ITEM PEMBAYARAN NO. : 1.

2
JENIS PEKERJAAN : Mobilisasi

% TERHADAP TOTAL BIAYA PROYEK = 19.27 %


Lembar 1.2-1
HARGA JUMLAH
No. URAIAN SATUAN VOL. SATUAN HARGA
(Rp.) (Rp.)

A. Sewa Tanah M2 - - -

B. PERALATAN
Periksa lembar 1.2-2 5,000,000.00

C. FASILITAS KONTRAKTOR
1 Direksi Keet M2 - - -

D. FASILITAS LABORATORIUM
1 Ruang Laboratorium (sesuai Gambar) M2 - - -

E. MOBILISASI LAINNYA
E.I. PEKERJAAN DARURAT
1 Perkuatan Jembatan Lama Ls - -
2 Pemeliharaan Jalan Kerja / Samping Ls - -
3 ...................... .... - -
4 ...................... .... - -
5 ...................... .... - -
6 ...................... .... - -

E.II. LAIN-LAIN
1 Laporan Set 1.00 415,900.00 415,900.00
2 Dokumentasi/Administrasi Ls 1.00 351,650.00 351,650.00
3 As Built Drawing Ls 1.00 - -
4 Jasa Laboratorium Ls 1.00 - -
5 Pengukuran Ls 1.00 - -
6 Papan Proyek Bh 1.00 435,000.00 435,000.00

F. DEMOBILISASI Ls 1.00 5,000,000.00 5,000,000.00

Total Biaya Mobilisasi 11,202,550.00

Catatan : Jumlah yang tercantum pada masing-masing item mobilisasi di atas sudah termasuk over-head dan laba
serta seluruh pajak dan bea (kecuali PPn), dan pengeluaran lainnya.
ITEM PEMBAYARAN NO. : 1.2
JENIS PEKERJAAN : Mobilisasi
Lembar 1.2-2
KODE HARGA JUMLAH
No. JENIS ALAT ALAT SATUAN VOL. SATUAN HARGA
(Rp.) (Rp.)

B. PERALATAN

1 EXCAVATOR 80-140 HP E10 Unit 1.00 5,000,000.00 5,000,000.00

Total untuk Item B pada Lembar 1 5,000,000.00