SECTION 1 : EARTHWORK
1.3 EXCAVATIONS
1
from walls and footings to allow for the proper erection
and dismantling of forms, installation of service lines and
for inspection.
2
1.4 BACKFILLING AND GRADING
1.4.1 After the forms have been removed from the footings,
piers, foundation walls, etc., and when the concrete is
hard enough to resist pressure from resulting fill, all
trash, wood chips and other debris shall be removed
from areas to be back filled.
1.4.4 Before placing fill materials, the surface upon which it will
be placed shall be cleared of all bushes, roots, vegetable
matters and debris, scarified and thoroughly wetted to
insure good bonding between the ground and the fill
materials. Fill in contact with the new concrete work
shall not be placed until at least 48 hours after removal
of forms, or as directed by the Engineer.
1.4.6 The Contractor shall fill and grade the whole area around
the structure to the indicated sub-grade elevation as
directed by the Engineer. The contractor shall verify the
finish grade elevations of the proposed pavements
around the structure. Prior to grading operations, the
area shall be cleared of all heavy growth of vegetation
stumps, roots, cables, wires, rocks and other debris.
The finished sub-grade shall be reasonably smooth and
compacted and ready to receive the base course for the
proposed pavements.
3
1.6 DISPOSAL OF EXCESS MATERIALS
- End of Section -
4
SECTION 2: CONCRETE BORED PILES
Preparatory Works
The ground level for pile construction shall be at least 1 meter higher
than elevation of the W.T. such level shall be achieved by forming if
necessary an embankment of cohesive soils.
To check the presence of artesian water tables, Casagrande type
piezometers or equivalents shall be placed at the top of the hole, in the
same way, before starting the drilling of piles from platworms or self-
elevating platforms, a temporary or permanent casing shall be driven into
the soil underlying the water to ensure the stability of the hole,
Slurry Preparation
The slurry shall be obtained by mixing the following materials until a finely
dispersed suspension is obtained:
- water
- bentonite in powder forms
- eventual activities
5
7 Kg/cm2 < 25 cm3
Slurry “Ageing” basins or tanks shall be adopted in which the slurry shall
be kept for 24 hours after preparation, before being used in excavating
operations.
The characteristics of the slurry ready for use shall not exceed the
following limits:
The values indicated above refer to the slurry close to the bottom of the
hole and shall be obtained from slurry samples by means of submerged
pump. The values determined before the start of the pouring operations
6
shall be obtained form samples taken 80 cm. ,Above the bottom of the
pit.
Excavation Procedure
After the excavation has been completed, the bottom of the pit shall be
carefully cleaned, using the bucket it-self, in order to take away any loose
material or soil detrites which may have been broken up by the tool.
Pile Reinforcement
Concrete preparation
The initial setting of the mixed concrete in the pit shall not occur before
the end the casting period, In order to comply with all the above
requirements suitable admixtures may be used.
The truck mixing time will be determined on the bases of the job trial
mixes.
7
The tube shall consist of steel sections not exceeding 2.5 m in length with
an inside diameter of at least 20 cm.
During grouting, suitable stopper shall be placed at the top of the tremie
pipe.
The length of the pipe may reduced during grouting provided that the
open end results immerged at least 2,5 m in the concrete at all times.
The concrete shall be produced and delivered at such rate to permit the
completion of the pouring of each element of the piles within the time
limits allowed by the workability of the mix.
Concrete characteristics.
Testing
Two type of tests shall run to control the quality and determine the
mechanical characteristics of the cast concrete.
One test of the above mentioned types shall be carried out for each
hundred pile elements.
Tolerance Limits
Records
1. Drilling
2. Concreting
8
The above mentioned controls of the bentonite slurry shall be done after
the mud has been cleaned and before starting the grouting operations.
- End of Section -
9
SECTION 3 : REINFORCED CONCRETE
3.2 MATERIAL
3.2.4 Water: Mixing water for concrete shall be free, clean and
free from injurious amount of oil, acids, alkali, organic
materials or other substances that maybe deleterious to
concrete or steel.
10
3. Natural or manufactured sand shall be allowed to
drain until had reached a relatively uniform
moisture content before it is used.
3.3 PROPORTIONING
3.3.1 General: Concrete for all parts of the work shall be of the
specified quality capable of being placed without excessive
segregation.
3.3.3 Durability:
11
3.3.6 Admixtures: If required or permitted, admixtures used
shall be subject to the following limitations:
3.4 FORMWORKS
12
2. The formwork shall designed for the loads, lateral
pressure and allowable stresses outlined in the
“RECOMMENDED PRACTICE FOR CONCRETE
FORMWORK (ACI 347) and for design
consideration, wind load, allowable stresses and
other applicable requirements of the local building
code.
13
3.4.3 Tolerances: Unless otherwise specified, formwork shall be
constracted so that the concrete surfaces shall be conform
to the following tolerance limits
In any bay - 6 mm
In any 6.0 meter of length - 6 mm
Max. for the entire length - 25 mm
Minus - 6 mm
Plus - 12 mm
6. Footings
14
7. Variation in Steps:
A. In flight of stairs
Rise - + 3 mm
Tread - + 6 mm
B. In consecutive steps
Rise - + 1.5mm
Tread - + 6 mm
3.4.6 Reshoring :
15
than the end of the working day on which stripping
occurs.
3.5 REINFORCEMENT
16
3.5.2 Welding : When required or approved, welding of
reinforcing steel shall conform to “REINFORCING STEEL
WELDING CODE (AWS D12.1). No welding shall be
done at the bend in a bar welding of crossing bars (tack
welding) shall not be permitted except as authorized or
directed by the Structural Engineer: The ASTM
Specification s shall be supplemented by requirements
assuming satisfactory weldability by this procedure.
5. Lengthwise of members - + 50 mm
Bars > ø 20 - 50 mm
Bars < ø 20 - 35 mm
3. Interior surfaces
17
All reinforcement shall be supported and fastened
together to prevent displacement b, construction loads
or the placing of concrete beyond the tolerances of
section 2.5.3. On ground, where necessary,
supporting blocks maybe used. Over formwork,
concrete, metal, or other approved bars chairs and
spacers shall be used.
18
3.7 PRODUCTION OF CONCRETE:
3.8 PLACING
3.8.2 Conveying.
19
operations shall conform to the following additional
requirements.
3.8.3 Depositing
20
Unless adequate protection is provided and approved by
the Project Manager is obtained, concrete shall not be
placed during rain.
3.8.4 Bonding
21
After surface water has evaporated from the area to be
patched, the bond coat shall be will brushed unto the
surface. When the bond coated begins to lose the water
sheen, the provided patching mortar shall be applied. The
mortar shall be thoroughly consolidated into place and
stuck off so as to leave the patch slightly higher than the
surrounding surface. To permit initial shrinkage, it shall be
left undistributed for at least 1 hour before being finally
finished. The patched area shall be kept damp for 7 days.
Metal toll shall not be used in finishing a patch in formed
wall which will be exposed.
- End of Section -
22
TABLE OF CONTENTS
23