Anda di halaman 1dari 2

LAPORAN PROGRES SCHEDULE KUALITAS

PEKERJAAN PLUMBING RUKO SUNCITY BIZ PORONG SAMPAI TANGGAL 30 SEPTEMBER 2017
PROYEK : GUDANG & RUKO SUN CITY BIZ PORONG
LOKASI : SIDOARJO
SUBYEK : MEKANIKAL, ELEKTRIKAL & PLUMBING ( M E & P )

BOBOT REALISASI S/D MINGGU LALU REALISASI MINGGU INI REALISASI S/D MINGGU INI
NO URAIAN PEKERJAAN Vol Stn (%) VOLUME PROGRES BOBOT VOLUME PROGRES BOBOT VOLUME PROGRES BOBOT
% % % % % %
II PEKERJAAN MEKANIKAL
1 Unit Ruko ukuran 5 x 14 m RB 2 dan RB 3
A INSTALASI AIR BERSIH GROUND TANK
1 Pipa PVC AW Ø 20 mm (3/4") dari PDAM esisting ke GWT 256.00 m' 0.3978 250.00 97.66 0.3885 - - - 250.00 97.66 0.3885
Pipa PVC AW Ø 20 mm (3/4") dari PDAM esisting ke GWT 598.00 m' 0.9773 487.00 81.44 0.7959 85.00 14.21 0.1389 572.00 95.65 0.9348
2 Pipa PVC AW Ø 20 mm (3/4") dari Roof Tank ke Jaringan 256.00 m' 0.3978 15.00 5.86 0.0233 9.00 3.52 0.0140 24.00 9.38 0.0373
Pipa PVC AW Ø 20 mm (3/4") dari Roof Tank ke Jaringan 944.00 m' 1.5428 16.00 1.69 0.0261 11.00 1.17 0.0180 27.00 2.86 0.0441
3 Pipa PVC AW Ø 25 mm (1") dari GWT ke Roof Tank 256.00 m' 0.5033 15.00 5.86 0.0295 15.00 5.86 0.0295 30.00 11.72 0.0590
Pipa PVC AW Ø 25 mm (1") dari GWT ke Roof Tank 1,184.00 m' 2.4546 16.00 1.35 0.0332 7.00 0.59 0.0145 23.00 1.94 0.0477
4 Asesories pipa PVC 60.00 bh 1.3048 30.00 50.00 0.6524 12.00 20.00 0.2610 42.00 70.00 0.9134
5 Suport pipa 60.00 bh 0.9065 20.00 33.33 0.3022 20.00 33.33 0.3022 40.00 66.67 0.6043
6 Stop kran Ø 20 mm (3/4) di Ground tank 60.00 bh 1.2040 - - - - - - - - -
7 Stop kran Ø 25 mm (1") di Poma 60.00 bh 2.0922 - - - - - - - - -
8 Plampung Ø 20 mm (3/4) 60.00 bh 1.5001 - - - - - - - - -
9 Galian & Urugan kembali 210.00 m3 1.6580 194.00 92.38 1.5316 10.00 4.76 0.0790 204.00 97.14 1.6106
B INSTALASI AIR KOTOR & AIR BEKAS - - - -
1 Pipa PVC D Ø 4 " ( Air kotor ) 288.00 m' 1.7720 268.00 93.06 1.6490 10.00 3.47 0.0615 278.00 96.53 1.7105
Pipa PVC D Ø 4 " ( Air kotor ) 1,152.00 m' 7.9900 800.00 69.44 5.5486 50.00 4.34 0.3468 850.00 73.78 5.8954
2 Pipa PVC D Ø 3 " ( Air bekas ) 288.00 m' 1.1975 224.00 77.78 0.9314 40.00 13.89 0.1663 264.00 91.67 1.0977
Pipa PVC D Ø 3 " ( Air bekas ) 1,120.00 m' 5.2141 800.00 71.43 3.7244 45.00 4.02 0.2095 845.00 75.45 3.9338
3 Pipa PVC D Ø 2 " ( Wastafel ) 240.00 m' 0.6929 20.00 8.33 0.0577 20.00 8.33 0.0577 40.00 16.67 0.1155
4 Pipa venting PVC D Ø 2 " di Biosetictenk 90.00 m' 0.2598 65.00 72.22 0.1877 15.00 16.67 0.0433 80.00 88.89 0.2310
5 Pipa venting PVC D Ø 1,5 " ( closet ) 600.00 m' 1.2034 430.00 71.67 0.8624 65.00 10.83 0.1304 495.00 82.50 0.9928
6 Asesories pipa PVC 60.00 ls 3.9607 32.00 53.33 2.1124 22.00 36.67 1.4523 54.00 90.00 3.5647
7 Suport pipa 60.00 ls 2.6629 15.00 25.00 0.6657 15.00 25.00 0.6657 30.00 50.00 1.3315
8 Galian & Urugan kembali 184.20 m3 1.4543 176.00 95.55 1.3895 4.00 2.17 0.0316 180.00 97.72 1.4211
PERALATAN SANITER - - - -
9 Bio Setictenk kap 1m3 60.00 bh 2.9212 30.00 50.00 1.4606 16.00 26.67 0.7790 46.00 76.67 2.2396
10 Floor Drain Ø 2" ( Toto ) 60.00 unit 0.1421 - - - - - - - - -
11 Closet Duduk 60.00 bh 1.1053 - - - - - - - - -
12 Hand Shower 60.00 bh 0.2369 - - - - - - - - -
13 Jet Shower 60.00 bh 0.1579 - - - - - - - - -
C INSTALASI AIR HUJAN - - - -
1 Roof Drain Ø 3 " ( besi tuang ) 60.00 bh 1.2632 - - - - - - - - -
2 Roof Drain Ø 4 " ( besi tuang ) 60.00 bh 1.6698 - - - - - - - - -
3 Floor Drain Ø 2 " ( Toto ) 60.00 bh 2.5264 - - - - - - - - -
4 Pipa PVC D Ø 3 " 540.00 m' 2.3164 276.00 51.11 1.1839 80.00 14.81 0.3432 356.00 65.93 1.5271
5 Pipa PVC D Ø 4 " 990.00 m' 6.0913 687.00 69.39 4.2270 222.00 22.42 1.3659 909.00 91.82 5.5930
6 Asesories pipa PVC 60.00 bh 2.0214 50.00 83.33 1.6845 3.00 5.00 0.1011 53.00 88.33 1.7856
7 Suport pipa 60.00 m' 1.3541 26.00 43.33 0.5868 22.00 36.67 0.4965 48.00 80.00 1.0833
8 Galian & Urugan kembali 96.00 hrg 0.7579 65.00 67.71 0.5132 15.00 15.63 0.1184 80.00 83.33 0.6316
- -
LAPORAN PROGRES SCHEDULE KUALITAS
PEKERJAAN PLUMBING RUKO SUNCITY BIZ PORONG SAMPAI TANGGAL 30 SEPTEMBER 2017
PROYEK : GUDANG & RUKO SUN CITY BIZ PORONG
LOKASI : SIDOARJO
SUBYEK : MEKANIKAL, ELEKTRIKAL & PLUMBING ( M E & P )

BOBOT REALISASI S/D MINGGU LALU REALISASI MINGGU INI REALISASI S/D MINGGU INI
NO URAIAN PEKERJAAN Vol Stn (%) VOLUME PROGRES BOBOT VOLUME PROGRES BOBOT VOLUME PROGRES BOBOT
% % % % % %
GUDANG SUN CITY BIZ PORONG Uk 12 X 36 M - -
A INSTALASI AIR BERSIH - - - - - - - - - -
1 Pipa PVC AW Ø 20 mm (3/4") dari PDAM esisting ke GWT 231.00 m' 0.3775 46.00 19.91 0.0752 46.00 19.91 0.0752 92.00 39.83 0.1504
2 Asesories pipa PVC 20.00 ls 0.0768 4.00 20.00 0.0154 2.00 10.00 0.0077 6.00 30.00 0.0230
3 Stop kran Ø 20 mm (3/4) di Ground tank 40.00 bh 0.8027 - - - - - - - - -
4 Kran 20.00 bh 0.2632 - - - - - - - - -
5 Plampung Ø 20 mm (3/4) 20.00 bh 0.5000 - - - - - - - - -
6 Galian & Urugan kembali 38.40 mᶟ 0.3032 8.00 20.83 0.0632 8.00 20.83 0.0632 16.00 41.67 0.1263
B INSTALASI AIR KOTOR & AIR BEKAS - - - - - - - - - -
1 Pipa PVC D Ø 4 " 242.00 m' 1.6785 50.00 20.66 0.3468 50.00 20.66 0.3468 100.00 41.32 0.6936
2 Pipa PVC D Ø 3 " 70.40 m' 0.3277 18.00 25.57 0.0838 18.00 25.57 0.0838 36.00 51.14 0.1676
3 Asesories pipa PVC 20.00 ls 0.1063 4.00 20.00 0.0213 4.00 20.00 0.0213 8.00 40.00 0.0425
4 Galian & Urugan kembali 43.20 mᶟ 0.3411 15.00 34.72 0.1184 15.00 34.72 0.1184 30.00 69.44 0.2369
VENTING - - -
5 Pipa venting PVC D Ø 2 " di Biosetictenk 200.00 m' 0.5774 - - -
6 Asesories pipa PVC 20.00 ls 0.1119 - - - - - - - - -
PERALATAN SANITER -
7 Bio Setictenk kap 1m3 20.00 bh 0.9737 - - - - - - - - -
8 Floor Drain Ø 2" 20.00 bh 0.0474 - - - - - - - - -
9 Closet Duduk 20.00 bh 0.3684 - - - - - - - - -
10 Hand Shower 20.00 bh 0.0790 - - - - - - - - -
INSTALASI AIR HUJAN - - - - - - - - - -
1 Pipa PVC D Ø 4 " 120.00 m' 0.8323 - - - - - - - - -
2 Pipa PVC D Ø 6 " 1,596.00 m' 19.9222 70.00 4.39 0.8738 72.00 4.51 0.8987 142.00 8.90 1.7725
3 Asesories pipa PVC 20.00 ls 4.7086 - - - 6.00 30.00 1.4126 6.00 30.00 1.4126
4 Suport pipa Air Hujan 20.00 ls 3.3505 4.00 20.00 0.6701 - - - 4.00 20.00 0.6701
5 Galian & Urugan kembali 43.20 mᶟ 0.3411 10.00 23.15 - 16.00 37.04 - 26.00 60.19 -
- - - - - - - - - -
TOTAL PEKERJAAN PLUMBING TAHAP 1 100 32.8354 10.2538 43.0892

Di setujui Di periksa Dibuat Oleh


PT. INDO PURNAMA INVESTAMA PT. INDO PURNAMA INVESTAMA CV. HARAAN I

Yusuf Prihartono Wahyu Hendratmo Abu Bachri


Proyek Manager Site Manager Proyek Manager

Anda mungkin juga menyukai