Task Project Summary Inactive Milestone Manual Summary Rollup Deadline Manual Progress
Split External Tasks Inactive Summary Manual Summary Critical
Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline Manual Progress
Split External Tasks Inactive Summary Manual Summary Critical
Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline Manual Progress
Split External Tasks Inactive Summary Manual Summary Critical
Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline Manual Progress
Split External Tasks Inactive Summary Manual Summary Critical
Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline Manual Progress
Split External Tasks Inactive Summary Manual Summary Critical
Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline Manual Progress
Split External Tasks Inactive Summary Manual Summary Critical
Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline Manual Progress
Split External Tasks Inactive Summary Manual Summary Critical
Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress
1388 Ductwork distribution, including insulation, dampers and accessories 0% 20 dys 10/07/2019 01/08/2019
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline Manual Progress
Split External Tasks Inactive Summary Manual Summary Critical
Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress
1488 Ductwork distribution, including insulation, dampers and accessories 0% 20 dys 03/12/2018 03/01/2019
1489 Equipment 0% 20 dys 14/12/2018 15/01/2019
1490 Last fix: grilles-subject for Employer's confirmation for Ceilings 0% 10 dys 15/05/2019 25/05/2019
1491 Sanitary and fire fighting 0% 137 dys 08/12/2018 29/05/2019
1492 Water and sewage piping distribution, including valves and accessories 0% 15 dys 08/12/2018 03/01/2019
1493 Sprinkler and hydrant piping distribution, including valves and accessories 0% 20 dys 08/12/2018 09/01/2019
1494 Last fix: sanitary fixtures 0% 7 dys 22/05/2019 29/05/2019
1495 Last fix: sprinkler heads-subject for Employer's confirmation for Ceilings 0% 10 dys 15/05/2019 25/05/2019
1496 Last fix: hydrant boxes 0% 10 dys 11/02/2019 21/02/2019
1497 Low Voltage 0% 142 dys 14/12/2018 11/06/2019
1498 Cable trays and empty tubes 0% 20 dys 14/12/2018 15/01/2019
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline Manual Progress
Split External Tasks Inactive Summary Manual Summary Critical
Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline Manual Progress
Split External Tasks Inactive Summary Manual Summary Critical
Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline Manual Progress
Split External Tasks Inactive Summary Manual Summary Critical
Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline Manual Progress
Split External Tasks Inactive Summary Manual Summary Critical
Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline Manual Progress
Split External Tasks Inactive Summary Manual Summary Critical
Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress
2012 Ductwork distribution, including insulation, dampers and accessories 0% 70 dys 20/04/2019 15/07/2019
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline Manual Progress
Split External Tasks Inactive Summary Manual Summary Critical
Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress