Sr # Description of Item Qty Unit Unit Cost Total Cost Delivery Time

1 Digging of the borehole with installation of Handpump 50 No 76663.08 3,833,154.00 60 days

CONSTRUCTION OF WASH CATEGORY, 1 PROGECT


Abstract of Quantity and Cost for WASH-I Project

Sr # Description of Item Length Width H/D No Unit Quantity Unit Price Total Price

1 Boring (complete in all respect)

Digging of 5" dia straight borehole in any formation having total depth of 100-
120Rft bases on actual clean water table with loring of pipe and and insttalation 1 Rft 120 333 39960
of HP ,inculding cotton role for filtration,complete with all respect

2 Excavation (including backfilling of pad structure)

Excavation of handpump foundation long wall 10.75 1.5 1.25 2 Cft 40.31 10.00

Excavation of handpump foundation Short wall 2.75 1.5 1.25 2 Cft 10.31 10.00

Total Quantity 50.63 10.00 506.25

3 PCC (1:4:8) (complete in all respect)

PCC concrete (1:4:8) in bottom of handpump pad long walls 10.75 1.5 0.25 2 Cft 8.06 230.00

PCC concrete (1:4:8) in bottom of handpump pad Short walls 2.75 1.5 0.25 2 Cft 2.06 230.00

Net PCC (1:4:8) 10.13 230.00 2328.75

4 Brick Masonary (1:4) (complete in all respect)

Brick Masonary 1st step 13" long wall 10.333 1.125 0.5 2 Cft 11.62 222.00

Brick Masonary 1st step 13" short wall 3.16 1.125 0.5 2 Cft 3.56 222.00

Brick Masonary 2nd step super structure 9" long wall 10 0.75 1.5 2 Cft 22.50 222.00

Brick Masonary 2nd step superstructure 9" short wall 3.5 0.75 1.5 2 Cft 7.88 222.00

Brick Masonary parapet boundry Long wall 10 0.375 0.25 2 Cft 1.88 222.00

Brick Masonary parapet boundry short wall 4.25 0.375 0.25 2 Cft 0.80 222.00

Brick Masonary work for steps 10 1 1.5 1 Cft 15.00 222.00

Total Quantity 63.2 222.00 14036.28

5 Laying Brick Ballast and PCC (1:2:4) (complete in all respect)

Laying brick ballast at floor bed 8.5 3.5 0.25 1 Cft 7.4 48.0 357.0

PCC (1:2:4) in floor (FFL) 10 5 0.25 1 Cft 12.5 320.0

PCC (1:2:4) Concrete Block for handpump machine 2.16 2 2 1 Cft 8.6 320.0

Total Quantity 21.1 320.00 6764.8

6 Palaster 1/2" thick (1:4 C/S) (complete in all respect)

Long walls 10 2 2 Sft 40 25

short wall 5 2 2 Sft 20 25

Plaster 1/2" thick on PCC Block 2.16 2 5 Sft 21.6 25

Plaster 1/2" thick on steps 10 3 1 Sft 30 25

Total Quantity 111.6 25 2790

7 PVC 4" pipe with elbows/ bend for drainage of waste water complete in all
20 1 Rft 20.0 165.0 3300.0
respect

9 Floor Trap(waste water jali) (Master) complete in all respect 1 No 1 500 500.0

11 Weather shield 2 coats for pad structure complete in all respect 1 No 1 150 150.0

12 Handpump material transportation cost from warehouse to the site. 1 Job 1 300 300.0

13 Plenth Protection (one Length) Brick Ballast 3" thick 40 1.5 0.25 1 Cft 15 48.00 720.0

14 Plenth Protection (one Length) PCC (1:2:4) 3" thick 40 1.5 0.25 1 Cft 15 330.00 4950.0

GRAND TOTAL
76,663.08
Note: Hand pump assembly with accessories will be provided by Qatar Charity as supplies to the vendor at QC Shorkot Office
Details are (1. INDUS Hand Pump (UNICEF STAND) with 08 Rods,Complete accessorories. Plastic Rope, Solvent Cement 500 gm, Box spanner, Fishing tool for (100 ft Depth) with
Kawsar upvc pipe 4" dia, Filter pipe 4" dia and kawsar 63mm upve pipe complete all respect for WASH-I Projects)