062131 B173846-023-PR-101
TOYO-THAI CORPORATION
PUBLIC COMPANY METED
CALCULATION SHEET FOR PIPE BRIDGE
AT 6 KV (MODIFICATION)
Au 15, 12 Rev.1
1. DESIGN CRITERIA
1.1 Title
1.1.1 The steel structure calculated here after is for Pipe Bridge
1.1.2 The calculation consider only steel structure because owner do not have information for
existing sizing of foundation, therefor the calculation do not consider existing foundation.
1.1.3 The loading for design steel structure base on Job D-128 Everest Project
Steel structure.
AT 6 KV (MODIFICATION)
Aug 15, 1.2 Rev.1
• Structure Steel
1.5 Materials
• Concrete
• Structural steel
AT 6 KV (MODIFICATION)
Aug 15, 12 Rev.1
Not applicable.
• The velocity pressure (qz) shall be calculated from the following equations refer to.
0-4.6 75 0.85
6.1 80 0.90
7.6 83 0.94
9.1 86 0.98
12.2 92 1.04
15.2 96 1.09
Body load shall mean the total selfweight of the structure, and/ or foundations.
Dead load shall mean all materials permanently attached thereto or supported thereby.
AT 6 KV (MODIFICATION)
Aug 1 .2 Rev.1
- Pipe larger than 12 inch diameter shall be considered as concentrated loads in their actual
location.
- Pipe larger than 12 inch diameter shall be considered as concentrated loads in their actual
location.
- Vertical test load on structures or piperacks supporting up to four pipes must be taken as
the total weight of water in all pipes.
- Vertical test load on structures or piperacks supporting more than four pipes must be
designed with 50% of pipes full of water apply to produce maximum stress.
- For anchor bay of piperacks, the horizontal force shall be taken as the greater of ;
a) Anchor force from pipe stress calculation.
b) 10% of piping vertical loads from 4 bay length.
- 30% of the operating vertical pipe loads acting longitudinally for less than 4 pipes.
BANGKOK 0 THAILAND WINDMILL - CHAIYAPREUK PROJECT
alai B173846-023-PR-101
TOYO-THAI CORPORATION
PUBLIC COMPANY LIMITED CALCULATION SHEET FOR PIPE BRIDGE
AT 6 KV (MODIFICATION)
Aug 15, 12 Rev.1
Buildings
For buildings, imposed loads on floors shall be the actual loads when these are known, but in any
case shall not be less than the distributed loads given below or the minimum requirements imposed by
ASCE 7-05 ;
qk Qk(*)
Description
(kg/m2) (kg)
: All member shall be checked for an alternative point or concentrated load (Qk) to be applied
over a square of side 300 mm.
BANGKOK THAILAND WINDMILL - CHAIYAPREUK PROJECT
twitz B173846-023-PR-101
TOYO-T A/APO TION
PUBLIC COMPANY LIMITED CALCULATION SHEET FOR PIPE BRIDGE
AT 6 KV (MODIFICATION)
Aug 15, 12 Rev.1
qk Qk(*)
Description
(kg/m2) (kg)
Steel floor plates (Chequered plate and open grid flooring) 400 500
Minor platforms, walkways and floors used for access only 150 250
Ladder rungs - 90
AT 6 KV (MODIFICATION)
Aug15, 1.2 Rev.1
o Empty Erection
o Test
AT 6 KV (MODIFICATION)
Aug 15, 2 Rev.1
o Test
o Empty Erection
AT 6 KV (MODIFICATION)
Aug 15, 12 Rev.1
3. OTHER REQUIREMENTS
3.2.1 The average allowable uniform maximum settlement shall not exceed the following ;
Shall comply with the requirements of thailand national building regulations but shall not be
greater than:
A) Buildings
Short term Long term
B) Process plant
Short term Long term
Short ter InITIWI gettlemM.-ShrirT Term ttl et a-ritigre ore to be .etermined 'by test n
accordance with piling design guide.
Long term is consolidation settlement 1 to 10 years.
3.2.2 The maximum allowable differential settlement of foundations shall be limited to the
following ;
A) Buildings
Reinforced concrete structure with masonry infill, 0.001 to 0.002 L
single or two storey building on ground bearing
foundations.
B) Process plant
Continuous steel structure framing system 0.002 L
on ground bearing foundations.
"L" denotes the distance between two adjacent columns or two any points showing a
differential settlement. lowest figures shall be adopted for most sensitive structures to
differential settlement.
A) Lateral deflection
Maximum allowable lateral deflection of structural frames and buildings ;
Where ; H and Ho are respectively (Height between levels) and (Total height of structure).
B) Beam deflection
Maximum allowable deflection of beam and under total vertical load shall be ;
4. CALCULATION