Anda di halaman 1dari 2

Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.

BANYAN GROVE INTERNAL TILING PROGRAMME OF WORKS


ID Task Name Duration Start Finish 015 Half 1, 2016 Half 2, 2016 Half 1, 2017
A S O N D J F M A M J J A S O N D J F M A M J
1 INTERNAL FLOOR & WALL TILING HIGHLIGHTED 0 days Mon 07/09/15 Mon 07/09/15
2 Programme of Work Banyan Grove 416.11 days Mon 10/08/15 Tue 06/06/17
3 Mobilization 25 days Mon 07/09/15 Tue 13/10/15
7 Construction Works 395 days Mon 10/08/15 Mon 08/05/17
8 Bulk Earthworks 30 days Wed 16/09/15 Fri 30/10/15
11 Common Basement (AB, CD, GH) 129 days Mon 10/08/15 Mon 14/03/16
30 Block AB 303 days Wed 25/11/15 Thu 06/04/17
31 Structure 185 days Wed 25/11/15 Fri 16/09/16
68 Wet Trades 158 days Thu 21/04/16 Tue 13/12/16
69 Internally 154 days Thu 21/04/16 Tue 06/12/16
70 Basement 60 days Fri 26/08/16 Fri 25/11/16
73 Ground Floor 55 days Thu 21/04/16 Mon 11/07/16
74 Partition block wall & risers 12 days Thu 21/04/16 Mon 09/05/16
75 M&E 1st & 2nd fix 15 days Fri 22/04/16 Fri 13/05/16
76 Preplaster Check 10 days Tue 03/05/16 Tue 17/05/16
77 Render wall & ceilings internal 25 days Thu 05/05/16 Fri 10/06/16
78 Suspended ceiling grid work 10 days Wed 01/06/16 Wed 15/06/16
79 Floor & wall tiles 25 days Fri 03/06/16 Mon 11/07/16
80 Completion of AB GF Floor wet trades 0 days Mon 11/07/16 Mon 11/07/16
81 1st Floor 55 days Wed 06/07/16 Mon 26/09/16
82 Partition block wall & risers 12 days Wed 06/07/16 Mon 25/07/16
83 M&E 1st & 2nd fix 15 days Thu 07/07/16 Fri 29/07/16
84 Preplaster Check 10 days Tue 19/07/16 Tue 02/08/16
85 Render wall & ceilings internal 25 days Thu 21/07/16 Fri 26/08/16
86 Suspended ceiling grid work 10 days Wed 17/08/16 Wed 31/08/16
87 Floor & wall tiles 25 days Fri 19/08/16 Mon 26/09/16
88 Completion of AB 1st Floor wet trades 0 days Mon 26/09/16 Mon 26/09/16
89 2nd Floor 52 days Fri 16/09/16 Tue 06/12/16
90 Partition block wall & risers 12 days Fri 16/09/16 Wed 05/10/16
91 M&E 1st & 2nd fix 12 days Mon 19/09/16 Thu 06/10/16
92 Preplaster Check 10 days Mon 26/09/16 Mon 10/10/16
93 Render wall & ceilings internal 25 days Wed 28/09/16 Mon 07/11/16
94 Suspended ceiling grid work 10 days Mon 24/10/16 Thu 10/11/16
95 Floor & wall tiles 25 days Wed 26/10/16 Tue 06/12/16
96 Completion of AB 2nd Floor wet trades 0 days Tue 06/12/16 Tue 06/12/16
97 Externally (Block AB) 65 days Mon 05/09/16 Tue 13/12/16
104 Finishes 167 days Thu 07/07/16 Thu 06/04/17
200 Block CD 302 days Tue 08/12/15 Mon 17/04/17
201 Structure 184 days Tue 08/12/15 Wed 28/09/16
202 Ground Floor Slab 46 days Tue 08/12/15 Wed 09/03/16
207 Superstructure 161 days Fri 29/01/16 Wed 28/09/16
236 Wet Trades 158 days Mon 02/05/16 Wed 11/01/17
237 Internally 154 days Mon 02/05/16 Thu 05/01/17
238 Basement 60 days Tue 06/09/16 Tue 06/12/16
241 Ground Floor 55 days Mon 02/05/16 Thu 21/07/16
242 Partition block wall & risers 12 days Mon 02/05/16 Wed 18/05/16
243 M&E 1st & 2nd fix 15 days Tue 03/05/16 Tue 24/05/16
244 Preplaster Check 10 days Thu 12/05/16 Fri 27/05/16
245 Render wall & ceilings internal 25 days Mon 16/05/16 Tue 21/06/16
246 Suspended ceiling grid work 10 days Fri 10/06/16 Fri 24/06/16
247 Floor & wall tiles 25 days Tue 14/06/16 Thu 21/07/16
248 Completion of CD GF Floor wet trades 0 days Thu 21/07/16 Thu 21/07/16
249 1st Floor 55 days Fri 15/07/16 Wed 05/10/16
250 Partition block wall & risers 12 days Fri 15/07/16 Wed 03/08/16
251 M&E 1st & 2nd fix 15 days Tue 19/07/16 Tue 09/08/16
252 Preplaster Check 10 days Thu 28/07/16 Thu 11/08/16
253 Render wall & ceilings internal 25 days Mon 01/08/16 Tue 06/09/16
254 Suspended ceiling grid work 10 days Fri 26/08/16 Fri 09/09/16
255 Floor & wall tiles 25 days Tue 30/08/16 Wed 05/10/16
256 Completion of CD 1st Floor wet trades 0 days Wed 05/10/16 Wed 05/10/16
257 2nd Floor 52 days Wed 28/09/16 Thu 05/01/17
258 Partition block wall & risers 12 days Wed 28/09/16 Fri 14/10/16
259 M&E 1st & 2nd fix 12 days Thu 29/09/16 Mon 17/10/16
260 Preplaster Check 10 days Wed 05/10/16 Wed 19/10/16
261 Render wall & ceilings internal 25 days Fri 07/10/16 Thu 17/11/16
262 Suspended ceiling grid work 10 days Mon 07/11/16 Tue 22/11/16
263 Floor & wall tiles 25 days Wed 09/11/16 Thu 05/01/17
264 Completion of CD 2nd Floor wet trades 0 days Thu 05/01/17 Thu 05/01/17
265 Externally (Block CD) 65 days Wed 14/09/16 Wed 11/01/17
272 Finishes 167 days Tue 19/07/16 Mon 17/04/17
365 Block GH 301 days Mon 11/01/16 Fri 28/04/17
366 Structure 184 days Mon 11/01/16 Wed 12/10/16

Task Milestone Rolled Up Critical Task Split Group By Summary


STAGE OF POW: CONSTRUCTION
UPDATED:5 October 2015 Critical Task Summary Rolled Up Milestone External Tasks Deadline
REVISION: 2 Progress Rolled Up Task Rolled Up Progress Project Summary

1
Square Deal Multi Purpose Cooperative Society Ltd MONT CHOISY PROPERTY DEVELOPMENT Ltd.
BANYAN GROVE INTERNAL TILING PROGRAMME OF WORKS
ID Task Name Duration Start Finish 015 Half 1, 2016 Half 2, 2016 Half 1, 2017
A S O N D J F M A M J J A S O N D J F M A M J
367 Ground Floor Slab 46 days Mon 11/01/16 Thu 24/03/16
372 Superstructure 161 days Tue 16/02/16 Wed 12/10/16
401 Wet Trades 158 days Mon 16/05/16 Wed 25/01/17
402 Internally 154 days Mon 16/05/16 Thu 19/01/17
403 Basement 60 days Wed 21/09/16 Tue 10/01/17
406 Ground Floor 55 days Mon 16/05/16 Thu 04/08/16
407 Partition block wall & risers 12 days Mon 16/05/16 Thu 02/06/16
408 M&E 1st & 2nd fix 15 days Tue 17/05/16 Wed 08/06/16
409 Preplaster Check 10 days Fri 27/05/16 Fri 10/06/16
410 Render wall & ceilings internal 25 days Tue 31/05/16 Wed 06/07/16
411 Suspended ceiling grid work 10 days Fri 24/06/16 Mon 11/07/16
412 Floor & wall tiles 25 days Tue 28/06/16 Thu 04/08/16
413 Completion of GH GF Floor wet trades 0 days Thu 04/08/16 Thu 04/08/16
414 1st Floor 55 days Mon 01/08/16 Wed 19/10/16
415 Partition block wall & risers 12 days Mon 01/08/16 Thu 18/08/16
416 M&E 1st & 2nd fix 15 days Tue 02/08/16 Wed 24/08/16
417 Preplaster Check 10 days Thu 11/08/16 Fri 26/08/16
418 Render wall & ceilings internal 25 days Tue 16/08/16 Tue 20/09/16
419 Suspended ceiling grid work 10 days Fri 09/09/16 Mon 26/09/16
420 Floor & wall tiles 25 days Tue 13/09/16 Wed 19/10/16
421 Completion of GH 1st Floor wet trades 0 days Wed 19/10/16 Wed 19/10/16
422 2nd Floor 52 days Wed 12/10/16 Thu 19/01/17
423 Partition block wall & risers 12 days Wed 12/10/16 Mon 31/10/16
424 M&E 1st & 2nd fix 12 days Thu 13/10/16 Thu 03/11/16
425 Preplaster Check 10 days Wed 19/10/16 Mon 07/11/16
426 Render wall & ceilings internal 25 days Fri 21/10/16 Thu 01/12/16
427 Suspended ceiling grid work 10 days Tue 22/11/16 Tue 06/12/16
428 Floor & wall tiles 25 days Thu 24/11/16 Thu 19/01/17
429 Completion of GH 2nd Floor wet trades 0 days Thu 19/01/17 Thu 19/01/17
430 Externally (Block GH) 65 days Thu 29/09/16 Wed 25/01/17
437 Finishes 166 days Tue 02/08/16 Fri 28/04/17
530 Block EF 336 days Thu 08/10/15 Mon 10/04/17
531 Structure 218 days Thu 08/10/15 Tue 20/09/16
576 Wet Trades 227 days Thu 07/01/16 Thu 15/12/16
577 Internally 223 days Thu 07/01/16 Thu 08/12/16
578 Ground Floor 119 days Thu 07/01/16 Wed 06/07/16
579 Partition block wall & risers 12 days Fri 15/04/16 Wed 04/05/16
580 Appointment of Conceal Mixer Supplier 0 days Thu 07/01/16 Thu 07/01/16
581 M&E 1st & 2nd fix 15 days Tue 19/04/16 Tue 10/05/16
582 Preplaster Check 10 days Thu 28/04/16 Thu 12/05/16
583 Render wall & ceilings internal 25 days Mon 02/05/16 Tue 07/06/16
584 Appointment of Suspended Ceiling Subcontractor 0 days Wed 23/03/16 Wed 23/03/16
585 Suspended ceiling grid work 10 days Fri 27/05/16 Fri 10/06/16
586 Appointment of Floor and Wall tile Supplier 0 days Mon 22/02/16 Mon 22/02/16
587 Floor & wall tiles 25 days Tue 31/05/16 Wed 06/07/16
588 Completion of EF GF wet works 0 days Wed 06/07/16 Wed 06/07/16
589 1st Floor 55 days Fri 08/07/16 Wed 28/09/16
590 Partition block wall & risers 12 days Fri 08/07/16 Wed 27/07/16
591 M&E 1st & 2nd fix 15 days Mon 11/07/16 Tue 02/08/16
592 Preplaster Check 10 days Thu 21/07/16 Thu 04/08/16
593 Render wall & ceilings internal 25 days Mon 25/07/16 Tue 30/08/16
594 Suspended ceiling grid work 10 days Fri 19/08/16 Fri 02/09/16
595 Floor & wall tiles 25 days Tue 23/08/16 Wed 28/09/16
596 Completion of EF 1st floor wet works 0 days Fri 02/09/16 Fri 02/09/16
597 2nd Floor 52 days Wed 21/09/16 Thu 08/12/16
598 Partition block wall & risers 12 days Wed 21/09/16 Fri 07/10/16
599 M&E 1st & 2nd fix 12 days Thu 22/09/16 Mon 10/10/16
600 Preplaster Check 10 days Wed 28/09/16 Wed 12/10/16
601 Render wall & ceilings internal 25 days Fri 30/09/16 Wed 09/11/16
602 Suspended ceiling grid work 10 days Wed 26/10/16 Tue 15/11/16
603 Floor & wall tiles 25 days Mon 31/10/16 Thu 08/12/16
604 Completion of EF 2nd floor wet works 0 days Thu 08/12/16 Thu 08/12/16
605 Externally (Block E & F) 65 days Wed 07/09/16 Thu 15/12/16
612 Finishes 244 days Fri 18/03/16 Mon 10/04/17
713
714 External Works Blocks A, B, C & D 376 days Mon 07/09/15 Mon 08/05/17
806
807 Final Handover of Works 360.11 days Fri 30/10/15 Tue 06/06/17
900
908

Task Milestone Rolled Up Critical Task Split Group By Summary


STAGE OF POW: CONSTRUCTION
UPDATED:5 October 2015 Critical Task Summary Rolled Up Milestone External Tasks Deadline
REVISION: 2 Progress Rolled Up Task Rolled Up Progress Project Summary

Anda mungkin juga menyukai