EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER

S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

MEZCLA CONCRETO 1:2:3 3100 PSI - 22,0 Mpa Unidad: M3


ITEM: BASICO
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 190 0 16.00 3,040.00
ARENA GRUESA M3 0.56 0 60,000.00 33,600.00
GRAVA TRITURADA DE 3/4 M3 0.84 0 70,000.00 58,800.00
GASOLINA CORRIENTE GLN 0.1 0 8,700.00 870.00
CEMENTO GRIS KLS 350 0 600.00 210,000.00
ACEITE MOTOR 4 TIEMPOS GLN 0.006 0 70,000.00 420.00
SUBTOTAL MATERIALES 306,730.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 7.273 13,472.16
SUBTOTAL MANO DE OBRA 13,472.16
EQUIPO
MEZCLADORA DE 9 PIES CUBICOS DIA 0.06 0 38,800.00 2,328.00
HERRAMIENTA MENOR % 5% 0 13,472.16 673.60
SUBTOTAL EQUIPO 3,001.60

COSTO DIRECTO 323,203.76 323,204.00

MORTERO DE PEGA PARA BLOQUE Unidad: M3


ITEM: BASICO
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ARENA MEDIANA M3 1.1 1 27,000.00 29,997.00
CEMENTO GRIS KLS 359 1 600.00 217,554.00
CAL HIDRATADA NARE SACO 10 KILOS KLS 78 1 690.00 54,358.20
SUBTOTAL MATERIALES 301,909.20

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 5.334 18,369.52
SUBTOTAL MANO DE OBRA 18,369.52
EQUIPO
HERRAMIENTA MENOR % 5% 0 18,369.52 918.47
SUBTOTAL EQUIPO 918.47

COSTO DIRECTO 321,197.19 321,197.00

MEZCLA CONCRETO 1:2:4 2500 PSI - 17,5 Mpa Unidad: M3


ITEM: BASICO
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 160 0 16.00 2,560.00
ARENA GRUESA M3 0.52 0 60,000.00 31,200.00
GRAVA TRITURADA DE 3/4 M3 0.94 0 70,000.00 65,800.00
GASOLINA CORRIENTE GLN 0.1 0 8,700.00 870.00
CEMENTO GRIS KLS 260 0 600.00 156,000.00
ACEITE MOTOR 4 TIEMPOS GLN 0.006 0 70,000.00 420.00
SUBTOTAL MATERIALES 256,850.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 7.273 13,472.16
SUBTOTAL MANO DE OBRA 13,472.16
EQUIPO
MEZCLADORA DE 9 PIES CUBICOS DIA 0.06 0 38,800.00 2,328.00
HERRAMIENTA MENOR % 5% 0 13,472.16 673.60
SUBTOTAL EQUIPO 3,001.60

COSTO DIRECTO 273,323.76 273,324.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

MORTERO 1:2 Unidad: M3


ITEM: BASICO
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 250 0 16.00 4,000.00
ARENA MEDIANA M3 0.97 0 27,000.00 26,190.00
CEMENTO GRIS KLS 510 0 600.00 306,000.00
SUBTOTAL MATERIALES 336,190.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 5.334 18,369.52
SUBTOTAL MANO DE OBRA 18,369.52
EQUIPO
HERRAMIENTA MENOR % 5% 0 18,369.52 918.47
SUBTOTAL EQUIPO 918.47

COSTO DIRECTO 355,477.99 355,477.00

MEZCLA CONCRETO 1:2:4 2850 PSI - 20,0 Mpa Unidad: M3


ITEM: BASICO
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 180 0 16.00 2,880.00
ARENA GRUESA M3 0.48 0 60,000.00 28,800.00
GRAVA TRITURADA DE 3/4 M3 0.95 0 70,000.00 66,500.00
GASOLINA CORRIENTE GLN 0.1 0 8,700.00 870.00
CEMENTO GRIS KLS 300 0 600.00 180,000.00
ACEITE MOTOR 4 TIEMPOS GLN 0.006 0 70,000.00 420.00
SUBTOTAL MATERIALES 279,470.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 7.273 13,472.16
SUBTOTAL MANO DE OBRA 13,472.16
EQUIPO
MEZCLADORA DE 9 PIES CUBICOS DIA 0.06 0 38,800.00 2,328.00
HERRAMIENTA MENOR % 5% 0 13,472.16 673.60
SUBTOTAL EQUIPO 3,001.60

COSTO DIRECTO 295,943.76 295,944.00

MORTERO 1:3 Unidad: M3


ITEM: BASICO
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 220 0 16.00 3,520.00
ARENA MEDIANA M3 1.09 0 27,000.00 29,430.00
CEMENTO GRIS KLS 454 0 600.00 272,400.00
SUBTOTAL MATERIALES 305,350.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 5.334 18,369.52
SUBTOTAL MANO DE OBRA 18,369.52
EQUIPO
HERRAMIENTA MENOR % 5% 0 18,369.52 918.47
SUBTOTAL EQUIPO 918.47

COSTO DIRECTO 324,637.99 324,637.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

VALLA INFORMATIVA UNIDAD: UND


ITEM: 1.1
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUMINISTRO VALLA INFORMATIVA UND 1 0 1,100,000.00 1,100,000.00
MEZCLA CONCRETO 1:2:3 3100 PSI 210 MPa M3 0.3 5 323,204.00 101,809.26

SUBTOTAL MATERIALES 1,201,809.26


MANO DE OBRA
M.O. ALBANILERIA 2 AYUDANTE-1 OFI 97,094.00 185% 179,623.00 0.7928 226,567.86

SUBTOTAL- MANO DE OBRA 226,567.86


EQUIPO
ANDAMIO METALICO TUBULAR U/D 13.8028 1,050.00 14,492.94
CRUCETA ANDAMIO DIA 105 100.00 10,500.00
HERRAMIENTA MENOR % 5% 226,567.86 11,328.39

SUBTOTAL- EQUIPO 36,321.33

COSTO DIRECTO 1,464,698.45 1,464,698.00

TRAZADO, LOCALIZACION Y REPLANTEO ZONA ASCENSO Unidad: ML


ITEM: 1.2
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LISTON 2 x2x3M. UND 0.05 0 3,800.00 190.00
PUNTILLA 2 CC LBS 0.01 0 2,000.00 20.00
PIOLA GRUESA 50 METROS ROL 0.01 0 2,500.00 25.00
SUBTOTAL MATERIALES 235.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE-1 OFI 97,094.00 185% 179,623.00 71.8492 2,500.00
M.O. TOPOGRAFIA 1 CADENERO-1 TOP 194,469.00 185% 359,767.00 75.2839 4,778.80
SUBTOTAL MANO DE OBRA 7,278.80
EQUIPO
HERRAMIENTA MENOR % 5% 0 7,278.80 363.94
SUBTOTAL EQUIPO 363.94

COSTO DIRECTO 7,877.74 7,878.00

DESCAPOTE Y LIMPIEZA DE LA ZONA DE TRABAJO ZONA ASCENSO Unidad: ML


ITEM: 1.3
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 8.1830 5,986.92
SUBTOTAL MANO DE OBRA 5,986.92
EQUIPO
HERRAMIENTA MENOR % 5% 0 5,986.92 299.34
SUBTOTAL EQUIPO 299.34

COSTO DIRECTO 6,286.26 6,286.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

TRAZADO, LOCALIZACION Y REPLANTEO ZONA MESA Unidad: ML


ITEM: 1.4
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LISTON 2 x2x3M. UND 0.05 0 3,800.00 190.00
PUNTILLA 2 CC LBS 0.01 0 2,000.00 20.00
PIOLA GRUESA 50 METROS ROL 0.01 0 2,500.00 25.00
SUBTOTAL MATERIALES 235.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE-1 OFI 97,094.00 185% 179,623.00 224.5288 800.00
M.O. TOPOGRAFIA 1 CADENERO-1 TOP 194,469.00 185% 359,767.00 362.2708 993.09
SUBTOTAL MANO DE OBRA 1,793.09
EQUIPO
HERRAMIENTA MENOR % 5% 0 1,793.09 89.65
SUBTOTAL EQUIPO 89.65

COSTO DIRECTO 2,117.74 2,118.00

DESCAPOTE Y LIMPIEZA DE LA ZONA DE TRABAJO ZONA MESA Unidad: ML


ITEM: 1.5
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 16.1106 3,040.92
SUBTOTAL MANO DE OBRA 3,040.92
EQUIPO
HERRAMIENTA MENOR % 5% 0 3,040.92 152.04
SUBTOTAL EQUIPO 152.04

COSTO DIRECTO 3,192.96 3,193.00

MANEJO DE AGUAS Unidad: GLB


ITEM: 2.1
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
MANGUERA Y OTROS UND 100 0 7,500.00 750,000.00

SUBTOTAL MATERIALES 750,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 0.0403 1,215,657.57
SUBTOTAL MANO DE OBRA 1,215,657.57
EQUIPO
MOTOBOMBA DE 3" DIA 50.6133 39,500.00 1,999,225.35
HERRAMIENTA MENOR % 0.05 1,215,657.57 60,781.05

SUBTOTAL EQUIPO 2,060,006.40

COSTO DIRECTO 4,025,663.97 4,025,664.00

EXCAVACION EN CONGLOMERADO A MAQUINA Unidad: M3


ITEM: 2.2
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

EQUIPO
RETROEXCAVADORA JD-510 HRS 0.18239 88,000.00 16,050.32
SUBTOTAL EQUIPO 16,050.32

COSTO DIRECTO 16,050.32 16,050.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

CONCRETO IMPERMEABILIZADO 4000 PSI Unidad: M3


ITEM: 2.3
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
PLASTOCRETE D.M. (20 KGS) KLS 3 0 6,366.00 19,098.00
AGUA LTS 210 0 16.00 3,360.00
ARENA GRUESA M3 0.87 0 60,000.00 52,200.00
GRAVA TRITURADA DE 3/4 M3 0.47 0 70,000.00 32,900.00
GASOLINA CORRIENTE GLN 0.1 0 8,700.00 870.00
CEMENTO GRIS KLS 480 0 600.00 288,000.00
ACEITE MOTOR 4 TIEMPOS GLN 0.006 0 70,000.00 420.00
SUBTOTAL MATERIALES 396,848.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. oficial + 2 AYUDANTE 118,130.83 185% 218,542.04 1.30 168,109.26
SUBTOTAL MANO DE OBRA 168,109.26
EQUIPO
MEZCLADORA DE 9 PIES CUBICOS DIA 0.07999 0 38,800.00 3,103.61
HERRAMIENTA MENOR % 0.04999 0 59,189.92 2,958.90
SUBTOTAL EQUIPO 6,062.51

COSTO DIRECTO 462,100.43 571,020.00

ACERO REFUERZO FLEJADO 60000 PSI 420Mpa Unidad: KLS


ITEM: 2.4
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ALAMBRE NEGRO # 18 KLS 0.04 0.03 3,500.00 140.04
SEGUETA SIN MARCO UND 0.04 0.03 2,600.00 104.03
HIERR.DE 60000 PSI 420 MPA KLS 1.03 0 4,000.00 4,120.00
SUBTOTAL MATERIALES 4,364.07

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 62.3058 786.30
SUBTOTAL MANO DE OBRA 786.30

COSTO DIRECTO 5,150.37 5,150.00

FILTRO SEGUN NORMA INVIAS Unidad: M3


ITEM: 2.5
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ROCA MUERTA (SIN TRANSPORTE) M3 1 0 18,500.00 18,500.00
GEODREN FILTRO ML 1 0 24,500.00 24,500.00
SUBTOTAL MATERIALES 43,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 3 AYUDANTE-1 OFI 123,576.00 185% 228,615.00 7.9062 28,915.91
SUBTOTAL MANO DE OBRA 28,915.91
EQUIPO
VOLQUETA TRANSPORTE MAT.PETREOS 1-10KMS M3 1 7,000.00 7,000.00
RETROEXCAVADORA JD-510 HRS 0.16 88,000.00 14,080.00
HERRAMIENTA MENOR % 5% 0 28,915.91 1,445.79
SUBTOTAL EQUIPO 22,525.79

COSTO DIRECTO 94,441.70 94,442.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
RELLENO MATERIAL SITIO COMPACATDO-RANA Unidad: M3
ITEM: 2.6
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 7 0 16.00 112.00
GASOLINA CORRIENTE GLN 0.05 0 8,700.00 435.00
ACEITE MOTOR 4 TIEMPOS GLN 0.015 0 70,000.00 1,050.00
SUBTOTAL MATERIALES 1,597.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 7.3049 13,413.33
SUBTOTAL MANO DE OBRA 13,413.33
EQUIPO
VIBROCOMPACTADOR TIPO RANA DIA 0.1 39,000.00 3,900.00
HERRAMIENTA MENOR % 5% 0 13,413.33 670.66
SUBTOTAL EQUIPO 4,570.66

COSTO DIRECTO 19,580.99 19,581.00

CONCRETO 1:2:4 2500 PSI - 17,5 Mpa Unidad: M3


ITEM: 2.7
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 160 0 16.00 2,560.00
ARENA GRUESA M3 0.52 0 60,000.00 31,200.00
GRAVA TRITURADA DE 3/4 M3 0.94 0 70,000.00 65,800.00
GASOLINA CORRIENTE GLN 0.1 0 8,700.00 870.00
CEMENTO GRIS KLS 280 0 600.00 168,000.00
ACEITE MOTOR 4 TIEMPOS GLN 0.006 0 70,000.00 420.00
SUBTOTAL MATERIALES 268,850.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 3 AYUDANTE-1 OFI 123,576.00 185% 228,615.60 1.4000 163,296.86
SUBTOTAL MANO DE OBRA 163,296.86
EQUIPO
MEZCLADORA DE 9 PIES CUBICOS DIA 0.0601 0 38,800.00 2,331.88
HERRAMIENTA MENOR % 0.04999 0 75,838.24 3,791.15
SUBTOTAL EQUIPO 6,123.03

COSTO DIRECTO 338,811.27 438,269.89

EXCAVACION EN ROCA Unidad: M3


ITEM: 2.8
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

EQUIPO
COMPRESOR DE DOS MARTILLOS HRS 0.8608 0 92,000.00 79,193.60
RETROEXCAVADORA JD-510 HRS 0.035 88,000.00 3,080.00
HERRAMIENTA MENOR GLB 0.8029 0 1,400.00 1,124.06
SUBTOTAL EQUIPO 83,397.66

COSTO DIRECTO 83,397.66 83,398.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
CONCRETO 3.00 PSI, ZAPATAS, V.CIMENTACION Y PISOS Unidad: M3
ITEM: 2.9
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
PUNTILLA 2 CC LBS 0.5 0 2,000.00 1,000.00
TABLA 1X10x3M [2C] UND 0.2 0 9,000.00 1,800.00
VARETA 2"x2"x3M UND 0.2 0 2,400.00 480.00
MEZCLA CONCRETO 1:2:3 3100 PSI - 22,0 Mpa M3 1.05 0 323,204.00 339,364.20
SUBTOTAL MATERIALES 342,644.20

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 3 AYUDANTE-1 OFI 123,576.00 185% 228,615.60 1.7000 134,479.76
SUBTOTAL MANO DE OBRA 134,479.76
EQUIPO
VIBRADOR ELECTRICO DIA 0.05 0 34,800.00 1,740.00
VOLQUETA TRANSPORTE MAT.PETREOS 1-10KMS M3 0.3 0 7,000.00 2,100.00
SUBTOTAL EQUIPO 3,840.00

COSTO DIRECTO 364,020.54 480,963.96

PLACA STEEL DECK (CAL. 22, APOYO MAX. 1,5M, MALLA 7X150X150MM) 3000 PSI, E=12 Unidad: M2
CM ITEM: 2.10
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CUARTON 2"x4"x3M UND 0.1 0 10,500.00 1,050.00
PUNTILLA 2 CC LBS 0.05 0 2,000.00 100.00
TABLA 1x10x3M UND 0.15 0 8,500.00 1,275.00
PERFIL AG C120mmX 60mm-1.5 CAL.16 L= 6MTS. ACESCO UND 0.4 5 63,260.00 26,569.20
MALLA ELEC.H-1.31/U131 ESP 15X30 1.38K/M2 KLS 1.38 5 4,000.00 5,796.00
LAM.METALDECK 2" CAL.22 0.75MM LARGO 12.0M ANCHO 70CM
M2 1 0 42,500.00 42,500.00
CONECTORES PARA LOSA STEEL DECK UND 1.5 0 1,000.00 1,500.00
MEZCLA CONCRETO 1:2:3 3100 PSI 210 MPa M3 0.12 3 323,204.00 39,948.01
SUBTOTAL MATERIALES 118,738.21

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE-1 OFI 70,612.00 185% 130,632.00 3.0000 43,544.00
M.O. ALBANILERIA 3 AYUDANTE-1 OFI 123,576.00 185% 228,615.00 40.5392 5,639.36
SUBTOTAL MANO DE OBRA 49,183.36
EQUIPO
CAMION TRANSPORTE CARGA 5-10 TONELADAS VJE 5.2083 2,400.00 12,499.92
VIBRADOR ELECTRICO DIA 0.2 0 34,800.00 6,960.00
HERRAMIENTA MENOR % 5% 0 49,183.36 2,459.16
SUBTOTAL EQUIPO 21,919.08

COSTO DIRECTO 189,840.65 189,841.00

GAVIONES MALLA CALIBRE 12 Unidad: M3


ITEM: 2.11
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ALAMBRE GALVANIZADO # 10 KLS 1.4 0 4,248.00 5,947.20
CUARTON 2"x4"x3M UND 0.2 0 10,500.00 2,100.00
GAVIONES 2X1X1 CAL.12 UND 0.5 0 68,400.00 34,200.00
PIEDRA RIO D<20 CM PIEDRA RIO DE MANO M3 1.2 0 57,500.00 69,000.00
TABLA 1x10x3M UND 0.4 0 8,500.00 3,400.00
SUBTOTAL MATERIALES 114,647.20
MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.
M.O. ALBANILERIA 5 AYUDANTE-1 OFI 176,541.00 185% 326,600.00 9.4117 34,701.49
SUBTOTAL MANO DE OBRA 34,701.49
EQUIPO
VOLQUETA TRANSPORTE MAT.PETREOS 1-10KMS M3 1.2513 0 7,000.00 8,759.10
HERRAMIENTA MENOR % 5% 0 34,701.49 1,735.07
SUBTOTAL EQUIPO 10,494.17

COSTO DIRECTO 159,842.86 159,843.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

CONCRETO 1:2:4 2500 PSI - 17,5 Mpa Unidad: M3


ITEM: 3.1
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 160 0 16.00 2,560.00
ARENA GRUESA M3 0.52 0 60,000.00 31,200.00
GRAVA TRITURADA DE 3/4 M3 0.94 0 70,000.00 65,800.00
GASOLINA CORRIENTE GLN 0.1 0 8,700.00 870.00
CEMENTO GRIS KLS 260 0 600.00 156,000.00
ACEITE MOTOR 4 TIEMPOS GLN 0.006 0 70,000.00 420.00
SUBTOTAL MATERIALES 256,850.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 1.2920 75,838.24
SUBTOTAL MANO DE OBRA 75,838.24
EQUIPO
MEZCLADORA DE 9 PIES CUBICOS DIA 0.0601 0 38,800.00 2,331.88
HERRAMIENTA MENOR % 0.04999 0 75,838.24 3,791.15
SUBTOTAL EQUIPO 6,123.03

COSTO DIRECTO 338,811.27 338,811.00

CONCRETO IMPERMEABILIZADO 4000 PSI Unidad: M3


ITEM: 3.2
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
PLASTOCRETE D.M. (20 KGS) KLS 3 0 6,366.00 19,098.00
AGUA LTS 210 0 16.00 3,360.00
ARENA GRUESA M3 0.87 0 60,000.00 52,200.00
GRAVA TRITURADA DE 3/4 M3 0.47 0 70,000.00 32,900.00
GASOLINA CORRIENTE GLN 0.1 0 8,700.00 870.00
CEMENTO GRIS KLS 480 0 600.00 288,000.00
ACEITE MOTOR 4 TIEMPOS GLN 0.006 0 70,000.00 420.00
SUBTOTAL MATERIALES 396,848.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 1.6554 59,189.92
SUBTOTAL MANO DE OBRA 59,189.92
EQUIPO
MEZCLADORA DE 9 PIES CUBICOS DIA 0.07999 0 38,800.00 3,103.61
HERRAMIENTA MENOR % 0.04999 0 59,189.92 2,958.90
SUBTOTAL EQUIPO 6,062.51

COSTO DIRECTO 462,100.43 462,100.00

ACERO REFUERZO FLEJADO 60000 PSI 420Mpa Unidad: KLS


ITEM: 3.3
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ALAMBRE NEGRO # 18 KLS 0.04 0.03 3,500.00 140.04
SEGUETA SIN MARCO UND 0.04 0.03 2,600.00 104.03
HIERR.DE 60000 PSI 420 MPA KLS 1.03 0 4,000.00 4,120.00
SUBTOTAL MATERIALES 4,364.07

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 62.3058 786.30
SUBTOTAL MANO DE OBRA 786.30

COSTO DIRECTO 5,150.37 5,150.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

CINTA PVC -15 O SIMILARES Unidad: ML


ITEM: 3.4
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CINTA PVC JUNT. DILATACION ML 1 0 21,000.00 21,000.00
SUBTOTAL MATERIALES 21,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 1 AYUDANTE-1 OFI 75,023.00 185% 138,792.00 23.2559 5,968.03
SUBTOTAL MANO DE OBRA 5,968.03
EQUIPO
HERRAMIENTA MENOR % 5% 0 5,968.03 298.40
SUBTOTAL EQUIPO 298.40

COSTO DIRECTO 27,266.43 27,266.00

CAJA VALVULAS Unidad: UND


ITEM: 3.5
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ALAMBRE NEGRO # 18 KLS 1 0 3,500.00 3,500.00
HIERRO .1/2" 60.000 [6M] FIGURADO KG 30 0 4,000.00 120,000.00
ROCA MUERTA (SIN TRANSPORTE) M3 1 0 18,500.00 18,500.00
MEZCLA CONCRETO 1:2:4 2850 PSI-20.0MPa M3 1 0 295,944.00 295,944.00
MORTERO 1:3 M3 0.3 0 324,637.00 97,391.10
SUBTOTAL MATERIALES 535,335.10

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 2.6132 37,495.41
M.O. ALBANILERIA 1 AYUDANTE-1 OFI 70,612.00 185% 130,632.00 2.000 65,316.00
SUBTOTAL MANO DE OBRA 102,811.41
EQUIPO
VOLQUETA TRANSPORTE MAT.PETREOS 1-10KMS M3 0.575 0 7,000.00 4,025.00
HERRAMIENTA MENOR % 0.04999 0 102,811.41 5,139.54
SUBTOTAL EQUIPO 9,164.54

COSTO DIRECTO 647,311.05 647,311.00

VALV COMP ELASTICA BRIDA 10" HD Unidad: UND


ITEM: 3.6
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALV COMP ELASTICA BRIDA 10" HD UND 1 0 3,750,080.00 3,750,080.00
SUBTOTAL MATERIALES 3,750,080.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 1 AYUDANTE-1 OFI 75,023.00 185% 138,792.00 1.1323 122,575.29
SUBTOTAL MANO DE OBRA 122,575.29
EQUIPO
HERRAMIENTA MENOR % 0.04997 0 122,575.29 6,125.08
SUBTOTAL EQUIPO 6,125.08

COSTO DIRECTO 3,878,780.37 3,878,780.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
VALV COMP ELASTICA 8 HD Unidad: UND
ITEM: 3.7
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALV COMP ELASTICA 8 HD UND 1 0 1,800,006.00 1,800,006.00
SUBTOTAL MATERIALES 1,800,006.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 1 AYUDANTE-1 OFI 75,023.00 185% 138,792.00 0.8132 170,673.88
SUBTOTAL MANO DE OBRA 170,673.88
EQUIPO
HERRAMIENTA MENOR % 0.05 0 170,673.88 8,533.69
SUBTOTAL EQUIPO 8,533.69

COSTO DIRECTO 1,979,213.57 1,979,214.00

CERRAMIENTO MALA ESLABONADA Unidad: ML


ITEM: 3.8
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
MALLA ESLABONADA GALV #12 ROMBO DE 11/2" M2 10 5 24,350.00 255,675.00
THINER DISOLVENTE GLN 0.07 0 18,000.00 1,260.00
SOLDADURA 6011 1/8" VARILLA KLS 0.5 0 7,200.00 3,600.00
ESMALTE PINTURA DE ALUMINI CROMADA GLN 0.2 0 62,320.00 12,464.00
SUBTOTAL MATERIALES 272,999.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. METALISTERIA 2 AYUDANTE-1 OFI 121,366.00 185% 224,527.00 10.0310 22,383.31
M.O. PINTURA 1 AYUDANTE-1 OFI 75,023.00 185% 138,792.00 30.0000 4,626.40
SUBTOTAL MANO DE OBRA 27,009.71
EQUIPO
SOLDADOR ELECTRICO DIA 0.15 0 28,500.00 4,275.00
HERRAMIENTA MENOR % 5% 0 27,009.71 1,350.48
SUBTOTAL EQUIPO 5,625.48

COSTO DIRECTO 305,634.19 305,634.00

EXCAVACION EN CONGLOMERADO Unidad: M3


ITEM: 3.9
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 1.7868 27,418.29
SUBTOTAL MANO DE OBRA 27,418.29
EQUIPO
HERRAMIENTA MENOR % 5% 0 27,418.29 1,370.91
SUBTOTAL EQUIPO 1,370.91

COSTO DIRECTO 28,789.20 28,789.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
RELLENO MATERIAL SITIO COMPACATDO-RANA Unidad: M3
ITEM: 3.10
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 7 0 16.00 112.00
GASOLINA CORRIENTE GLN 0.05 0 8,700.00 435.00
ACEITE MOTOR 4 TIEMPOS GLN 0.015 0 70,000.00 1,050.00
SUBTOTAL MATERIALES 1,597.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 7.3049 13,413.33
SUBTOTAL MANO DE OBRA 13,413.33
EQUIPO
VIBROCOMPACTADOR TIPO RANA DIA 0.1 39,000.00 3,900.00
HERRAMIENTA MENOR % 5% 0 13,413.33 670.66
SUBTOTAL EQUIPO 4,570.66

COSTO DIRECTO 19,580.99 19,581.00

POZO DE ALCANTARILLADO Unidad: UND


ITEM: 3.11
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TABLA 1x10x3M UND 2.5 0 8,500.00 21,250.00
HIERR.DE 60000 PSI 420 MPA KLS 66.5 3 4,000.00 273,980.00
HIERR.DE 37000 PSI 259 MPA U KLS 5 3 2,330.00 11,999.50
MEZCLA CONCRETO 1:2:3 3100 PSI 210 MPa M3 5.43 0 323,204.00 1,754,997.72
MORTERO 1:2 M3 0.02 0 355,477.00 7,109.54
SUBTOTAL MATERIALES 2,069,336.76

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE-1 OFI 97,094.00 185% 179,623.00 0.9208 195,072.76
SUBTOTAL MANO DE OBRA 195,072.76
EQUIPO
FORM.MET.CAM.DE INSPECCION UND 2 38,002.00 76,004.00
SUBTOTAL EQUIPO 76,004.00

COSTO DIRECTO 2,340,413.52 2,340,414.00

INSTALACION TUBERIA ALCANTARILLADO 10" Unidad: UND


ITEM: 3.12
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA
M.O. HIDROSANIT. 1 AYUDANTE-1 OFI 75,023.00 185% 138,792.00 7.7963 17,802.29

SUBTOTAL MANO DE OBRA 17,802.29


EQUIPO
HERRAMIENTA MENOR % 5% 17,802.29 890.11

SUBTOTAL EQUIPO 890.11

COSTO DIRECTO 18,692.40 18,692.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
CABEZOTE DE ENTREGA Unidad: M3
ITEM: 3.13
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CUARTON 2"x4"x3M UND 1 0 10,500.00 10,500.00
GUADUA [TACO] 2.50-3M UND 2 0 6,000.00 12,000.00
PUNTILLA 2 CC LBS 2 0 2,000.00 4,000.00
TABLA 1x10x3M UND 2.1 0 8,500.00 17,850.00
MEZCLA CONCRETO 1:2.5:4« 2500 PSI-17.5MPa M3 1.3 0 273,324.00 355,321.20
SUBTOTAL MATERIALES 399,671.20

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE-1 OFI 97,094.00 185% 179,623.00 0.8825 203,538.81
SUBTOTAL MANO DE OBRA 203,538.81
EQUIPO
HERRAMIENTA MENOR % 5% 0 203,538.81 10,176.94
SUBTOTAL EQUIPO 10,176.94

COSTO DIRECTO 613,386.95 613,387.00

EXCAVACION EN CONGLOMERADO Unidad: M3


ITEM: 4,1
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 1.7868 27,418.29
SUBTOTAL MANO DE OBRA 27,418.29
EQUIPO
HERRAMIENTA MENOR % 5% 0 27,418.29 1,370.91
SUBTOTAL EQUIPO 1,370.91

COSTO DIRECTO 28,789.20 28,789.00

RELLENO MATERIAL SITIO COMPACATDO-RANA Unidad: M3


ITEM: 4,2
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 7 0 16.00 112.00
GASOLINA CORRIENTE GLN 0.05 0 8,700.00 435.00
ACEITE MOTOR 4 TIEMPOS GLN 0.015 0 70,000.00 1,050.00
SUBTOTAL MATERIALES 1,597.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 7.3049 13,413.33
SUBTOTAL MANO DE OBRA 13,413.33
EQUIPO
VIBROCOMPACTADOR TIPO RANA DIA 0.1 39,000.00 3,900.00
HERRAMIENTA MENOR % 5% 0 13,413.33 670.66
SUBTOTAL EQUIPO 4,570.66

COSTO DIRECTO 19,580.99 19,581.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

INSTALACION TUBERIA EN PVC 10 RDE 21 Unidad: ML


ITEM: 4.3
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.03 0 11,395.00 341.85
SUBTOTAL MATERIALES 341.85

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 16.6625 11,514.66
SUBTOTAL MANO DE OBRA 11,514.66
EQUIPO
HERRAMIENTA MENOR % 5% 0 11,514.66 575.73
SUBTOTAL EQUIPO 575.73

COSTO DIRECTO 12,432.24 12,432.00

CONCRETO 1:2:4 2500 PSI - 17,5 Mpa Unidad: M3


ITEM: 4.4
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 160 0 16.00 2,560.00
ARENA GRUESA M3 0.52 0 60,000.00 31,200.00
GRAVA TRITURADA DE 3/4 M3 0.94 0 70,000.00 65,800.00
GASOLINA CORRIENTE GLN 0.1 0 8,700.00 870.00
CEMENTO GRIS KLS 260 0 600.00 156,000.00
ACEITE MOTOR 4 TIEMPOS GLN 0.006 0 70,000.00 420.00
SUBTOTAL MATERIALES 256,850.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 1.2920 75,838.24
SUBTOTAL MANO DE OBRA 75,838.24
EQUIPO
MEZCLADORA DE 9 PIES CUBICOS DIA 0.0601 0 38,800.00 2,331.88
HERRAMIENTA MENOR % 0.04999 0 75,838.24 3,791.15
SUBTOTAL EQUIPO 6,123.03

COSTO DIRECTO 338,811.27 338,811.00

EXCAVACION EN ROCA Unidad: M3


ITEM: 5.1
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

EQUIPO
COMPRESOR DE DOS MARTILLOS HRS 0.8608 0 92,000.00 79,193.60
RETROEXCAVADORA JD-510 HRS 0.035 88,000.00 3,080.00
HERRAMIENTA MENOR GLB 0.8029 0 1,400.00 1,124.06
SUBTOTAL EQUIPO 83,397.66

COSTO DIRECTO 83,397.66 83,398.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
INSTALACION VALVULA VENTOSA DN 2" (INCLUYE ACCESORIOS PARA CONECTAR A Unidad: UND
RED) ITEM: 5.2
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 1 AYUDANTE-1 OFI 75,023.00 185% 138,792.00 1.4656 94,699.78
SUBTOTAL MANO DE OBRA 94,699.78
EQUIPO
HERRAMIENTA MENOR % 0.05001 0 94,699.78 4,735.93
SUBTOTAL EQUIPO 4,735.93

COSTO DIRECTO 99,435.71 99,436.00

INSTALACION TUBERIA HD 10" PRESS. TRABAJO 500 M.C.A.JUNTA ACERROJADA Unidad: ML


ITEM: 5.3
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.3 0 11,395.00 3,418.50
SUBTOTAL MATERIALES 3,418.50

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 3.1127 61,638.77
SUBTOTAL MANO DE OBRA 61,638.77
EQUIPO
HERRAMIENTA MENOR % 5% 0 61,638.77 3,081.93
SUBTOTAL EQUIPO 3,081.93

COSTO DIRECTO 68,139.20 68,139.00

INSTALACION TUBERIA HD 10" PRESS. TRABAJO 340 M.C.A.JUNTA ACERROJADA Unidad: ML


ITEM: 5.4
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.3 0 11,395.00 3,418.50
SUBTOTAL MATERIALES 3,418.50

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 3.1127 61,638.77
SUBTOTAL MANO DE OBRA 61,638.77
EQUIPO
HERRAMIENTA MENOR % 5% 0 61,638.77 3,081.93
SUBTOTAL EQUIPO 3,081.93

COSTO DIRECTO 68,139.20 68,139.00

INSTALACION TUBERIA HD 10" PRESS. TRABAJO 170 M.C.A Unidad: ML


ITEM: 5.5
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.3 0 11,395.00 3,418.50
SUBTOTAL MATERIALES 3,418.50

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 3.1127 61,638.77
SUBTOTAL MANO DE OBRA 61,638.77
EQUIPO
HERRAMIENTA MENOR % 5% 0 61,638.77 3,081.93
SUBTOTAL EQUIPO 3,081.93

COSTO DIRECTO 68,139.20 68,139.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

INSTALACION TUBERIA EN PVC 8" Unidad: ML


ITEM: 5.6
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.03 0 11,395.00 341.85
SUBTOTAL MATERIALES 341.85

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 10.9783 17,476.57
SUBTOTAL MANO DE OBRA 17,476.57
EQUIPO
HERRAMIENTA MENOR % 5% 0 17,476.57 873.82
SUBTOTAL EQUIPO 873.82

COSTO DIRECTO 18,692.24 18,692.00

INSTALACION TUBERIA EN PVC 6" Unidad: ML


ITEM: 5.7
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.03 0 11,395.00 341.85
SUBTOTAL MATERIALES 341.85

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 14.2097 13,502.26
SUBTOTAL MANO DE OBRA 13,502.26
EQUIPO
HERRAMIENTA MENOR % 5% 0 13,502.26 675.11
SUBTOTAL EQUIPO 675.11

COSTO DIRECTO 14,519.22 14,519.00

INSTALACION TUBERIA HD 6" Unidad: ML


ITEM: 5.8
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.3 0 11,395.00 3,418.50
SUBTOTAL MATERIALES 3,418.50

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 29.0798 6,597.81
SUBTOTAL MANO DE OBRA 6,597.81
EQUIPO
HERRAMIENTA MENOR % 5% 0 6,597.81 329.89
SUBTOTAL EQUIPO 329.89

COSTO DIRECTO 10,346.20 10,346.00

VALV COMP ELASTICA 6 HD Unidad: UND


ITEM: 5.9
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 1 AYUDANTE-1 OFI 75,023.00 185% 138,792.00 2.1387 64,895.50
SUBTOTAL MANO DE OBRA 64,895.50
EQUIPO
HERRAMIENTA MENOR % 0.04998 0 64,895.50 3,243.47
SUBTOTAL EQUIPO 3,243.47

COSTO DIRECTO 68,138.97 68,139.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

RETIRO ESCOMBROS Unidad: M3


ITEM: 5.10
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

EQUIPO
VOLQUETA 5 M3 VJE 0.2601 0 43,500.00 11,314.35
RETROEXCAVADORA CARGADORA HRS 0.06458 0 85,000.00 5,489.30
SUBTOTAL EQUIPO 16,803.65

COSTO DIRECTO 16,803.65 16,804.00

EXCAVACION EN MATERIAL COMUN Unidad: M3


ITEM: 5.11
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 2.3563 20,791.50
SUBTOTAL MANO DE OBRA 20,791.50
EQUIPO
HERRAMIENTA MENOR % 5% 0 20,791.50 1,039.57
SUBTOTAL EQUIPO 1,039.57

COSTO DIRECTO 21,831.07 21,831.00

RELLENO MATERIAL SITIO COMPACATDO-RANA Unidad: M3


ITEM: 5.12
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 7 0 16.00 112.00
GASOLINA CORRIENTE GLN 0.05 0 8,700.00 435.00
ACEITE MOTOR 4 TIEMPOS GLN 0.015 0 70,000.00 1,050.00
SUBTOTAL MATERIALES 1,597.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 7.3049 13,413.33
SUBTOTAL MANO DE OBRA 13,413.33
EQUIPO
VIBROCOMPACTADOR TIPO RANA DIA 0.1 39,000.00 3,900.00
HERRAMIENTA MENOR % 5% 0 13,413.33 670.66
SUBTOTAL EQUIPO 4,570.66

COSTO DIRECTO 19,580.99 19,581.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
CONCRETO 2500 P.S.I. PARA ANCLAJE DE ACCESORIOS Unidad: M3
ITEM: 5.13
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 180 0 16.00 2,880.00
ARENA GRUESA M3 0.48 0 60,000.00 28,800.00
GRAVA TRITURADA DE 3/4 M3 0.95 0 70,000.00 66,500.00
GASOLINA CORRIENTE GLN 0.1 0 8,700.00 870.00
CEMENTO GRIS KLS 300 0 600.00 180,000.00
ACEITE MOTOR 4 TIEMPOS GLN 0.006 0 70,000.00 420.00
SUBTOTAL MATERIALES 279,470.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 1.8045 54,299.25
SUBTOTAL MANO DE OBRA 54,299.25
EQUIPO
MEZCLADORA DE 9 PIES CUBICOS DIA 0.06 0 38,800.00 2,328.00
HERRAMIENTA MENOR % 0.04997 0 54,299.25 2,713.33
SUBTOTAL EQUIPO 5,041.33

COSTO DIRECTO 338,810.58 338,811.00

INSTALACION TEE HD 8" BRIDA Unidad: UND


ITEM: 5.14
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.03 0 11,395.00 341.85
SUBTOTAL MATERIALES 341.85

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 3.7293 51,447.46
SUBTOTAL MANO DE OBRA 51,447.46
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 51,447.46 2,571.85
SUBTOTAL EQUIPO 2,571.85

COSTO DIRECTO 54,361.16 54,361.00

INSTALACION TEE HD 8"X 2" BRIDA Unidad: UND


ITEM: 5.15
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.03 0 11,395.00 341.85
SUBTOTAL MATERIALES 341.85

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 3.7293 51,447.46
SUBTOTAL MANO DE OBRA 51,447.46
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 51,447.46 2,571.85
SUBTOTAL EQUIPO 2,571.85

COSTO DIRECTO 54,361.16 54,361.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

INSTALACION CODO HD 8"X 90º BRIDA Unidad: UND


ITEM: 5.16
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.03 0 11,395.00 341.85
SUBTOTAL MATERIALES 341.85

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 4.6219 41,511.72
SUBTOTAL MANO DE OBRA 41,511.72
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 41,511.72 2,075.17
SUBTOTAL EQUIPO 2,075.17

COSTO DIRECTO 43,928.74 43,929.00

INSTALACION CODO HD 8"X 90º JH Unidad: UND


ITEM: 5.17
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.03 0 11,395.00 341.85
SUBTOTAL MATERIALES 341.85

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 5.3970 35,549.94
SUBTOTAL MANO DE OBRA 35,549.94
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 35,549.94 1,777.14
SUBTOTAL EQUIPO 1,777.14

COSTO DIRECTO 37,668.93 37,669.00

INSTALACION CODO HD 8"X 45º JH Unidad: UND


ITEM: 5.18
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.03 0 11,395.00 341.85
SUBTOTAL MATERIALES 341.85

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 5.3970 35,549.94
SUBTOTAL MANO DE OBRA 35,549.94
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 35,549.94 1,777.14
SUBTOTAL EQUIPO 1,777.14

COSTO DIRECTO 37,668.93 37,669.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

INSTALACION CODO HD 8"X 22.5º JH Unidad: UND


ITEM: 5.19
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.03 0 11,395.00 341.85
SUBTOTAL MATERIALES 341.85

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 5.3970 35,549.94
SUBTOTAL MANO DE OBRA 35,549.94
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 35,549.94 1,777.14
SUBTOTAL EQUIPO 1,777.14

COSTO DIRECTO 37,668.93 37,669.00

INSTALACION CODO HD 8"X 11.25º JH Unidad: UND


ITEM: 5.20
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.03 0 11,395.00 341.85
SUBTOTAL MATERIALES 341.85

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 5.3970 35,549.94
SUBTOTAL MANO DE OBRA 35,549.94
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 35,549.94 1,777.14
SUBTOTAL EQUIPO 1,777.14

COSTO DIRECTO 37,668.93 37,669.00

INSTALACION TEE HD 6"X 2" BRIDA LISA Unidad: UND


ITEM: 5.21
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.03 0 11,395.00 341.85
SUBTOTAL MATERIALES 341.85

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 4.2180 45,486.72
SUBTOTAL MANO DE OBRA 45,486.72
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 45,486.72 2,273.88
SUBTOTAL EQUIPO 2,273.88

COSTO DIRECTO 48,102.45 48,102.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
INSTALACION CODO HD 6"X 90º LISA Unidad: UND
ITEM: 5.22
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.03 0 11,395.00 341.85
SUBTOTAL MATERIALES 341.85

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 5.3970 35,549.94
SUBTOTAL MANO DE OBRA 35,549.94
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 35,549.94 1,777.14
SUBTOTAL EQUIPO 1,777.14

COSTO DIRECTO 37,668.93 37,669.00

INSTALACION CODO HD 6"X 90º LISA Unidad: UND


ITEM: 5.23
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.03 0 11,395.00 341.85
SUBTOTAL MATERIALES 341.85

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 5.3970 35,549.94
SUBTOTAL MANO DE OBRA 35,549.94
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 35,549.94 1,777.14
SUBTOTAL EQUIPO 1,777.14

COSTO DIRECTO 37,668.93 37,669.00

INSTALACION CODO HD 6"X 22.5º LISA-CAMPANA Unidad: UND


ITEM: 5.24
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.03 0 11,395.00 341.85
SUBTOTAL MATERIALES 341.85

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 5.3970 35,549.94
SUBTOTAL MANO DE OBRA 35,549.94
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 35,549.94 1,777.14
SUBTOTAL EQUIPO 1,777.14

COSTO DIRECTO 37,668.93 37,669.00

INSTALACION CODO HD 6"X 11.25º LISA-CAMPANA Unidad: UND


ITEM: 5.25
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.03 0 11,395.00 341.85
SUBTOTAL MATERIALES 341.85

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 7.4904 25,614.52
SUBTOTAL MANO DE OBRA 25,614.52
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 25,614.52 1,280.46
SUBTOTAL EQUIPO 1,280.46

COSTO DIRECTO 27,236.83 27,237.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

INSTALACION UNION RAPIDA PVC 6" Unidad: UND


ITEM: 5.26
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.03 0 11,395.00 341.85
SUBTOTAL MATERIALES 341.85

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 16.3917 11,704.89
SUBTOTAL MANO DE OBRA 11,704.89
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 11,704.89 585.12
SUBTOTAL EQUIPO 585.12

COSTO DIRECTO 12,631.86 12,632.00

CONCRETO SOPORTERIA 2500 PSI Unidad: M3


ITEM: 5.27
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 180 0 16.00 2,880.00
ARENA GRUESA M3 0.48 0 60,000.00 28,800.00
GRAVA TRITURADA DE 3/4 M3 0.95 0 70,000.00 66,500.00
GASOLINA CORRIENTE GLN 0.1 0 8,700.00 870.00
CEMENTO GRIS KLS 300 0 600.00 180,000.00
ACEITE MOTOR 4 TIEMPOS GLN 0.006 0 70,000.00 420.00
SUBTOTAL MATERIALES 279,470.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 1.8045 54,299.25
SUBTOTAL MANO DE OBRA 54,299.25
EQUIPO
MEZCLADORA DE 9 PIES CUBICOS DIA 0.06 0 38,800.00 2,328.00
HERRAMIENTA MENOR % 0.04998 0 54,299.25 2,713.87
SUBTOTAL EQUIPO 5,041.87

COSTO DIRECTO 338,811.12 338,811.00

CAJA VALVULAS Unidad: UND


ITEM: 5.28
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ALAMBRE NEGRO # 18 KLS 1 0 3,500.00 3,500.00
HIERRO .1/2" 60.000 [6M] FIGURADO KG 30 0 4,000.00 120,000.00
ROCA MUERTA (SIN TRANSPORTE) M3 1 0 18,500.00 18,500.00
MEZCLA CONCRETO 1:2:4 2850 PSI - 20,0 Mpa M3 1.25 0 295,944.00 369,930.00
MORTERO 1:3 M3 0.3 0 324,637.00 97,391.10
SUBTOTAL MATERIALES 609,321.10

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 2.6132 37,495.41
M.O. ALBANILERIA 1 AYUDANTE-1 OFI 70,612.00 185% 130,632.00 1.5928 82,014.06
SUBTOTAL MANO DE OBRA 119,509.47
EQUIPO
VOLQUETA TRANSPORTE MAT.PETREOS 1-10KMS M3 0.5753 0 7,000.00 4,027.10
HERRAMIENTA MENOR % 0.04999 0 119,509.47 5,974.27
SUBTOTAL EQUIPO 10,001.37

COSTO DIRECTO 738,831.94 738,832.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SISTEMA PARA TRANSPORTE DE MATERIALES Y EQUIPOS CIMA DE LA MOJARRA Y UNIDAD: GLB


OTROS TRANSPORTES INTERNOS ITEM: 5.29
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES

SUBTOTAL MATERIALES -
MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO
VOLQUETA HORA 8000 42,024.00 336,192,000.00
GRUA-MONTACARGA 3 TONELADAS HRS 500 30,000.00 15,000,000.00
CAMA BAJA DISTANCIA < 50 KM T/K 93668.3 820.00 76,808,000.01
CAMION TRANSPORTE CARGA 5-10 TONELADAS VJE 113333 2,400.00 271,999,999.92

SUBTOTAL- EQUIPO 699,999,999.93

COSTO DIRECTO 699,999,999.93 700,000,000.00

INSTALACION VALVULAS DE PIE DE COLADERA BRIDADA 10" , 150psi , ACERO Unidad: UND
ITEM: 5.30
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACIÓN VALVULAS DE PIE DE COLADERA BRIDADA 8" , 150psi , ACERO Unidad: UND
ITEM: 5.31
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

INSTALACION VALVULA DE MARIPOSA BRIDADA HD 10" , 400psi Unidad: UND


ITEM: 5.32
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION VALVULA DE MARIPOSA BRIDADA HD 8" , 400psi Unidad: UND


ITEM: 5.33
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION REDUCCIÓN EXCENTRICA BRIDADO 10"X5" , ACERO SCHEDULE 40 ASTM Unidad: UND
A-53 GRADO B ITEM: 5.34
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION REDUCCIÓN EXCENTRICA BRIDADO 8"X5" , ACERO SCHEDULE 40 ASTM A- Unidad: UND
53 GRADO B ITEM: 5.35
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

INSTALACION REDUCCIÓN CONCENTRICA BRIDADO 6"X4" , ACERO SCHEDULE 40 ASTM Unidad: UND
A-53 GRADO B ITEM: 5.36
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION REDUCCIÓN CONCENTRICA BRIDADO 6"X3" , ACERO SCHEDULE 40 ASTM Unidad: UND
A-53 GRADO B ITEM: 5.37
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION REDUCCIÓN CONCENTRICA BRIDADO 6"X2" , ACERO SCHEDULE 40 ASTM Unidad: UND
A-53 GRADO B ITEM: 5.38
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION REDUCCIÓN CONCENTRICA BRIDADO 10"X6" , ACERO SCHEDULE 40 Unidad: UND


ASTM A-53 GRADO B ITEM: 5.39
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

INSTALACION REDUCCIÓN CONCENTRICA BRIDADO 8"X6" , ACERO SCHEDULE 40 ASTM Unidad: UND
A-53 GRADO B ITEM: 5.40
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION VALVULAS CHEQUE BRIDADA ACERO 10" 640 MCA Unidad: UND
ITEM: 5.41
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION VALVULAS CHEQUE BRIDADA HD 10" 340 MCA Unidad: UND


ITEM: 5.42
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION VALVULAS CHEQUE BRIDADA HD 10" 340 MCA Unidad: UND


ITEM: 5.43
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

INSTALACION VALVULAS MARIPOSA BRIDADA ACERO 10" 640 MCA Unidad: UND
ITEM: 5.44
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION JUNTA DE DILATACIÓN BRIDADA 10" 640 MCA Unidad: UND


ITEM: 5.45
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION JUNTA DE DILATACIÓN BRIDADA 10" 340 MCA Unidad: UND


ITEM: 5.46
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION JUNTA DE DILATACIÓN BRIDADA 8" 340 MCA Unidad: UND


ITEM: 5.47
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

INSTALACION CODO BRIDADO 45° , 10" , ACERO SCHEDULE 40 ASTM A-53 GRADO B Unidad: UND
ITEM: 5.48
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION CODO BRIDADO 90° , 10" , ACERO SCHEDULE 40 ASTM A-53 GRADO B Unidad: UND
ITEM: 5.49
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION CODO BRIDADO 45° , 8" , ACERO SCHEDULE 40 ASTM A-53 GRADO B Unidad: UND
ITEM: 5.50
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

INSTALACION Y BRIDADO , 10" , ACERO SCHEDULE 40 ASTM A-53 GRADO B Unidad: UND
ITEM: 5.51
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION TUBERIA BRIDADO , 10" , ACERO SCHEDULE 40 ASTM A-53 GRADO B, Unidad: ML
(TAMAÑOS DE NIPLES SEGÚN DETALLES ESTACIONES DE BOMBEO)
ITEM: 5.52

DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.3 0 11,395.00 3,418.50
SUBTOTAL MATERIALES 3,418.50

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 3.1127 61,638.77
SUBTOTAL MANO DE OBRA 61,638.77
EQUIPO
HERRAMIENTA MENOR % 5% 0 61,638.77 3,081.93
SUBTOTAL EQUIPO 3,081.93

COSTO DIRECTO 68,139.20 68,139.00

INSTALACION TUBERIA BRIDADO , 8" , ACERO SCHEDULE 40 ASTM A-53 GRADO B, Unidad: UND
(TAMAÑOS DE NIPLES SEGÚN DETALLES ESTACIONES DE BOMBEO)
ITEM: 5.53

DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

INSTALACION TUBERIA BRIDADO , 3" , ACERO SCHEDULE 40 ASTM A-53 GRADO B, Unidad: UND
(TAMAÑOS DE NIPLES SEGÚN DETALLES ESTACIONES DE BOMBEO)
ITEM: 5.54

DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION TUBERIA BRIDADO , 2" , ACERO SCHEDULE 40 ASTM A-53 GRADO B, Unidad: UND
(TAMAÑOS DE NIPLES SEGÚN DETALLES ESTACIONES DE BOMBEO)
ITEM: 5.55

DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION VALVULAS ALIVIO(TIPO GLOBO) BRIDADA ACERO 3" 640 MCA Unidad: UND
ITEM: 5.56
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -
MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.
M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION VALVULAS ALIVIO(TIPO GLOBO) BRIDADA ACERO 2" 640 MCA Unidad: UND
ITEM: 5.57
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

INSTALACION VALVULAS AIRE BRIDADA ENTRADA 8" Y SALIDA 1/4" , 350 MCA Unidad: UND
ITEM: 5.58
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION VALVULAS AIRE BRIDADA ENTRADA 6" Y SALIDA 1/2" , 350 MCA Unidad: UND
ITEM: 5.59
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION VALVULAS AIRE BRIDADA ENTRADA 6" Y SALIDA 1/4" , 350 MCA Unidad: UND
ITEM: 5.60
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00

INSTALACION VALVULAS AIRE BRIDADA ENTRADA 4" Y SALIDA 1/4" , 350 MCA Unidad: UND
ITEM: 5.61
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SUBTOTAL MATERIALES -

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 2.9565 64,895.32
SUBTOTAL MANO DE OBRA 64,895.32
EQUIPO
HERRAMIENTA MENOR % 0.04999 0 64,895.32 3,244.11
SUBTOTAL EQUIPO 3,244.11

COSTO DIRECTO 68,139.43 68,139.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

INSTALACION TUBERIA 24", SCHEDULE 40 , PARA ALMENARA Unidad: ML


ITEM: 5.62
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LUBRICANTE TUB PVC/500GR 500GRS UND 0.3 0 11,395.00 3,418.50
SUBTOTAL MATERIALES 3,418.50

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. HIDROSANIT. 2 AYUDANTE - 1 OFIC. 103,710.00 185% 191,863.00 1.5163 126,533.67
SUBTOTAL MANO DE OBRA 126,533.67
EQUIPO
HERRAMIENTA MENOR % 5% 0 126,533.67 6,326.68
SUBTOTAL EQUIPO 6,326.68

COSTO DIRECTO 136,278.85 136,279.00

ACERO REFUERZO FLEJADO 60000 PSI 420Mpa Unidad: KLS


ITEM: 5.63
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ALAMBRE NEGRO # 18 KLS 0.04 0.03 3,500.00 140.04
SEGUETA SIN MARCO UND 0.04 0.03 2,600.00 104.03
HIERR.DE 60000 PSI 420 MPA KLS 1.03 0 4,000.00 4,120.00
SUBTOTAL MATERIALES 4,364.07

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 62.3058 786.30
SUBTOTAL MANO DE OBRA 786.30

COSTO DIRECTO 5,150.37 5,150.00

EXCAVACION EN ROCA Unidad: M3


ITEM: 6,1
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

EQUIPO
COMPRESOR DE DOS MARTILLOS HRS 0.8608 0 92,000.00 79,193.60
RETROEXCAVADORA JD-510 HRS 0.035 88,000.00 3,080.00
HERRAMIENTA MENOR GLB 0.8029 0 1,400.00 1,124.06
SUBTOTAL EQUIPO 83,397.66

COSTO DIRECTO 83,397.66 83,398.00

EXCAVACION EN CONGLOMERADO Unidad: M3


ITEM: 6,2
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 1.7868 27,418.29
SUBTOTAL MANO DE OBRA 27,418.29
EQUIPO
HERRAMIENTA MENOR % 5% 0 27,418.29 1,370.91
SUBTOTAL EQUIPO 1,370.91

COSTO DIRECTO 28,789.20 28,789.00

RETIRO ESCOMBROS Unidad: M3


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
ITEM: 6,3
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

EQUIPO
VOLQUETA 5 M3 VJE 0.2601 0 43,500.00 11,314.35
RETROEXCAVADORA CARGADORA HRS 0.06458 0 85,000.00 5,489.30
SUBTOTAL EQUIPO 16,803.65

COSTO DIRECTO 16,803.65 16,804.00

CONCRETO 2500 PSI - SOLADOS Unidad: M3


ITEM: 6.4
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 160 0 16.00 2,560.00
ARENA GRUESA M3 0.52 0 60,000.00 31,200.00
GRAVA TRITURADA DE 3/4 M3 0.94 0 70,000.00 65,800.00
GASOLINA CORRIENTE GLN 0.1 0 8,700.00 870.00
CEMENTO GRIS KLS 260 0 600.00 156,000.00
ACEITE MOTOR 4 TIEMPOS GLN 0.006 0 70,000.00 420.00
SUBTOTAL MATERIALES 256,850.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 1.2920 75,838.24
SUBTOTAL MANO DE OBRA 75,838.24
EQUIPO
MEZCLADORA DE 9 PIES CUBICOS DIA 0.0601 0 38,800.00 2,331.88
HERRAMIENTA MENOR % 0.04999 0 75,838.24 3,791.15
SUBTOTAL EQUIPO 6,123.03

COSTO DIRECTO 338,811.27 338,811.00

CONCRETO 3.00 PSI, ZAPATAS, V.CIMENTACION Y PISOS Unidad: M3


ITEM: 6.5
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
PUNTILLA 2 CC LBS 0.5 0 2,000.00 1,000.00
TABLA 1X10x3M [2C] UND 0.2 0 9,000.00 1,800.00
VARETA 2"x2"x3M UND 0.2 0 2,400.00 480.00
MEZCLA CONCRETO 1:2:3 3100 PSI 210 MPa M3 1.05 0 323,204.00 339,364.20
SUBTOTAL MATERIALES 342,644.20

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE-1 OFI 97,094.00 185% 179,623.00 10.2429 17,536.34
SUBTOTAL MANO DE OBRA 17,536.34
EQUIPO
VIBRADOR ELECTRICO DIA 0.05 0 34,800.00 1,740.00
VOLQUETA TRANSPORTE MAT.PETREOS 1-10KMS M3 0.3 0 7,000.00 2,100.00
SUBTOTAL EQUIPO 3,840.00

COSTO DIRECTO 364,020.54 364,021.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
CONCRETO 3000 PSI COLUMNAS Y VIGAS Unidad: M3
ITEM: 6.6
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ANTISOL BLANCO KLS 0.05 0 6,300.00 315.00
SEPAROL DESFORMALETEANTE TARRO 15 KLS KLS 0.05 0 11,800.00 590.00
SIKAMENT NS SUPERPLASTIFIC TARRO DE 25 KLS KLS 0.05 0 6,500.00 325.00
CUARTON 2"x4"x3M UND 0.05 0 10,500.00 525.00
PUNTILLA 2 CC LBS 0.3 0 2,000.00 600.00
TABLA 1x10x3M UND 0.05 0 8,500.00 425.00
VARETA 2"x2"x3M UND 0.05 0 2,400.00 120.00
MEZCLA CONCRETO 1:2:3 3100 PSI 210 MPa M3 1 0 323,204.00 323,204.00
SUBTOTAL MATERIALES 326,104.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 3 AYUDANTE-1 OFI 123,576.00 185% 228,615.00 4.2253 54,106.22
SUBTOTAL MANO DE OBRA 54,106.22
EQUIPO
VIBRADOR ELECTRICO DIA 0.05 0 34,800.00 1,740.00
HERRAMIENTA MENOR % 5% 0 54,106.22 2,705.31
TACO METALICO EXTENSION DE 2.OM A 3.30MT DIA 10 0 170.00 1,700.00
ANDAMIO METALICO TUBULAR U/D 1 0 1,050.00 1,050.00
SUBTOTAL EQUIPO 7,195.31

COSTO DIRECTO 387,405.53 387,406.00

CONCRETO 4000 PSI - IMPERM. TANQUES DE BOMBEO Unidad: M3


ITEM: 6.7
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
PLASTOCRETE D.M. (20 KGS) KLS 3 0 6,366.00 19,098.00
AGUA LTS 210 0 16.00 3,360.00
ARENA GRUESA M3 0.87 0 60,000.00 52,200.00
GRAVA TRITURADA DE 3/4 M3 0.47 0 70,000.00 32,900.00
GASOLINA CORRIENTE GLN 0.1 0 8,700.00 870.00
CEMENTO GRIS KLS 480 0 600.00 288,000.00
ACEITE MOTOR 4 TIEMPOS GLN 0.006 0 70,000.00 420.00
SUBTOTAL MATERIALES 396,848.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 1.6554 59,189.92
SUBTOTAL MANO DE OBRA 59,189.92
EQUIPO
MEZCLADORA DE 9 PIES CUBICOS DIA 0.08 0 38,800.00 3,104.00
HERRAMIENTA MENOR % 0.04998 0 59,189.92 2,958.31
SUBTOTAL EQUIPO 6,062.31

COSTO DIRECTO 462,100.23 462,100.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
PLACA STEEL DECK (CAL. 22, APOYO MAX. 1,5M, MALLA 7X150X150MM) 3000 PSI, E=12 Unidad: M2
CM ITEM: 6.8
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CUARTON 2"x4"x3M UND 0.1 0 10,500.00 1,050.00
PUNTILLA 2 CC LBS 0.05 0 2,000.00 100.00
TABLA 1x10x3M UND 0.15 0 8,500.00 1,275.00
PERFIL AG C120mmX 60mm-1.5 CAL.16 L= 6MTS. ACESCO UND 0.4 5 63,260.00 26,569.20
MALLA ELEC.H-1.31/U131 ESP 15X30 1.38K/M2 KLS 1.38 5 4,000.00 5,796.00
LAM.METALDECK 2" CAL.22 0.75MM LARGO 12.0M ANCHO 70CM
M2 1 0 42,500.00 42,500.00
CONECTORES PARA LOSA STEEL DECK UND 1.5 0 1,000.00 1,500.00
MEZCLA CONCRETO 1:2:3 3100 PSI 210 MPa M3 0.12 3 323,204.00 39,948.01
SUBTOTAL MATERIALES 118,738.21

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE-1 OFI 70,612.00 185% 130,632.00 3.0000 43,544.00
M.O. ALBANILERIA 3 AYUDANTE-1 OFI 123,576.00 185% 228,615.00 40.5392 5,639.36
SUBTOTAL MANO DE OBRA 49,183.36
EQUIPO
CAMION TRANSPORTE CARGA 5-10 TONELADAS VJE 5.2083 2,400.00 12,499.92
VIBRADOR ELECTRICO DIA 0.2 0 34,800.00 6,960.00
HERRAMIENTA MENOR % 5% 0 49,183.36 2,459.16
SUBTOTAL EQUIPO 21,919.08

COSTO DIRECTO 189,840.65 189,841.00

ACERO REFUERZO FLEJADO 60000 PSI 420Mpa Unidad: KLS


ITEM: 6.9
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ALAMBRE NEGRO # 18 KLS 0.04 0.03 3,500.00 140.04
SEGUETA SIN MARCO UND 0.04 0.03 2,600.00 104.03
HIERR.DE 60000 PSI 420 MPA KLS 1.03 0 4,000.00 4,120.00
SUBTOTAL MATERIALES 4,364.07

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 62.3058 786.30
SUBTOTAL MANO DE OBRA 786.30

COSTO DIRECTO 5,150.37 5,150.00

INSTALACION CONJUNTO MOTOR-BOMBA( INC. INSTALACION TABLEROS,CONJUNTO UNIDAD: GLB


MOTOR BOMBA EN SITIO) ITEM: 6.10
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES

SUBTOTAL MATERIALES -
MANO DE OBRA
M.O. ALBANILERIA 5 AYUDANTE-1 OFI 176,541.00 185% 326,600.00 0.0184 17,750,000.00
M.O. ELECTRICAS 2 AYUDANTE-1 OFI 134,603.00 185% 249,015.00 0.0300 8,300,500.00

SUBTOTAL- MANO DE OBRA 26,050,500.00


EQUIPO
HERRAMIENTA MENOR % 0.05006 26,050,500.00 1,304,018.99

SUBTOTAL- EQUIPO 1,304,018.99

COSTO DIRECTO 27,354,518.99 27,354,519.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

TRANSPORTE DE CONJUNTO BOMBA TABLERO (BOGOTA-LOS SANTOS) UNIDAD: GLB


ITEM: 6.11
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES

SUBTOTAL MATERIALES -
MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO
CAMA BAJA T/K 11515 450.00 5,181,741.00

SUBTOTAL- EQUIPO 5,181,741.00

COSTO DIRECTO 5,181,741.00 5,181,741.00

CORREAS (PERFIL C 150X50 CAL 14) Unidad: ML


ITEM: 6.12
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
PERFIL HR C10"x2.5/8"2.5MM TIRA 6M UND 0.166 0 159,443.00 26,467.53
THINER DISOLVENTE GLN 0.025 0 18,000.00 450.00
SOLDADURA 6011 1/8" VARILLA KLS 0.06 0 7,200.00 432.00
ANTICORROSIVO PHCL GLN 0.05 0 37,862.00 1,893.10
SUBTOTAL MATERIALES 29,242.63

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 319.997 306.20
M.O. CARP.TALLER 1 AYUDANTE-1 OFI 81,642.00 185% 151,037.00 21.765 6,939.44
M.O. PINTURA 1 AYUDANTE-1 OFI 75,023.00 185% 138,792.00 160.000 867.45
SUBTOTAL MANO DE OBRA 8,113.09
EQUIPO
PULIDORA CON PIEDRA O DISCO DIA 0.04 0 26,000.00 1,040.00
SOLDADOR ELECTRICO DIA 0.06 0 28,500.00 1,710.00
HERRAMIENTA MENOR % 5% 0 8,113.09 405.65
ANDAMIO METALICO TUBULAR U/D 0.1 0 1,050.00 105.00
SUBTOTAL EQUIPO 3,260.65

COSTO DIRECTO 40,616.37 40,616.00

TEJAS (SEGÚN ESPECIFICACIONES) Unidad: M2


ITEM: 6.13
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TORN.LAMINA AUT.1/4-14X7/8 CABEZA HEXAGONAL 5/16-ARANDELA
UND 1.5 0 710.00 1,065.00
TEJA ALUM-POLIURETANO-ALUM L=.05MM E=1" ACABADO 1 M2
CARA 1.5 0 124,850.00 187,275.00
ESPIGO ALUM.-TUERCA 250MM UND 2.66 0 997.00 2,652.02
SUBTOTAL MATERIALES 190,992.02

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE-1 OFI 70,612.00 185% 130,632.00 1.2778 102,231.96
SUBTOTAL MANO DE OBRA 102,231.96
EQUIPO
HERRAMIENTA MENOR % 5% 0 102,231.96 5,111.59
ANDAMIO METALICO TUBULAR U/D 0.2 0 1,050.00 210.00
CRUCETA ANDAMIO DIA 0.2 0 100.00 20.00
SUBTOTAL EQUIPO 5,341.59

COSTO DIRECTO 298,565.57 298,566.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

CERRAMIENTOS ARQUITECTONICOS (SEGÚN ESPECIFICACIONES) Unidad: M2


ITEM: 6.14
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
GUADUA [TACO] 2.50-3M UND 0.2 0 6,000.00 1,200.00
PUNTILLA 2 CC LBS 0.1 0 2,000.00 200.00
ALAMBRE GALVANIZADO # 18 U KG 0.2 0 5,647.00 1,129.40
CERRAMIENTOS ARQUITECTONICOS (SEGÚN ESPECIFICACIONES)
M2 1 0 80,000.00 80,000.00
SUBTOTAL MATERIALES 82,529.40

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE-1 OFI 70,612.00 185% 130,632.00 6.3885 20,447.99
SUBTOTAL MANO DE OBRA 20,447.99
EQUIPO
HERRAMIENTA MENOR % 5% 0 20,447.99 1,022.39
SUBTOTAL EQUIPO 1,022.39

COSTO DIRECTO 103,999.78 104,000.00

MAMPOSTERIA (BLOQUE EN CONCRETO LISO A LA VISTA H-15 0,20 CM X 0,40 CM) Unidad: M2
ITEM: 6.15
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
BLOQUE CONCRETO N 14X19X39 UND 10 2 1,780.00 18,156.00
BLOQUE CONCRETO M 14X19X19 UND 2 2 1,077.00 2,197.08
BLOQUE CONCRETO T 14X19X39 UND 1.5 2 1,780.00 2,723.40
MORTERO DE PEGA PARA BLOQUE M3 0.015 0 321,197.00 4,817.95
SUBTOTAL MATERIALES 27,894.43

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE-1 OFI 70,612.00 185% 130,632.00 12.1740 10,730.41
SUBTOTAL MANO DE OBRA 10,730.41
EQUIPO
HERRAMIENTA MENOR % 5% 0 10,730.41 536.52
ANDAMIO METALICO TUBULAR U/D 0.2 0 1,050.00 210.00
SUBTOTAL EQUIPO 746.52

COSTO DIRECTO 39,371.36 39,371.00

LAMINA EN ACERO INOXIDABLE PERFORADA GALVANIZADA CALIBRE 16 6MM DE 1 X 2 Unidad: M2


MTS ITEM: 6.16
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TORNILLO AUTOPERFORANTE 3/16X3/4" CC DE 5/16+NEOPRENO
UND 1 0 252.00 252.00
LAMINA EN ACERO INOXIDABLE PERFORADA GALVANIZADA CALIBRE 16 6MM
UND 0.2 DE 1 X 2 MTS
0 769,800.00 153,960.00
REMATE U 6X2010MM POLICARB LATERAL-FINAL LAMINA UND 0.155 0 8,900.00 1,379.50
SILICONA TRANSPARENT.11 OZ UND 0.01 0 8,950.00 89.50
SUBTOTAL MATERIALES 155,681.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE-1 OFI 97,094.00 185% 179,623.00 3.6450 49,279.29
SUBTOTAL MANO DE OBRA 49,279.29
EQUIPO
HERRAMIENTA MENOR % 5% 0 49,279.29 2,463.96
ANDAMIO METALICO TUBULAR U/D 0.501 0 1,050.00 526.05
CRUCETA ANDAMIO DIA 0.5 0 100.00 50.00
SUBTOTAL EQUIPO 3,040.01

COSTO DIRECTO 208,000.30 208,000.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

LOGO DE ESANT EN LAMINA GALVANIZADA LISA DE COLOR Unidad: M2


ITEM: 6.17
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LIJA 320 AGUA PLI 3 0 1,000.00 3,000.00
SOLDADURA 6011 1/8" VARILLA KLS 1 0 7,200.00 7,200.00
LAM.COLL-ROLLED C.20 DE 122X244 UND 3.2 0 34,000.00 108,800.00
ANTICORROSIVO PHCL GLN 0.01 0 37,862.00 378.62
MASILLA PLASTICA INTERIORES CUム 0.01 0 37,500.00 375.00
ANGULO 11/2 x 1/ 8 TIRA DE 6 METROS UND 2 0 33,000.00 66,000.00
RODAMIENTO NYLON VC-50-20 CON BALINERA-VENTANERIA
UND 2 0 1,800.00 3,600.00
CARRILERA RODAMIENTO ML 2 0 4,800.00 9,600.00
SUBTOTAL MATERIALES 198,953.62

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. METALISTERIA 1 AYUDANTE-1 OFI 92,207.00 185% 170,582.00 1.6129 105,761.05
SUBTOTAL MANO DE OBRA 105,761.05
EQUIPO
HERRAMIENTA MENOR % 5% 0 105,761.05 5,288.05
SUBTOTAL EQUIPO 5,288.05

COSTO DIRECTO 310,002.72 310,003.00

PINTURA EPOXICA PARA CONCRERTO DUROCOLOR Unidad: M2


ITEM: 6.18
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 0.035 0 16.00 0.56
PINTURA EPOXICA GLN 0.1 0 85,500.00 8,550.00
SUBTOTAL MATERIALES 8,550.56

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. PINTURA 1 AYUDANTE-1 OFI 75,023.00 185% 138,792.00 21.2905 6,518.96
SUBTOTAL MANO DE OBRA 6,518.96
EQUIPO
HERRAMIENTA MENOR % 5% 0 6,518.96 325.94
ANDAMIO METALICO TUBULAR U/D 0.1 0 1,050.00 105.00
SUBTOTAL EQUIPO 430.94

COSTO DIRECTO 15,500.46 15,500.00

PUERTAS METALICAS 1X1.9 Unidad: UND


ITEM: 6.19
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LIJA 320 AGUA PLI 2 0 1,000.00 2,000.00
WASH PRIMER LTS 0.3 0 5,740.00 1,722.00
SOLDADURA 6011 1/8" VARILLA KLS 1 0 7,200.00 7,200.00
MASILLA PLASTICA INTERIORES CUム 0.06 0 37,500.00 2,250.00
TUBO GALV. 2" DE 6 ML UND 0.75 0 95,750.00 71,812.50
TUBO GALV. 1" *6.0M UND 1.3 0 12,570.00 16,341.00
SUBTOTAL MATERIALES 101,325.50

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. METALISTERIA 1 AYUDANTE-1 OFI 92,207.00 185% 170,582.00 2.6081 65,404.70
SUBTOTAL MANO DE OBRA 65,404.70
EQUIPO
HERRAMIENTA MENOR % 5% 0 65,404.70 3,270.23
SUBTOTAL EQUIPO 3,270.23

COSTO DIRECTO 170,000.43 170,000.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

PORTON METALICO 2.5X1.9 Unidad: UND


ITEM: 6.20
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
BISAGRA 3x3" COBRIZ PAR 6 0 3,480.00 20,880.00
LIJA 320 AGUA PLI 3 0 1,000.00 3,000.00
SOLDADURA 6011 1/8" VARILLA KLS 1 0 7,200.00 7,200.00
LAM.COLL-ROLLED C.20 DE 122X244 UND 6 0 34,000.00 204,000.00
ANTICORROSIVO PHCL GLN 0.01 0 37,862.00 378.62
MASILLA PLASTICA INTERIORES CUム 0.01 0 37,500.00 375.00
FALLEVA SOBREPONER 8" METALICA UND 1 0 10,925.00 10,925.00
RODAMIENTO NYLON VC-50-20 CON BALINERA-VENTANERIA
UND 1 0 1,800.00 1,800.00
CARRILERA RODAMIENTO ML 1 0 4,800.00 4,800.00
SUBTOTAL MATERIALES 253,358.62

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. METALISTERIA 1 AYUDANTE-1 OFI 92,207.00 185% 170,582.00 2.0673 82,514.39
SUBTOTAL MANO DE OBRA 82,514.39
EQUIPO
HERRAMIENTA MENOR % 0.05001 0 82,514.39 4,126.54
SUBTOTAL EQUIPO 4,126.54

COSTO DIRECTO 339,999.55 340,000.00

PLATAFORMA DE ACCESO Unidad: KLS


ITEM: 6.21
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SOLDADURA 6011 1/8" VARILLA KLS 0.05 0 7,200.00 360.00
ANTICORROSIVO PHCL GLN 0.001 0 37,862.00 37.86
HIERR.DE 60000 PSI 420 MPA KLS 0.134 0 4,000.00 536.00
ACERO ESTRUCT. ASTM A-36 KLS 1 0 2,800.00 2,800.00
SUBTOTAL MATERIALES 3,733.86
MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.
M.O. ALBANILERIA 3 AYUDANTE 86,456.00 185% 159,943.00 435.291 367.44
M.O. METALISTERIA 1 AYUDANTE-1 OFI 92,207.00 185% 170,582.00 254.4226 670.47
M.O. PINTURA 1 AYUDANTE-1 OFI 75,023.00 185% 138,792.00 800.000 173.49
SUBTOTAL MANO DE OBRA 1,211.40
EQUIPO
SOLDADOR ELECTRICO DIA 0.012 0 28,500.00 342.00
HERRAMIENTA MENOR % 5% 0 1,211.40 60.56
OXICORTE (OXIGENO-ACETILENO) DIA 0.005 0 27,500.00 137.50
ANDAMIO METALICO TUBULAR U/D 0.3 0 1,050.00 315.00
SUBTOTAL EQUIPO 855.06
OTROS

SUBTOTAL OTROS -

COSTO DIRECTO 5,800.32 5,800.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO E INSTALACIÓN SISTEMA TRANSPORTE PARA MOTOR - BOMBA EN UNIDAD: UND
ESTACIÓN ITEM: 6.22
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SISTEMA TRANSPORTE PARA MOTOR - BOMBA EN ESTACIÓN
UND 1 0 2,949,994.00 2,949,994.00

SUBTOTAL MATERIALES 2,949,994.00


MANO DE OBRA
M.O. ELECTRICAS 2 AYUDANTE-1 OFI 134,603.00 185% 249,015.00 0.9779 254,642.60

SUBTOTAL- MANO DE OBRA 254,642.60


EQUIPO
HERRAMIENTA MENOR % 0.05 254,642.60 12,732.13

SUBTOTAL- EQUIPO 12,732.13

COSTO DIRECTO 3,217,368.73 3,217,369.00

CERRAMIENTO MALA ESLABONADA Unidad: ML


ITEM: 7,1
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
MALLA ESLABONADA GALV #12 ROMBO DE 11/2" M2 10 5 24,350.00 255,675.00
THINER DISOLVENTE GLN 0.07 0 18,000.00 1,260.00
SOLDADURA 6011 1/8" VARILLA KLS 0.5 0 7,200.00 3,600.00
ESMALTE PINTURA DE ALUMINI CROMADA GLN 0.2 0 62,320.00 12,464.00
SUBTOTAL MATERIALES 272,999.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. METALISTERIA 2 AYUDANTE-1 OFI 121,366.00 185% 224,527.00 10.0310 22,383.31
M.O. PINTURA 1 AYUDANTE-1 OFI 75,023.00 185% 138,792.00 30.0000 4,626.40
SUBTOTAL MANO DE OBRA 27,009.71
EQUIPO
SOLDADOR ELECTRICO DIA 0.15 0 28,500.00 4,275.00
HERRAMIENTA MENOR % 5% 0 27,009.71 1,350.48
SUBTOTAL EQUIPO 5,625.48

COSTO DIRECTO 305,634.19 305,634.00

CONCRETO 1:2:1 4000 PSI - CIMENTACION Unidad: M3


ITEM: 7.2
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
PLASTOCRETE D.M. (20 KGS) KLS 3 0 6,366.00 19,098.00
AGUA LTS 210 0 16.00 3,360.00
ARENA GRUESA M3 0.87 0 60,000.00 52,200.00
GRAVA TRITURADA DE 3/4 M3 0.47 0 70,000.00 32,900.00
GASOLINA CORRIENTE GLN 0.1 0 8,700.00 870.00
CEMENTO GRIS KLS 480 0 600.00 288,000.00
ACEITE MOTOR 4 TIEMPOS GLN 0.006 0 70,000.00 420.00
SUBTOTAL MATERIALES 396,848.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 1.6351 59,924.78
SUBTOTAL MANO DE OBRA 59,924.78
EQUIPO
MEZCLADORA DE 9 PIES CUBICOS DIA 0.0601 0 38,800.00 2,331.88
HERRAMIENTA MENOR % 0.04999 0 59,924.78 2,995.63
SUBTOTAL EQUIPO 5,327.51

COSTO DIRECTO 462,100.29 462,100.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

ACERO REFUERZO FLEJADO 60000 PSI 420Mpa Unidad: KLS


ITEM: 7.3
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ALAMBRE NEGRO # 18 KLS 0.04 0.03 3,500.00 140.04
SEGUETA SIN MARCO UND 0.04 0.03 2,600.00 104.03
HIERR.DE 60000 PSI 420 MPA KLS 1.03 0 4,000.00 4,120.00
SUBTOTAL MATERIALES 4,364.07

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 62.3058 786.30
SUBTOTAL MANO DE OBRA 786.30

COSTO DIRECTO 5,150.37 5,150.00

EXCAVACION EN CONGLOMERADO A MAQUINA + RETIRO Y DISPOSICION FINAL UNIDAD: M3


ITEM: 7.4
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES

SUBTOTAL MATERIALES -
MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO
RETROEXCAVADORA CARGADORA HRS 0.11 85,000.00 9,350.00
VOLQUETA HORA 0.14278 42,024.00 6,000.18

SUBTOTAL- EQUIPO 15,350.18

COSTO DIRECTO 15,350.18 15,350.00

EXCAVACION EN ROCA Unidad: M3


ITEM: 7.5
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

EQUIPO
COMPRESOR DE DOS MARTILLOS HRS 0.8608 0 92,000.00 79,193.60
RETROEXCAVADORA JD-510 HRS 0.035 88,000.00 3,080.00
HERRAMIENTA MENOR GLB 0.8029 0 1,400.00 1,124.06
SUBTOTAL EQUIPO 83,397.66

COSTO DIRECTO 83,397.66 83,398.00

EMPRADIZACION CON GEOMANTO TRM-500 Unidad: M2


ITEM: 7.6
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
GEOMANTO TRM-500 M2 1 0 8,500.00 8,500.00
PRADO M2 1.1 0 7,500.00 8,250.00
TIERRA NEGRA M3 0.065 0 14,500.00 942.50
SUBTOTAL MATERIALES 17,692.50

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE-1 OFI 70,612.00 185% 130,632.00 36.6312 3,566.14
SUBTOTAL MANO DE OBRA 3,566.14
EQUIPO
HERRAMIENTA MENOR % 5% 0 3,566.14 178.30
SUBTOTAL EQUIPO 178.30

COSTO DIRECTO 21,436.94 21,437.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

CAJA MACROMEDIDOR Unidad: UND


ITEM: 8,1
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CAJA MACROMEDIDOR UND 1 0 940,000.00 940,000.00
SUBTOTAL MATERIALES 940,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 1 AYUDANTE-1 OFI 98,854.00 185% 182,879.00 3.2004 57,142.54
SUBTOTAL MANO DE OBRA 57,142.54
EQUIPO
HERRAMIENTA MENOR % 5% 0 57,142.54 2,857.12
SUBTOTAL EQUIPO 2,857.12

COSTO DIRECTO 999,999.66 1,000,000.00

EXCAVACION EN MATERIAL COMUN Unidad: M3


ITEM: 8.2
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 2.3563 20,791.50
SUBTOTAL MANO DE OBRA 20,791.50
EQUIPO
HERRAMIENTA MENOR % 5% 0 20,791.50 1,039.57
SUBTOTAL EQUIPO 1,039.57

COSTO DIRECTO 21,831.07 21,831.00

ACERO REFUERZO FLEJADO 60000 PSI 420Mpa Unidad: KLS


ITEM: 8.3
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ALAMBRE NEGRO # 18 KLS 0.04 0.03 3,500.00 140.04
SEGUETA SIN MARCO UND 0.04 0.03 2,600.00 104.03
HIERR.DE 60000 PSI 420 MPA KLS 1.03 0 4,000.00 4,120.00
SUBTOTAL MATERIALES 4,364.07

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 62.3058 786.30
SUBTOTAL MANO DE OBRA 786.30

COSTO DIRECTO 5,150.37 5,150.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
CONCRETO 3.00 PSI, ZAPATAS, V.CIMENTACION Y PISOS Unidad: M3
ITEM: 8.4
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
PUNTILLA 2 CC LBS 0.5 0 2,000.00 1,000.00
TABLA 1X10x3M [2C] UND 0.2 0 9,000.00 1,800.00
VARETA 2"x2"x3M UND 0.2 0 2,400.00 480.00
MEZCLA CONCRETO 1:2:3 3100 PSI - 22,0 Mpa M3 1.05 0 323,204.00 339,364.20
SUBTOTAL MATERIALES 342,644.20

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE-1 OFI 97,094.00 185% 179,623.00 10.2429 17,536.34
SUBTOTAL MANO DE OBRA 17,536.34
EQUIPO
VIBRADOR ELECTRICO DIA 0.05 0 34,800.00 1,740.00
VOLQUETA TRANSPORTE MAT.PETREOS 1-10KMS M3 0.3 0 7,000.00 2,100.00
SUBTOTAL EQUIPO 3,840.00

COSTO DIRECTO 364,020.54 364,021.00

CONCRETO 3000 PSI COLUMNAS Y VIGAS Unidad: M3


ITEM: 8.5
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ANTISOL BLANCO KLS 0.05 0 6,300.00 315.00
SEPAROL DESFORMALETEANTE TARRO 15 KLS KLS 0.05 0 11,800.00 590.00
SIKAMENT NS SUPERPLASTIFIC TARRO DE 25 KLS KLS 0.05 0 6,500.00 325.00
CUARTON 2"x4"x3M UND 0.05 0 10,500.00 525.00
PUNTILLA 2 CC LBS 0.3 0 2,000.00 600.00
TABLA 1x10x3M UND 0.05 0 8,500.00 425.00
VARETA 2"x2"x3M UND 0.05 0 2,400.00 120.00
MEZCLA CONCRETO 1:2:3 3100 PSI - 22,0 Mpa M3 1 0 323,204.00 323,204.00
SUBTOTAL MATERIALES 326,104.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 3 AYUDANTE-1 OFI 123,576.00 185% 228,615.00 4.2253 54,106.22
SUBTOTAL MANO DE OBRA 54,106.22
EQUIPO
VIBRADOR ELECTRICO DIA 0.05 0 34,800.00 1,740.00
HERRAMIENTA MENOR % 5% 0 54,106.22 2,705.31
TACO METALICO EXTENSION DE 2.OM A 3.30MT DIA 10 0 170.00 1,700.00
ANDAMIO METALICO TUBULAR U/D 1 0 1,050.00 1,050.00
SUBTOTAL EQUIPO 7,195.31

COSTO DIRECTO 387,405.53 387,406.00

ACERO REFUERZO FLEJADO 60000 PSI 420Mpa Unidad: KLS


ITEM: 8.6
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ALAMBRE NEGRO # 18 KLS 0.04 0.03 3,500.00 140.04
SEGUETA SIN MARCO UND 0.04 0.03 2,600.00 104.03
HIERR.DE 60000 PSI 420 MPA KLS 1.03 0 4,000.00 4,120.00
SUBTOTAL MATERIALES 4,364.07

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 62.3058 786.30
SUBTOTAL MANO DE OBRA 786.30

COSTO DIRECTO 5,150.37 5,150.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

CONCRETO 1:2:4 2500 PSI - SOLADOS Unidad: M3


ITEM: 8.7
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 160 0 16.00 2,560.00
ARENA GRUESA M3 0.52 0 60,000.00 31,200.00
GRAVA TRITURADA DE 3/4 M3 0.94 0 70,000.00 65,800.00
GASOLINA CORRIENTE GLN 0.1 0 8,700.00 870.00
CEMENTO GRIS KLS 260 0 600.00 156,000.00
ACEITE MOTOR 4 TIEMPOS GLN 0.006 0 70,000.00 420.00
SUBTOTAL MATERIALES 256,850.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 1.2920 75,838.24
SUBTOTAL MANO DE OBRA 75,838.24
EQUIPO
MEZCLADORA DE 9 PIES CUBICOS DIA 0.0601 0 38,800.00 2,331.88
HERRAMIENTA MENOR % 0.04999 0 75,838.24 3,791.15
SUBTOTAL EQUIPO 6,123.03

COSTO DIRECTO 338,811.27 338,811.00

EXCAVACION EN MATERIAL COMUN Unidad: M3


ITEM: 8.8
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 2.3563 20,791.50
SUBTOTAL MANO DE OBRA 20,791.50
EQUIPO
HERRAMIENTA MENOR % 5% 0 20,791.50 1,039.57
SUBTOTAL EQUIPO 1,039.57

COSTO DIRECTO 21,831.07 21,831.00

PLANTA DE TRATAMIENTO DE AGUA POTABLE (PTAP) UNIDAD: UND


ITEM: 9,1
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
PLANTA DE TRATAMIENTO DE AGUA POTABLE UND 1 0 543,015,664.00 543,015,664.00

SUBTOTAL MATERIALES 543,015,664.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 543,015,664.00 543,015,664.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

REPLANTEO DE LÍNEA DE M.T HASTA 34,5 KV Unidad: ML


ITEM: 10.1
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LISTON 2 x2x3M. UND 0.01 0 3,800.00 38.00
PUNTILLA 2 CC LBS 0.003 0 2,000.00 6.00
PIOLA GRUESA 50 METROS ROL 0.003 0 2,500.00 7.50
SUBTOTAL MATERIALES 51.50

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. TOPOGRAFIA 1 CADENERO-1 TOP 194,469.00 185% 359,767.00 1700.0000 211.63
M.O. ALBANILERIA 2 AYUDANTE-1 OFI 97,094.00 185% 179,623.00 2026.2989 88.65
SUBTOTAL MANO DE OBRA 300.27
EQUIPO
HERRAMIENTA MENOR % 5% 0 300.27 15.01
SUBTOTAL EQUIPO 15.01

COSTO DIRECTO 366.78 367.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN POSTE DE CONCETRO 14 ML - TR 1500 KG Unidad: UND


ITEM: 10.2
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
POSTE DE CONCETRO 14 ML - TR 1500 KG UND 1 0 2,147,359.00 2,147,359.00
MEZCLA CONCRETO 1:2.5:4« 2500 PSI-17.5MPa M3 0.15 0 273,324.00 40,998.60
SUBTOTAL MATERIALES 2,188,357.60

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 3.922 159,103.26
SUBTOTAL MANO DE OBRA 159,103.26
EQUIPO
GRUA-MONTACARGA 3 TONELADAS HRS 0.3958 0 30,000.00 11,874.00
SUBTOTAL EQUIPO 11,874.00

COSTO DIRECTO 2,359,334.86 2,359,335.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN POSTE DE CONCETRO 14 ML - TR 1050 KG Unidad: UND


ITEM: 10.3
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
POSTE DE CONCETRO 14 ML - TR 1050 KG UND 1 0 1,844,353.00 1,844,353.00
MEZCLA CONCRETO 1:2.5:4« 2500 PSI-17.5MPa M3 0.15 0 273,324.00 40,998.60
SUBTOTAL MATERIALES 1,885,351.60

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 3.9220 159,103.26
SUBTOTAL MANO DE OBRA 159,103.26
EQUIPO
GRUA-MONTACARGA 3 TONELADAS HRS 0.396 0 30,000.00 11,880.00
SUBTOTAL EQUIPO 11,880.00

COSTO DIRECTO 2,056,334.86 2,056,335.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS Unidad: UND


ESTRUCTURA TIPO 507 ITEM: 10.4
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AISLADOR ESPIGO 3.2KV UND 2 0 12,862.00 25,724.00
ANGULAR EN V 18X48" CONJUNTO PRIMARIO UND 1 0 29,464.00 29,464.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 2 0 18,587.00 37,174.00
CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO UND 1 0 102,730.00 102,730.00
ESPIGO ACANALADO EXTR POST CONJUNTO PRIMARIO UND 2 0 24,493.00 48,986.00
TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR UND 2 0 631.00 1,262.00
TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR UND 2 0 1,263.00 2,526.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 2 0 1,436.00 2,872.00
ALAMBRE ALUMINIO # 4 AMARRE ML 2 0 295.00 590.00
CORAZA PARA ACSR CON GRILL CORAZA PARA ACSR CONUND
GRILLETES 2 0 1,972.00 3,944.00
CINTA DE ALUMINIO P/ACSR CINTA DE ALUMINIO PARA ACSR
ML 4 0 1,137.00 4,548.00
SUBTOTAL MATERIALES 259,820.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 4.8270 129,273.46
SUBTOTAL MANO DE OBRA 129,273.46
EQUIPO
HERRAMIENTA MENOR % 5% 0 129,273.46 6,463.67
SUBTOTAL EQUIPO 6,463.67

COSTO DIRECTO 395,557.13 395,557.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS Unidad: UND


ESTRUCTURA TIPO 514 ITEM: 10.5
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AISLADOR ESPIGO 3.2KV UND 2 0 12,862.00 25,724.00
ANGULAR EN V 18X48" CONJUNTO PRIMARIO UND 1 0 29,464.00 29,464.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 2 0 18,587.00 37,174.00
CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO
102,730.00
UND 1 0 102,730.00
ESPIGO ACANALADO EXTR POST CONJUNTO
48,986.00
PRIMARIO UND 2 0 24,493.00
TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR
1,262.00
UND 2 0 631.00
TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR
2,526.00
UND 2 0 1,263.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 2 0 1,436.00 2,872.00
ALAMBRE ALUMINIO # 4 AMARRE ML 2 0 295.00 590.00
CORAZA PARA ACSR CON GRILL CORAZA PARA
3,944.00
ACSR CON GRILLETES UND 2 0 1,972.00
CINTA DE ALUMINIO P/ACSR CINTA DE ALUMINIO
4,548.00
PARA ACSR ML 4 0 1,137.00
SUBTOTAL MATERIALES 259,820.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 4.8270 129,273.46
SUBTOTAL MANO DE OBRA 129,273.46
EQUIPO
HERRAMIENTA MENOR % 5% 0 129,273.46 6,463.67
SUBTOTAL EQUIPO 6,463.67

COSTO DIRECTO 395,557.13 395,557.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS Unidad: UND
ESTRUCTURA TIPO 523M ITEM: 10.6
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AISLADOR ESPIGO 3.2KV UND 2 0 12,862.00 25,724.00
ANGULAR EN V 18X48" CONJUNTO PRIMARIO UND 1 0 29,464.00 29,464.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 2 0 18,587.00 37,174.00
CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO UND 1 0 102,730.00 102,730.00
ESPIGO ACANALADO EXTR POST CONJUNTO PRIMARIO UND 2 0 24,493.00 48,986.00
TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR UND 2 0 631.00 1,262.00
TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR UND 2 0 1,263.00 2,526.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 2 0 1,436.00 2,872.00
ALAMBRE ALUMINIO # 4 AMARRE ML 2 0 295.00 590.00
CORAZA PARA ACSR CON GRILL CORAZA PARA ACSR CONUND
GRILLETES 2 0 1,972.00 3,944.00
CINTA DE ALUMINIO P/ACSR CINTA DE ALUMINIO PARA ACSR
ML 4 0 1,137.00 4,548.00
SUBTOTAL MATERIALES 259,820.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 4.8270 129,273.46
SUBTOTAL MANO DE OBRA 129,273.46
EQUIPO
HERRAMIENTA MENOR % 5% 0 129,273.46 6,463.67
SUBTOTAL EQUIPO 6,463.67

COSTO DIRECTO 395,557.13 395,557.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS Unidad: UND


ESTRUCTURA TIPO P103 ITEM: 10.7
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AISLADOR ESPIGO 3.2KV UND 2 0 12,862.00 25,724.00
ANGULAR EN V 18X48" CONJUNTO PRIMARIO UND 1 0 29,464.00 29,464.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 2 0 18,587.00 37,174.00
CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO UND 1 0 102,730.00 102,730.00
ESPIGO ACANALADO EXTR POST CONJUNTO PRIMARIO UND 2 0 24,493.00 48,986.00
TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR UND 2 0 631.00 1,262.00
TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR UND 2 0 1,263.00 2,526.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 2 0 1,436.00 2,872.00
ALAMBRE ALUMINIO # 4 AMARRE ML 2 0 295.00 590.00
CORAZA PARA ACSR CON GRILL CORAZA PARA ACSR CONUND
GRILLETES 2 0 1,972.00 3,944.00
CINTA DE ALUMINIO P/ACSR CINTA DE ALUMINIO PARA ACSR
ML 4 0 1,137.00 4,548.00
SUBTOTAL MATERIALES 259,820.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 11.2804 55,317.45
SUBTOTAL MANO DE OBRA 55,317.45
EQUIPO
HERRAMIENTA MENOR % 5% 0 55,317.45 2,765.87
SUBTOTAL EQUIPO 2,765.87

COSTO DIRECTO 317,903.32 317,903.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS Unidad: UND


ESTRUCTURA TIPO P112 ITEM: 10.8
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AISLADOR ESPIGO 3.2KV UND 2 0 12,862.00 25,724.00
AISLADOR SUSPENSION 6" CONJUNTO PRIMARIO
177,758.00
UND 7 0 25,394.00
ANGULAR EN V 18X48" CONJUNTO PRIMARIO UND 4 0 29,464.00 117,856.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 4 0 18,587.00 74,348.00
CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO
308,190.00
UND 3 0 102,730.00
ESPIGO ACANALADO EXTR POST CONJUNTO
48,986.00
PRIMARIO UND 2 0 24,493.00
PIN RECTO5/8X7 1/2CRU/META CONJUNTO PRIMARIO
19,720.00
UND 2 0 9,860.00
TORN.PASANTE 12" CONJUNTO PRIMARIO UND 4 0 5,570.00 22,280.00
TUERCA DE OJO 3/4" O 5/8" CONJUNTO PRIMARIO
35,372.00
UND 4 0 8,843.00
TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR
5,048.00
UND 8 0 631.00
TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR
10,104.00
UND 8 0 1,263.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 8 0 1,436.00 11,488.00
GRAPA TERMINAL DE ALUMINIO CONJUNTO
57,915.00
PRIMARIO UND 3 0 19,305.00
SUBTOTAL MATERIALES 914,789.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 6.2967 99,100.00
SUBTOTAL MANO DE OBRA 99,100.00
EQUIPO
HERRAMIENTA MENOR % 0.05 0 99,100.00 4,955.00
SUBTOTAL EQUIPO 4,955.00

COSTO DIRECTO 1,018,844.00 1,018,844.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS Unidad: UND


ESTRUCTURA TIPO R114 ITEM: 10.9
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AISLADOR SUSPENSION 6" CONJUNTO PRIMARIO UND 4 0 25,394.00 101,576.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 2 0 18,587.00 37,174.00
CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO UND 2 0 102,730.00 205,460.00
TORN.PASANTE 12" CONJUNTO PRIMARIO UND 2 0 5,570.00 11,140.00
TUERCA DE OJO 3/4" O 5/8" CONJUNTO PRIMARIO UND 2 0 8,843.00 17,686.00
TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR UND 2 0 631.00 1,262.00
TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR UND 4 0 1,263.00 5,052.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 2 0 1,436.00 2,872.00
ANGULAR BANDERA 8"X 2.44MT CONJUNTO PRIMARIO UND 2 0 43,869.00 87,738.00
GRAPA TERMINAL DE ALUMINIO CONJUNTO PRIMARIO UND 2 0 19,305.00 38,610.00
SUBTOTAL MATERIALES 508,570.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 4.9062 127,186.62
SUBTOTAL MANO DE OBRA 127,186.62
EQUIPO
HERRAMIENTA MENOR % 5% 0 127,186.62 6,359.33
SUBTOTAL EQUIPO 6,359.33

COSTO DIRECTO 642,115.95 642,116.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS Unidad: UND


ESTRUCTURA TIPO R130 ITEM: 10.10
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AISLADOR ESPIGO 3.2KV UND 1 0 12,862.00 12,862.00
AISLADOR SUSPENSION 6" CONJUNTO PRIMARIO UND 12 0 25,394.00 304,728.00
ANGULAR EN V 18X48" CONJUNTO PRIMARIO UND 2 0 29,464.00 58,928.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 2 0 18,587.00 37,174.00
CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO UND 2 0 102,730.00 205,460.00
PIN RECTO5/8X7 1/2CRU/META CONJUNTO PRIMARIO UND 1 0 9,860.00 9,860.00
TORN.PASANTE 12" CONJUNTO PRIMARIO UND 2 0 5,570.00 11,140.00
TUERCA DE OJO 3/4" O 5/8" CONJUNTO PRIMARIO UND 6 0 8,843.00 53,058.00
TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR UND 4 0 631.00 2,524.00
TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR UND 4 0 1,263.00 5,052.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 4 0 1,436.00 5,744.00
GRAPA TERMINAL DE ALUMINIO CONJUNTO PRIMARIO UND 6 0 19,305.00 115,830.00
SUBTOTAL MATERIALES 822,360.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 4.9431 126,237.18
SUBTOTAL MANO DE OBRA 126,237.18
EQUIPO
HERRAMIENTA MENOR % 5% 0 126,237.18 6,311.85
SUBTOTAL EQUIPO 6,311.85

COSTO DIRECTO 954,909.03 954,909.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS Unidad: UND


ESTRUCTURA TIPO R130T ITEM: 10.11
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AISLADOR ESPIGO 3.2KV UND 1 0 12,862.00 12,862.00
AISLADOR SUSPENSION 6" CONJUNTO PRIMARIO UND 12 0 25,394.00 304,728.00
ANGULAR EN V 18X48" CONJUNTO PRIMARIO UND 2 0 29,464.00 58,928.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 2 0 18,587.00 37,174.00
CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO UND 2 0 102,730.00 205,460.00
PIN RECTO5/8X7 1/2CRU/META CONJUNTO PRIMARIO UND 1 0 9,860.00 9,860.00
TORN.PASANTE 12" CONJUNTO PRIMARIO UND 2 0 5,570.00 11,140.00
TUERCA DE OJO 3/4" O 5/8" CONJUNTO PRIMARIO UND 6 0 8,843.00 53,058.00
TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR UND 4 0 631.00 2,524.00
TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR UND 4 0 1,263.00 5,052.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 4 0 1,436.00 5,744.00
GRAPA TERMINAL DE ALUMINIO CONJUNTO PRIMARIO UND 6 0 19,305.00 115,830.00
SUBTOTAL MATERIALES 822,360.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 4.9431 126,237.18
SUBTOTAL MANO DE OBRA 126,237.18
EQUIPO
HERRAMIENTA MENOR % 5% 0 126,237.18 6,311.85
SUBTOTAL EQUIPO 6,311.85

COSTO DIRECTO 954,909.03 954,909.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS Unidad: UND


ESTRUCTURA TIPO R131 ITEM: 10.12
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AISLADOR ESPIGO 3.2KV UND 3 0 12,862.00 38,586.00
AISLADOR SUSPENSION 6" CONJUNTO PRIMARIO UND 12 0 25,394.00 304,728.00
ANGULAR EN V 18X48" CONJUNTO PRIMARIO UND 4 0 29,464.00 117,856.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 4 0 18,587.00 74,348.00
CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO UND 4 0 102,730.00 410,920.00
PIN RECTO5/8X7 1/2CRU/META CONJUNTO PRIMARIO UND 3 0 9,860.00 29,580.00
TORN.PASANTE 12" CONJUNTO PRIMARIO UND 4 0 5,570.00 22,280.00
TUERCA DE OJO 3/4" O 5/8" CONJUNTO PRIMARIO UND 6 0 8,843.00 53,058.00
TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR UND 8 0 631.00 5,048.00
TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR UND 8 0 1,263.00 10,104.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 8 0 1,436.00 11,488.00
GRAPA TERMINAL DE ALUMINIO CONJUNTO PRIMARIO UND 6 0 19,305.00 115,830.00
SUBTOTAL MATERIALES 1,193,826.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 3.4672 179,973.18
SUBTOTAL MANO DE OBRA 179,973.18
EQUIPO
HERRAMIENTA MENOR % 5% 0 179,973.18 8,998.65
SUBTOTAL EQUIPO 8,998.65

COSTO DIRECTO 1,382,797.83 1,382,798.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS Unidad: UND


ESTRUCTURA TIPO R180 ITEM: 10.13
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ANGULAR EN V 18X48" CONJUNTO PRIMARIO UND 2 0 29,464.00 58,928.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 2 0 18,587.00 37,174.00
CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO UND 2 0 102,730.00 205,460.00
TORN.PASANTE 12" CONJUNTO PRIMARIO UND 2 0 5,570.00 11,140.00
TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR UND 4 0 631.00 2,524.00
TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR UND 4 0 1,263.00 5,052.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 4 0 1,436.00 5,744.00
ESPIGO PARA AISL LINE POST CONJUNTO PRIMARIO UND 6 0 14,360.00 86,160.00
SOPORTE AISL LINE POST PTA CONJUNTO PRIMARIO UND 2 0 44,451.00 88,902.00
TORN.MAQUINA 5/8 X 9" CONJUNTO PRIMARIO UND 2 0 5,627.00 11,254.00
BASE ANGULAR PARA LINE POS CONJUNTO PRIMARIO UND 4 0 38,493.00 153,972.00
ALAMBRE ALUMINIO # 4 AMARRE ML 3 0 295.00 885.00
CORAZA PARA ACSR CON GRILL CORAZA PARA ACSR CONUND
GRILLETES 3 0 1,972.00 5,916.00
CINTA DE ALUMINIO P/ACSR CINTA DE ALUMINIO PARA ACSR
ML 6 0 1,137.00 6,822.00
AISLADOR LINE POST 35 KV AISLADOR LINE POST PARA 34UND
KV 9 0 120,154.00 1,081,386.00
SUBTOTAL MATERIALES 1,761,319.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 4.8069 129,814.02
SUBTOTAL MANO DE OBRA 129,814.02
EQUIPO
HERRAMIENTA MENOR % 5% 0 129,814.02 6,490.70
SUBTOTAL EQUIPO 6,490.70

COSTO DIRECTO 1,897,623.72 1,897,624.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS Unidad: UND


ESTRUCTURA TIPO RH214 ITEM: 10.14
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AISLADOR SUSPENSION 6" CONJUNTO PRIMARIO UND 6 0 25,394.00 152,364.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 2 0 18,587.00 37,174.00
CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO UND 2 0 102,730.00 205,460.00
TORN.PASANTE 12" CONJUNTO PRIMARIO UND 3 0 5,570.00 16,710.00
TUERCA DE OJO 3/4" O 5/8" CONJUNTO PRIMARIO UND 3 0 8,843.00 26,529.00
TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR UND 2 0 631.00 1,262.00
TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR UND 4 0 1,263.00 5,052.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 4 0 1,436.00 5,744.00
ANGULAR BANDERA 8"X 2.44MT CONJUNTO PRIMARIO UND 2 0 43,869.00 87,738.00
GRAPA TERMINAL DE ALUMINIO CONJUNTO PRIMARIO UND 3 0 19,305.00 57,915.00
SUBTOTAL MATERIALES 595,948.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 5.0475 123,626.15
SUBTOTAL MANO DE OBRA 123,626.15
EQUIPO
HERRAMIENTA MENOR % 5% 0 123,626.15 6,181.30
SUBTOTAL EQUIPO 6,181.30

COSTO DIRECTO 725,755.45 725,755.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS Unidad: UND


ESTRUCTURA TIPO RH230 ITEM: 10.15
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ANGULAR EN V 18X48" CONJUNTO PRIMARIO UND 2 0 29,464.00 58,928.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 2 0 18,587.00 37,174.00
CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO UND 2 0 102,730.00 205,460.00
TORN.PASANTE 12" CONJUNTO PRIMARIO UND 2 0 5,570.00 11,140.00
TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR UND 2 0 631.00 1,262.00
TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR UND 4 0 1,263.00 5,052.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 4 0 1,436.00 5,744.00
AISLADOR LINE POST 25 KV CONJUNTO PRIMARIO UND 6 0 62,186.00 373,116.00
ESPIGO PARA AISL LINE POST CONJUNTO PRIMARIO UND 6 0 14,360.00 86,160.00
SOPORTE AISL LINE POST PTA CONJUNTO PRIMARIO UND 2 0 44,451.00 88,902.00
TORN.MAQUINA 5/8 X 9" CONJUNTO PRIMARIO UND 2 0 5,627.00 11,254.00
BASE ANGULAR PARA LINE POS CONJUNTO PRIMARIO UND 4 0 38,493.00 153,972.00
ALAMBRE ALUMINIO # 4 AMARRE ML 3 0 295.00 885.00
CORAZA PARA ACSR CON GRILL CORAZA PARA ACSR CONUND
GRILLETES 3 0 1,972.00 5,916.00
CINTA DE ALUMINIO P/ACSR CINTA DE ALUMINIO PARA ACSR
ML 6 0 1,137.00 6,822.00
SUBTOTAL MATERIALES 1,051,787.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 5.0265 124,142.64
SUBTOTAL MANO DE OBRA 124,142.64
EQUIPO
HERRAMIENTA MENOR % 5% 0 124,142.64 6,207.13
SUBTOTAL EQUIPO 6,207.13

COSTO DIRECTO 1,182,136.77 1,182,137.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
DESINSTALACIÓN POSTE DE CONCRETO 12 ML - TR 1050 KG. Unidad: UND
ITEM: 10.16
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 4.0039 155,848.80
SUBTOTAL MANO DE OBRA 155,848.80
EQUIPO
CARRO GRUA 5 TONELADAS HRS 3 0 51,000.00 153,000.00
SUBTOTAL EQUIPO 153,000.00

COSTO DIRECTO 308,848.80 308,849.00

DESINSTALACIÓN POSTE DE CONCRETO 15 ML - TR 1050 KG Unidad: UND


ITEM: 10.17
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 3.9962 156,149.09
SUBTOTAL MANO DE OBRA 156,149.09
EQUIPO
CARRO GRUA 5 TONELADAS HRS 3 0 51,000.00 153,000.00
SUBTOTAL EQUIPO 153,000.00

COSTO DIRECTO 309,149.09 309,149.00

DESINSTALACIÓN POSTE DE CONCRETO 12 ML - TR 510 KG. Unidad: UND


ITEM: 10.18
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 4.0000 156,000.75
SUBTOTAL MANO DE OBRA 156,000.75
EQUIPO
CARRO GRUA 5 TONELADAS HRS 3 0 51,000.00 153,000.00
SUBTOTAL EQUIPO 153,000.00

COSTO DIRECTO 309,000.75 309,001.00

DESINSTALACIÓN POSTE DE CONCRETO 14 ML - TR 1500 KG. Unidad: UND


ITEM: 10.19
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 3.1362 198,967.86
SUBTOTAL MANO DE OBRA 198,967.86
EQUIPO
CARRO GRUA 5 TONELADAS HRS 3 0 51,000.00 153,000.00
SUBTOTAL EQUIPO 153,000.00

COSTO DIRECTO 351,967.86 351,968.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
DESINSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS ESTRUCTURA TIPO 510. Unidad: UND
ITEM: 10.20
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 9.4994 65,688.68
SUBTOTAL MANO DE OBRA 65,688.68
EQUIPO
HERRAMIENTA MENOR % 5% 0 65,688.68 3,284.43
SUBTOTAL EQUIPO 3,284.43

COSTO DIRECTO 68,973.11 68,973.00

DESINSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS ESTRUCTURA TIPO 510. Unidad: UND
ITEM: 10.21
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 9.4994 65,688.68
SUBTOTAL MANO DE OBRA 65,688.68
EQUIPO
HERRAMIENTA MENOR % 5% 0 65,688.68 3,284.43
SUBTOTAL EQUIPO 3,284.43

COSTO DIRECTO 68,973.11 68,973.00

DESINSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS ESTRUCTURA TIPO 521. Unidad: UND
ITEM: 10.22
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 9.4994 65,688.68
SUBTOTAL MANO DE OBRA 65,688.68
EQUIPO
HERRAMIENTA MENOR % 5% 0 65,688.68 3,284.43
SUBTOTAL EQUIPO 3,284.43

COSTO DIRECTO 68,973.11 68,973.00

DESINSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS ESTRUCTURA TIPO 523M. Unidad: UND
ITEM: 10.23
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 9.4994 65,688.68
SUBTOTAL MANO DE OBRA 65,688.68
EQUIPO
HERRAMIENTA MENOR % 5% 0 65,688.68 3,284.43
SUBTOTAL EQUIPO 3,284.43

COSTO DIRECTO 68,973.11 68,973.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
DESINSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS ESTRUCTURA TIPO 530. Unidad: UND
ITEM: 10.24
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 9.4994 65,688.68
SUBTOTAL MANO DE OBRA 65,688.68
EQUIPO
HERRAMIENTA MENOR % 5% 0 65,688.68 3,284.43
SUBTOTAL EQUIPO 3,284.43

COSTO DIRECTO 68,973.11 68,973.00

DESINSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS ESTRUCTURA TIPO 533. Unidad: UND
ITEM: 10.25
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 9.4994 65,688.68
SUBTOTAL MANO DE OBRA 65,688.68
EQUIPO
HERRAMIENTA MENOR % 5% 0 65,688.68 3,284.43
SUBTOTAL EQUIPO 3,284.43

COSTO DIRECTO 68,973.11 68,973.00

DESINSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS ESTRUCTURA TIPO P101. Unidad: UND
ITEM: 10.26
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 9.4994 65,688.68
SUBTOTAL MANO DE OBRA 65,688.68
EQUIPO
HERRAMIENTA MENOR % 5% 0 65,688.68 3,284.43
SUBTOTAL EQUIPO 3,284.43

COSTO DIRECTO 68,973.11 68,973.00

DESINSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS ESTRUCTURA TIPO R114. Unidad: UND
ITEM: 10.27
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 9.4994 65,688.68
SUBTOTAL MANO DE OBRA 65,688.68
EQUIPO
HERRAMIENTA MENOR % 5% 0 65,688.68 3,284.43
SUBTOTAL EQUIPO 3,284.43

COSTO DIRECTO 68,973.11 68,973.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
DESINSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS ESTRUCTURA TIPO R130. Unidad: UND
ITEM: 10.28
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 9.4994 65,688.68
SUBTOTAL MANO DE OBRA 65,688.68
EQUIPO
HERRAMIENTA MENOR % 5% 0 65,688.68 3,284.43
SUBTOTAL EQUIPO 3,284.43

COSTO DIRECTO 68,973.11 68,973.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES Y ELEMENTOS PARA Unidad: UND


BAJANTE A TIERRA - ALTA TENSIÓN. ITEM: 10.29
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ANGULAR EN V 18X48" CONJUNTO PRIMARIO UND 1 0 29,464.00 29,464.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 2 0 18,587.00 37,174.00

CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO 102,730.00


UND 1 0 102,730.00

TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR 1,262.00


UND 2 0 631.00

TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR 5,052.00


UND 4 0 1,263.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 2 0 1,436.00 2,872.00

AISLADOR LINE POST 25 KV CONJUNTO PRIMARIO 124,372.00


UND 2 0 62,186.00

ESPIGO PARA AISL LINE POST CONJUNTO PRIMARIO 28,720.00


UND 2 0 14,360.00
TORN.MAQUINA 5/8 X 9" CONJUNTO PRIMARIO UND 2 0 5,627.00 11,254.00
ARANDELA CUADRADA 11/16" CONJ PRIM O
580.00
SECUNDAR UND 2 0 290.00
ALAMBRE ALUMINIO # 4 AMARRE ML 2 0 295.00 590.00
CORAZA PARA ACSR CON GRILL CORAZA PARA
3,944.00
ACSR CON GRILLETES UND 2 0 1,972.00
CINTA DE ALUMINIO P/ACSR CINTA DE ALUMINIO
4,548.00
PARA ACSR ML 4 0 1,137.00
SUBTOTAL MATERIALES 352,562.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 7.3846 84,500.58
SUBTOTAL MANO DE OBRA 84,500.58
EQUIPO
HERRAMIENTA MENOR % 5% 0 84,500.58 4,225.02
SUBTOTAL EQUIPO 4,225.02

COSTO DIRECTO 441,287.60 441,288.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE UN CONDUCTOR ASCR NO 2/0 PARA M.T Unidad: ML


ITEM: 10.30
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CABLE ACSR NUMERO 2/0 CONDUC PRIM O SECUND ML 1 0 2,800.00 2,800.00
SUBTOTAL MATERIALES 2,800.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 1030.3639 605.61
SUBTOTAL MANO DE OBRA 605.61
EQUIPO
HERRAMIENTA MENOR % 5% 0 605.61 30.28
SUBTOTAL EQUIPO 30.28

COSTO DIRECTO 3,435.89 3,436.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

PREPARACIÓN CONCRETO 2500 PSI Unidad: M3


ITEM: 10.31
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AGUA LTS 160 0 16.00 2,560.00
ARENA GRUESA M3 0.52 0 60,000.00 31,200.00
GRAVA TRITURADA DE 3/4 M3 0.94 0 70,000.00 65,800.00
GASOLINA CORRIENTE GLN 0.1 0 8,700.00 870.00
CEMENTO GRIS KLS 260 0 600.00 156,000.00
ACEITE MOTOR 4 TIEMPOS GLN 0.006 0 70,000.00 420.00
SUBTOTAL MATERIALES 256,850.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 2 AYUDANTE 52,964.00 185% 97,983.00 1.2920 75,838.24
SUBTOTAL MANO DE OBRA 75,838.24
EQUIPO
MEZCLADORA DE 9 PIES CUBICOS DIA 0.0601 0 38,800.00 2,331.88
HERRAMIENTA MENOR % 0.04999 0 75,838.24 3,791.15
SUBTOTAL EQUIPO 6,123.03

COSTO DIRECTO 338,811.27 338,811.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN RECONECTADOR 34,5 KV. Unidad: UND


ITEM: 10.32
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
RECONECTADOR 34,5 KV. UND 1 0 65,236,080.00 65,236,080.00
SUBTOTAL MATERIALES 65,236,080.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 2 AYUDANTE-1 OFI 134,603.00 185% 249,015.00 0.0351 7,094,444.44
SUBTOTAL MANO DE OBRA 7,094,444.44
EQUIPO
GRUA-MONTACARGA 3 TONELADAS HRS 6.0674 0 30,000.00 182,022.00
HERRAMIENTA MENOR % 5% 0 7,094,444.44 354,722.22
SUBTOTAL EQUIPO 536,744.22

COSTO DIRECTO 72,867,268.66 72,867,269.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES PARA DERIVACIÓN Unidad: UND


TRIFÁSICA CON CORTACIRCUITOS - 730.
ITEM: 10.33

DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AISLADOR ESPIGO 3.2KV UND 3 0 12,862.00 38,586.00

AISLADOR SUSPENSION 6" CONJUNTO PRIMARIO UND 12 0 25,394.00 304,728.00

ANGULAR EN V 18X48" CONJUNTO PRIMARIO UND 4 0 29,464.00 117,856.00


BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 4 0 18,587.00 74,348.00

CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO UND 4 0 102,730.00 410,920.00

PIN RECTO5/8X7 1/2CRU/META CONJUNTO PRIMARIO UND 3 0 9,860.00 29,580.00

TORN.PASANTE 12" CONJUNTO PRIMARIO UND 4 0 5,570.00 22,280.00

TUERCA DE OJO 3/4" O 5/8" CONJUNTO PRIMARIO UND 6 0 8,843.00 53,058.00

TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR UND 8 0 631.00 5,048.00

TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR UND 8 0 1,263.00 10,104.00

TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 8 0 1,436.00 11,488.00


GRAPA TERMINAL DE ALUMINIO CONJUNTO
UND 6 0 19,305.00 115,830.00
PRIMARIO
SUBTOTAL MATERIALES 1,193,826.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 1.8505 337,207.78
SUBTOTAL MANO DE OBRA 337,207.78
EQUIPO
HERRAMIENTA MENOR % 5% 0 337,207.78 16,860.38
SUBTOTAL EQUIPO 16,860.38

COSTO DIRECTO 1,547,894.16 1,547,894.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE UN PARARRAYO 35 KV Unidad: UND


ITEM: 10.34
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TUBO GALV. 1/2" X 3 MTS COLMENA UND 1 0 25,624.00 25,624.00
CONECTOR COMPRES ALUMINIO UND 2 0 3,016.00 6,032.00
PARARRAYO 10KA POLIMERICO ELECTRICOS DEL VALLE UND 1 0 102,093.00 102,093.00
ALAMBRE CUBRE D.D.# 4 U ML 14 0 13,954.00 195,356.00
VARILLA CU-CU 9/16 X 2.40 CODECO UND 1 0 117,711.00 117,711.00
CONECTOR PARA VARILLA COBR CONECTOR PARA VARILLA
UNDDE COBRE 1 0 5,067.00 5,067.00
SUBTOTAL MATERIALES 451,883.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 6.5369 95,458.55
SUBTOTAL MANO DE OBRA 95,458.55
EQUIPO
HERRAMIENTA MENOR % 5% 0 95,458.55 4,772.92
SUBTOTAL EQUIPO 4,772.92

COSTO DIRECTO 552,114.47 552,114.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO, TRANSPORTE E INSTALACIÓN DE 1 HILO - CABLE DE GUARDA 1/4" Unidad: ML
ITEM: 10.35
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CABLE DE GUARDA 1/4" ML 1 0.05 1,334.00 1,334.66
SUBTOTAL MATERIALES 1,334.66

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 1,088.251 573.40
SUBTOTAL MANO DE OBRA 573.40
EQUIPO
HERRAMIENTA MENOR % 5% 0 573.40 28.66
SUBTOTAL EQUIPO 28.66

COSTO DIRECTO 1,936.72 1,937.00

REPLANTEO DE LÍNEA DE M.T HASTA 13,2 KV Unidad: ML


ITEM: 10.36
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LISTON 2 x2x3M. UND 0.01 0 3,800.00 38.00
PUNTILLA 2 CC LBS 0.003 0 2,000.00 6.00
PIOLA GRUESA 50 METROS ROL 0.003 0 2,500.00 7.50
SUBTOTAL MATERIALES 51.50

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. TOPOGRAFIA 1 CADENERO-1 TOP 194,469.00 185% 359,767.00 1700.0000 211.63
M.O. ALBANILERIA 2 AYUDANTE-1 OFI 97,094.00 185% 179,623.00 2026.2989 88.65
SUBTOTAL MANO DE OBRA 300.27
EQUIPO
HERRAMIENTA MENOR % 5% 0 300.27 15.01
SUBTOTAL EQUIPO 15.01

COSTO DIRECTO 366.78 367.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN POSTE DE CONCETRO 12 ML - TR 1500 KG Unidad: UND


ITEM: 10.37
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
POSTE CONCRET 12x1050KG CONJUNTO PRIMARIO UND 1 0 1,680,000.00 1,680,000.00
MEZCLA CONCRETO 1:2.5:4« 2500 PSI-17.5MPa M3 0.12 0 273,324.00 32,798.88
SUBTOTAL MATERIALES 1,712,798.88

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 4.0459 154,230.95
SUBTOTAL MANO DE OBRA 154,230.95
EQUIPO
GRUA-MONTACARGA 3 TONELADAS HRS 0.4841 0 30,000.00 14,523.00
SUBTOTAL EQUIPO 14,523.00

COSTO DIRECTO 1,881,552.83 1,881,553.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO, TRANSPORTE E INSTALACIÓN POSTE DE CONCETRO 12 ML - TR 1050 KG Unidad: UND
ITEM: 10.38
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
POSTE DE CONCETRO 12 ML - TR 1050 KG UND 1 0 1,444,200.00 1,444,200.00
MEZCLA CONCRETO 1:2.5:4« 2500 PSI-17.5MPa M3 0.12 0 273,324.00 32,798.88
SUBTOTAL MATERIALES 1,476,998.88

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 4.6196 135,077.28
SUBTOTAL MANO DE OBRA 135,077.28
EQUIPO
GRUA-MONTACARGA 3 TONELADAS HRS 0.3958 0 30,000.00 11,874.00
SUBTOTAL EQUIPO 11,874.00

COSTO DIRECTO 1,623,950.16 1,623,950.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS Unidad: UND


ESTRUCTURA TIPO P112. ITEM: 10.39
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES

AISLADOR ESPIGO 3.2KV ELECTRICOS DEL VALLE 38,586.00


UND 3 0 12,862.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 2 0 18,587.00 37,174.00

CRUCETA MET.4X4X 3/8X4 MT CONJUNTO PRIMARIO 179,610.00


UND 1 0 179,610.00
PIN PECHIPALOMO CRUC METAL CONJUNTO
56,037.00
PRIMARIO UND 3 0 18,679.00

TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR 1,262.00


UND 2 0 631.00

TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR 5,052.00


UND 4 0 1,263.00
ALAMBRE ALUMINIO # 4 AMARRE ML 3 0 295.00 885.00
CORAZA PARA ACSR CON GRILL CORAZA PARA
5,916.00
ACSR CON GRILLETES UND 3 0 1,972.00
CINTA DE ALUMINIO P/ACSR CINTA DE ALUMINIO
6,822.00
PARA ACSR ML 6 0 1,137.00
SUBTOTAL MATERIALES 331,344.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 6.8791 90,709.98
SUBTOTAL MANO DE OBRA 90,709.98
EQUIPO
HERRAMIENTA MENOR % 5% 0 90,709.98 4,535.49
SUBTOTAL EQUIPO 4,535.49

COSTO DIRECTO 426,589.47 426,589.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS Unidad: UND
ESTRUCTURA TIPO R130 ITEM: 10.40
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES

AISLADOR SUSPENSION 6" CONJUNTO PRIMARIO 101,576.00


UND 4 0 25,394.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 2 0 18,587.00 37,174.00

CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO 205,460.00


UND 2 0 102,730.00
TORN.PASANTE 12" CONJUNTO PRIMARIO UND 2 0 5,570.00 11,140.00

TUERCA DE OJO 3/4" O 5/8" CONJUNTO PRIMARIO 17,686.00


UND 2 0 8,843.00

TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR 1,262.00


UND 2 0 631.00

TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR 5,052.00


UND 4 0 1,263.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 2 0 1,436.00 2,872.00
ANGULAR BANDERA 8"X 2.44MT CONJUNTO
87,738.00
PRIMARIO UND 2 0 43,869.00
GRAPA TERMINAL DE ALUMINIO CONJUNTO
38,610.00
PRIMARIO UND 2 0 19,305.00
SUBTOTAL MATERIALES 508,570.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 4.4959 138,793.79
SUBTOTAL MANO DE OBRA 138,793.79
EQUIPO
HERRAMIENTA MENOR % 5% 0 138,793.79 6,939.68
SUBTOTAL EQUIPO 6,939.68

COSTO DIRECTO 654,303.47 654,303.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS Unidad: UND


ESTRUCTURA TIPO R114. ITEM: 10.41
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AISLADOR ESPIGO 3.2KV UND 2 0 12,862.00 25,724.00

AISLADOR SUSPENSION 6" CONJUNTO PRIMARIO 177,758.00


UND 7 0 25,394.00
ANGULAR EN V 18X48" CONJUNTO PRIMARIO UND 4 0 29,464.00 117,856.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 4 0 18,587.00 74,348.00

CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO 410,920.00


UND 4 0 102,730.00
ESPIGO ACANALADO EXTR POST CONJUNTO
48,986.00
PRIMARIO UND 2 0 24,493.00

PIN RECTO5/8X7 1/2CRU/META CONJUNTO PRIMARIO 19,720.00


UND 2 0 9,860.00
TORN.PASANTE 12" CONJUNTO PRIMARIO UND 4 0 5,570.00 22,280.00

TUERCA DE OJO 3/4" O 5/8" CONJUNTO PRIMARIO 35,372.00


UND 4 0 8,843.00

TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR 5,048.00


UND 8 0 631.00

TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR 10,104.00


UND 8 0 1,263.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 8 0 1,436.00 11,488.00
GRAPA TERMINAL DE ALUMINIO CONJUNTO
57,915.00
PRIMARIO UND 3 0 19,305.00
SUBTOTAL MATERIALES 1,017,519.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 5.6569 110,308.30
SUBTOTAL MANO DE OBRA 110,308.30
EQUIPO
HERRAMIENTA MENOR % 0.05 0 110,308.30 5,515.41
SUBTOTAL EQUIPO 5,515.41

COSTO DIRECTO 1,133,342.71 1,133,343.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS Unidad: UND
ESTRUCTURA TIPO RH230 ITEM: 10.42
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AISLADOR ESPIGO 3.2KV ELECTRICOS DEL VALLE UND 6 0 12,862.00 77,172.00
ANGULAR EN V 18X48" CONJUNTO PRIMARIO UND 2 0 29,464.00 58,928.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 2 0 18,587.00 37,174.00
CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO UND 2 0 102,730.00 205,460.00
PIN PECHIPALOMO CRUC METAL CONJUNTO PRIMARIO UND 4 0 18,679.00 74,716.00
PIN RECTO5/8X7 1/2CRU/META CONJUNTO PRIMARIO UND 2 0 9,860.00 19,720.00
TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR UND 2 0 631.00 1,262.00
TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR UND 4 0 1,263.00 5,052.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 4 0 1,436.00 5,744.00
SUBTOTAL MATERIALES 485,228.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 18.0941 34,486.55
SUBTOTAL MANO DE OBRA 34,486.55
EQUIPO
CARRO GRUA 5 TONELADAS HRS 0.3519 0 51,000.00 17,946.90
SUBTOTAL EQUIPO 17,946.90

COSTO DIRECTO 537,661.45 537,661.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES EN POSTE PARA 3 HILOS Unidad: UND


ESTRUCTURA TIPO PH210 ITEM: 10.43
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AISLADOR SUSPENSION 6" CONJUNTO PRIMARIO UND 6 0 25,394.00 152,364.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 2 0 18,587.00 37,174.00
CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO UND 2 0 102,730.00 205,460.00
TORN.PASANTE 12" CONJUNTO PRIMARIO UND 3 0 5,570.00 16,710.00
TUERCA DE OJO 3/4" O 5/8" CONJUNTO PRIMARIO UND 3 0 8,843.00 26,529.00
TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR UND 2 0 631.00 1,262.00
TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR UND 4 0 1,263.00 5,052.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 4 0 1,436.00 5,744.00
ANGULAR BANDERA 8"X 2.44MT CONJUNTO PRIMARIO UND 2 0 43,869.00 87,738.00
GRAPA TERMINAL DE ALUMINIO CONJUNTO PRIMARIO UND 3 0 19,305.00 57,915.00
SUBTOTAL MATERIALES 595,948.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 4.0883 152,631.41
SUBTOTAL MANO DE OBRA 152,631.41
EQUIPO
HERRAMIENTA MENOR % 5% 0 152,631.41 7,631.57
SUBTOTAL EQUIPO 7,631.57

COSTO DIRECTO 756,210.98 756,211.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES Y ELEMENTOS PARA Unidad: UND
TEMPLETE DIRECTO A TIERRA. M.T ITEM: 10.44
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
BANDA COPA DOBLE 7" CONJUNTO SECUNDARIO UND 3 0 18,895.00 56,685.00
TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR UND 3 0 631.00 1,893.00
TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR UND 6 0 1,263.00 7,578.00
PERCHA SECUNDAR 3 PUESTOS CONJUNTO SECUNDARIOUND 1 0 19,701.00 19,701.00
AISLADOR TIPO CARRETE 76MM CONJUNTO SECUNDARIO UND 3 0 3,496.00 10,488.00
SUBTOTAL MATERIALES 96,345.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 16.9902 36,727.23
SUBTOTAL MANO DE OBRA 36,727.23
EQUIPO
HERRAMIENTA MENOR % 5% 0 36,727.23 1,836.36
SUBTOTAL EQUIPO 1,836.36

COSTO DIRECTO 134,908.59 134,909.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES Y ELEMENTOS PARA Unidad: UND


BAJANTE A TIERRA - ALTA TENSIÓN. ITEM: 10.45
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AISLADOR ESPIGO 3.2KV UND 2 0 12,862.00 25,724.00
ANGULAR EN V 18X48" CONJUNTO PRIMARIO UND 1 0 29,464.00 29,464.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 2 0 18,587.00 37,174.00

CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO 102,730.00


UND 1 0 102,730.00
ESPIGO ACANALADO EXTR POST CONJUNTO
48,986.00
PRIMARIO UND 2 0 24,493.00
TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR UND 2 0 631.00 1,262.00
TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR UND 2 0 1,263.00 2,526.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 2 0 1,436.00 2,872.00
ALAMBRE ALUMINIO # 4 AMARRE ML 2 0 295.00 590.00
CORAZA PARA ACSR CON GRILL CORAZA PARA
3,944.00
ACSR CON GRILLETES UND 2 0 1,972.00
CINTA DE ALUMINIO P/ACSR CINTA DE ALUMINIO
4,548.00
PARA ACSR ML 4 0 1,137.00
SUBTOTAL MATERIALES 259,820.00
MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.
M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 6.3875 97,691.27
SUBTOTAL MANO DE OBRA 97,691.27
EQUIPO
HERRAMIENTA MENOR % 5% 0 97,691.27 4,884.56
SUBTOTAL EQUIPO 4,884.56

COSTO DIRECTO 362,395.83 362,396.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE UN CONDUCTOR ASCR NO 2/0 PARA M.T Unidad: ML


ITEM: 10.46
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CABLE ACSR NUMERO 2/0 CONDUC PRIM O SECUND ML 1 0 2,800.00 2,800.00
SUBTOTAL MATERIALES 2,800.00
MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.
M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 1030.3639 605.61
SUBTOTAL MANO DE OBRA 605.61
EQUIPO
HERRAMIENTA MENOR % 5% 0 605.61 30.28
SUBTOTAL EQUIPO 30.28

COSTO DIRECTO 3,435.89 3,436.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO, TRANSPORTE E INSTALACIÓN RECONECTADOR 13,2 KV Unidad: UND


ITEM: 10.47
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
RECONECTADOR 13,2 KV UND 1 0 50,000,000.00 50,000,000.00
SUBTOTAL MATERIALES 50,000,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 2 AYUDANTE-1 OFI 134,603.00 185% 249,015.00 0.1364 1,825,623.17
SUBTOTAL MANO DE OBRA 1,825,623.17
EQUIPO
GRUA-MONTACARGA 3 TONELADAS HRS 6.0122 0 30,000.00 180,366.00
HERRAMIENTA MENOR % 5% 0 1,825,623.17 91,281.15
SUBTOTAL EQUIPO 271,647.15

COSTO DIRECTO 52,097,270.32 52,097,270.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE HERRAJES PARA DERIVACIÓN Unidad: UND


TRIFÁSICA CON CORTACIRCUITOS - 730.
ITEM: 10.48

DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
AISLADOR ESPIGO 3.2KV ELECTRICOS DEL VALLE UND 2 0 12,862.00 25,724.00
AISLADOR SUSPENSION 6" CONJUNTO PRIMARIO UND 12 0 25,394.00 304,728.00
BANDA COPA DOBLE 6" CONJ PRIM Y SECUND UND 2 0 18,587.00 37,174.00
CRUCETA MET.3X3X 3/8X2.4MT CONJUNTO PRIMARIO UND 2 0 102,730.00 205,460.00
PIN RECTO5/8X7 1/2CRU/META CONJUNTO PRIMARIO UND 2 0 9,860.00 19,720.00
TORN.PASANTE 12" CONJUNTO PRIMARIO UND 3 0 5,570.00 16,710.00
TUERCA DE OJO 3/4" O 5/8" CONJUNTO PRIMARIO UND 6 0 8,843.00 53,058.00
TORN.CARRUA 5/8 X 1 1/2 CONJ PRIM O SECUNDAR UND 2 0 631.00 1,262.00
TORN.CARRUA 5/8 X 3 3/4 CONJ PRIM O SECUNDAR UND 4 0 1,263.00 5,052.00
TORN.MAQUINA 5/8 X 2" CONJUNTO PRIMARIO UND 4 0 1,436.00 5,744.00
ANGULAR BANDERA 8"X 2.44MT CONJUNTO PRIMARIO UND 2 0 43,869.00 87,738.00
GRAPA TERMINAL DE ALUMINIO CONJUNTO PRIMARIO UND 6 0 19,305.00 115,830.00
SUBTOTAL MATERIALES 878,200.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 3.6776 169,676.69
SUBTOTAL MANO DE OBRA 169,676.69
EQUIPO
HERRAMIENTA MENOR % 5% 0 169,676.69 8,483.83
SUBTOTAL EQUIPO 8,483.83

COSTO DIRECTO 1,056,360.52 1,056,361.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE UN PARARRAYO 15 KV Unidad: UND


ITEM: 10.49
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TUBO GALV. 1" X 3 MTS COLMENA UND 1 0 41,304.00 41,304.00
PARARRAYO 15 KV UND 1 0 110,534.00 110,534.00
SUBTOTAL MATERIALES 151,838.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 16.4474 37,939.31
SUBTOTAL MANO DE OBRA 37,939.31
EQUIPO
HERRAMIENTA MENOR % 5% 37,939.31 1,896.96
SUBTOTAL EQUIPO 1,896.96

COSTO DIRECTO 191,674.27 191,674.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE 1 HILO - CABLE DE GUARDA 3/8" Unidad: ML


ITEM: 10.50
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CABLE DE GUARDA 3/8" ML 1 0 1,927.00 1,927.00
SUBTOTAL MATERIALES 1,927.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 518.8105 1,202.76
SUBTOTAL MANO DE OBRA 1,202.76
EQUIPO
HERRAMIENTA MENOR % 5% 0 1,202.76 60.13
SUBTOTAL EQUIPO 60.13

COSTO DIRECTO 3,189.89 3,190.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN TRANSFORMADOR TIPO PEDESTAL 34,5 KV - Unidad: UND


1800 KVA ITEM: 10.51
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TRANSFORMADOR TIPO PEDESTAL 34,5 KV - 1800 KVA UND 1 0 94,000,000.00 94,000,000.00
SUBTOTAL MATERIALES 94,000,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 0.1342 4,649,798.81
SUBTOTAL MANO DE OBRA 4,649,798.81
EQUIPO
HERRAMIENTA MENOR % 0.0504 0 4,649,798.81 234,349.85
SUBTOTAL EQUIPO 234,349.85

COSTO DIRECTO 98,884,148.66 98,884,149.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN ESTRUCTURAS Y BARRAJES SUBESTACIÓN Unidad: UND


DE 34,5 KV. ITEM: 10.52
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ESTRUCTURAS Y BARRAJES SUBESTACIÓN DE 34,5 KV. UND 1 0 23,000,000.00 23,000,000.00
SUBTOTAL MATERIALES 23,000,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 0.4238 1,472,399.72
SUBTOTAL MANO DE OBRA 1,472,399.72
EQUIPO
HERRAMIENTA MENOR % 0.05 0 1,472,399.72 73,619.98
SUBTOTAL EQUIPO 73,619.98

COSTO DIRECTO 24,546,019.70 24,546,020.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO, TRANSPORTE E INSTALACIÓN SISTEMA DE TIERRA SUBESTACIÓN Unidad: UND


ITEM: 10.53
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ALAMBRE NEGRO # 18 KLS 1 5 3,500.00 3,675.00
HIERRO .1/2" 60.000 [6M] FIGURADO KG 1.5 0 4,000.00 6,000.00
ANGULO 11/2 x 3/16 TIRA DE 6 METROS UND 2 0 43,900.00 87,800.00
ROCA MUERTA (SIN TRANSPORTE) M3 0.5 0 18,500.00 9,250.00
TABLA 1x10x3M UND 5 0 8,500.00 42,500.00
SOLDADURA 6011 1/8" VARILLA KLS 2.5 0 7,200.00 18,000.00
CABLE COBRE DESNUDO #4 ML 45 5 6,180.00 292,005.00
HIDROSOLTA X 15 KGS BULTO UND 15 0 71,247.00 1,068,705.00
TAPA REGISTRO A TIERRA 20 UNIDAD UND 15 0 44,277.00 664,155.00
VARILLA CU-CU 9/16 X 2.40 CODECO UND 15 0 117,711.00 1,765,665.00
HIERR.DE 37000 PSI 259 MPA U KLS 3 0 2,330.00 6,990.00
MEZCLA CONCRETO 1:2:3 3100 PSI 210 MPa M3 5 0 323,204.00 1,616,020.00
SUBTOTAL MATERIALES 5,580,765.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 0.7000 69,987.14
M.O. ELECTRICAS 1 AYUDANTE-1 OFI 98,854.00 185% 182,879.00 0.9333 195,948.78
SUBTOTAL MANO DE OBRA 265,935.93
EQUIPO
HERRAMIENTA MENOR % 0.05 0 265,935.93 13,296.79
SUBTOTAL EQUIPO 13,296.79

COSTO DIRECTO 5,859,997.72 5,859,998.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DE EQUIPO DE MEDIDA EN 34,5 KV. Unidad: UND


ITEM: 10.54
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
EQUIPO DE MEDIDA EN 34,5 KV. UND 1 0 27,000,000.00 27,000,000.00
SUBTOTAL MATERIALES 27,000,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 2 AYUDANTE-1 OFI 134,603.00 185% 249,015.00 0.1803 1,381,114.81
SUBTOTAL MANO DE OBRA 1,381,114.81
EQUIPO
HERRAMIENTA MENOR % 5% 0 1,381,114.81 69,055.74
SUBTOTAL EQUIPO 69,055.74

COSTO DIRECTO 28,450,170.55 28,450,171.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN PROTECCIÓN DERIVACIÓN 13,2 KV. Unidad: UND


ITEM: 10.55
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
PROTECCIÓN DERIVACIÓN 13,2 KV. UND 1 0 1,687,690.00 1,687,690.00
SUBTOTAL MATERIALES 1,687,690.00

COSTO DIRECTO 1,687,690.00 1,687,690.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO, TRANSPORTE E INSTALACIÓN BAJANTE EN DUCTO GALVANIZADO DE 3" Unidad: UND
ITEM: 10.56
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CABLE COBRE THW # 1/0 ML 3 0 37,231.00 111,693.00
CABLE COBRE THW # 2/0 ML 6 0 46,550.00 279,300.00
CONECTOR AMFRAU KZ3-95 CONECTOR PERFORACION P/SECUNDA
UND 3 0 10,542.00 31,626.00
SUBTOTAL MATERIALES 422,619.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 73.1860 8,526.26
SUBTOTAL MANO DE OBRA 8,526.26
EQUIPO
HERRAMIENTA MENOR % 5% 0 8,526.26 426.31
SUBTOTAL EQUIPO 426.31

COSTO DIRECTO 431,571.57 431,572.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN CAJA DE INSPECCIÓN DE MEDIA TENSIÓN Unidad: UND


0,7X1,2X1,17 ML ITEM: 10.57
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CINTA BANDIT CONJ PRIM O SECUNDAR UND 2 0 2,641.00 5,282.00
HEBILLA - CINTA-BANDIT CONJ PRIM O SECUNDAR UND 2 0 574.00 1,148.00
CONECTOR AMFRAU P/ACOMETID CONECTOR PERFORACION UNDP/ACOMETI 3 0 21,820.00 65,460.00
CAJA CAJA DE INSPECCIÓN DE MEDIA TENSIÓN 0,7X1,2X1,17
UNDML 1 0 565,400.00 565,400.00
LLAVE PARA CAJA ACOMETIDAS LLAVE DE SEGURIDAD PARA
UNDCAJAS 1 0 46,630.00 46,630.00
SUBTOTAL MATERIALES 683,920.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 7.4224 84,070.25
SUBTOTAL MANO DE OBRA 84,070.25
EQUIPO
HERRAMIENTA MENOR % 5% 0 84,070.25 4,203.51
SUBTOTAL EQUIPO 4,203.51

COSTO DIRECTO 772,193.76 772,194.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN DUCTO CANALIZADO PVC TIPO PESADO Unidad: UND
2X3" ITEM: 10.58
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
INSTALACIÓN DUCTO CANALIZADO PVC TIPO
19,000.00
PESADO 2X3" ML 1 0 19,000.00
SUBTOTAL MATERIALES 19,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 1 AYUDANTE-1 OFI 98,854.00 185% 182,879.00 27.1688 6,731.21
SUBTOTAL MANO DE OBRA 6,731.21
EQUIPO
HERRAMIENTA MENOR % 5% 6,731.21 336.56
SUBTOTAL EQUIPO 336.56

COSTO DIRECTO 26,067.77 26,068.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO, TRANSPORTE E INSTALACIÓN DE RED DE COBRE XLPE 3 NO 2 AWG 15 Unidad: ML
KV. ITEM: 10.59
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CABLE CUADRUPLEX AWG 2/0 CONDUCTORSECUNDARIO ML 1 0 78,500.00 78,500.00
SUBTOTAL MATERIALES 78,500.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 117.4665 5,312.18
SUBTOTAL MANO DE OBRA 5,312.18
EQUIPO
HERRAMIENTA MENOR % 5% 0 5,312.18 265.60
SUBTOTAL EQUIPO 265.60

COSTO DIRECTO 84,077.78 84,078.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN TERMINALES PREMOLDEADOS EXTERIOR Unidad: JGO


15 KV. ITEM: 10.60
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TERMINALES PREMOLDEADOS EXTERIOR 15 KV. JGO 1 0 525,838.00 525,838.00
SUBTOTAL MATERIALES 525,838.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 2 AYUDANTE-1 OFI 134,603.00 185% 249,015.00 0.5475 454,821.92
SUBTOTAL MANO DE OBRA 454,821.92
EQUIPO
HERRAMIENTA MENOR % 5% 454,821.92 22,741.09
SUBTOTAL EQUIPO 22,741.09

COSTO DIRECTO 1,003,401.01 1,003,401.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN TRANSFORMADOR 75 KVA - 13200/480 V. Unidad: UND


ITEM: 10.61
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TRANSFORMADOR 75 KVA - 13200/480 V. UND 1 0 9,750,000.00 9,750,000.00
SUBTOTAL MATERIALES 9,750,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 0.4918 1,268,814.56
SUBTOTAL MANO DE OBRA 1,268,814.56
EQUIPO
HERRAMIENTA MENOR % 5% 0 1,268,814.56 63,440.72
SUBTOTAL EQUIPO 63,440.72

COSTO DIRECTO 11,082,255.28 11,082,255.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO, TRANSPORTE E INSTALACIÓN TABLERO GENERAL DE BAJA TENSIÓN 480 Unidad: UND
V. ITEM: 10.62
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TABLERO GENERAL DE BAJA TENSIÓN 480 V. UND 1 0 18,500,000.00 18,500,000.00
ANALIZADOR RED PTO RS-485 CELCO DMK UND 2 0 1,950,000.00 3,900,000.00
MINIBREAKER CELCO UND 2 0 257,500.00 515,000.00
ESPACIO MEDICION DIGITAL CELCO UND 2 0 151,500.00 303,000.00
SUBTOTAL MATERIALES 23,218,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 2 AYUDANTE-1 OFI 134,603.00 185% 249,015.00 0.2396 1,039,294.66
SUBTOTAL MANO DE OBRA 1,039,294.66
EQUIPO
HERRAMIENTA MENOR % 5% 1,039,294.66 51,964.73
SUBTOTAL EQUIPO 51,964.73

COSTO DIRECTO 24,309,259.39 24,309,259.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN TABLERO DE BAJA TENSIÓN 220/127 Unidad: UND


VOLTIOS. ITEM: 10.63
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TABLERO DE BAJA TENSIÓN 220/127 VOLTIOS. UND 1 0 392,000.00 392,000.00
SUBTOTAL MATERIALES 392,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 1 AYUDANTE-1 OFI 98,854.00 185% 182,879.00 2.3677 77,239.09
SUBTOTAL MANO DE OBRA 77,239.09
EQUIPO
HERRAMIENTA MENOR % 5% 0 77,239.09 3,861.95
SUBTOTAL EQUIPO 3,861.95

COSTO DIRECTO 473,101.04 473,101.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN TRANSFORMADOR SECO TIPO PEDESTAL Unidad: UND


15 KVA. ITEM: 10.64
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TRANSFORMADOR SECO TIPO PEDESTAL 15 KVA. UND 1 0 3,470,000.00 3,470,000.00
SUBTOTAL MATERIALES 3,470,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 4.2880 145,523.09
SUBTOTAL MANO DE OBRA 145,523.09
EQUIPO
HERRAMIENTA MENOR % 0.05 0 145,523.09 7,276.15
SUBTOTAL EQUIPO 7,276.15

COSTO DIRECTO 3,622,799.24 3,622,799.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO, TRANSPORTE E INSTALACIÓN TRANSFORMADOR PAD MOUNTED 400 KVA - Unidad: UND
13200/480 V. ITEM: 10.65
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TRANSFORMADOR PAD MOUNTED 400 KVA - 13200/480 V. UND 1 0 31,943,887.00 31,943,887.00
SUBTOTAL MATERIALES 31,943,887.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 0.3750 1,664,008.00
SUBTOTAL MANO DE OBRA 1,664,008.00
EQUIPO
HERRAMIENTA MENOR % 5% 1,664,008.00 83,200.40
SUBTOTAL EQUIPO 83,200.40

COSTO DIRECTO 33,691,095.40 33,691,095.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN CONDUCTOR CU 3 (3X350 MCM) Unidad: ML


ITEM: 10.66
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CONDUCTOR CU 3 (3X350 MCM) ML 1 0 536,000.00 536,000.00
SUBTOTAL MATERIALES 536,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 39.1933 15,921.17
SUBTOTAL MANO DE OBRA 15,921.17
EQUIPO
HERRAMIENTA MENOR % 5% 0 15,921.17 796.05
SUBTOTAL EQUIPO 796.05

COSTO DIRECTO 552,717.22 552,717.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN CONDUCTOR CU 3 NO 1/0 + 1 NO 6 Unidad: ML


ITEM: 10.67
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CONDUCTOR CU 3 NO 1/0 + 1 NO 6 ML 1 0 68,500.00 68,500.00
SUBTOTAL MATERIALES 68,500.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 148.2395 4,209.42
SUBTOTAL MANO DE OBRA 4,209.42
EQUIPO
HERRAMIENTA MENOR % 5% 0 4,209.42 210.47
SUBTOTAL EQUIPO 210.47

COSTO DIRECTO 72,919.89 72,920.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO, TRANSPORTE E INSTALACIÓN CONDUCTOR CU 3 NO 2 + 1NO 1/0 Unidad: ML
ITEM: 10.68
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
INSTALACIÓN CONDUCTOR CU 3 NO 2 + 1NO 1/0 ML 1 0 58,500.00 58,500.00
SUBTOTAL MATERIALES 58,500.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 155.2653 4,018.95
SUBTOTAL MANO DE OBRA 4,018.95
EQUIPO
HERRAMIENTA MENOR % 5% 0 4,018.95 200.94
SUBTOTAL EQUIPO 200.94

COSTO DIRECTO 62,719.89 62,720.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN BANCO DE CONDENSADORES 120 KVAR / Unidad: UND


460 V ITEM: 10.69
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
BANCO DE CONDENSADORES 120 KVAR / 460 V UND 1 0 13,150,000.00 13,150,000.00
SUBTOTAL MATERIALES 13,150,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 2 AYUDANTE-1 OFI 134,603.00 185% 249,015.00 0.3735 666,706.83
SUBTOTAL MANO DE OBRA 666,706.83
EQUIPO
HERRAMIENTA MENOR % 5% 0 666,706.83 33,335.34
SUBTOTAL EQUIPO 33,335.34

COSTO DIRECTO 13,850,042.17 13,850,042.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN BANCO DE CONDENSADORES 30 KVAR / 460 Unidad: UND


V ITEM: 10.70
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
BANCO DE CONDENSADORES 30 KVAR / 460 V UND 1 0 3,789,000.00 3,789,000.00
SUBTOTAL MATERIALES 3,789,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 2 AYUDANTE-1 OFI 134,603.00 185% 249,015.00 1.3073 190,480.38
SUBTOTAL MANO DE OBRA 190,480.38
EQUIPO
HERRAMIENTA MENOR % 5% 0 190,480.38 9,524.01
SUBTOTAL EQUIPO 9,524.01

COSTO DIRECTO 3,989,004.39 3,989,004.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO, TRANSPORTE E INSTALACIÓN SALIDA ESPECIAL 220 V Unidad: UND
ITEM: 10.71
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ALAMBRE COBRE THW #12 CEAT ML 10 5 2,118.00 22,239.00
GRAPA GALV-GRUESA 3/4" NACIONAL UND 3 0 662.00 1,986.00
SALIDA ESPECIAL 220 V UND 1 0 6,148.00 6,148.00
ADAPTADOR EMT 3/4" COLMENA UND 2 0 1,119.00 2,238.00
UNION 3/4" EMT COLMENA UND 2 0 629.00 1,258.00
CURVA EMT 3/4" COLMENA UND 1 0 1,426.00 1,426.00
CAJA RAWELT 3/4" CAJA PARA EMT UND 1 0 7,656.00 7,656.00
TUBO EMT 3/" X 3 MT COLMENA UND 2 0 13,530.00 27,060.00
SUBTOTAL MATERIALES 70,011.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 1 AYUDANTE-1 OFI 98,854.00 185% 182,879.00 9.8225 18,618.38
SUBTOTAL MANO DE OBRA 18,618.38
EQUIPO
HERRAMIENTA MENOR % 5% 0 18,618.38 930.91
SUBTOTAL EQUIPO 930.91

COSTO DIRECTO 89,560.29 89,560.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN SALIDA ILUMINACIÓN DE EMERGENCIA Unidad: UND


ITEM: 10.72
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ALAMBRE COBRE THW #12 CEAT ML 9 0 2,118.00 19,062.00
ALAMBRE COBRE THW #14 CEAT ML 4.5 0 1,453.00 6,538.50
GRAPA GALV-GRUESA 3/4" NACIONAL UND 3 0 662.00 1,986.00
CINTA AISLANTE # 33 ROLLO x 20 MTS UND 0.01 0 9,695.00 96.95
TOMA DOBLE P-T AMBIA LUMINEX UND 1 0 8,468.00 8,468.00
ADAPTADOR EMT 3/4" COLMENA UND 2 0 1,119.00 2,238.00
UNION 3/4" EMT COLMENA UND 2 0 629.00 1,258.00
CURVA EMT 3/4" COLMENA UND 1 0 1,426.00 1,426.00
CAJA RAWELT 3/4" CAJA PARA EMT UND 1 0 7,656.00 7,656.00
TUBO EMT 3/" X 3 MT COLMENA UND 0.6 0 13,530.00 8,118.00
SUBTOTAL MATERIALES 56,847.45

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 1 AYUDANTE-1 OFI 98,854.00 185% 182,879.00 9.1700 19,943.18
SUBTOTAL MANO DE OBRA 19,943.18
EQUIPO
HERRAMIENTA MENOR % 0.3214 0 19,943.18 6,409.73
SUBTOTAL EQUIPO 6,409.73

COSTO DIRECTO 83,200.36 83,200.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO, TRANSPORTE E INSTALACIÓN SALIDA ILUMINACIÓN DE EMERGENCIA Unidad: UND
ITEM: 10.73
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SOLDADURA PVC 1/ 2 GLN UND 0.03 5 56,900.00 1,792.35
ALAMBRE COBRE THW #14 CEAT ML 12 5 1,453.00 18,307.80
ALAMBRE COBRE THW #12 CEAT ML 24 10 2,118.00 55,915.20
TERMINAL PVC 1/2" UND 8 0 150.00 1,200.00
LIMPIADOR PVC 760-G 1/4 GL UND 0.03 5 28,925.00 911.13
TUBO PVC 1/2" X 3 MTS UND 4 5 2,473.00 10,386.60
CAJA OCTOGONAL PVC UND 4 0 1,208.00 4,832.00
ALAMBRE GALVANIZADO # 18 U KG 2 0 5,647.00 11,294.00
CINTA AISLANTE # 33 ROLLO x 20 MTS UND 0.1 0 9,695.00 969.50
SUBTOTAL MATERIALES 105,608.58

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 1 AYUDANTE-1 OFI 98,854.00 185% 182,879.00 5.6492 32,372.55
SUBTOTAL MANO DE OBRA 32,372.55
EQUIPO
HERRAMIENTA MENOR % 5% 0 32,372.55 1,618.62
SUBTOTAL EQUIPO 1,618.62

COSTO DIRECTO 139,599.75 139,600.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN SALIDA DE ILUMINACIÓN NORMAL. Unidad: UND


ITEM: 10.74
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ALAMBRE COBRE THW #12 CEAT ML 9 0 2,118.00 19,062.00
ALAMBRE COBRE THW #14 CEAT ML 4.5 0 1,453.00 6,538.50
ALAMBRE GALVANIZADO # 18 U KG 0.1 0 5,647.00 564.70
GRAPA GALV-GRUESA 3/4" NACIONAL UND 3 0 662.00 1,986.00
CINTA AISLANTE # 33 ROLLO x 20 MTS UND 0.01 0 9,695.00 96.95
ADAPTADOR EMT 3/4" COLMENA UND 2 0 1,119.00 2,238.00
UNION 3/4" EMT COLMENA UND 2 0 629.00 1,258.00
CURVA EMT 3/4" COLMENA UND 1 0 1,426.00 1,426.00
CAJA RAWELT 3/4" CAJA PARA EMT UND 1 0 7,656.00 7,656.00
TUBO EMT 3/" X 3 MT COLMENA UND 1 0 13,530.00 13,530.00
SUBTOTAL MATERIALES 54,356.15

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 1 AYUDANTE-1 OFI 98,854.00 185% 182,879.00 10.2993 17,756.45
SUBTOTAL MANO DE OBRA 17,756.45
EQUIPO
HERRAMIENTA MENOR % 5% 0 17,756.45 887.82
SUBTOTAL EQUIPO 887.82

COSTO DIRECTO 73,000.42 73,000.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO, TRANSPORTE E INSTALACIÓN SALIDA LAMPARA ILUMINACIÓN EXTERIOR Unidad: UND
400 W. ITEM: 10.75
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ALAMBRE COBRE THW #12 CEAT ML 6 0 2,118.00 12,708.00
BANDA SENCILLA 6" CONJ PRIM Y SECUND UND 2 0 13,551.00 27,102.00
LUMINARIA ENTERIZA 400 W ALUMBRADO PUBLICO UND 1 0 508,080.00 508,080.00
CONECTOR TIPO CUNA CONJUNTO SECUNDARIO UND 2 0 14,500.00 29,000.00
BRAZO GALVANIZ 1.1/2"X3 MT UND 1 0 60,320.00 60,320.00
BOMBILLO TUBULAR NA 400 WA UND 1 0 27,260.00 27,260.00
GRILLETES 3/4" ALUMBRADO PUBLICO UND 2 0 5,627.00 11,254.00
SUBTOTAL MATERIALES 675,724.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 19.347 32,253.22
SUBTOTAL MANO DE OBRA 32,253.22
EQUIPO
HERRAMIENTA MENOR % 5% 0 32,253.22 1,612.66
SUBTOTAL EQUIPO 1,612.66

COSTO DIRECTO 709,589.88 709,590.00

SUMINISTRO, TRANSPORTE E INSTALACIÓN SISTEMA DE TIERRA SUBESTACIÓN Unidad: UND


ITEM: 10.76
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
ALAMBRE NEGRO # 18 KLS 1 5 3,500.00 3,675.00
HIERRO .1/2" 60.000 [6M] FIGURADO KG 1.5 0 4,000.00 6,000.00
ANGULO 11/2 x 3/16 TIRA DE 6 METROS UND 2 0 43,900.00 87,800.00
ROCA MUERTA (SIN TRANSPORTE) M3 0.5 0 18,500.00 9,250.00
TABLA 1x10x3M UND 5 0 8,500.00 42,500.00
SOLDADURA 6011 1/8" VARILLA KLS 2.5 0 7,200.00 18,000.00
CABLE COBRE DESNUDO #4 ML 30 5 6,180.00 194,670.00
HIDROSOLTA X 15 KGS BULTO UND 5 0 71,247.00 356,235.00
TAPA REGISTRO A TIERRA 20 UNIDAD UND 8 0 44,277.00 354,216.00
VARILLA CU-CU 9/16 X 2.40 CODECO UND 6 0 117,711.00 706,266.00
HIERR.DE 37000 PSI 259 MPA U KLS 3 0 2,330.00 6,990.00
MEZCLA CONCRETO 1:2:3 3100 PSI 210 MPa M3 3 0 323,204.00 969,612.00
SUBTOTAL MATERIALES 2,755,214.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ALBANILERIA 1 AYUDANTE 26,482.00 185% 48,991.00 0.7000 69,987.14
M.O. ELECTRICAS 1 AYUDANTE-1 OFI 98,854.00 185% 182,879.00 0.5165 354,073.57
SUBTOTAL MANO DE OBRA 424,060.71
EQUIPO
HERRAMIENTA MENOR % 0.0501 0 424,060.71 21,245.44
SUBTOTAL EQUIPO 21,245.44

COSTO DIRECTO 3,200,520.15 3,200,520.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO, TRANSPORTE E INSTALACIÓN TABLERO AUXILIAR PARA MOTORES Unidad: UND
460/220 VOLTIOS. ITEM: 10.77
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TABLERO AUXILIAR PARA MOTORES 460/220 VOLTIOS. UND 1 0 2,014,984.00 2,014,984.00
SUBTOTAL MATERIALES 2,014,984.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 1 AYUDANTE-1 OFI 98,854.00 185% 182,879.00 0.6106 299,507.04
M.O. HIDROSANIT. 1 AYUDANTE-1 OFI 75,023.00 185% 138,792.00 3.2005 43,365.72
SUBTOTAL MANO DE OBRA 342,872.77
EQUIPO
HERRAMIENTA MENOR % 0.05 0 342,872.77 17,143.63
SUBTOTAL EQUIPO 17,143.63

COSTO DIRECTO 2,375,000.40 2,375,000.00

CERTIFICACION RETIE Unidad: UND


ITEM: 10.78
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CERTIFICACION CERTIFICACION RETIE UND 1 0 14,470,000.00 14,470,000.00
SUBTOTAL MATERIALES 14,470,000.00

COSTO DIRECTO 14,470,000.00 14,470,000.00

INSTRUMENTACION: SUMINSITRO E INSTALACION DE UN CAUDALIMETROS 0-52 LTS/S


PN16, SUMINISTRO E INSTALACION DE UN TRASMISOR DE PRESION MAX 147 PSI, 2
VALVULAS MOTORIZADAS 8" 150 LBS Y 2 CHEQUES ANTIRETORNOS 300 LBS (INCLUYE UNIDAD: UND
MANO DE OBRA DE INSTALACIÓN ELECTRICA, MECANICA Y CONTROL PARA TODAS LAS
ACTIVIDADES DE LA ESTACION)

ITEM: 11,1
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CAUDALIMETROS 0-52 LTS/S PN16, 2 VALVULAS MOTORIZADAS
UND 8" 150 LBS 1
Y 2 CHEQUES0ANTIRETORNOS 300 LBS
150,000,000.00 150,000,000.00

SUBTOTAL MATERIALES 150,000,000.00


MANO DE OBRA
M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 0.0884 7,058,857.47

SUBTOTAL- MANO DE OBRA 7,058,857.47


EQUIPO
HERRAMIENTA MENOR % 0.0499 7,058,857.47 352,236.98

SUBTOTAL- EQUIPO 352,236.98

COSTO DIRECTO 157,411,094.45 157,411,094.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
AUTOMATIZACION: DISEÑO, SUMINISTRO E INSTALACION DE UN TABLERO PARA UNIDAD: UND
CONTROL LOCAL, CON PROTECCIONES, FUENTE DE ALIMENTACION PARA
INSTRUMENTACION, MICROCONTROLADOR Y TOUCH DE 6" A COLOR ITEM: 11,2
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
2 VARIADORES DE 75 HP EN CELDAS CON EXTRACCION DEUND
CALOR, TABLERO
1 DE FUERZA
0 Y MANIOBRA PARA VARIADORES
9,300,000.00 DE 75 HP CON SUS RESPECTIVAS PRO
9,300,000.00

SUBTOTAL MATERIALES 9,300,000.00


MANO DE OBRA
M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 0.2388 2,613,077.89

SUBTOTAL- MANO DE OBRA 2,613,077.89


EQUIPO
HERRAMIENTA MENOR % 0.05 2,613,077.89 130,653.89

SUBTOTAL- EQUIPO 130,653.89

COSTO DIRECTO 12,043,731.78 12,043,732.00

CCM: SUMINISTRO E INSTALACION DE 2 VARIADORES DE 75 HP EN CELDAS CON UNIDAD: UND


EXTRACCION DE CALOR, TABLERO DE FUERZA Y MANIOBRA PARA VARIADORES DE 75
HP CON SUS RESPECTIVAS PROTECCIONES , E INTERCONEXION EN CAMPO ITEM: 11,3
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TABLERO PARA CONTROL LOCAL, CON PROTECCIONES, FUENTE
UND DE ALIMENTACION
1 PARA
0 INSTRUMENTACION,
60,000,000.00 MICROCONTROLADOR
60,000,000.00 Y TOUCH DE 6" A COLOR

SUBTOTAL MATERIALES 60,000,000.00


MANO DE OBRA
M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 0.1903 3,279,048.87

SUBTOTAL- MANO DE OBRA 3,279,048.87


EQUIPO
HERRAMIENTA MENOR % 0.0498 3,279,048.87 163,296.63

SUBTOTAL- EQUIPO 163,296.63

COSTO DIRECTO 63,442,345.50 63,442,346.00

INSTRUMENTACIÓN: SUMINISTRO E INSTALACIÓN DE UN CAUDALIMETROS 0-52 LTS/S UNIDAD: UND


PN40, SUMINISTRO E INSTALACIÓN DE UN TRASMISOR DE PRESIÓN MAX 914 PSI,
SUMINISTRO E INSTALACIÓN DE SENSOR DE NIVEL ULTRASÓNICO PARA MAX 5 M, 2
VALVULAS MOTORIZADAS 6" 300 LBS Y 2 CHEQUES ANTIRETORNOS 300 LBS (INCLUYE ITEM: 11,4
MANO DE OBRA DE INSTALACIÓN ELECTRICA, MECANICA Y CONTROL CONTROL PARA
TODAS LAS ACTIVIDADES DE LA ESTACIÓN)
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
UN CAUDALIMETROS 0-52 LTS/S PN40, SUMINISTRO E INSTALACIÓN
UND DE UN 1TRASMISOR DE
0 PRESIÓN MAX 914 PSI, SUMINISTRO
162,255,000.00 E INSTALACIÓN DE SENSOR DE NIV
162,255,000.00

SUBTOTAL MATERIALES 162,255,000.00


MANO DE OBRA
M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 0.0924 6,753,279.22

SUBTOTAL- MANO DE OBRA 6,753,279.22


EQUIPO
HERRAMIENTA MENOR % 0.0498 6,753,279.22 336,313.30

SUBTOTAL- EQUIPO 336,313.30

COSTO DIRECTO 169,344,592.52 169,344,593.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
CCM: SUMINISTRO E INSTALACION DE CUARTO DE CONTROL DE MOTORES, CON UNIDAD: UND
TABLERO DE FUERZA Y MANIOBRA PARA VARIADORES DE 350 HP CON SUS
RESPECTIVAS CONEXIONES, E INTERCONEXION EN CAMPO ITEM: 11,5
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CUARTO DE CONTROL DE MOTORES, CON TABLERO DE FUERZA
UND Y MANIOBRA
1 PARA VARIADORES
0 DE 350 HP
101,600,000.00 101,600,000.00

SUBTOTAL MATERIALES 101,600,000.00


MANO DE OBRA
M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 0.1073 5,815,498.60

SUBTOTAL- MANO DE OBRA 5,815,498.60


EQUIPO
HERRAMIENTA MENOR % 0.0494 5,815,498.60 287,285.63

SUBTOTAL- EQUIPO 287,285.63

COSTO DIRECTO 107,702,784.23 107,702,784.00

AUTOMATIZACION: DISEÑO, SUMINISTRO E INSTALACION DE UN TABLERO PARA UNIDAD: UND


CONTROL PRINCIPAL , CON PROTECCIONES, FUENTE DE ALIMENTACION PARA
INSTRUMENTACION, SISTEMA CONTROLLOGIX Y SCADA DE VISUALIZACION Y CONTROL ITEM: 11,6
LOCAL EN ESTACIÓN Y REMOTO EN CENTRAL BUCARAMANGA
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TABLERO PARA CONTROL PRINCIPAL , CON PROTECCIONES,
UND FUENTE DE ALIMENTACION
1 0 PARA87,650,000.00
INSTRUMENTACION, SISTEMA CONTROLLOGIX Y SCADA DE VISUAL
87,650,000.00

SUBTOTAL MATERIALES 87,650,000.00


MANO DE OBRA
M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 0.1031 6,052,405.43

SUBTOTAL- MANO DE OBRA 6,052,405.43


EQUIPO
HERRAMIENTA MENOR % 0.0485 6,052,405.43 293,541.66

SUBTOTAL- EQUIPO 293,541.66

COSTO DIRECTO 93,995,947.09 93,995,947.00

SUMINISTRO E INSTALACION DE SISTEMA DE COMUNICACIÓN POR FIBRA OPTICA CON UNIDAD: UND
FO AEREA 6 HILOS PARA VANOS MENORES DE 200M, HERRAJES DE SOPORTE Y
SUSPENSION. (INCLUYE MANO DE OBRA INSTALACION ITEM: 11,7

DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
SISTEMA DE COMUNICACIÓN POR FIBRA OPTICA CON FO AEREA
UND 6 HILOS PARA
1 VANOS MENORES
0 DE 200M, HERRAJES109,568,935.00
109,568,935.00 DE SOPORTE Y SUSPENSION

SUBTOTAL MATERIALES 109,568,935.00


MANO DE OBRA
M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 0.1791 3,484,103.85

SUBTOTAL- MANO DE OBRA 3,484,103.85


EQUIPO
HERRAMIENTA MENOR % 0.0494 3,484,103.85 172,114.73

SUBTOTAL- EQUIPO 172,114.73

COSTO DIRECTO 113,225,153.58 113,225,154.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
INSTRUMENTACIÓN: SUMINISTRO E INSTALACIÓN DE CAUDALIMETRO 0-52 LTS/S PN40, UNIDAD: UND
SUMINSTRO E INSTALACIÓN DE SENSOR DE NIVEL MAX 12 M, (INCLUYE MANO DE OBRA
DE INSTALACIÓN ELÉCTRICA, MECÁNICA Y CONTROL PARA TODAS LAS ACTIVIDADES
DE LA ESTACIÓN) ITEM: 11,8

DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CAUDALIMETRO 0-52 LTS/S PN40 Y SENSOR DE NIVEL MAXUND
12 M 1 0 100,956,385.00 100,956,385.00

SUBTOTAL MATERIALES 100,956,385.00


MANO DE OBRA
M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 0.2225 2,804,507.87

SUBTOTAL- MANO DE OBRA 2,804,507.87


EQUIPO
HERRAMIENTA MENOR % 0.0494 2,804,507.87 138,542.68

SUBTOTAL- EQUIPO 138,542.68

COSTO DIRECTO 103,899,435.55 103,899,436.00

INSTRUMENTACION: SUMINSITRO E INSTACION DE CAUDALIMETRO 0-52 LTS/S PN40, Unidad: UND


SUMINSTRO E INSTALACION DE SENSOR DE NIVEL MAX 12 M, 2 VALVULAS
MOTORIZADAS 10" 150 LBS Y 2 CHEQUES ANTIRETORNOS 300 LBS (INCLUYE MANO DE
OBRA DE INSTALACIÓN ELECTRICA, MECANICA Y CONTROL CONTROL PARA TODAS ITEM: 11.9
LAS ACTIVIDADES DE LA ESTACION)
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CAUDALIMETRO 0-52 LTS/S PN40, SUMINSTRO E INSTALACION
UNDDE SENSOR 1DE NIVEL MAX
0 12 M, 2 VALVULAS MOTORIZADAS
151,500,000.00 10" 150 LBS Y 2 CHEQUES ANTIRETOR
151,500,000.00
SUBTOTAL MATERIALES 151,500,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


M.O. ELECTRICAS 3 AYUD-1 OFI-1 PROF 337,299.00 185% 624,003.00 1.000 624,003.00
SUBTOTAL MANO DE OBRA 624,003.00

COSTO DIRECTO 152,124,003.00 152,124,003.00

TUBERIA HD 10" PRESION TRABAJO 500 M.C.A. JUNTA ACERROJADA UNIDAD: ML


ITEM: 12,1
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TUBERIA HD 10" PRESION TRABAJO 500 M.C.A. JUNTA ACERROJADA
ML 1 0 294,408.00 294,408.00
SUBTOTAL MATERIALES 294,408.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 294,408.00 294,408.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
TUBERIA HD 10" PRESION TRABAJO 340 M.C.A. JUNTA ACERROJADA UNIDAD: ML
ITEM: 12,2
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TUBERIA HD 10" PRESION TRABAJO 340 M.C.A. JUNTA ACERROJADA
ML 1 0 207,060.00 207,060.00
SUBTOTAL MATERIALES 207,060.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 207,060.00 207,060.00

TUBERIA HD 10" PRESION TRABAJO 170 M.C.A. UNIDAD: ML


ITEM: 12,3
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TUBERIA HD 10" PRESION TRABAJO 170 M.C.A. ML 1 0 173,420.00 173,420.00
SUBTOTAL MATERIALES 173,420.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 173,420.00 173,420.00

TUBERIA HD 6" PRESION DE TRABAJO 340 M.C.A UNIDAD: ML


ITEM: 12,4
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TUBERIA HD 6" PRESION DE TRABAJO 340 M.C.A ML 1 0 101,094.00 101,094.00
SUBTOTAL MATERIALES 101,094.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 101,094.00 101,094.00

TUBERIA DE PVC RDE 21 8" UNIDAD: ML


ITEM: 12,5
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TUBERIA DE PVC RDE 21 8" ML 1 0 98,547.00 98,547.00
SUBTOTAL MATERIALES 98,547.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 98,547.00 98,547.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

TUBERIA DE PVC RDE 21 6" UNIDAD: ML


ITEM: 12,6
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TUBERIA DE PVC RDE 21 6" ML 1 0 58,178.00 58,178.00
SUBTOTAL MATERIALES 58,178.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 58,178.00 58,178.00

TUBERIA DE PVC RDE 13.5 6" UNIDAD: ML


ITEM: 12,7
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TUBERIA DE PVC RDE 13.5 6" ML 1 0 101,094.00 101,094.00
SUBTOTAL MATERIALES 101,094.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 101,094.00 101,094.00

TUBERIA DE PVC 10" PARA ALCANTARILLADO UNIDAD: ML


ITEM: 12,8
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TUBERIA DE PVC 10" PARA ALCANTARILLADO ML 1 0 55,388.00 55,388.00
SUBTOTAL MATERIALES 55,388.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 55,388.00 55,388.00

SUMINISTRO DE TEE HD 8" BRIDADA 200MCA UNIDAD: UND


ITEM: 12,9
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TEE HD 8" BRIDADA 200MCA UND 1 0 1,074,160.00 1,074,160.00
SUBTOTAL MATERIALES 1,074,160.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 1,074,160.00 1,074,160.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO DE TEE HD 8" X 2" BRIDADA 200MCA UNIDAD: UND
ITEM: 12,1
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TEE HD 8" X 2" BRIDADA 200MCA UND 1 0 792,280.00 792,280.00
SUBTOTAL MATERIALES 792,280.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 792,280.00 792,280.00

SUMINISTRO DE CODO HD 8" X 90° BRIDADA 200MCA UNIDAD: UND


ITEM: 12,11
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO HD 8" X 90° BRIDADA 200MCA UND 1 0 1,191,320.00 1,191,320.00
SUBTOTAL MATERIALES 1,191,320.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 1,191,320.00 1,191,320.00

SUMINISTRO DE CODO HD 8" X 90° JH 200MCA UNIDAD: UND


ITEM: 12,12
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO HD 8" X 90° JH 200MCA UND 1 0 1,056,760.00 1,056,760.00
SUBTOTAL MATERIALES 1,056,760.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 1,056,760.00 1,056,760.00

SUMINISTRO DE CODO HD 8" X 45° JH 200MCA UNIDAD: UND


ITEM: 12,13
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO HD 8" X 45° JH 200MCA UND 1 0 597,400.00 597,400.00
SUBTOTAL MATERIALES 597,400.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 597,400.00 597,400.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO DE CODO HD 8" X 22.5° JH 200MCA UNIDAD: UND


ITEM: 12,14
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO HD 8" X 22.5° JH 200MCA UND 1 0 397,800.00 397,800.00
SUBTOTAL MATERIALES 397,800.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 397,800.00 397,800.00

SUMINISTRO DE CODO HD 8" X 11.25° JH 200MCA UNIDAD: UND


ITEM: 12,15
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO HD 8" X 11.25° JH 200MCA UND 1 0 401,360.00 401,360.00
SUBTOTAL MATERIALES 401,360.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 401,360.00 401,360.00

SUMINISTRO DE TEE HD 6" X 2" BRIDADA - LISA. 400MCA UNIDAD: UND


ITEM: 12,16
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TEE HD 6" X 2" BRIDADA - LISA. 400MCA UND 1 0 453,560.00 453,560.00
SUBTOTAL MATERIALES 453,560.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 453,560.00 453,560.00

SUMINISTRO DE CODO HD 6" X 90° LISA 400MCA UNIDAD: UND


ITEM: 12,17
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO HD 6" X 90° LISA 400MCA UND 1 0 294,640.00 294,640.00
SUBTOTAL MATERIALES 294,640.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 294,640.00 294,640.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO DE CODO HD 6" X 45° LISA 400MCA UNIDAD: UND
ITEM: 12,18
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO HD 6" X 45° LISA 400MCA UND 1 0 225,040.00 225,040.00
SUBTOTAL MATERIALES 225,040.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 225,040.00 225,040.00

SUMINISTRO DE CODO HD 6" X 22.5° LISA 400MCA UNIDAD: UND


ITEM: 12,19
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO HD 6" X 22.5° LISA 400MCA UND 1 0 199,520.00 199,520.00
SUBTOTAL MATERIALES 199,520.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 199,520.00 199,520.00

SUMINISTRO DE CODO HD 6" X 11.25° LISA 400MCA UNIDAD: UND


ITEM: 12,2
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO HD 6" X 11.25° LISA 400MCA UND 1 0 199,520.00 199,520.00
SUBTOTAL MATERIALES 199,520.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 199,520.00 199,520.00

SUMINISTRO DE TEE HD 10" X 2" BRIDADA - LISA 40OMCA UNIDAD: UND


ITEM: 12,21
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TEE HD 10" X 2" BRIDADA - LISA 40OMCA UND 1 0 1,477,840.00 1,477,840.00
SUBTOTAL MATERIALES 1,477,840.00

COSTO DIRECTO 1,477,840.00 1,477,840.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO DE TEE HD 10" X 2" BRIDADA - LISA 640MCA UNIDAD: UND


ITEM: 12,22
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TEE HD 10" X 2" BRIDADA - LISA 640MCA UND 1 0 1,477,840.00 1,477,840.00
SUBTOTAL MATERIALES 1,477,840.00

COSTO DIRECTO 1,477,840.00 1,477,840.00

CODO 10" X 11.25° HD LISA 640MCA UNIDAD: UN


ITEM: 12,23
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO 10" X 11.25° HD LISA 640MCA UND 1 0 1,071,260.00 1,071,260.00
SUBTOTAL MATERIALES 1,071,260.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 1,071,260.00 1,071,260.00

CODO 10" X 22.5° HD LISA 640MCA UNIDAD: UN


ITEM: 12,24
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO 10" X 22.5° HD LISA 640MCA UND 1 0 1,291,060.00 1,291,060.00
SUBTOTAL MATERIALES 1,291,060.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 1,291,060.00 1,291,060.00

CODO 10" X 45° HD LISA 640 MCA UNIDAD: UN


ITEM: 12,25
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO 10" X 45° HD LISA 640 MCA UND 1 0 1,420,420.00 1,420,420.00
SUBTOTAL MATERIALES 1,420,420.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 1,420,420.00 1,420,420.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
CODO 10" X 90° JH LISA 640MCA UNIDAD: UN
ITEM: 12,26
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO 10" X 90° JH LISA 640MCA UND 1 0 1,594,420.00 1,594,420.00
SUBTOTAL MATERIALES 1,594,420.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 1,594,420.00 1,594,420.00

CODO 10" X 11.25° HD LISA 400MCA UNIDAD: UN


ITEM: 12,27
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO 10" X 11.25° HD LISA 400MCA UND 1 0 673,960.00 673,960.00
SUBTOTAL MATERIALES 673,960.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 673,960.00 673,960.00

CODO 10" X 22.5° HD LISA 400MCA UNIDAD: UN


ITEM: 12,28
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO 10" X 22.5° HD LISA 400MCA UND 1 0 673,960.00 673,960.00
SUBTOTAL MATERIALES 673,960.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 673,960.00 673,960.00

CODO 10" X 45° HD LISA 400 MCA UNIDAD: UN


ITEM: 12,29
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO 10" X 45° HD LISA 400 MCA UND 1 0 808,520.00 808,520.00
SUBTOTAL MATERIALES 808,520.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 808,520.00 808,520.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
CODO 10" X 90° JH LISA 400MCA UNIDAD: UN
ITEM: 12,3
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO 10" X 90° JH LISA 400MCA UND 1 0 954,680.00 954,680.00
SUBTOTAL MATERIALES 954,680.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 954,680.00 954,680.00

SUMINISTRO VALVULA PURGA 2" BRIDADA 640MCA UNIDAD: UN


ITEM: 12,31
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALVULA PURGA 2" BRIDADA 640MCA UND 1 0 485,000.00 485,000.00
SUBTOTAL MATERIALES 485,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 485,000.00 485,000.00

SUMINISTRO VALVULA PURGA 2" BRIDADA 350MCA UNIDAD: UN


ITEM: 12,32
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALVULA PURGA 2" BRIDADA 350MCA UND 1 0 472,120.00 472,120.00
SUBTOTAL MATERIALES 472,120.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 472,120.00 472,120.00

SUMINISTRO VENTOSAS DE DOBLE ACCION 2" 350 MCA UNIDAD: UND


ITEM: 12,33
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VENTOSAS DE DOBLE ACCION 2" 350 MCA UND 1 0 668,160.00 668,160.00
SUBTOTAL MATERIALES 668,160.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 668,160.00 668,160.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO VENTOSAS DE DOBLE ACCION 2" 640 MCA UNIDAD: UND
ITEM: 12,34
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VENTOSAS DE DOBLE ACCION 2" 640 MCA UND 1 0 785,000.00 785,000.00
SUBTOTAL MATERIALES 785,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 785,000.00 785,000.00

SUMINISTRO UNION RAPIDA PVC 6" UNIDAD: UND


ITEM: 12,35
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
UNION RAPIDA PVC 6" UND 1 0 111,413.00 111,413.00
SUBTOTAL MATERIALES 111,413.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 111,413.00 111,413.00

SUMINISTRO VALVULAS DE PIE DE COLADERA 10" UNIDAD: UND


ITEM: 12,36
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALVULAS DE PIE DE COLADERA 10" UND 1 0 3,785,000.00 3,785,000.00
SUBTOTAL MATERIALES 3,785,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 3,785,000.00 3,785,000.00

SUMINISTRO VALVULAS DE PIE DE COLADERA 8" UNIDAD: UND


ITEM: 12,37
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALVULAS DE PIE DE COLADERA 8" UND 1 0 2,860,000.00 2,860,000.00
SUBTOTAL MATERIALES 2,860,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 2,860,000.00 2,860,000.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO VALVULA DE MARIPOSA BRIDADA HD 10" , 400PSI UNIDAD: UND
ITEM: 12.38
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALVULA DE MARIPOSA BRIDADA HD 10" , 400PSI UND 1 0 6,050,000.00 6,050,000.00

SUBTOTAL MATERIALES 6,050,000.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 6,050,000.00 6,050,000.00

SUMINISTRO VALVULA DE MARIPOSA BRIDADA HD 8" , 400PSI UNIDAD: UND


ITEM: 12.39
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALVULA DE MARIPOSA BRIDADA HD 8" , 400PSI UND 1 0 3,325,140.00 3,325,140.00

SUBTOTAL MATERIALES 3,325,140.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 3,325,140.00 3,325,140.00

SUMINISTRO REDUCCIÓN EXCENTRICA BRIDADO 10"X5" , ACERO SCHEDULE 40 ASTM A- UNIDAD: UND
53 GRADO B ITEM: 12.40
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
REDUCCIÓN EXCENTRICA BRIDADO 10"X5" , ACERO SCHEDULE
UND 40 ASTM A-53
1 GRADO B 0 1,602,463.00 1,602,463.00

SUBTOTAL MATERIALES 1,602,463.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 1,602,463.00 1,602,463.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO REDUCCIÓN EXCENTRICA BRIDADO 8"X5" , ACERO SCHEDULE 40 ASTM A- UNIDAD: UND
53 GRADO B ITEM: 12.41
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
REDUCCIÓN EXCENTRICA BRIDADO 8"X5" , ACERO SCHEDULE
UND40 ASTM A-53
1 GRADO B 0 1,602,463.00 1,602,463.00

SUBTOTAL MATERIALES 1,602,463.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 1,602,463.00 1,602,463.00

SUMINISTRO REDUCCIÓN CONCENTRICA BRIDADO 6"X4" , ACERO SCHEDULE 40 ASTM UNIDAD: UND
A-53 GRADO B ITEM: 12.42
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
REDUCCIÓN CONCENTRICA BRIDADO 6"X4" , ACERO SCHEDULE
UND 40 ASTM A-53
1 GRADO B 0 1,602,463.00 1,602,463.00

SUBTOTAL MATERIALES 1,602,463.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 1,602,463.00 1,602,463.00

SUMINISTRO REDUCCIÓN CONCENTRICA BRIDADO 6"X3" , ACERO SCHEDULE 40 ASTM UNIDAD: UND
A-53 GRADO B ITEM: 12.43
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
REDUCCIÓN CONCENTRICA BRIDADO 6"X3" , ACERO SCHEDULE
UND 40 ASTM A-53
1 GRADO B 0 1,602,463.00 1,602,463.00

SUBTOTAL MATERIALES 1,602,463.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 1,602,463.00 1,602,463.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO REDUCCIÓN CONCENTRICA BRIDADO 6"X2" , ACERO SCHEDULE 40 ASTM UNIDAD: UND
A-53 GRADO B ITEM: 12.44
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
REDUCCIÓN CONCENTRICA BRIDADO 6"X2" , ACERO SCHEDULE
UND 40 ASTM A-53
1 GRADO B 0 1,602,463.00 1,602,463.00

SUBTOTAL MATERIALES 1,602,463.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 1,602,463.00 1,602,463.00

SUMINISTRO REDUCCIÓN CONCENTRICA BRIDADO 10"X6" , ACERO SCHEDULE 40 ASTM UNIDAD: UND
A-53 GRADO B ITEM: 12.45
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
REDUCCIÓN CONCENTRICA BRIDADO 10"X6" , ACERO SCHEDULE
UND 40 ASTM A-53
1 GRADO B0 1,602,463.00 1,602,463.00

SUBTOTAL MATERIALES 1,602,463.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 1,602,463.00 1,602,463.00

SUMINISTRO REDUCCIÓN CONCENTRICA BRIDADO 8"X6" , ACERO SCHEDULE 40 ASTM UNIDAD: UND
A-53 GRADO B ITEM: 12.46
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
REDUCCIÓN CONCENTRICA BRIDADO 8"X6" , ACERO SCHEDULE
UND 40 ASTM A-53
1 GRADO B 0 1,602,463.00 1,602,463.00

SUBTOTAL MATERIALES 1,602,463.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 1,602,463.00 1,602,463.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO VALVULAS CHEQUE BRIDADA ACERO 10" 640 MCA UNIDAD: UND
ITEM: 12.47
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALVULA CHEQUE BRIDADA ACERO 10" 640 MCA UND 1 0 8,187,000.00 8,187,000.00

SUBTOTAL MATERIALES 8,187,000.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 8,187,000.00 8,187,000.00

SUMINISTRO VALVULAS CHEQUE BRIDADA HD 10" 340 MCA UNIDAD: UND


ITEM: 12.48
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALVULA CHEQUE BRIDADA HD 10" 340 MCA UND 1 0 6,050,000.00 6,050,000.00

SUBTOTAL MATERIALES 6,050,000.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 6,050,000.00 6,050,000.00

SUMINISTRO VALVULAS CHEQUE BRIDADA HD 8" 340 MCA UNIDAD: UND


ITEM: 12.49
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALVULA CHEQUE BRIDADA HD 8" 340 MCA UND 1 0 6,050,000.00 6,050,000.00

SUBTOTAL MATERIALES 6,050,000.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 6,050,000.00 6,050,000.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO VALVULAS MARIPOSA BRIDADA ACERO 10" 640 MCA UNIDAD: UND
ITEM: 12.50
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALVULA DE MARIPOSA BRIDADA HD 10" , 400PSI UND 1 0 6,050,000.00 6,050,000.00

SUBTOTAL MATERIALES 6,050,000.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 6,050,000.00 6,050,000.00

SUMINISTRO JUNTA DE DILATACIÓN BRIDADA 10" 640 MCA UNIDAD: UND


ITEM: 12.51
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
JUNTA DE DILATACIÓN BRIDADA 10" 640 MCA UND 1 0 742,400.00 742,400.00

SUBTOTAL MATERIALES 742,400.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 742,400.00 742,400.00

SUMINISTRO JUNTA DE DILATACIÓN BRIDADA 10" 340 MCA UNIDAD: UND


ITEM: 12.52
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
JUNTA DE DILATACIÓN BRIDADA 10" 340 MCA UND 1 0 371,200.00 371,200.00

SUBTOTAL MATERIALES 371,200.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 371,200.00 371,200.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO JUNTA DE DILATACIÓN BRIDADA 8" 340 MCA UNIDAD: UND


ITEM: 12.53
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
JUNTA DE DILATACIÓN BRIDADA 8" 340 MCA UND 1 0 255,200.00 255,200.00

SUBTOTAL MATERIALES 255,200.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 255,200.00 255,200.00

SUMINISTRO CODO BRIDADO 45° , 10" , ACERO SCHEDULE 40 ASTM A-53 GRADO B UNIDAD: UND
ITEM: 12.54
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO BRIDADO 45° , 10" , ACERO SCHEDULE 40 ASTM A-53UND
GRADO B 1 0 1,574,452.00 1,574,452.00

SUBTOTAL MATERIALES 1,574,452.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 1,574,452.00 1,574,452.00

SUMINISTRO CODO BRIDADO 90° , 10" , ACERO SCHEDULE 40 ASTM A-53 GRADO B UNIDAD: UND
ITEM: 12.55
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO BRIDADO 90° , 10" , ACERO SCHEDULE 40 ASTM A-53UND
GRADO B 1 0 1,574,452.00 1,574,452.00

SUBTOTAL MATERIALES 1,574,452.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 1,574,452.00 1,574,452.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

SUMINISTRO CODO BRIDADO 45° , 8" , ACERO SCHEDULE 40 ASTM A-53 GRADO B UNIDAD: UND
ITEM: 12.56
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CODO BRIDADO 45° , 8" , ACERO SCHEDULE 40 ASTM A-53 GRADO
UND B 1 0 1,496,577.00 1,496,577.00

SUBTOTAL MATERIALES 1,496,577.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 1,496,577.00 1,496,577.00

SUMINISTRO "Y" BRIDADO , 10" , ACERO SCHEDULE 40 ASTM A-53 GRADO B UNIDAD: UND
ITEM: 12.57
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
LLE (Y) BRIDADO , 10" , ACERO SCHEDULE 40 ASTM A-53 GRADO
UND B 1 0 3,264,327.00 3,264,327.00

SUBTOTAL MATERIALES 3,264,327.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 3,264,327.00 3,264,327.00

SUMINISTRO TUBERIA BRIDADO , 10" , ACERO SCHEDULE 40 ASTM A-53 GRADO B,


UNIDAD: ML
(TAMAÑOS DE NIPLES SEGÚN DETALLES ESTACIONES DE BOMBEO)
ITEM: 12.58
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TUBERIA BRIDADO , 10" , ACERO SCHEDULE 40 ASTM A-53 GRADO
ML B 1 0 956,971.00 956,971.00

SUBTOTAL MATERIALES 956,971.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 956,971.00 956,971.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO TUBERIA BRIDADO , 8" , ACERO SCHEDULE 40 ASTM A-53 GRADO B,
UNIDAD: ML
(TAMAÑOS DE NIPLES SEGÚN DETALLES ESTACIONES DE BOMBEO)
ITEM: 12.59
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TUBERIA BRIDADO , 8" , ACERO SCHEDULE 40 ASTM A-53 GRADO
ML B 1 0 403,899.00 403,899.00

SUBTOTAL MATERIALES 403,899.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 403,899.00 403,899.00

SUMINISTRO TUBERIA BRIDADO , 3" , ACERO SCHEDULE 40 ASTM A-53 GRADO B,


UNIDAD: ML
(TAMAÑOS DE NIPLES SEGÚN DETALLES ESTACIONES DE BOMBEO)
ITEM: 12.60
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TUBERIA BRIDADO , 3" , ACERO SCHEDULE 40 ASTM A-53 GRADO
ML B 1 0 220,959.00 220,959.00

SUBTOTAL MATERIALES 220,959.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 220,959.00 220,959.00

SUMINISTRO TUBERIA BRIDADO , 2" , ACERO SCHEDULE 40 ASTM A-53 GRADO B,


UNIDAD: ML
(TAMAÑOS DE NIPLES SEGÚN DETALLES ESTACIONES DE BOMBEO)
ITEM: 12.61
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TUBERIA BRIDADO , 2" , ACERO SCHEDULE 40 ASTM A-53 GRADO
ML B 1 0 211,599.00 211,599.00

SUBTOTAL MATERIALES 211,599.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 211,599.00 211,599.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO VALVULAS ALIVIO(TIPO GLOBO) BRIDADA ACERO 3" 640 MCA UNIDAD: UND
ITEM: 12.62
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALVULA ALIVIO(TIPO GLOBO) BRIDADA ACERO 3" 640 MCAUND 1 0 1,047,000.00 1,047,000.00

SUBTOTAL MATERIALES 1,047,000.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 1,047,000.00 1,047,000.00

SUMINISTRO VALVULAS ALIVIO(TIPO GLOBO) BRIDADA ACERO 2" 640 MCA UNIDAD: UND
ITEM: 12.63
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALVULA ALIVIO(TIPO GLOBO) BRIDADA ACERO 2" 640 MCAUND 1 0 638,000.00 638,000.00

SUBTOTAL MATERIALES 638,000.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 638,000.00 638,000.00

SUMINISTRO VALVULAS AIRE BRIDADA ENTRADA 8" Y SALIDA 1/4" , 350 MCA UNIDAD: UND
ITEM: 12.64
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALVULA AIRE BRIDADA ENTRADA 8" Y SALIDA 1/4" , 350 MCA
UND 1 0 6,519,200.00 6,519,200.00

SUBTOTAL MATERIALES 6,519,200.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 6,519,200.00 6,519,200.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO VALVULAS AIRE BRIDADA ENTRADA 6" Y SALIDA 1/2" , 350 MCA UNIDAD: UND
ITEM: 12.65
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALVULA AIRE BRIDADA ENTRADA 6" Y SALIDA 1/2" , 350 MCA
UND 1 0 6,519,200.00 6,519,200.00

SUBTOTAL MATERIALES 6,519,200.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 6,519,200.00 6,519,200.00

SUMINISTRO VALVULAS AIRE BRIDADA ENTRADA 6" Y SALIDA 1/4" , 350 MCA UNIDAD: UND
ITEM: 12.66
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALVULA AIRE BRIDADA ENTRADA 6" Y SALIDA 1/4" , 350 MCA
UND 1 0 6,519,200.00 6,519,200.00

SUBTOTAL MATERIALES 6,519,200.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 6,519,200.00 6,519,200.00

SUMINISTRO VALVULAS AIRE BRIDADA ENTRADA 4" Y SALIDA 1/4" , 350 MCA UNIDAD: UND
ITEM: 12.67
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VALVULA AIRE BRIDADA ENTRADA 4" Y SALIDA 1/4" , 350 MCA
UND 1 0 6,519,200.00 6,519,200.00

SUBTOTAL MATERIALES 6,519,200.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 6,519,200.00 6,519,200.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
SUMINISTRO TUBERIA 24", SCHEDULE 40 , PARA ALMENARA UNIDAD: ML
ITEM: 12.68
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TUBERIA 24", SCHEDULE 40 , PARA ALMENARA ML 1 0 1,913,689.00 1,913,689.00

SUBTOTAL MATERIALES 1,913,689.00


MANO DE OBRA

SUBTOTAL- MANO DE OBRA -


EQUIPO

SUBTOTAL- EQUIPO -

COSTO DIRECTO 1,913,689.00 1,913,689.00

BOMBA SUMERGIBLE CON CAPACIDAD DE 32 L/S CONTRA UNA CABEZA TOTAL DE 30 M, UNIDAD: UND
2 ETAPAS, CON MOTOR ELÉCTRICO DE 30 HP X 440 V X 3 FASES X 60 HZ, DESCARGA EN
5" Y CAMISA DE REFRIGERACIÓN. ITEM: 13,1

DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
BOMBA SUMERGIBLE CON CAPACIDAD DE 32 L/S CONTRA UND
UNA CABEZA TOTAL
1 DE 30 M, 2
0 ETAPAS, CON MOTOR ELÉCTRICO
25,810,000.00 DE 30 HP X 440 V X 3 FASES X 60 HZ, D
25,810,000.00
SUBTOTAL MATERIALES 25,810,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 25,810,000.00 25,810,000.00

MOTOBOMBA MULTIETAPAS, TRES ETAPAS, SUCCIÓN DE 125 MM DESCARGA DE 100 UNIDAD: UND
MM, MATERIALES EN HIERRO FUNDIDO, EJE Y MANGUITO EN ACERO INOXIDABLE
CAPACIDAD DE 32 LPS VS 340 MTS, SELLO MECANICO INCLUYE BASE COMÚN MOTOR
BOMBA, ACOPLE Y GUARDA ACOPLE MOTOR CON POTENCIA NOMINAL DE 225 HP, ITEM: 13,2
CONECTADA A 460 VAC, 3576 RPM, 3 FASES, 60 HZ, INCLUYE TABLERO DE CONTROL
ELECTRICO
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
MOTOBOMBA MULTIETAPAS, TRES ETAPAS, CON POTENCIA NOMINAL DE 225
UND 1 HP, CONECTADA
0 A 460 VAC, 3576 RPM, 3 101,451,275.00
101,451,275.00 FASES, 60 HZ, INCLUYE TABLERO DE CONTR
SUBTOTAL MATERIALES 101,451,275.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 101,451,275.00 101,451,275.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
MOTO BOMBA MULTIETAPAS, TRES ETAPAS, SUCCIÓN DE 150 MM DESCARGA DE 125 UNIDAD: UND
MM, CAPACIDAD DE 32 LPS VS 90 MTS, SELLO MECANICO INCLUYE BASE COMÚN
MOTOR BOMBA, ACOPLE Y GUARDA ACOPLE MOTOR CON POTENCIA NOMINAL DE 70
ITEM: 13,3
HP, CONECTADA A 460VAC, 1752 RPM, 3 FASES, 60 HZ. INCLUYE TABLERO DE CONTROL
ELECTRICO
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
MOTO BOMBA MULTIETAPAS, TRES ETAPAS, CAPACIDAD DE 32 LPS VS 90 MTS,
UND 1 SELLO MECANICO
0 CON POTENCIA NOMINAL
48,829,500.00 DE 70 HP, CONECTADA A 460VAC, 1752
48,829,500.00
SUBTOTAL MATERIALES 48,829,500.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 48,829,500.00 48,829,500.00

TANQUE DE ACERO FUSIONADO EN VIDRIO (33.25M X 8.66 M ) VOLUMEN 8235 M3 UNIDAD: UND
ITEM: 14,1
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TANQUE DE ACERO FUSIONADO EN VIDRIO (33.25M X 8.66 UND
M ) VOLUMEN 8235
1 M3 0 2,469,031,065.00 2,469,031,065.00
SUBTOTAL MATERIALES 2,469,031,065.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -

COSTO DIRECTO 2,469,031,065.00 2,469,031,065.00

TANQUE DE ACERO FUSIONADO EN VIDRIO (19.61M X 7.27 M ) VOLUMEN 2000 M3 UNIDAD: UND
ITEM: 14,2
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TANQUE DE ACERO FUSIONADO EN VIDRIO (19.61M X 7.27 UND
M ) VOLUMEN 2000
1 M3 0 1,646,020,710.00 1,646,020,710.00
SUBTOTAL MATERIALES 1,646,020,710.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 1,646,020,710.00 1,646,020,710.00

FLOCULADOR 4 PUESTOS PÁRA LABORATORIO 10-300 RPM MODELO ET 740, 100-240 V Unidad: UND
ITEM: 15,1
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
FLOCULADOR 4 PUESTOS PÁRA LABORATORIO 10-300 RPM MODELO ET 740,
UND 1 100-240 V 0 6,613,740.00 6,613,740.00
SUBTOTAL MATERIALES 6,613,740.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 6,613,740.00 6,613,740.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA
VASO DE PRECIPITADO Unidad: UND
ITEM: 15,2
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
VASO DE PRECIPITADO UND 1 0 14,616.00 14,616.00
SUBTOTAL MATERIALES 14,616.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 14,616.00 14,616.00

EQUIPO PARA PH Unidad: UND


ITEM: 15,3
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
EQUIPO PARA PH UND 1 0 2,472,964.00 2,472,964.00
SUBTOTAL MATERIALES 2,472,964.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 2,472,964.00 2,472,964.00

COLORIMETRO PORTATIL Unidad: UND


ITEM: 15,4
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
CLORADOR COLORIMETRO PORTATIL UND 1 0 6,681,087.00 6,681,087.00
SUBTOTAL MATERIALES 6,681,087.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
SUBTOTAL EQUIPO -

COSTO DIRECTO 6,681,087.00 6,681,087.00

TURBIDIMETRO PORTATIL Unidad: UND


ITEM: 15,5
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
TURBIDIMETRO PORTATIL UND 1 0 6,152,368.00 6,152,368.00
SUBTOTAL MATERIALES 6,152,368.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 6,152,368.00 6,152,368.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

COLORIMETRO DE BOLSILLO Unidad: UND


ITEM: 15,6
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
COLORIMETRO DE BOLSILLO UND 1 0 2,326,366.00 2,326,366.00
SUBTOTAL MATERIALES 2,326,366.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 2,326,366.00 2,326,366.00

JUEGO DE REACTIVOS PARA DETERMINAR ALUMINIO Unidad: UND


ITEM: 15,7
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
JUEGO DE REACTIVOS PARA DETERMINAR ALUMINIO UND 1 0 567,773.00 567,773.00
SUBTOTAL MATERIALES 567,773.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 567,773.00 567,773.00

REACTIVO PARA CLORO LIBRE Unidad: UND


ITEM: 15,8
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
REACTIVO PARA CLORO LIBRE UND 1 0 115,779.00 115,779.00
SUBTOTAL MATERIALES 115,779.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 115,779.00 115,779.00

REACTIVO DE HIERRO Unidad: UND


ITEM: 15,9
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
REACTIVO DE HIERRO UND 1 0 107,264.00 107,264.00
SUBTOTAL MATERIALES 107,264.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 107,264.00 107,264.00


EMPRESA DE SERVICIOS PUBLICOS DE SANTANDER
S.A. E.S.P.
ANALISIS DE PRECIOS UNITARIOS
PRESUPUESTO DE OBRA A TODO COSTO ACUEDUCTO REGIONAL DEL FECHA: may-15
CHICAMOCHA

REACTIVO STD COLOR Unidad: UND


ITEM: 15,1
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
REACTIVO STD COLOR UND 1 0 903,946.00 903,946.00
SUBTOTAL MATERIALES 903,946.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 903,946.00 903,946.00

BALANZA PRECISION, CAPACIDAD 2000 GRAMOS , PRESICION 0,1 GRAMO PARA PESAR Unidad: UND
LA CAL Y EL SULFATO DE ALUMINIO.
ITEM: 15,11

DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
BALANZA PRECISION, CAPACIDAD 2000 GRAMOS , PRESICION
UND0,1 GRAMO PARA
1 PESAR LA
0 CAL Y3,364,000.00
EL SULFATO DE ALUMINIO.
3,364,000.00
SUBTOTAL MATERIALES 3,364,000.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -

COSTO DIRECTO 3,364,000.00 3,364,000.00

MATERIALES Y VIDRIERIA PARA LABORATORIO Unidad: GLB


ITEM: 15,12
DESCRIPCION UND CANT. DESP.% PRECIO UNIT VALOR TOTAL

MATERIALES
MATERIALES Y VIDRIERIA PARA LABORATORIO GLB 1 0 1,958,723.00 1,958,723.00
SUBTOTAL MATERIALES 1,958,723.00

MANO DE OBRA Jornal Prestac. Jornal Ttl Rendim/Día Valor-Unit.


SUBTOTAL MANO DE OBRA -
EQUIPO
HERRAMIENTA MENOR % 5% 0 - -
SUBTOTAL EQUIPO -

COSTO DIRECTO 1,958,723.00 1,958,723.00