Design And Manufacture Of

5-Stage High Speed Progression


Tool For lamination
Project work
at

Crompton Greaves Ltd.,


by

S.Rama Murthy
IV semester
Postgraduate in Tool Engineering
2003 – 2004

External guide Internal guide

Mr. S.V.Karnik Mr.R.Venkatesh


Design Manager Associate Principal, SPG,
Crompton Greaves Limited, N.T.T.F
Mumbai., Bangalore.,

SCHOOL OF POSTGRADUATE STUDIES


NETTUR TECHNICAL TRAINING FOUNDATION
BANGALORE-560058
SCHOOL OF POSTGRADUATE STUDIES

CERTIFICATE

This project is the work done by Mr. S.RAMA MURTHY & submitted in
partial fulfillment of the requirements for the award of Postgraduate
Degree in Tool Engineering.

Title : DESIGN & MANUFACTURING OF 5-STAGE HIGH


SPEED PROGRESSION TOOL FOR LAMINATIONS

Batch : 2003-2004

Signature of the student:

Guide(s)
(Name & Signature) :

Examiner(s)
(Name & Signature) :
Acknowledgment
I am grateful for the opportunity provided by the management of
CROMPTON GREAVES LTD., Mumbai for carrying out this project
at their works. I am equally grateful to the School of Post Graduate
Studies, NTTF, Bangalore for the support extended towards this
project work.

I profusely thank my guide Mr. S.V.Karnik, Design Head for his


constant guidance & support during this project work. I articulate my
sincere thanks to Mr. Bala Krishnan, Senior Tool Room Executive
Senior for his exceptional support and coordination throughout this
project.

I am very happy to thank all the members those who are


working in CROMPTON GREAVES LTD., for their kind support
during this project work.

I would like to thank Mr.R.Venkatesh, Associate Principal & Dr.


N. Ramani, Principal, School of Post Graduate Studies, NTTF,
Bangalore, for his guidance & encouragement in course of
completion of this project work. I would like to thank all the members
of School of Post Graduate Studies, NTTF, Bangalore, for their
support extended. Finally, I extend my indebtedness to all those
who were directly or indirectly responsible for the successful
completion of this project work.

s.rama murthy
Synopsis

The project was undertaken at Crompton Greaves Ltd., is the one of


the leader in lamination production & has in-house tool manufacturing
facility.

During project period I have worked in the following areas:


• Design and manufacturing of 5-stage high-speed progression
tool.
• Design of segmental compound blanking tool with cut and carry.
• Design of segmental blanking tool with cut and carry.
• Modification of existing tool.

Amongst all, Design and manufacturing of 5-stage high-speed


progression tool is taken as the core project

The Tool is designed and manufactured for Newage, England.


Since to meet the production requirement progression was best
process.

Component study

Design Layout (strip layout)

Design calculation

Assembly and Detail Drawing

Manufacture of tools

Assembly & try out


CONTENTS

1. INTRODUCTION 1

2. PROJECT ALLOCATION 3

3. COMPANY PROFILE 4

4. LITERATURE SURVEY 11

5.CUSTOMER REQUIREMENT 28

6. MATERIAL SELECTION 32

7. DESIGN CALCULATION 37

8.TOOL MANUFACTURING PROCESS 64

9. CONCLUSION 73

10.BIBILOGRAPHY 74