-6.38.RC
1 M3 Beton Balok Latei 11/11 cm
- Besi Beton polos Kg 70.0000 9,702.94 679,205.80
- Bekisting / Mal + Perancah M2 7.0000 192,461.40 1,347,229.80
- Beton Cor K-200 M3 1.0100 674,533.00 681,278.33
- Membongkar Bekisting Dan Merawat Beton Unit 1.0000 144,000.00 144,000.00
Jumlah 2,707,713.93
BETON BERTULANG PLAT
I. SNI-03-02-B-6.38.PA
1 M3 Beton Pelat Dack Tebal 10 cm
- Besi Beton polos Kg 65.0000 9,702.94 630,691.10
- Bekisting / Mal + Perancah M2 6.0000 185,861.40 1,115,168.40
- Beton Cor K-200 M3 1.0100 674,533.00 681,278.33
- Membongkar Bekisting Dan Merawat Beton Unit 1.0000 144,000.00 144,000.00
Jumlah 2,571,137.83
II. SNI-03-02-B-6.38.PB
1 M3 Beton Pelat Dack Tebal 7 cm
- Besi Beton polos Kg 103.0000 9,702.94 999,402.82
- Bekisting / Mal + Perancah M2 14.2860 185,861.40 2,655,215.96
- Beton Cor K-200 M3 1.1000 674,533.00 741,986.30
- Membongkar Bekisting Dan Merawat Beton Ls 1.0000 144,000.00 144,000.00
Jumlah 4,540,605.08
I. SNI-03-02-B-6.38.KA
1 M3 Beton Kolom Praktis 13/13 cm
- Besi Beton Ulir Kg 70.0000 10,227.94 715,955.80
- Bekisting / Mal + Perancah M2 10.0000 185,141.40 1,851,414.00
- Beton Cor K-200 M3 1.1000 674,533.00 741,986.30
- Membongkar Bekisting Dan Merawat Beton Unit 1.0000 144,000.00 144,000.00
Jumlah 3,453,356.10
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
II. SNI-03-02-B-6.38.Kba
1 M3 Beton Kolom 60/70 cm
- Besi Beton Ulir Kg 101.4583 10,227.94 1,037,709.40
- Besi Beton polos Kg 38.1643 9,702.94 370,305.91
- Bekisting / Mal + Perancah M2 13.7143 185,141.40 2,539,082.06
- Beton Cor K-200 M3 1.0000 674,533.00 674,533.00
- Membongkar Bekisting Dan Merawat Beton Unit 1.0000 144,000.00 144,000.00
Jumlah 4,765,630.38
II. SNI-03-02-B-6.38.Kbb
1 M3 Beton Kolom 30/30 cm
- Besi Beton Ulir Kg 39.4560 10,227.94 403,553.60
- Besi Beton polos Kg 82.2000 9,702.94 797,581.67
- Bekisting / Mal + Perancah M2 13.7143 185,141.40 2,539,082.06
- Beton Cor K-200 M3 1.0000 674,533.00 674,533.00
- Membongkar Bekisting Dan Merawat Beton Unit 1.0000 144,000.00 144,000.00
Jumlah 4,558,750.33
III. SNI-03-02-B-6.38.KC
1 M3 Beton Kolom Praktis 13/13 cm
- Besi Beton polos Kg 101.4583 9,702.94 984,443.80
- Bekisting / Mal + Perancah M2 13.7143 185,141.40 2,539,082.06
- Beton Cor K-200 M3 1.0000 674,533.00 674,533.00
- Membongkar Bekisting Dan Merawat Beton Unit 1.0000 144,000.00 144,000.00
Jumlah 4,342,058.85
BETON BERTULANG PONDASI
I. SNI-03-3435-2002-A
1 M3 Pondasi Tapak
- Beton Cor K250 M3 1.0000 674,533.00 674,533.00
- Pekerjaan Besi Kg 211.4080 10,227.94 2,162,268.34
- Cetakan Beton M2 0.8030 185,861.40 149,246.70
- Pekerjaan Lain - lain Oh 1.0000 185,141.40 185,141.40
Jumlah 3,171,189.44
II. SNI-03-2836-2002-p
1 M3 Pondasi Sumuran
- Batu belah 15/20 cm M3 1.0000 128,304.00 128,304.00
- Semen portland zak 5.2850 40,600.00 214,571.00
- Pasir Beton M3 0.8030 116,640.00 93,661.92
- Koral beton M3 1.0000 116,640.00 116,640.00
- Upah
- Tukang batu Org/Hri 0.3000 45,000.00 13,500.00
- Pekerja Org/Hri 2.3800 36,000.00 85,680.00
- Kepala Tukang Org/Hri 3.0300 55,000.00 166,650.00
- Mandor Org/Hri 0.0800 50,000.00 4,000.00
-
Jumlah 823,006.92
- Upah
- Tukang Besi Org/Hri 0.0070 45,000.00 315.00
- Pekerja Org/Hri 0.0070 36,000.00 252.00
- Kepala Tukang Org/Hri 0.0010 45,000.00 45.00
- Mandor Org/Hri 0.0003 36,000.00 10.80
Jumlah 1,900,402.80
- Upah
- Pekerja Oh 5.600 36,000.00 201,600.00
- Tukang Batu Oh 0.350 45,000.00 15,750.00
- Tukang Kayu Oh 2.300 45,000.00 103,500.00
- Tukang Besi Oh 1.400 45,000.00 63,000.00
- Kepala tukang Oh 0.405 45,000.00 18,225.00
- Mandor Oh 0.202 50,000.00 10,100.00
Jumlah 3,967,765.60
DAFTAR
ANALISA HARGA SATUAN
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
- Upah
- Tukang Batu Org/Hri 0.1000 45,000.00 4,500.00
- Pekerja Org/Hri 0.3200 36,000.00 11,520.00
- Kepala Tukang Org/Hri 0.0100 55,000.00 550.00
- Mandor Org/Hri 0.0150 50,000.00 750.00
b. Sub. Jumlah 17,320.00
Jumlah ( a + b ) 84,500.59
II. SNI-03-02-D-6.10
1 M2 Pasangan Bata Merah Tebal 1/2 Bata, 1 PC : 4 PS
- Bahan
- Batu Bata Bh 70.0000 583.00 40,810.00
- Semen Padang @ 40 Kg Zak 0.2875 40,600.00 11,672.50
- Pasir Pasang M3 0.0430 104,976.00 4,513.97
a. Sub. Jumlah 56,996.47
- Upah
- Tukang Batu Org/Hri 0.1000 45,000.00 4,500.00
- Pekerja Org/Hri 0.3200 36,000.00 11,520.00
- Kepala Tukang Org/Hri 0.0100 55,000.00 550.00
- Mandor Org/Hri 0.0150 50,000.00 750.00
b. Sub. Jumlah 17,320.00
Jumlah ( a + b ) 74,316.47
III. SNI-03-02-D-6.2
1 M2 Pasangan Bata Merah Tebal 1 Bata, 1 PC : 2 PS
- Bahan
- Batu Bata Bh 140.0000 583.00 81,620.00
- Semen Padang @ 40 Kg Zak 1.0911 40,600.00 44,298.66
- Pasir Pasang M3 0.0801 104,976.00 8,405.43
a. Sub. Jumlah 134,324.09
- Upah
- Tukang Batu Org/Hri 0.2000 45,000.00 9,000.00
- Pekerja Org/Hri 0.6500 36,000.00 23,400.00
- Kepala Tukang Org/Hri 0.0200 55,000.00 1,100.00
- Mandor Org/Hri 0.0300 50,000.00 1,500.00
b. Sub. Jumlah 35,000.00
Jumlah ( a + b ) 169,324.09
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
IV. SNI-03-02-PL-6.29
1 M2 Aci Beton 1 Pc : 2 Ps, Tebal 15 mm
- Bahan
- Semen Padang @ 40 Kg Zak 0.2325 40,600.00 9,439.50
- Pasir Pasang M3 0.0180 104,976.00 1,889.57
a. Sub. Jumlah 11,329.07
- Upah
- Tukang Batu Org/Hri 0.2000 45,000.00 9,000.00
- Pekerja Org/Hri 0.2600 36,000.00 9,360.00
- Kepala Tukang Org/Hri 0.0200 55,000.00 1,100.00
- Mandor Org/Hri 0.0130 50,000.00 650.00
b. Sub. Jumlah 20,110.00
Jumlah ( a + b ) 31,439.07
V. SNI-03-02-PL-6.2
1 M2 Plesteran 1 Pc : 2 Ps, Tebal 15 mm
- Bahan
- Semen Padang @ 40 Kg Zak 0.2130 40,600.00 8,647.80
- Pasir Pasang M3 0.0170 104,976.00 1,784.59
a. Sub. Jumlah 10,432.39
- Upah
- Tukang Batu Org/Hri 0.1500 45,000.00 6,750.00
- Pekerja Org/Hri 0.2000 36,000.00 7,200.00
- Kepala Tukang Org/Hri 0.0150 55,000.00 825.00
- Mandor Org/Hri 0.0100 50,000.00 500.00
b. Sub. Jumlah 15,275.00
Jumlah ( a + b ) 25,707.39
VI. SNI-03-02-PL-6.4
1 M2 Plesteran 1 Pc : 4 Ps, Tebal 15 mm
- Bahan
- Semen Padang @ 40 Kg Zak 0.1300 40,600.00 5,278.00
- Pasir Pasang M3 0.0200 104,976.00 2,099.52
a. Sub. Jumlah 7,377.52
- Upah
- Tukang Batu Org/Hri 0.1500 45,000.00 6,750.00
- Pekerja Org/Hri 0.2000 36,000.00 7,200.00
- Kepala Tukang Org/Hri 0.0150 55,000.00 825.00
- Mandor Org/Hri 0.0100 50,000.00 500.00
b. Sub. Jumlah 15,275.00
Jumlah ( a + b ) 22,652.52
DAFTAR
ANALISA HARGA SATUAN
PEKERJAAN KAYU
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
I. SNI 03-3434-2002 - b
1 M³ Pasang kusen pintu dan jendela kayu kamper
- Bahan
- Kayu kamper, balok M3 1.2000 2,500,000.00 3,000,000.00
a. Sub. Jumlah 3,000,000.00
- Upah
- Pekerja Org/Hri 6.000 36,000.00 216,000.00
- Tukang Kayu Org/Hri 18.000 45,000.00 810,000.00
- Kepala Tukang Org/Hri 2.000 55,000.00 110,000.00
- Mandor Org/Hri 0.300 50,000.00 15,000.00
b. Sub. Jumlah 1,151,000.00
Jumlah ( a + b ) 4,151,000.00
I. SNI 03-3434-2002 - h
1 M² Pasang pintu panel kayu kamper
- Bahan
- Kayu kamper, papan M3 0.0400 2,500,000.00 100,000.00
a. Sub. Jumlah 100,000.00
- Upah
- Pekerja Org/Hri 1.000 36,000.00 36,000.00
- Tukang Kayu Org/Hri 2.500 45,000.00 112,500.00
- Kepala Tukang Org/Hri 0.250 55,000.00 13,750.00
- Mandor Org/Hri 0.050 50,000.00 2,500.00
b. Sub. Jumlah 164,750.00
Jumlah ( a + b ) 264,750.00
I. SNI 03-2838-2002- 3 - i
1 m² Pasang pintu alluminium
- Bahan
- Pintu alluminium M2 1.0000 150,000.00 150,000.00
a. Sub. Jumlah 150,000.00
- Upah
- Pekerja Org/Hri 1.050 36,000.00 37,800.00
- Tukang Besi Org/Hri 1.050 45,000.00 47,250.00
- Kepala tukang Org/Hri 0.105 55,000.00 5,775.00
- Mandor Org/Hri 0.0052 50,000.00 260.00
b. Sub. Jumlah 91,085.00
Jumlah ( a + b ) 241,085.00
I. SNI-03-02-K-6.27
1 M3 Pasang Konstruksi Kuda - Kuda
- Bahan
- Kayu Kelas II M3 1.1000 2,500,000.00 2,750,000.00
- Paku Biasa 2" - 5" Kg 0.8000 9,396.00 7,516.80
a. Sub. Jumlah 2,757,516.80
- Upah
- Tukang Kayu Org/Hri 12.0000 45,000.00 540,000.00
- Pekerja Org/Hri 4.0000 36,000.00 144,000.00
- Kepala Tukang Org/Hri 1.2000 55,000.00 66,000.00
- Mandor Org/Hri 0.2000 50,000.00 10,000.00
b. Sub. Jumlah 760,000.00
Jumlah ( a + b ) 3,517,516.80
II. SNI-03-02-K-6.48
1 M' Pasang Lisplank Ukuran ( 3 x 20 ) cm,
- Bahan
- Kayu Kelas II, Papan M3 0.0072 2,500,000.00 18,000.00
- Paku Biasa 2" - 5" Kg 0.0700 9,396.00 657.72
a. Sub. Jumlah 18,657.72
- Upah
- Tukang Kayu Org/Hri 0.2500 45,000.00 11,250.00
- Pekerja Org/Hri 0.1800 36,000.00 6,480.00
- Kepala Tukang Org/Hri 0.0350 55,000.00 1,925.00
- Mandor Org/Hri 0.0050 50,000.00 250.00
b. Sub. Jumlah 19,905.00
Jumlah ( a + b ) 38,562.72
DAFTAR
ANALISA HARGA SATUAN
PEKERJAAN ATAP
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
I. SNI-03-A-6.38.A
1 M2 Pasang Atap Seng Gelombang
- Bahan
- Seng Gelombang BJLS 0,20 MM 8 Kaki Lbr 0.4629 41,040.00 18,997.42
- Paku Seng Bh 10.0000 100.00 1,000.00
a. Sub. Jumlah 19,997.42
- Upah
- Tukang Kayu Org/Hri 0.0600 45,000.00 2,700.00
- Pekerja Org/Hri 0.1200 36,000.00 4,320.00
- Kepala Tukang Org/Hri 0.0060 55,000.00 330.00
- Mandor Org/Hri 0.0060 50,000.00 300.00
b. Sub. Jumlah 7,650.00
Jumlah ( a + b ) 27,647.42
II. SNI-03-A-6.39.A
1 M' Pasang Rabung Seng
- Bahan
- Seng Plat BJLS 0,30 MM 6 Kaki Lbr 0.3000 41,040.00 12,312.00
- Paku Biasa 1/2" - 1" Kg 0.0400 100.00 4.00
a. Sub. Jumlah 12,316.00
- Upah
- Tukang Kayu Org/Hri 0.0700 45,000.00 3,150.00
- Pekerja Org/Hri 0.1500 36,000.00 5,400.00
- Kepala Tukang Org/Hri 0.0080 55,000.00 440.00
- Mandor Org/Hri 0.0060 50,000.00 300.00
b. Sub. Jumlah 9,290.00
Jumlah ( a + b ) 21,606.00
DAFTAR
ANALISA HARGA SATUAN
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
I. SNI-03-02-K-6.38.A
1 M2 Pasang Rangka Langit - Langit ( 1,00 x 1,00 ) m
- Bahan
- Kayu Kelas II M3 0.0120 2,500,000.00 30,000.00
- Paku Biasa 2" - 5" Kg 0.1000 9,396.00 939.60
a. Sub. Jumlah 30,939.60
- Upah
- Tukang Kayu Org/Hri 0.2500 45,000.00 11,250.00
- Pekerja Org/Hri 0.1500 36,000.00 5,400.00
- Kepala Tukang Org/Hri 0.0250 55,000.00 1,375.00
- Mandor Org/Hri 0.0750 50,000.00 3,750.00
b. Sub. Jumlah 21,775.00
Jumlah ( a + b ) 52,714.60
- Upah
- Pekerja Oh 0.100 36,000.00 3,600.00
- Tukang Kayu Oh 0.050 45,000.00 2,250.00
- Kepala tukang Oh 0.005 55,000.00 275.00
- Mandor Oh 0.005 50,000.00 250.00
b. Sub. Jumlah 6,375.00
Jumlah ( a + b ) 36,815.00
- Upah
- Pekerja Org/Hri 0.021 36,000.00 756.00
- Tukang Kayu Org/Hri 0.021 45,000.00 945.00
- Kepala Tukang Org/Hri 0.002 55,000.00 110.00
- Mandor Org/Hri 0.001 50,000.00 50.00
b. Sub. Jumlah 1,861.00
Jumlah ( a + b ) 8,686.00
II. SNI-03-PF-6.10.A
1 M2 Plafond Multiplek , Tebal 4 mm
- Bahan
- Multiplek 4 mm Lbr 0.4750 64,152.00 30,472.20
- Paku Multiplek Kg 0.0400 9,396.00 375.84
a. Sub. Jumlah 30,848.04
- Upah
- Tukang Kayu Org/Hri 0.2000 45,000.00 9,000.00
- Pekerja Org/Hri 0.4500 36,000.00 16,200.00
- Kepala Tukang Org/Hri 0.0200 55,000.00 1,100.00
- Mandor Org/Hri 0.0200 50,000.00 1,000.00
b. Sub. Jumlah 27,300.00
Jumlah ( a + b ) 58,148.04
DAFTAR
ANALISA HARGA SATUAN
PEKERJAAN CAT
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
I. SNI-03-02-PC-6.14.A
1 M2 Pengecatan Dinding Exterior
- Bahan
- Plamir Kg 0.1500 11,556.00 1,733.40
- Cat Dasar Kg 0.1200 23,112.00 2,773.44
- Cat Penutup 2 x Kg 0.4200 23,112.00 9,707.04
- Steger Werk Ls 1.0000 0.00 0.00
a. Sub. Jumlah 14,213.88
- Upah
- Tukang Cat Org/Hri 0.0630 45,000.00 2,835.00
- Pekerja Org/Hri 0.0200 36,000.00 720.00
- Kepala Tukang Org/Hri 0.0063 55,000.00 346.50
- Mandor Org/Hri 0.0025 50,000.00 125.00
b. Sub. Jumlah 4,026.50
Jumlah ( a + b ) 18,240.38
II. SNI-03-02-PC-6.14.B
1 M2 Pengecatan Dinding Interior
- Bahan
- Plamir Kg 0.1500 11,556.00 1,733.40
- Cat Dasar Kg 0.1200 23,112.00 2,773.44
- Cat Penutup 2 x Kg 0.4200 23,112.00 9,707.04
- Steger Werk Ls 1.0000 10,000.00 10,000.00
a. Sub. Jumlah 24,213.88
- Upah
- Tukang Cat Org/Hri 0.0630 45,000.00 2,835.00
- Pekerja Org/Hri 0.0200 36,000.00 720.00
- Kepala Tukang Org/Hri 0.0063 55,000.00 346.50
- Mandor Org/Hri 0.0025 50,000.00 125.00
b. Sub. Jumlah 4,026.50
Jumlah ( a + b ) 28,240.38
III. SNI-03-02-PC-6.14.C
1 M2 Pengecatan Plafond
( 1 Lapis Cat Dasar, 2 Lapis Cat Penutup )
- Bahan
- Cat Dasar Kg 0.1800 23,112.00 4,160.16
- Cat Penutup 2 x Kg 0.5200 23,112.00 12,018.24
- Steger Werk Ls 1.0000 8,500.00 8,500.00
a. Sub. Jumlah 24,678.40
- Upah
- Tukang Cat Org/Hri 0.0630 45,000.00 2,835.00
- Pekerja Org/Hri 0.0200 36,000.00 720.00
- Kepala Tukang Org/Hri 0.0063 55,000.00 346.50
- Mandor Org/Hri 0.0025 50,000.00 125.00
b. Sub. Jumlah 4,026.50
Jumlah ( a + b ) 28,704.90
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
IV. SNI-03-02-PC-6.8
1 M2 Mengecat Bidang Kayu Baru ( 1 Lapis Plamir),
1 Lapis Cat Dasar, 2 Lapis Cat Penutup
- Bahan
- Cat Meni Kg 0.2500 19,872.00 4,968.00
- Plamir Kg 0.2500 15,768.00 3,942.00
- Cat Dasar Kg 0.2100 23,328.00 4,898.88
- Cat Penutup 2 Kali Kg 0.4200 34,992.00 14,696.64
a. Sub. Jumlah 28,505.52
- Upah
- Tukang Cat Org/Hri 0.0090 45,000.00 405.00
- Pekerja Org/Hri 0.0700 36,000.00 2,520.00
- Kepala Tukang Org/Hri 0.0060 55,000.00 330.00
- Mandor Org/Hri 0.0025 50,000.00 125.00
b. Sub. Jumlah 3,380.00
Jumlah ( a + b ) 31,885.52
V. SNI-03-02-PC-6.12
1 M2 Pelaburan Bidang Kayu Dengan Cat Residu Dan Ter
- Bahan
- Residu Atau Ter Ltr 0.3500 1,836.00 642.60
a. Sub. Jumlah 642.60
- Upah
- Tukang Cat Org/Hri 0.2500 45,000.00 11,250.00
- Pekerja Org/Hri 0.1800 36,000.00 6,480.00
- Kepala Tukang Org/Hri 0.0200 55,000.00 1,100.00
- Mandor Org/Hri 0.0200 50,000.00 1,000.00
b. Sub. Jumlah 19,830.00
Jumlah ( a + b ) 20,472.60
DAFTAR
ANALISA HARGA SATUAN
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
I. SNI-03-02-KK-6.17.A
1 M2 Pasang Kaca, Tebal 5 mm
- Bahan
- Kaca Tebal 5 mm M2 1.1000 93,312.00 102,643.20
a. Sub. Jumlah 102,643.20
- Upah
- Tukang Kayu Org/Hri 0.1500 45,000.00 6,750.00
- Pekerja Org/Hri 0.0150 36,000.00 540.00
- Kepala Tukang Org/Hri 0.0150 55,000.00 825.00
- Mandor Org/Hri 0.00075 50,000.00 37.50
b. Sub. Jumlah 8,152.50
Jumlah ( a + b ) 110,795.70
- Upah
- Pekerja Org/Hri 0.010 36,000.00 360.00
- Tukang Kayu Org/Hri 0.500 45,000.00 22,500.00
- Kepala tukang Org/Hri 0.010 55,000.00 550.00
- Mandor Org/Hri 0.005 50,000.00 250.00
b. Sub. Jumlah 23,660.00
Jumlah ( a + b ) 73,660.00
- Upah
- Pekerja Org/Hri 0.005 36,000.00 180.00
- Tukang Kayu Org/Hri 0.500 45,000.00 22,500.00
- Kepala tukang Org/Hri 0.005 55,000.00 275.00
- Mandor Org/Hri 0.0025 50,000.00 125.00
b. Sub. Jumlah 23,080.00
Jumlah ( a + b ) 73,080.00
- Upah
- Pekerja Org/Hri 0.015 36,000.00 540.00
- Tukang Kayu Org/Hri 0.150 45,000.00 6,750.00
- Kepala tukang Org/Hri 0.015 55,000.00 825.00
- Mandor Org/Hri 0.00075 50,000.00 37.50
b. Sub. Jumlah 8,152.50
Jumlah ( a + b ) 58,152.50
V. SNI 03-2838-2002- 4 - f
1 buah pasang engsel jendela kupu-kupu
- Bahan
- Engsel jendela bh 1.0000 35,000.00 35,000.00
a. Sub. Jumlah 35,000.00
- Upah
- Pekerja Org/Hri 0.010 36,000.00 360.00
- Tukang Kayu Org/Hri 0.100 45,000.00 4,500.00
- Kepala tukang Org/Hri 0.010 55,000.00 550.00
- Mandor Org/Hri 0.0005 50,000.00 25.00
b. Sub. Jumlah 5,435.00
Jumlah ( a + b ) 40,435.00
- Upah
- Pekerja Org/Hri 0.015 36,000.00 540.00
- Tukang Kayu Org/Hri 0.150 45,000.00 6,750.00
- Kepala tukang Org/Hri 0.015 55,000.00 825.00
- Mandor Org/Hri 0.00075 50,000.00 37.50
b. Sub. Jumlah 8,152.50
Jumlah ( a + b ) 20,788.50
- Upah
- Pekerja Org/Hri 0.020 36,000.00 720.00
- Tukang Kayu Org/Hri 0.200 45,000.00 9,000.00
- Kepala tukang Org/Hri 0.020 55,000.00 1,100.00
- Mandor Org/Hri 0.001 50,000.00 50.00
b. Sub. Jumlah 10,870.00
Jumlah ( a + b ) 21,454.00
DAFTAR
ANALISA HARGA SATUAN
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
SANITARY
I. SNI-03-02-SN-6.36
Memasang 1 Buah Floor Drain
- Bahan
- Floor Drain Bh 1.0000 29,160.00 29,160.00
a. Sub. Jumlah 29,160.00
- Upah
- Tukang Batu Org/Hri 0.1000 45,000.00 4,500.00
- Pekerja Org/Hri 0.0100 36,000.00 360.00
- Kepala Tukang Org/Hri 0.0100 55,000.00 550.00
- Mandor Org/Hri 0.0050 50,000.00 250.00
b. Sub. Jumlah 5,660.00
Jumlah ( a + b ) 34,820.00
II. SNI-03-02-SN-6.35.A
Memasang 1 Buah Kran Air Nikel
- Bahan
- Kran Air Nikel Bh 1.0000 130,000.00 130,000.00
- Seal Tape Bh 0.0250 5,000.00 125.00
a. Sub. Jumlah 130,125.00
- Upah
- Tukang Batu Org/Hri 0.1000 45,000.00 4,500.00
- Pekerja Org/Hri 0.0100 36,000.00 360.00
- Kepala Tukang Org/Hri 0.0100 55,000.00 550.00
- Mandor Org/Hri 0.0050 50,000.00 250.00
b. Sub. Jumlah 5,660.00
Jumlah ( a + b ) 135,785.00
HARGA JUMLAH
NO. ITEM PEKERJAAN org/Hri KOEF. SATUAN HARGA
( Rp ) ( Rp )
I. SNI-03-02-SN-6.2.A
Memasang 1 Buah Kloset jongkok
- Bahan
- Kloset Jongkok Keramik KIA Bh 1.0000 104,976.00 104,976.00
- Semen Padang @ 40 Kg Zak 0.1500 40,600.00 6,090.00
- Pasir Pasang M3 0.0100 104,976.00 1,049.76
a. Sub. Jumlah 112,115.76
- Upah
- Tukang Batu Org/Hri 1.5000 45,000.00 67,500.00
- Pekerja Org/Hri 1.0000 36,000.00 36,000.00
- Kepala Tukang Org/Hri 1.5000 55,000.00 82,500.00
- Mandor Org/Hri 0.1600 50,000.00 8,000.00
b. Sub. Jumlah 194,000.00
Jumlah ( a + b ) 306,115.76
MEKANIKAL/PEMIPAAN
I. SNI-03-02-SN-6.25.A
Memasang 1 M' Pipa PVC Type AWE Diameter 3/4"
- Bahan
- Pipa PVC Type AWE Diameter 3/4" M' 1.2000 6,723.00 8,067.60
- Perlengkapan ( 35% Harga pipa ) Ls 1.0000 4,200.00 4,200.00
a. Sub. Jumlah 12,267.60
- Upah
- Tukang Batu Org/Hri 0.0600 45,000.00 2,700.00
- Pekerja Org/Hri 0.0360 36,000.00 1,296.00
- Kepala Tukang Org/Hri 0.0060 55,000.00 330.00
- Mandor Org/Hri 0.0018 50,000.00 90.00
b. Sub. Jumlah 4,416.00
Jumlah ( a + b ) 16,683.60
II. SNI-03-02-SN-6.25.B
Memasang 1 M' Pipa PVC Type AWE Diameter 3"
- Bahan
- Pipa PVC Type AWE Diameter 3" M' 1.2000 26,244.00 31,492.80
- Perlengkapan ( 35% Harga pipa ) Ls 1.0000 4,200.00 4,200.00
a. Sub. Jumlah 35,692.80
- Upah
- Tukang Batu Org/Hri 0.0600 45,000.00 2,700.00
- Pekerja Org/Hri 0.0360 36,000.00 1,296.00
- Kepala Tukang Org/Hri 0.0060 55,000.00 330.00
- Mandor Org/Hri 0.0018 50,000.00 90.00
b. Sub. Jumlah 4,416.00
Jumlah ( a + b ) 40,108.80
HARGA JUMLAH
NO. ITEM PEKERJAAN SAT. KOEF. SATUAN HARGA
( Rp ) ( Rp )
III. SNI-03-02-SN-6.25.D
Memasang 1 M' Pipa PVC Type AWE Diameter 4"
- Bahan
- Pipa PVC Type AWE Diameter 4" M' 1.2000 43,740.00 52,488.00
- Perlengkapan ( 35% Harga pipa ) Ls 1.0000 14,000.00 14,000.00
a. Sub. Jumlah 66,488.00
- Upah
- Tukang Batu Org/Hri 0.0600 45,000.00 2,700.00
- Pekerja Org/Hri 0.0360 36,000.00 1,296.00
- Kepala Tukang Org/Hri 0.0060 55,000.00 330.00
- Mandor Org/Hri 0.0018 50,000.00 90.00
b. Sub. Jumlah 4,416.00
Jumlah ( a + b ) 70,904.00
IV. SNI-03-02-SN-6.25.E
Memasang 1 M' Pipa PVC Type AWE Diameter 4" Berlubang
- Bahan
- Pipa PVC Type AWE Diameter 4" Berlubang M' 1.2000 52,488.00 62,985.60
- Perlengkapan ( 35% Harga pipa ) Ls 1.0000 14,000.00 14,000.00
a. Sub. Jumlah 76,985.60
- Upah
- Tukang Batu Org/Hri 0.0600 45,000.00 2,700.00
- Pekerja Org/Hri 0.0360 36,000.00 1,296.00
- Kepala Tukang Org/Hri 0.0060 55,000.00 330.00
- Mandor Org/Hri 0.0018 50,000.00 90.00
b. Sub. Jumlah 4,416.00
Jumlah ( a + b ) 81,401.60
V. SNI 03-2838-2002- 6 - n
Pekerjaan Pengecatan per m2
- Bahan
- Cat dinding acrylic emulsion setara Vinilex kg 0.4000 22,500.00 9,000.00
- Waste kg 0.0300 22,500.00 675.00
- Alat bantu ls 1.0000 7,500.00 7,500.00
a. Sub. Jumlah 9,675.00
Upah
Pekerja OH 0.600 36,000.00 21,600.00
Tukang OH 0.150 45,000.00 6,750.00
Kepala Tukang OH 0.045 55,000.00 2,475.00
Mandor OH 0.030 50,000.00 1,500.00
b. Sub. Jumlah 32,325.00
Jumlah ( a + b ) 121,683.90
VI. SNI 03-2838-2002- 5 - a
### Pas. Keramik Dinding Roman 40 x 40 per m2
Keramik 40 x 40 m2 1.000 48,000.00 48,000.00
Waste m2 0.050 48,000.00 2,400.00
Semen portland kg 12.300 1,015.00 12,484.50
Pasir pasang m3 0.025 104,976.00 2,624.40
grout nat kg 0.500 7,500.00 3,750.00
Alat bantu ls 1.000 7,500.00 7,500.00
a. Sub. Jumlah 76,758.90
Upah
Pekerja OH 0.600 36,000.00 21,600.00
Tukang OH 0.150 45,000.00 6,750.00
Kepala Tukang OH 0.045 55,000.00 2,475.00
Mandor OH 0.030 50,000.00 1,500.00
b. Sub. Jumlah 32,325.00
Jumlah ( a + b ) 109,083.90
DAFTAR HARGA UPAH DAN BAHAN D
HARGA
NO. URAIAN SATUAN
( Rp )
A. UPAH PEKERJA
Page 27
DAFTAR HARGA UPAH DAN BAHAN D
HARGA
NO. URAIAN SATUAN
( Rp )
Page 28
DAFTAR HARGA UPAH DAN BAHAN D
HARGA
NO. URAIAN SATUAN
( Rp )
Page 29
Panjang Lebar Tebal Luas Volume Jumlah Total Panjang
J1 6.44 0.06 0.13 1.6008 0.050232 2 12.88
J2 4.04 0.06 0.13 0.9048 0.031512 2 8.08
J3 7.26 0.06 0.13 2.2968 0.056628 1 7.26
Kuda - Kuda
Kayu Kuda 36
Gording 80
Ikat Angin 16
Total Luas Total Volume
3.2016 0.100464
1.8096 0.063024
2.2968 0.056628
2.2032 0.041652
5.9616 0.122616
1.7712 0.01381536
17.244 0.39819936