Anda di halaman 1dari 2

Environment

and Safety
N. KADAM, IBI Chematur Engineering
and Consultancy, Mumbai, India

A brief guide to fire zone analysis


Every process plant has a dedicated source of fire irrespective of the elevation pass across other equipment, then
disposal system to ensure that gases from aboveground. To simplify the procedure, those pieces of equipment are
equipment, instruments and pressure equipment located below 7.6 m is consid- considered to form a composite
safety valves are flared to follow environ- ered a source of fire in most cases. fire zone.
mental norms for the gases vented to the • Provision of dike. Tanks handling
atmosphere from the flare stack. Marking a fire circle. As an optimized flammable liquid or combustible
To estimate the combined relief load approach, the fire impact area is considered liquid above flashpoint are provided
for the external fire scenario, the maxi- to be 230 m2 in most cases. Fire circles are with a dike to avoid spillage to other
mum extent of the fire should be esti- then marked, considering the source of equipment. As a general rule, each
mated. API 5211 defines a fire impact area the fire as a nucleus. The radius of the fire dike is considered to be a fire zone.
of 230 m2 to 460 m2 around the source circle is 8.6 m, which is equivalent to a fire
of fire. However, it does not define the impact area of 230 m2. Relieving load for Checking protection against fire. Af-
exact shape of the area. For a simplified the fire scenario must be calculated for all ter marking fire circles around the sources
approach, the shape is always considered equipment inside the fire circle. of fire, the pieces of equipment inside
as a circle, often referred to as a fire circle. each fire circle are checked for protec-
This ensures that every piece of equip- Identification of fire zones. Identify- tion against fire contingency. To comply
ment in the fire circle radius is considered ing fire zones is a subjective process, and with requirements, process safety valves
for estimating the combined relief load. the criteria varies on a case-by-case basis. (PSVs) on this equipment must be sized
Various considerations, such as actual Two terms can be used to explain the cri- for the fire scenario. If any equipment in-
layout of the plant, the location of the fire teria in brief: side the fire circle is not provided with a
source and provision of the drainage and • Ground slope direction. For ease PSV, then a PSV must be provided and
dikes, need to be addressed while defin- of calculations, each fire circle sized specifically for the fire case.
ing fire circles. Basic steps for defining fire is considered to be a fire zone. The following example gives a clear
circles and fire zones are outlined in the However, in some cases, if ground picture of the procedure. FIG. 1 shows the
following sections. slope direction is such that spillage layout of equipment with a sloping grade
from one piece of equipment can and a trench location. The first step to
Identification of fire source. Equip-
ment that handles flammable fluid or Dike
D-01
combustible liquid above flashpoint is D-02 T-03 T-02
considered a source of fire. A list of such T-01
Dike
equipment should be prepared, and these E-01A V-05
V-01 V-08
items should be identified on an equip-
V-09 V-07
ment layout. Note: API does not specify V-03
E-03

E-01B FL-01
the height (elevation from the grade) lim-
E-04

V-06
V-04
it to identify equipment as a source of fire.
E-02

E-01C
It dictates only the limit of the fire, which V-02
C-01
is 7.6 m from the grade or any solid floor V-10
where a pool fire can occur.
In the absence of an international code, Legend
the user may assume that, even if the equip- Slope direction Fire Zone 4
Fire Zone 1 Fire Zone 5
ment is elevated 7.6 m above fire height, Fire Zone 2 Trench (drainage)
it can still accumulate enough liquid on Fire Zone 3 Equipment located above 7.6 m
the ground to trigger a pool fire. There-
FIG. 1. Equipment layout for fire zone consideration.
fore, that equipment may be considered a
Hydrocarbon Processing | JULY 2018 83
Environment and Safety

around E-03 and V-06. As


TABLE 1. Equipment and fire source identification.
explained above, these pieces
Equipment tag Fluid Elevation from grade Source of fire of equipment could form a fire
C-01 Flammable Above 7.6 m No
zone. However, referring to
FIG. 1, the sloping of the grade is
D-01 Not flammable At grade No such that, in the event of spillage
D-02 Not flammable At grade No from E-02 or E-03, liquid would
E-01A/B/C Flammable Below 7.6 m Yes not flow toward vessel V-06.
E-02 Flammable Below 7.6 m Yes
Also, in the event of spillage
from V-06, liquid would not flow
E-03 Combustible Below 7.6 m Yes toward E-02 or E-03. Therefore,
(above flashpoint)
different fire zones have been
E-04 Not flammable Below 7.6 m No defined considering the slope
FL-01 Not flammable Below 7.6 m No direction. E-02 and E-03, along
T-01 Not flammable At grade No with V-02 and V-03, form Fire
Zone 2, whereas V-06 and F-01
T-02 Flammable At grade Yes
together form Fire Zone 3.
T-03 Not flammable At grade No o Fire Zone 4: T-02, which
V-01 Not flammable Below 7.6 m No handles a flammable liquid, is
V-02 Not flammable Below 7.6 m No provided with a dike to hold up
a total tank inventory in the case
V-03 Not flammable Below 7.6 m No
of spillage. A dedicated fire zone
V-04 Not flammable Below 7.6 m No for this tank may also serve as a
V-05 Flammable Above 7.6 m No dike. T-02 forms Fire Zone 4.
V-06 Flammable Below 7.6 m Yes o Fire Zone 5: V-09 forms Fire
Zone 5.
V-07 Flammable Above 7.6 m No
• Checking safeguards against fire.
V-08 Not flammable Below 7.6 m No TABLE 2 shows lists of equipment
V-09 Flammable Below 7.6 m Yes contained within different fire
V-10 Not flammable Below 7.6 m No zones. Relief designers must check
the safeguards provided to this
equipment against various fire
located above 7.6 m are not scenarios. As an example, before
TABLE 2. Equipment contained within
fire zones.
considered to be sources of fire, fire zone analysis, V-02 and V-03
even if they handle flammable fluid. were not provided with PSVs since
Zone Source of fire Equipment Equipment pieces C-01, V-05 and these vessels handle condensate.
in fire zone
V-07 in FIG. 1 are drawn with dotted However, since they are located in
Zone 1 E-01A/B/C E-01A/B/C lines to identify them as being a fire zone, PSVs must be provided
Zone 2 E-02 E-02 located 7.6 m above the grade. to these vessels to protect them in a
E-03 E-03
• Marking a fire circle. A circle with fire scenario.
a radius of 8.6 m shall be marked Considerations for fire zone analysis
V-02
around equipment identified in vary based on user discretion. However,
V-03 TABLE 1 as sources of fire. the procedure outlined here can be fol-
Zone 3 V-06 V-06 • Defining fire zones. As shown lowed if no special requirements exist to
FL-01
in FIG. 1, five fire zones have been define fire zones.
defined considering the layout,
Zone 4 T-02 T-02 sloping and other parameters: LITERATURE CITED
Zone 5 V-09 V-09 o Fire Zone 1: E-01A/B/C handle 1
American Petroleum Institute, API Standard 521,
flammable fluid and are located “Pressure-relieving and depressuring systems,” 6th
below 7.6 m. The fire circle Ed., 2014.
identify fire zones in this area is to iden- around E-01B intersects with
tify the sources of fire. TABLE 1 shows a list the fire circle around E-01A and NIKHIL KADAM is a Principal
of equipment and identifies certain pieces E-01C. A fire in either of these Process Engineer with IBI Chematur
Engineering and Consultancy in
as sources of fire. exchangers would affect the Mumbai, India. He has more than 11
• Identifying sources of fire. other exchangers. Together, these yr of experience in front-end
Referring to TABLE 1, equipment exchangers form Fire Zone 1. engineering and design (FEED) and
detailed engineering, and has
located below 7.6 m and handling o Fire Zone 2 and Fire Zone 3: worked on various oil and gas, refinery and chemical
flammable fluid are considered The fire circle around E-02 projects. He holds a BS degree in chemical
to be sources of fire. Equipment intersects with the fire circles engineering from Mumbai University in Mumbai, India.

84 JULY 2018 | HydrocarbonProcessing.com

Anda mungkin juga menyukai