1 Documentation to be submitted
1.1 Verification Form Attachment Sheet, if any of the items on this form are not
applicable.
2 Consultant's Assurance
2.5 The Construction Verification and Survey Verification Forms have been
submitted to Central Highlands Water.
2.6 We have received the Acceptance of Works and Commencement of Defects
Liability Period Letter from Central Highlands Water.
2.7 Testing and repairs of live assets has been carried out in accordance with the
specifications.
2.8 All faults have been rectified.
2.9 Clearance has been obtained from the relevant authority for restoration to
paved areas.
2.10 Permanent repairs to the unpaved surfaces have been completed.
2.11 Covers on all surface structures conform to the tolerances in the specifications
and the surrounding final surface level.
2.12 All surplus material has been removed from site in accordance with the
specifications and AS 2124.
2.13 The defects liability period of 6 months has expired.
2.14 Release notices have been obtained from council, relevant authorities or
developers of the properties affected.
Nominated Representative
___________________________________ _________________________________
Name Company Position
___________________________________ _________________________________
Signature Date