BACK UP DATA QUANTITY

SATUAN KERJA : DINAS KEHUTANAN PROVINSI SULAWESI TENGAH


PEKERJAAN : PEMBUATAN SELOKAN RUMAH DINAS KEHUTANAN PROPINSI SULAWESI TENGAH
LOKASI : JL. S. PARMAN NO. 09 PALU
TAHUN ANGGARAN : 2018

No. Item Pekerjaan Sketsa Uraian Perhitungan Volume

A. PEKERJAAN SALURAN TYPE 30/25

1. Pek. Galian Sedalam < 1 meter = a x b x P


= 0.3 x 0.6 x 129
= 23.2 M³

2. Pek. Urugan Pasir Bawah Lantai = a x b x P


= 0.05 x 0.25 x 129
= 1.61 M³

3. Pek. Pondasi Batu kali 1 Pc : 4 Psr = ( a + b ) x c x P x 2


2
= ( 0.15 + 0.17 ) x 0.37 x 129 x 2
2
= 15.3 M³

4. Pek. Cor Lantai Saluran, T = 0,05 = a x b x P


= 0.05 x 0.25 x 129
= 1.61 M³
5. Pek. Plesteran 1 Pc : 3 Psr = ( a + b + c + d ) x P
= ( 0.15 + 0.26 + 0.26 + 0.15 ) x 129
= 106 M²

6. Pek. Acian = ( a + b + c + d ) x P
= ( 0.15 + 0.26 + 0.26 + 0.15 ) x 129
= 106 M²
B. PEKERJAAN SALURAN TYPE 50/40

1. Pek. Galian Sedalam < 1 meter = a x b x P


= 0.6 x 0.9 x 242
= 131 M³

2. Pek. Urugan Pasir Bawah Lantai = a x b x P


= 0.05 x 0.4 x 242
= 4.83 M³

3. Pek. Pondasi Batu kali 1 Pc : 4 Psr = ( a + b ) x c x P x 2


2
= ( 0.2 + 0.25 ) x 0.67 x 242 x 2
2
= 72.9 M³

4. Pek. Cor Lantai Saluran, T = 0,05 = a x b x P


= 0.05 x 0.4 x 242
= 4.83 M³
5. Pek. Plesteran 1 Pc : 3 Psr = ( a + b + c + d ) x P
= ( 0.2 + 0.57 + 0.57 + 0.2 ) x 242
= 372 M²

6. Pek. Acian = ( a + b + c + d ) x P
= ( 0.2 + 0.57 + 0.57 + 0.2 ) x 242
= 372 M²