Installation Instructions
SIAE – Eband - Dual polarization
LEAX Arkivator Telecom disclaims any liability for the results of improper or unsafe installation, inspection,
maintenance, or removal practices.
2(7)
Included parts
Item Qty Description
A 1 Antenna (0.3m or 0.6m)
1 Antenna
1 Antenna support
B 1 OMT
1 OMT
8 M6 Nuts
8 M6 Hex distance
4 M8x25 Screw
2 M6x50 Screw
C 1 IPL Lid kit (optional)
1 IPL Lid incl. O-ring
3 M3x10 Screw
Tools required
Allen key; 2,5mm for M3, 3mm for M4 and 5mm for M6.
Combination wrench (ring/open jaw); 2pcs Hex 10 for M6 and 1pcs Hex 13 for M8.
Tool for torque levels; 0,9Nm, 7Nm and 24Nm.
3(7)
Assembly
Step 1 – OMT
a) Mount 8pcs M6 Hex distance with 8pcs Nuts through Adapter plates on OMT.
b) Use two Combination wrenches (Hex 10) and tighten the nuts with 7Nm±5%.
8pcs M6 hex
distance
8pcs M6 nut
Arrows
indicates UP
Aligned for H,
indicates
Horizontal side
4(7)
c) Remove 1pc protection tape from Feed.
Do NOT
remove Feed
d) Place OMT against Feed. Check that guide pins in OMT are properly inserted in guide
pin holes in Feed, mount 2pcs M6x50 (Allen) and tighten them by hand.
e) Mount 4pcs M8x25 (Hex) Polarization screws, through OMT, into Antenna and tighten
them with 24Nm±5%.
f) Tighten the 2pcs of screws M6x50 (Allen) with 7Nm±5%
2pcs M6x50
4pcs M8x25
polarization screws
5(7)
Step 3 – IPL Lid kit (optional)
If only one radio shall be mounted an optional Lid can be mounted on the opposite side of OMT.
Aligned for V,
indicates
Vertical side
3pcs M3x10
6(7)
Antenna Alignment
Polarization adjustment
For Azimuth and Elevation adjustment see antenna manual.
Polarization
screws 4pcs
M8x25
Polarization -5°
Polarization
screws 4pcs
M8x25
Polarization +5°
7(7)