HARGA
NO URAIAN PEKERJAAN VOL SAT
SATUAN
A BACKDROOF
1 Pasangan Rangka Hollow 4x4; 2/4 101.21 m² 313,698.29
2 Pasangan Multipleks 18 mm 40.77 m² 158,436.22
3 Pasangan Multipleks 12 mm 40.77 m² 134,951.22
4 Pasangan HPL 81.54 m² 188,347.85
5 Pasangan Strip Stainless 1 mm 28.00 btg 40,000.00
6 Pasangan Gypsum 9mm 125.86 m² 47,027.00
7 Pasangan Wallpaper 125.86 m² 154,129.00
8 Pasangan Plint Lantai (Multipleks 12 mm) 3.00 m² 143,309.03
9 Pasangan HPL Plint Lantai 5.00 m² 188,347.85
B PLAFOND
1 Pasangan Rangka Hollow 4x4 9.80 m² 92,185.83
2 Pasangan Gypsum 9 mm 9.80 m² 47,027.43
3 Pasangan Instalasi Listrik 5.00 ttk 274,999.15
4 Pasangan Lampu Down Light 5.00 bh 317,622.10
5 Pasangan Lampu SL 18 Watt 5.00 bh 647,622.10
6 Pasangan Lampu Barret 1.00 bh 250,000.00
7 Pasangan Saklar Tunggal 1.00 bh 86,478.92
D PENGECATAN
1 Pengecatan Plafond 65.21 m² 61,908.20
Jumlah
Ppn 10%
JUMLAH TOTAL
JUMLAH
HARGA
31,749,403.87
6,459,444.60
5,501,961.15
15,357,883.61
1,120,000.00
5,918,818.22
19,398,675.94
429,927.09
941,739.24
903,421.14
460,868.84
1,374,995.76
1,588,110.50
3,238,110.50
250,000.00
86,478.92
2,440,000.00
302,866.52
420,000.00
4,037,033.75
7,800,000.00
5,900,000.00
8,073,000.00
1,173,000.00
804,000.00
125,729,739.66
12,572,973.97
138,302,713.62