Selesai Pekerjaan Pondasi Tower
Selesai Pekerjaan Pondasi Tower
Tower #10 (AA6+3, 32piles, 6.9m) 16 days Thu 8/25/16 Fri 9/9/16
Tower #11 (AA6+6, 32piles, 10.1m) 18 days Fri 9/23/16 Mon 10/10/16
Tower #12 (AA6+0, 32piles, 8.5m) 24 days Tue 5/30/17 Thu 6/22/17
Tower #08 (AA6+6, 32piles, 7.5m) 33 days Sat 7/1/17 Wed 8/2/17
Tower #07 (BB6+3, 40piles, 9.1m) 23 days Fri 8/11/17 Sat 9/2/17
Tower #03 (BB6+6, 40piles, 8.1m) 24 days Tue 10/10/17 Thu 11/2/17
Tower #14 (BB6+3, 40piles, 5.5m) 15 days Sat 9/9/17 Sat 9/23/17
Tower #20A (CC6+6, 100 Piles) 27 days Wed 10/4/17 Mon 10/30/17
Tower #02 (BB6+9, 40piles, 6.7m) 20 days Fri 9/15/17 Wed 10/4/17
Foundation
Task Name Duration Start Finish