ID Task Task Name Duration Start Finish Mar 11, '18 May 6, '18 Jul 1, '18 Aug 26,

r 11, '18 May 6, '18 Jul 1, '18 Aug 26, '18 Oct 21, '18
Mode M F T S W S T M F T S W
0 Commercial 344 days Thu 5/3/18 Tue
Construction 8/27/19
1 General Conditions17 days Thu 5/3/18 Fri 5/25/18
2 Receive notice 3 days Thu 5/3/18 Mon 5/7/18 G.C. General Management
to proceed and
sign contract
3 Submit bond 2 days Tue 5/8/18 Wed 5/9/18 G.C. Project Management,G.C. General Management[25%]
and insurance
documents
4 Prepare and 2 days Thu 5/10/18 Fri 5/11/18 G.C. Project Management[25%],G.C. Scheduler
submit project
schedule
5 Prepare and 2 days Mon Tue 5/15/18 G.C. General Management[10%],G.C. Project Management
submit 5/14/18
schedule of
6 Obtain building 4 days Tue 5/8/18 Fri 5/11/18 G.C. Project Management[50%],G.C. Procurement[50%]
permits
7 Submit 2 wks Mon Fri 5/25/18 G.C. Project Management[50%],G.C. Procurement[50%]
preliminary 5/14/18
shop drawings
8 Submit monthly 1 day Tue 5/8/18 Tue 5/8/18
requests for
payment
9 Long Lead 70 days Wed 5/9/18 Tue 8/14/18
Procurement

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Mar 11, '18 May 6, '18 Jul 1, '18 Aug 26, '18 Oct 21, '18
Mode M F T S W S T M F T S W
10 Submit shop 2 wks Wed 5/9/18 Tue 5/22/18 Steel Erection Contractor Management
drawings and
order long lead
items - steel
11 Submit shop 2 wks Mon Fri 6/8/18 Roofing Contractor Management
drawings and 5/28/18
order long lead
items - roofing
12 Submit shop 2 wks Mon Fri 6/8/18 Elevator Contractor Management
drawings and 5/28/18
order long lead
items - elevator
13 Submit shop 2 wks Mon Fri 6/8/18 Plumbing Contractor Management
drawings and 5/28/18
order long lead
items -
plumbing
14 Submit shop 2 wks Mon Fri 6/8/18 Electric Contractor Management
drawings and 5/28/18
order long lead
items - electric
15 Submit shop 2 wks Mon Fri 6/8/18 HVAC Contractor Management
drawings and 5/28/18
order long lead
items - HVAC

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration Start Finish Mar 11, '18 May 6, '18 Jul 1, '18 Aug 26, '18 Oct 21, '18
Mode M F T S W S T M F T S W
16 Detail, fabricate 12 wks Wed Tue 8/14/18 Steel Erection Contractor Managemen
and deliver 5/23/18
17 Mobilize on Site 10 days Tue 5/8/18 Mon 5/21/18
18 Install 2 days Tue 5/8/18 Wed 5/9/18 Electric Contractor
temporary
power
19 Install 2 days Tue 5/8/18 Wed 5/9/18 Plumbing Contractor
temporary
water service
20 Set up site office3 days Thu 5/10/18 Mon 5/14/18 G.C. Superintendent,G.C. Labor Crew[10%]
21 Set line and 3 days Tue 5/15/18 Thu 5/17/18 G.C. Survey Crew
grade
benchmarks
22 Prepare site - 2 days Fri 5/18/18 Mon Site Grading Contractor,G.C. Labor Crew[10%]
lay down yard 5/21/18
and temporary
fencing
23 Site Grading and 35 days Tue 5/22/18 Mon 7/9/18
Utilities
24 Clear and grub 3 days Tue 5/22/18 Thu 5/24/18 Site Grading Contractor
site
25 Stone site 2 days Fri 5/25/18 Mon Site Grading Contractor
access and 5/28/18
temporary
26 Rough grade 1 wk Tue 5/29/18 Mon 6/4/18 Site Grading Contractor
site (cut and fill)

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task Task Name Duration Start Finish Mar 11, '18 May 6, '18 Jul 1, '18 Aug 26, '18 Oct 21, '18
Mode M F T S W S T M F T S W
27 Install storm 2 wks Tue 6/5/18 Mon Site Grading Contractor
drainage 6/18/18
28 Install exterior 2 wks Tue 6/5/18 Mon Plumbing Contractor
fire line and 6/18/18
building fire
riser
29 Perform final 2 wks Tue 6/19/18 Mon 7/2/18 Site Grading Contractor
site grading
30 Erect building 1 wk Tue 7/3/18 Mon 7/9/18 G.C. Survey Crew
batter boards
and layout
building
31 Foundations 33 days Tue 7/10/18 Thu 8/23/18
32 Excavate 2 wks Tue 7/10/18 Mon Site Grading Contractor[50%]
foundations 7/23/18
33 Excavate 2 days Tue 7/10/18 Wed Site Grading Contractor
elevator pit 7/11/18
34 Form column 4 days Tue 7/24/18 Fri 7/27/18 G.C. Rough Carpenter Crew
piers and
spread
35 Rough-in 4 days Thu 7/12/18 Tue 7/17/18 Plumbing Contractor,Electric Contractor
electric and
plumbing in
elevator
36 Form elevator 4 days Wed Mon G.C. Rough Carpenter Crew
pit walls 7/18/18 7/23/18

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
ID Task Task Name Duration Start Finish Mar 11, '18 May 6, '18 Jul 1, '18 Aug 26, '18 Oct 21, '18
Mode M F T S W S T M F T S W
37 Set reinforcing 4 days Mon Thu 8/2/18 G.C. Rough Carpenter Crew
and anchor 7/30/18
38 Pour column 5 days Fri 8/3/18 Thu 8/9/18 G.C. Concrete Crew
piers and
foundations
39 Pour concrete 1 day Tue 7/24/18 Tue 7/24/18 G.C. Concrete Crew
elevator walls
40 Cure elevator 7 days Wed Thu 8/2/18 G.C. Labor Crew[10%]
wall concrete 7/25/18
41 Cure piers and 7 days Fri 8/10/18 Mon G.C. Labor Crew[10%]
foundations 8/20/18
42 Strip wall forms 1 day Fri 8/3/18 Fri 8/3/18 G.C. Labor Crew[10%]
43 Strip column 3 days Tue 8/21/18 Thu 8/23/18 G.C. Labor Crew
piers and
foundation
forms
44 Install 3 days Mon 8/6/18 Wed 8/8/18 Elevator Contractor
pneumatic tube
in elevator pit
45 Prepare and 1 day Thu 8/9/18 Thu 8/9/18 G.C. Concrete Crew
pour concrete
floor in elevator
pit
46 Steel Erection 45 days Fri 8/24/18 Thu 10/25/18

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
ID Task Task Name Duration Start Finish Mar 11, '18 May 6, '18 Jul 1, '18 Aug 26, '18 Oct 21, '18
Mode M F T S W S T M F T S W
47 Erect steel 2 wks Fri 8/24/18 Thu 9/6/18 Steel Erection Contractor
columns, beams
and joist - 1st
and 2nd floors
48 Erect steel 2 wks Fri 9/7/18 Thu 9/20/18 Steel Erection Contractor
columns, beams
and joist - 3rd
floor and roof
49 Install 2 wks Fri 9/7/18 Thu 9/20/18 Steel Erection Contractor[75
miscellaneous
iron and bracing
- 1st and 2nd
floors
50 Install 2 wks Fri 9/21/18 Thu 10/4/18 Steel Erection Contractor
miscellaneous
iron and bracing
- 3rd floor and
roof
51 Install stairs and 2 wks Fri 10/5/18 Thu Steel Erection Contrac
miscellaneous 10/18/18
iron railing
52 Touch-up paint 1 wk Fri 10/19/18 Thu Steel Erection Contr
on steel 10/25/18
53 Form and Pour 85 days Fri 9/7/18 Thu 1/3/19
Concrete - Floors
and Roof

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
ID Task Task Name Duration Start Finish Mar 11, '18 May 6, '18 Jul 1, '18 Aug 26, '18 Oct 21, '18
Mode M F T S W S T M F T S W
54 Form 2nd floor 5 days Fri 10/26/18 Thu 11/1/18 G.C. Rough Carpen
including all
floor openings
55 Install rebar and 5 days Fri 9/7/18 Thu 9/13/18 G.C. Labor Crew[33%],Plumbin
in-floor utilities
(including
mechanical,
electrical,
plumbing)
56 Pour 2nd floor 4 days Fri 11/2/18 Wed G.C. Concrete Cr
slab 11/7/18
57 Cure 2nd floor 7 days Thu 11/8/18 Fri 11/16/18 G.C. Labor Cre
slab
58 Strip forms 2 days Mon Tue G.C. Labor Cre
from 2nd floor 11/19/18 11/20/18
59 Form 3rd floor 5 days Mon Fri 11/23/18 G.C. Rough C
including all 11/19/18
floor openings
60 Install rebar and 5 days Mon Fri 11/23/18 G.C. Labor Cr
in-floor utilities 11/19/18
(including
mechanical,
electrical,
plumbing)
61 Pour 3rd floor 4 days Mon Thu G.C. Concre
slab 11/26/18 11/29/18

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
ID Task Task Name Duration Start Finish Mar 11, '18 May 6, '18 Jul 1, '18 Aug 26, '18 Oct 21, '18
Mode M F T S W S T M F T S W
62 Cure 3rd floor 7 days Fri 11/30/18 Mon G.C. Labo
slab 12/10/18
63 Strip forms 2 days Tue Wed
from 3rd floor 12/11/18 12/12/18
64 Form roof slab 5 days Tue Mon
including all 12/11/18 12/17/18
floor openings
65 Install rebar and 5 days Tue Mon
in-floor utilities 12/11/18 12/17/18
(including
mechanical,
electrical,
plumbing)
66 Pour roof slab 4 days Tue 12/18/18Fri 12/21/18
67 Cure roof slab 7 days Mon 12/24/18Tue 1/1/19
68 Strip forms 2 days Wed 1/2/19 Thu 1/3/19
from roof slab
69 Form 1st floor 4 days Wed 11/21/18Mon 11/26/18 G.C. Rough
70 Install electrical 1 wk Wed Tue Electric Con
underground 11/21/18 11/27/18
71 Install plumbing 1 wk Wed Tue Plumbing C
underground 11/21/18 11/27/18
72 Install rebar and 4 days Wed Mon G.C. Labor C
in-floor utilities 11/21/18 11/26/18
73 Pour 1st floor 4 days Wed Mon G.C. Concr
slab 11/28/18 12/3/18

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8
ID Task Task Name Duration Start Finish Mar 11, '18 May 6, '18 Jul 1, '18 Aug 26, '18 Oct 21, '18
Mode M F T S W S T M F T S W
74 Cure 1st floor 7 days Tue 12/4/18 Wed
slab 12/12/18
75 Strip forms 2 days Thu Fri 12/14/18
from 1st floor 12/13/18
76 Carpentry Work 15 days Fri 1/4/19 Thu 1/24/19
77 Install exterior 3 wks Fri 1/4/19 Thu 1/24/19
sheathing and
metal studs
78 Masonry Work 110 days Fri 10/5/18 Thu 3/7/19
79 Rough-in 4 wks Mon Fri 1/11/19
plumbing at 12/17/18
toilets and
masonry walls
80 Lay masonry at 4 wks Fri 10/5/18 Thu 11/1/18 Masonry Contract
core,
mechanical, and
toilets
81 Install exterior 5 wks Fri 1/25/19 Thu 2/28/19
masonry work
82 Install roof 2 days Fri 3/1/19 Mon 3/4/19
drains
83 Install tile in 2 wks Mon Fri 1/25/19
toilet rooms 1/14/19
84 Clean masonry 1 wk Fri 3/1/19 Thu 3/7/19
85 Clean toilet 1 wk Mon Fri 2/1/19
room tile 1/28/19

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 9
ID Task Task Name Duration Start Finish Mar 11, '18 May 6, '18 Jul 1, '18 Aug 26, '18 Oct 21, '18
Mode M F T S W S T M F T S W
86 Roofing 31 days Fri 3/1/19 Fri 4/12/19
87 Install flashing 4 days Fri 3/1/19 Wed 3/6/19
at parapet walls
88 Pour 2 days Thu 3/7/19 Fri 3/8/19
lightweight
89 Install seamless 5 days Mon Fri 3/22/19
roofing material 3/18/19
90 Spread stone 5 days Mon Fri 3/29/19
ballast on 3/25/19
seamless roof
91 Set rooftop 2 wks Mon 4/1/19 Fri 4/12/19
equipment
92 Window wall and 60 days Fri 3/1/19 Thu 5/23/19
store front
93 Install window 5 wks Fri 3/1/19 Thu 4/4/19
wall aluminum
and glass
94 Install interior 5 wks Fri 4/5/19 Thu 5/9/19
stud walls and
drywall
95 Install interior 2 wks Fri 5/10/19 Thu 5/23/19
doors and
hardware
96 Install store 3 wks Fri 3/1/19 Thu 3/21/19
front doors and
hardware

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 10
ID Task Task Name Duration Start Finish Mar 11, '18 May 6, '18 Jul 1, '18 Aug 26, '18 Oct 21, '18
Mode M F T S W S T M F T S W
97 Building Finishes 80 days Fri 4/5/19 Thu 7/25/19
98 Install millwork 3 wks Fri 5/10/19 Thu 5/30/19
and wood trim
99 Paint walls and 4 wks Fri 5/31/19 Thu 6/27/19
woodwork
100 Install conduit 3 wks Fri 4/5/19 Thu 4/25/19
at ceiling
plenum space
101 Install duct in 3 wks Fri 5/10/19 Thu 5/30/19
ceiling plenum
space
102 Install ceiling 2 wks Fri 5/31/19 Thu 6/13/19
grid
103 Install ceiling 2 wks Fri 6/14/19 Thu 6/27/19
tile
104 Hang wallpaper 2 wks Fri 6/14/19 Thu 6/27/19
105 Install building 4 wks Fri 6/28/19 Thu 7/25/19
carpet
106 Install hardware 3 wks Fri 6/28/19 Thu 7/18/19
and accessories
107 Complete 2 wks Fri 6/28/19 Thu 7/11/19
interior and
exterior sod
and plantings

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 11
ID Task Task Name Duration Start Finish Mar 11, '18 May 6, '18 Jul 1, '18 Aug 26, '18 Oct 21, '18
Mode M F T S W S T M F T S W
108 Pave, curb, and 2 wks Fri 7/12/19 Thu 7/25/19
stripe parking
lot
109 Elevators 40 days Fri 11/2/18 Thu 12/27/18
110 Set elevator 4 wks Fri 11/2/18 Thu Elevator Co
equipment in 11/29/18
shafts
111 Set equipment 2 wks Fri 11/30/18 Thu
in mechanical 12/13/18
room
112 Test and align 2 wks Fri 12/14/18 Thu
doors and 12/27/18
equipment
113 Plumbing 90 days Fri 3/8/19 Thu 7/11/19
114 Rough-in 4 wks Fri 4/5/19 Thu 5/2/19
plumbing in
drywall walls
115 Tie-in fire line 2 wks Fri 3/8/19 Thu 3/21/19
riser and set
valves
116 Set plumbing 3 wks Fri 5/3/19 Thu 5/23/19
fixtures and
117 Flush, test, and 2 wks Fri 6/28/19 Thu 7/11/19
clean piping and
fixtures
118 Electrical 139 days Mon 12/17/18
Thu 6/27/19

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 12
ID Task Task Name Duration Start Finish Mar 11, '18 May 6, '18 Jul 1, '18 Aug 26, '18 Oct 21, '18
Mode M F T S W S T M F T S W
119 Rough-in 4 wks Mon Fri 1/11/19
electrical in 12/17/18
masonry walls
120 Rough-in 4 wks Fri 4/5/19 Thu 5/2/19
electrical in
drywall walls
121 Pull wire in 3 wks Fri 4/26/19 Thu 5/16/19
conduit and set
area
transformers
122 Install and 3 wks Fri 5/17/19 Thu 6/6/19
terminate
electrical
devices
123 Make electrical 2 days Fri 5/17/19 Mon
terminations 5/20/19
for HVAC
equipment
124 Install light 2 wks Fri 6/14/19 Thu 6/27/19
fixtures - test
and clean
125 Heating and 180 days Fri 11/2/18 Thu 7/11/19
Ventilating - AC
126 Set equipment 2 wks Fri 11/2/18 Thu HVAC Contract
in mechanical 11/15/18
room

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 13
ID Task Task Name Duration Start Finish Mar 11, '18 May 6, '18 Jul 1, '18 Aug 26, '18 Oct 21, '18
Mode M F T S W S T M F T S W
127 Rough-in 4 wks Mon Fri 1/11/19
mechanical in 12/17/18
masonry walls
128 Rough-in 2 wks Fri 4/5/19 Thu 4/18/19
mechanical in
drywall walls
129 Install duct in 3 wks Fri 4/5/19 Thu 4/25/19
building chase
130 Set HVAC trim 4 wks Fri 6/14/19 Thu 7/11/19
and test and
balance system
131 Final Clean-up 60 days Fri 5/10/19 Thu 8/1/19
and Occupancy
132 Install hard tile 1 wk Fri 5/10/19 Thu 5/16/19
flooring in
common areas
133 Clean hard tile 4 days Fri 5/17/19 Wed
floors 5/22/19
134 Remove debris 4 days Fri 7/26/19 Wed
from building 7/31/19
and do final
clean-up
135 Substantial 1 day Thu 8/1/19 Thu 8/1/19
completion
136 Complete Final 6 days Thu 8/1/19 Thu 8/8/19
Inspections

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 14
ID Task Task Name Duration Start Finish Mar 11, '18 May 6, '18 Jul 1, '18 Aug 26, '18 Oct 21, '18
Mode M F T S W S T M F T S W
137 Complete 3 days Thu 8/1/19 Mon 8/5/19
elevator
inspection and
certification
138 Perform 1 day Tue 8/6/19 Tue 8/6/19
architect's
inspection
139 Perform local 1 day Wed 8/7/19 Wed 8/7/19
building agency
inspection
140 Perform Fire 1 day Thu 8/8/19 Thu 8/8/19
Marshal's
inspection
141 Complete punch 2 wks Fri 8/9/19 Thu 8/22/19
list items from all
inspections
142 Obtain certificate 2 days Fri 8/23/19 Mon
of occupancy 8/26/19
143 Issue final 1 day Fri 8/23/19 Fri 8/23/19
completion
documents
including
warranties
144 Issue final request 1 day Tue 8/27/19 Tue 8/27/19
for payment

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 15
Dec 16, '18 Feb 10, '19 Apr 7, '19 Jun 2, '19 Jul 28, '19 Sep 22, '19 Nov 17, '19 Jan 12, '20 Mar 8, '20 May 3, '20 Jun 28, '20
W S T M F T S W S T M F T S W S T M F T S W S T M

Management[25%]

Project Management

rocurement[50%]

C. Procurement[50%]

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 16
Dec 16, '18 Feb 10, '19 Apr 7, '19 Jun 2, '19 Jul 28, '19 Sep 22, '19 Nov 17, '19 Jan 12, '20 Mar 8, '20 May 3, '20 Jun 28, '20
W S T M F T S W S T M F T S W S T M F T S W S T M

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 17
Dec 16, '18 Feb 10, '19 Apr 7, '19 Jun 2, '19 Jul 28, '19 Sep 22, '19 Nov 17, '19 Jan 12, '20 Mar 8, '20 May 3, '20 Jun 28, '20
W S T M F T S W S T M F T S W S T M F T S W S T M
Contractor Management[50%],Steel Erection Contractor[50%]

Crew[10%]

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 18
Dec 16, '18 Feb 10, '19 Apr 7, '19 Jun 2, '19 Jul 28, '19 Sep 22, '19 Nov 17, '19 Jan 12, '20 Mar 8, '20 May 3, '20 Jun 28, '20
W S T M F T S W S T M F T S W S T M F T S W S T M

tor[50%]

Electric Contractor

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 19
Dec 16, '18 Feb 10, '19 Apr 7, '19 Jun 2, '19 Jul 28, '19 Sep 22, '19 Nov 17, '19 Jan 12, '20 Mar 8, '20 May 3, '20 Jun 28, '20
W S T M F T S W S T M F T S W S T M F T S W S T M
nter Crew

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 20
Dec 16, '18 Feb 10, '19 Apr 7, '19 Jun 2, '19 Jul 28, '19 Sep 22, '19 Nov 17, '19 Jan 12, '20 Mar 8, '20 May 3, '20 Jun 28, '20
W S T M F T S W S T M F T S W S T M F T S W S T M
tion Contractor

Erection Contractor

Erection Contractor[75%]

eel Erection Contractor[75%]

Steel Erection Contractor[50%]

Steel Erection Contractor[20%]

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 21
Dec 16, '18 Feb 10, '19 Apr 7, '19 Jun 2, '19 Jul 28, '19 Sep 22, '19 Nov 17, '19 Jan 12, '20 Mar 8, '20 May 3, '20 Jun 28, '20
W S T M F T S W S T M F T S W S T M F T S W S T M
G.C. Rough Carpenter Crew,G.C. Labor Crew[20%]

bor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

G.C. Concrete Crew

G.C. Labor Crew[10%]

G.C. Labor Crew

G.C. Rough Carpenter Crew[50%],G.C. Labor Crew[20%]

G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

G.C. Concrete Crew

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 22
Dec 16, '18 Feb 10, '19 Apr 7, '19 Jun 2, '19 Jul 28, '19 Sep 22, '19 Nov 17, '19 Jan 12, '20 Mar 8, '20 May 3, '20 Jun 28, '20
W S T M F T S W S T M F T S W S T M F T S W S T M
G.C. Labor Crew[10%]

G.C. Labor Crew

G.C. Rough Carpenter Crew,G.C. Labor Crew[20%]

G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

G.C. Concrete Crew


G.C. Labor Crew[10%]
G.C. Labor Crew

G.C. Rough Carpenter Crew


Electric Contractor

Plumbing Contractor

G.C. Labor Crew[33%],Plumbing Contractor[33%],Electric Contractor[33%]

G.C. Concrete Crew

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 23
Dec 16, '18 Feb 10, '19 Apr 7, '19 Jun 2, '19 Jul 28, '19 Sep 22, '19 Nov 17, '19 Jan 12, '20 Mar 8, '20 May 3, '20 Jun 28, '20
W S T M F T S W S T M F T S W S T M F T S W S T M
G.C. Labor Crew[10%]

G.C. Labor Crew

Drywall Contractor

Plumbing Contractor

Masonry Contractor

Masonry Contractor

Roofing Contractor

Tile Contractor

Masonry Contractor[50%]
Tile Contractor[50%]

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 24
Dec 16, '18 Feb 10, '19 Apr 7, '19 Jun 2, '19 Jul 28, '19 Sep 22, '19 Nov 17, '19 Jan 12, '20 Mar 8, '20 May 3, '20 Jun 28, '20
W S T M F T S W S T M F T S W S T M F T S W S T M

Roofing Contractor

Roofing Contractor

Roofing Contractor

Roofing Contractor

HVAC Contractor

Window Contractor

Drywall Contractor

G.C. Finish Carpenter Crew

Window Contractor

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 25
Dec 16, '18 Feb 10, '19 Apr 7, '19 Jun 2, '19 Jul 28, '19 Sep 22, '19 Nov 17, '19 Jan 12, '20 Mar 8, '20 May 3, '20 Jun 28, '20
W S T M F T S W S T M F T S W S T M F T S W S T M

G.C. Finish Carpenter Crew

Painting Contractor

Electric Contractor

HVAC Contractor

Drywall Contractor

Drywall Contractor

Painting Contractor
Carpet Contractor

G.C. Finish Carpenter Crew

Landscape Contractor

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 26
Dec 16, '18 Feb 10, '19 Apr 7, '19 Jun 2, '19 Jul 28, '19 Sep 22, '19 Nov 17, '19 Jan 12, '20 Mar 8, '20 May 3, '20 Jun 28, '20
W S T M F T S W S T M F T S W S T M F T S W S T M
Paving Contractor

Elevator Contractor

Elevator Contractor

Elevator Contractor

Plumbing Contractor

Plumbing Contractor

Plumbing Contractor

Plumbing Contractor

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 27
Dec 16, '18 Feb 10, '19 Apr 7, '19 Jun 2, '19 Jul 28, '19 Sep 22, '19 Nov 17, '19 Jan 12, '20 Mar 8, '20 May 3, '20 Jun 28, '20
W S T M F T S W S T M F T S W S T M F T S W S T M
Electric Contractor

Electric Contractor

Electric Contractor

Electric Contractor

Electric Contractor

Electric Contractor

HVAC Contractor

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 28
Dec 16, '18 Feb 10, '19 Apr 7, '19 Jun 2, '19 Jul 28, '19 Sep 22, '19 Nov 17, '19 Jan 12, '20 Mar 8, '20 May 3, '20 Jun 28, '20
W S T M F T S W S T M F T S W S T M F T S W S T M
HVAC Contractor

HVAC Contractor

HVAC Contractor

HVAC Contractor

Tile Contractor

Tile Contractor[50%]

G.C. Labor Crew

G.C. Superintendent

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 29
Dec 16, '18 Feb 10, '19 Apr 7, '19 Jun 2, '19 Jul 28, '19 Sep 22, '19 Nov 17, '19 Jan 12, '20 Mar 8, '20 May 3, '20 Jun 28, '20
W S T M F T S W S T M F T S W S T M F T S W S T M
Elevator Contractor

G.C. Superintendent[50%],G.C. Project Management[50%]

G.C. Project Management[50%],G.C. Superintendent[50%]

G.C. Superintendent[50%],G.C. Project Management[50%]

G.C. Superintendent[11%],G.C. Labor Crew[11%],Plumbing Contractor[11%],Electric Contractor

G.C. Project Management

G.C. Project Management

G.C. Project Management[33%],G.C. Accounting[33%],G.C. General Management[33%]

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 30
Aug 23, '20 Oct 18, '20 Dec 13, '20 Feb 7, '21 Apr 4, '21 May 30, '21 Jul 25, '21 Sep 19, '21 Nov 14, '21 Jan 9, '22 Mar 6, '22 May 1, '22
F T S W S T M F T S W S T M F T S W S T M F T S W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 31
Aug 23, '20 Oct 18, '20 Dec 13, '20 Feb 7, '21 Apr 4, '21 May 30, '21 Jul 25, '21 Sep 19, '21 Nov 14, '21 Jan 9, '22 Mar 6, '22 May 1, '22
F T S W S T M F T S W S T M F T S W S T M F T S W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 32
Aug 23, '20 Oct 18, '20 Dec 13, '20 Feb 7, '21 Apr 4, '21 May 30, '21 Jul 25, '21 Sep 19, '21 Nov 14, '21 Jan 9, '22 Mar 6, '22 May 1, '22
F T S W S T M F T S W S T M F T S W S T M F T S W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 33
Aug 23, '20 Oct 18, '20 Dec 13, '20 Feb 7, '21 Apr 4, '21 May 30, '21 Jul 25, '21 Sep 19, '21 Nov 14, '21 Jan 9, '22 Mar 6, '22 May 1, '22
F T S W S T M F T S W S T M F T S W S T M F T S W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 34
Aug 23, '20 Oct 18, '20 Dec 13, '20 Feb 7, '21 Apr 4, '21 May 30, '21 Jul 25, '21 Sep 19, '21 Nov 14, '21 Jan 9, '22 Mar 6, '22 May 1, '22
F T S W S T M F T S W S T M F T S W S T M F T S W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 35
Aug 23, '20 Oct 18, '20 Dec 13, '20 Feb 7, '21 Apr 4, '21 May 30, '21 Jul 25, '21 Sep 19, '21 Nov 14, '21 Jan 9, '22 Mar 6, '22 May 1, '22
F T S W S T M F T S W S T M F T S W S T M F T S W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 36
Aug 23, '20 Oct 18, '20 Dec 13, '20 Feb 7, '21 Apr 4, '21 May 30, '21 Jul 25, '21 Sep 19, '21 Nov 14, '21 Jan 9, '22 Mar 6, '22 May 1, '22
F T S W S T M F T S W S T M F T S W S T M F T S W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 37
Aug 23, '20 Oct 18, '20 Dec 13, '20 Feb 7, '21 Apr 4, '21 May 30, '21 Jul 25, '21 Sep 19, '21 Nov 14, '21 Jan 9, '22 Mar 6, '22 May 1, '22
F T S W S T M F T S W S T M F T S W S T M F T S W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 38
Aug 23, '20 Oct 18, '20 Dec 13, '20 Feb 7, '21 Apr 4, '21 May 30, '21 Jul 25, '21 Sep 19, '21 Nov 14, '21 Jan 9, '22 Mar 6, '22 May 1, '22
F T S W S T M F T S W S T M F T S W S T M F T S W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 39
Aug 23, '20 Oct 18, '20 Dec 13, '20 Feb 7, '21 Apr 4, '21 May 30, '21 Jul 25, '21 Sep 19, '21 Nov 14, '21 Jan 9, '22 Mar 6, '22 May 1, '22
F T S W S T M F T S W S T M F T S W S T M F T S W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 40
Aug 23, '20 Oct 18, '20 Dec 13, '20 Feb 7, '21 Apr 4, '21 May 30, '21 Jul 25, '21 Sep 19, '21 Nov 14, '21 Jan 9, '22 Mar 6, '22 May 1, '22
F T S W S T M F T S W S T M F T S W S T M F T S W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 41
Aug 23, '20 Oct 18, '20 Dec 13, '20 Feb 7, '21 Apr 4, '21 May 30, '21 Jul 25, '21 Sep 19, '21 Nov 14, '21 Jan 9, '22 Mar 6, '22 May 1, '22
F T S W S T M F T S W S T M F T S W S T M F T S W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 42
Aug 23, '20 Oct 18, '20 Dec 13, '20 Feb 7, '21 Apr 4, '21 May 30, '21 Jul 25, '21 Sep 19, '21 Nov 14, '21 Jan 9, '22 Mar 6, '22 May 1, '22
F T S W S T M F T S W S T M F T S W S T M F T S W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 43
Aug 23, '20 Oct 18, '20 Dec 13, '20 Feb 7, '21 Apr 4, '21 May 30, '21 Jul 25, '21 Sep 19, '21 Nov 14, '21 Jan 9, '22 Mar 6, '22 May 1, '22
F T S W S T M F T S W S T M F T S W S T M F T S W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 44
Aug 23, '20 Oct 18, '20 Dec 13, '20 Feb 7, '21 Apr 4, '21 May 30, '21 Jul 25, '21 Sep 19, '21 Nov 14, '21 Jan 9, '22 Mar 6, '22 May 1, '22
F T S W S T M F T S W S T M F T S W S T M F T S W

Electric Contractor[11%],HVAC Contractor[11%],Drywall Contractor[11%],Carpet Contractor[11%],Paving Contractor[11%],Painting Contractor[11%]

ment[33%]

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 45
May 1, '22 Jun 26, '22 Aug 21, '22 Oct 16, '22 Dec 11, '22 Feb 5, '23 Apr 2, '23 May 28, '23 Jul 23, '23 Sep 17, '23 Nov 12, '23 Jan 7, '24
S T M F T S W S T M F T S W S T M F T S W S T M F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 46
May 1, '22 Jun 26, '22 Aug 21, '22 Oct 16, '22 Dec 11, '22 Feb 5, '23 Apr 2, '23 May 28, '23 Jul 23, '23 Sep 17, '23 Nov 12, '23 Jan 7, '24
S T M F T S W S T M F T S W S T M F T S W S T M F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 47
May 1, '22 Jun 26, '22 Aug 21, '22 Oct 16, '22 Dec 11, '22 Feb 5, '23 Apr 2, '23 May 28, '23 Jul 23, '23 Sep 17, '23 Nov 12, '23 Jan 7, '24
S T M F T S W S T M F T S W S T M F T S W S T M F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 48
May 1, '22 Jun 26, '22 Aug 21, '22 Oct 16, '22 Dec 11, '22 Feb 5, '23 Apr 2, '23 May 28, '23 Jul 23, '23 Sep 17, '23 Nov 12, '23 Jan 7, '24
S T M F T S W S T M F T S W S T M F T S W S T M F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 49
May 1, '22 Jun 26, '22 Aug 21, '22 Oct 16, '22 Dec 11, '22 Feb 5, '23 Apr 2, '23 May 28, '23 Jul 23, '23 Sep 17, '23 Nov 12, '23 Jan 7, '24
S T M F T S W S T M F T S W S T M F T S W S T M F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 50
May 1, '22 Jun 26, '22 Aug 21, '22 Oct 16, '22 Dec 11, '22 Feb 5, '23 Apr 2, '23 May 28, '23 Jul 23, '23 Sep 17, '23 Nov 12, '23 Jan 7, '24
S T M F T S W S T M F T S W S T M F T S W S T M F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 51
May 1, '22 Jun 26, '22 Aug 21, '22 Oct 16, '22 Dec 11, '22 Feb 5, '23 Apr 2, '23 May 28, '23 Jul 23, '23 Sep 17, '23 Nov 12, '23 Jan 7, '24
S T M F T S W S T M F T S W S T M F T S W S T M F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 52
May 1, '22 Jun 26, '22 Aug 21, '22 Oct 16, '22 Dec 11, '22 Feb 5, '23 Apr 2, '23 May 28, '23 Jul 23, '23 Sep 17, '23 Nov 12, '23 Jan 7, '24
S T M F T S W S T M F T S W S T M F T S W S T M F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 53
May 1, '22 Jun 26, '22 Aug 21, '22 Oct 16, '22 Dec 11, '22 Feb 5, '23 Apr 2, '23 May 28, '23 Jul 23, '23 Sep 17, '23 Nov 12, '23 Jan 7, '24
S T M F T S W S T M F T S W S T M F T S W S T M F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 54
May 1, '22 Jun 26, '22 Aug 21, '22 Oct 16, '22 Dec 11, '22 Feb 5, '23 Apr 2, '23 May 28, '23 Jul 23, '23 Sep 17, '23 Nov 12, '23 Jan 7, '24
S T M F T S W S T M F T S W S T M F T S W S T M F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 55
May 1, '22 Jun 26, '22 Aug 21, '22 Oct 16, '22 Dec 11, '22 Feb 5, '23 Apr 2, '23 May 28, '23 Jul 23, '23 Sep 17, '23 Nov 12, '23 Jan 7, '24
S T M F T S W S T M F T S W S T M F T S W S T M F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 56
May 1, '22 Jun 26, '22 Aug 21, '22 Oct 16, '22 Dec 11, '22 Feb 5, '23 Apr 2, '23 May 28, '23 Jul 23, '23 Sep 17, '23 Nov 12, '23 Jan 7, '24
S T M F T S W S T M F T S W S T M F T S W S T M F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 57
May 1, '22 Jun 26, '22 Aug 21, '22 Oct 16, '22 Dec 11, '22 Feb 5, '23 Apr 2, '23 May 28, '23 Jul 23, '23 Sep 17, '23 Nov 12, '23 Jan 7, '24
S T M F T S W S T M F T S W S T M F T S W S T M F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 58
May 1, '22 Jun 26, '22 Aug 21, '22 Oct 16, '22 Dec 11, '22 Feb 5, '23 Apr 2, '23 May 28, '23 Jul 23, '23 Sep 17, '23 Nov 12, '23 Jan 7, '24
S T M F T S W S T M F T S W S T M F T S W S T M F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 59
May 1, '22 Jun 26, '22 Aug 21, '22 Oct 16, '22 Dec 11, '22 Feb 5, '23 Apr 2, '23 May 28, '23 Jul 23, '23 Sep 17, '23 Nov 12, '23 Jan 7, '24
S T M F T S W S T M F T S W S T M F T S W S T M F

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Commercial Constructio
Summary Manual Summary Rollup Progress
Date: Thu 5/3/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 60