Anda di halaman 1dari 142

Planning and Design WS

Reservoir Sizing

Name of Sub-Project Construction of Pinanag-an Level I Water System (Gravity Driven)


Sub-project Type Creek Source
Municipality Borongan City
Province Eastern Samar
Region VIII

I -DESIGN OF RESERVOIR:

A. Reason for installing a reservoir


To balance the supply and demand in the system, pressure breaker, fire hydrant reserve, settling or point of
disinfection.
Source discharge = 0.5 lps. Average Source Flow (ASF)
Demand (users) = 0.377 lps. Average Day Demand (ADD)

B. Location of the reservoir


Invert elevation = 176 m. (from plan and survey data)

Reason for choosing the location.


The reservoir is lower than the spring and generally higher than the distribution areas.

C. Capacity of the reservoir

Criteria:
Particular Description Data
Number of Household Actual number of household beneficiaries 86
Average Household Member 6 members 6
Total Population (No. of HH)(Ave. HH Member) 516
Average Population Growth Rate Percent annualy 0.03
Design Lifespan No. of years 10
Design Population (Total Population)(1+PGR)^life span 693
Average Daily Water Demand liters per capita per day 47
per Capita per Day
Average Daily Demand (ADD) (Design population)(ADWD/capita/day) 32,593
Average Demand per Second ADD/(24x60x60) 0.377

Consumption Standards 30 to 60 lps per capita per day demand for level 2
Design Period 5-15 years

Reservoir capacity:

1) By rule of thumb

Reservoir capacity = 1/4 (ADD)


= ADD/(4x1000)
= 8.15 cu.m.
2) By theory

Reservoir capacity = (Demand-Supply)(Ave. Day Length)


= (ADD-ASF)(60)(60)(12)/1000
= (5.30) cu.m.
3) Considering spring flow (100%)

Reservoir capacity = (Spring discharge)(Ave. Day Length)


= (ASF)(60)(60)(12)/1000
= 21.60 cu.m.
4) Adopted result

Reservoir capacity = 8.15 cu.m.

5) Reason for adoption


Use an average reservoir capacity which could meet the demand for the design period
and minimal investment cost consideration.

6) Reservoir dimension

Dimension (r.cap.)^1/3 = 2.01 cum


use

KALAHI-CIDSS PROJECT
Joey P. Zalavarria
Planning and Design WS
Reservoir Sizing

Length 2.01 = 2.01 m. 2.10 m.


Breadth 2.01 = 2.01 m. 2.10 m.
Height 2.01 = 2.31 m. 2.40 m.
Freeboard 0.20
Dead vol. Ht. 0.10

Therefore width length height


Use reservoir dimension = 2.10 2.10 2.40
Actual reservoir capacity = 9.26 cu.m.
Note: Computed dimension is INSIDE DIMENSION. 1.11 if + answer the size is OK

ECONOMICAL STORAGE CAPACITY


Simple Ratio Method
Calculate the ratio (R) of the average source flow (ASF) (for spring sources) over the
Average Day Demand and refer to the table below:
R = ASF ÷ ADD TIME FACTOR ANALYSIS

Minimum Time to Fill


Balancing Reservoir
Ratio Storage Capacity Ratio (in hours)
< 1.0 inadequate source
1.0-2.0 ½ of the average daily used
2.0-3.0 ¼ of the average daily used 1.32545 5.15
3.0-4.0 1/8
of the average daily used
> 4.0 no storage facility required

Note: The source above in the sample is inadequate and to balance the demand and supply-the minimum
required hours to fill a balancing reservoir is 5.15 hours

DEMAND-SUPPLY ANALYSIS BASED ON THE AVERAGE DAILY DEMAND (ADD)

DEFICIT(__)
YEAR DEMAND SUPPLY RESERVOIR SURPLUS
1 24,979.56 43,200.00 9,261.00 27,481.44
2 25,728.95 43,200.00 9,261.00 26,732.05
3 26,500.82 43,200.00 9,261.00 25,960.18
4 27,295.84 43,200.00 9,261.00 25,165.16
5 28,114.71 43,200.00 9,261.00 24,346.29
6 28,958.16 43,200.00 9,261.00 23,502.84
7 29,826.90 43,200.00 9,261.00 22,634.10
8 30,721.71 43,200.00 9,261.00 21,739.29
9 31,643.36 43,200.00 9,261.00 20,817.64
10 32,592.66 43,200.00 9,261.00 19,868.34
11 33,570.44 43,200.00 9,261.00 18,890.56
12 34,577.55 43,200.00 9,261.00 17,883.45
13 35,614.88 43,200.00 9,261.00 16,846.12
14 36,683.33 43,200.00 9,261.00 15,777.67
15 37,783.83 43,200.00 9,261.00 14,677.17

Note: Recommendation is to look for additional water source on the 4rth year or decrease water consumption per capita
per day or reduce household to be served etc…can no longer increase size of tank since beyond 12 hours filling already

MASS DIAGRAM METHOD OF ANALYSIS (RESERVOIR SIZING) FROM WATER DEMAND VARIATION:

HOURLY CUMULATIVE
DEMAND HOURLY DEMAND SUPPLY MINUS
TIME ADD RATIO (liters) (liters) SUPPLY (liters/hour) DRAFT (liters)
1 0.32 434.57 434.57 1,800.00 1,365.43
2 0.38 516.05 950.62 1,800.00 1,283.95
3 0.39 529.63 1,480.25 1,800.00 1,270.37
4 0.33 448.15 1,928.40 1,800.00 1,351.85
5 0.48 651.85 2,580.25 1,800.00 1,148.15
6 0.95 1,290.13 3,870.38 1,800.00 509.87
7 1.93 2,620.99 6,491.37 1,800.00 (820.99)
8 2.06 2,797.54 9,288.91 1,800.00 (997.54)

KALAHI-CIDSS PROJECT
Joey P. Zalavarria
Planning and Design WS
Reservoir Sizing

9 1.98 2,688.89 11,977.80 1,800.00 (888.89)


10 1.58 2,145.68 14,123.49 1,800.00 (345.68)
11 1.89 2,566.67 16,690.16 1,800.00 (766.67)
12 1.29 1,751.86 18,442.01 1,800.00 48.14
13 1.23 1,670.37 20,112.39 1,800.00 129.63
14 0.95 1,290.13 21,402.51 1,800.00 509.87
15 0.99 1,344.45 22,746.96 1,800.00 455.55
16 0.96 1,303.71 24,050.67 1,800.00 496.29
17 1.07 1,453.09 25,503.76 1,800.00 346.91
18 1.33 1,806.18 27,309.93 1,800.00 (6.18)
19 1.36 1,846.92 29,156.85 1,800.00 (46.92)
20 0.87 1,181.48 30,338.33 1,800.00 618.52
21 0.64 869.14 31,207.47 1,800.00 930.86
22 0.54 733.33 31,940.81 1,800.00 1,066.67
23 0.42 570.37 32,511.18 1,800.00 1,229.63
0 0.38 516.05 33,027.23 1,800.00 1,283.95

The storage capacity required is the sum of the positive storage variation and negative
variation
Total Capacity in liters
Total Capacity in cubic meters

6) Reservoir dimension

Dimension (r.cap.)^1/3 = 2.04 m.


use
Length 2.04 = 2.04 m. 2.10 m.
Breadth 2.04 = 2.04 m. 2.10 m.
Height 2.04 = 2.34 m. 2.40 m.
Freeboard 0.20
Dead vol. Ht. 0.10

Therefore width length height


Use reservoir dimension = 2.10 2.10 2.40
Actual reservoir capacity = 9.26 cu.m.
Note: Computed dimension is INSIDE DIMENSION. 0.76 if + answer the size is OK

ECONOMICAL STORAGE CAPACITY


Simple Ratio Method
Calculate the ratio (R) of the average source flow (ASF) (for spring sources) over the
Average Day Demand and refer to the table below:
R = ASF ÷ ADD TIME FACTOR ANALYSIS

Minimum Time to Fill


Ratio Storage Capacity Ratio Balancing Reservoir
(in hours)

< 1.0 inadequate source


1.0-2.0 ½ of the average daily used
2.0-3.0 ¼ of the average daily used 1.32545 5.15
3.0-4.0 1/8
of the average daily used
> 4.0 no storage facility required

Note: The source above in the sample is inadequate and to balance the demand and supply-the minimum
required hours to fill a balancing reservoir is 5.15 hours

2.5

1.5
Ratio to ADD

1 TIME
Colum
Colum
ADD R
KALAHI-CIDSS 0.5
PROJECT
Joey P. Zalavarria

0
Ratio to ADD
Planning and Design WS
Reservoir Sizing1 TIME
Colum
Colum
ADD R
0.5

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Time (Hours)

TYPICAL WATER DEMAND VARIATION

KALAHI-CIDSS PROJECT
Joey P. Zalavarria
Planning and Design WS
Reservoir Sizing

avity Driven)

ng or point of

Unit
HH
No.
No.
%
Years
No.
Liter

Liter
LPS

KALAHI-CIDSS PROJECT
Joey P. Zalavarria
Planning and Design WS
Reservoir Sizing

er the size is OK

ACTOR ANALYSIS

Minimum Time to Fill


Balancing Reservoir
(in hours)

5.15

REMARKS

Start of deficit on the


4rth year

sumption per capita


ond 12 hours filling already

STORAGE
VARIATION (liters)
1,365.43
2,649.38
3,919.75
5,271.60
6,419.75
6,929.62
6,108.63
5,111.09

KALAHI-CIDSS PROJECT
Joey P. Zalavarria
Planning and Design WS
Reservoir Sizing

4,222.20
3,876.51
3,109.84
3,157.99
3,287.61
3,797.49
4,253.04
4,749.33
5,096.24
5,090.07
5,043.15
5,661.67
6,592.53
7,659.19
8,888.82
10,172.77

5,397.48
3,103.47
8,500.95
8.50

er the size is OK

ACTOR ANALYSIS

Minimum Time to Fill


Balancing Reservoir
(in hours)

5.15

TIME
Column B
Column C
ADD RATIO
KALAHI-CIDSS PROJECT
Joey P. Zalavarria
Planning and Design WS
Reservoir TIME
Sizing
Column B
Column C
ADD RATIO

24

KALAHI-CIDSS PROJECT
Joey P. Zalavarria
Planning and Design WS
Reservoir Sizing

KALAHI-CIDSS PROJECT
Joey P. Zalavarria
Planning and Design WS
Reservoir Sizing

KALAHI-CIDSS PROJECT
Joey P. Zalavarria
Planning and Design WS
Reservoir Sizing

KALAHI-CIDSS PROJECT
Joey P. Zalavarria
Annex 1

Name of Sub-Project Construction of Pinanag-an Level I Water System (Gravity Driven)


Sub-project Type Groundwater Source
Municipality Borongan City
Province Eastern Samar
Region VIII

I -DESIGN OF RESERVOIR:

A. Reason for installing a reservoir


To balance the supply and demand in the system, pressure breaker, fire hydrant reserve, settling or point of
disinfection.
As measured Equivalent Discharge for 8 hours pumping
Pump Discharge = 1.28 0.426667 lps.
Demand (users) = 0.45 lps. Average Day Demand (ADD)

B. Location of the reservoir


Invert elevation = 5 m. (from plan and survey data)

Reason for choosing the location.


The reservoir is lower than the spring and generally higher than the distribution areas.

C. Capacity of the reservo

Criteria:
Particular Description
Number of Household Actual number of household beneficiaries
Average Household Member 6 members
Total Population (No. of HH)(Ave. HH Member)
Average Population Growth Rate Percent annualy
Design Lifespan No. of years
Design Population (Total Population)(1+PGR)^life span
Average Daily Water Demand liters per capita per day
per Capita per Day
Average Daily Demand (ADD) (Design population)(ADWD/capita/day)
Average Demand per Second ADD/(24x60x60)

Consumption Standards 30 to 60 lps per capita per day demand for level 2
Design Period 5-15 years

Reservoir capacity:

1) By rule of thumb

Reservoir capacity = 1/4 (ADD)


= ADD/(4x1000)
= 9.74 cu.m.
2) By theory

Reservoir capacity = (Demand-Supply)(Ave. Day Length)


= (ADD-ASF)(60)(60)(12)/1000
= 1.04 cu.m.
3) Considering spring flow (100%)

Reservoir capacity = (Spring discharge)(Ave. Day Length)


= (ASF)(60)(60)(12)/1000
= 18.43 cu.m.
4) Adopted result

Reservoir capacity = 9.74 cu.m.

5) Reason for adoption


Use an average reservoir capacity which could meet the demand for the design period
and minimal investment cost consideration.

6) Reservoir dimension

Dimension (r.cap.)^1/3 = 2.14 cum


use
Length 2.14 = 2.14 m. 2.20 m.
Breadth 2.14 = 2.14 m. 2.20 m.
Height 2.14 = 2.44 m. 2.50 m.
Freeboard 0.20
Dead vol. Ht. 0.10

Therefore width length height


Use reservoir dimension = 2.20 2.20 2.50
Actual reservoir capacity = 10.65 cu.m.
Note: Computed dimension is INSIDE DIMENSION. 0.91 if + answer the size is OK

ECONOMICAL STORAGE CAPACITY


Simple Ratio Method
Calculate the ratio (R) of the average source flow (ASF) (for spring sources) over the
Average Day Demand and refer to the table below:
R = ASF ÷ ADD

Ratio Storage Capacity Ratio

< 1.0 inadequate source


1.0-2.0 ½ of the average daily used
2.0-3.0 ¼ of the average daily used 0.94652
3.0-4.0 1/8
of the average daily used
> 4.0 no storage facility required

Note: The source above in the sample is inadequate and to balance the demand and supply-the minimum
required hours to fill a balancing reservoir is 6.93 hours

DEMAND-SUPPLY ANALYSIS BASED ON THE AVERAGE DAILY DEMAND (ADD)

DEFICIT(__)
YEAR DEMAND SUPPLY RESERVOIR SURPLUS
1 29,849.40 36864 10,648.00 17,662.60
2 30,744.88 36864 10,648.00 16,767.12
3 31,667.23 36864 10,648.00 15,844.77
4 32,617.25 36864 10,648.00 14,894.75
5 33,595.76 36864 10,648.00 13,916.24
6 34,603.64 36864 10,648.00 12,908.36
7 35,641.74 36864 10,648.00 11,870.26
8 36,711.00 36864 10,648.00 10,801.00
9 37,812.33 36864 10,648.00 9,699.67
10 38,946.70 36864 10,648.00 8,565.30
11 40,115.10 36864 10,648.00 7,396.90
12 41,318.55 36864 10,648.00 6,193.45
13 42,558.11 36864 10,648.00 4,953.89
14 43,834.85 36864 10,648.00 3,677.15
15 45,149.90 36864 10,648.00 2,362.10

Note:

MASS DIAGRAM METHOD OF RESERVOIR SIZING (Equivalent 8 hours Pumping spread over 24 hours)

HOURLY CUMULATIVE
DEMAND HOURLY DEMAND SUPPLY MINUS
TIME ADD RATIO (liters) (liters) SUPPLY (liters/hour) DRAFT (liters)
1 0.32 519.29 519.29 1,536.00 1,016.71
2 0.38 616.66 1,135.95 1,536.00 919.34
3 0.39 632.88 1,768.83 1,536.00 903.12
4 0.33 535.52 2,304.35 1,536.00 1,000.48
5 0.48 778.93 3,083.28 1,536.00 757.07
6 0.95 1,541.64 4,624.92 1,536.00 (5.64)
7 1.93 3,131.96 7,756.88 1,536.00 (1,595.96)
8 2.06 3,342.92 11,099.81 1,536.00 (1,806.92)
9 1.98 3,213.10 14,312.91 1,536.00 (1,677.10)
10 1.58 2,563.99 16,876.90 1,536.00 (1,027.99)
11 1.89 3,067.05 19,943.95 1,536.00 (1,531.05)
12 1.29 2,093.38 22,037.34 1,536.00 (557.38)
13 1.23 1,996.02 24,033.36 1,536.00 (460.02)
14 0.95 1,541.64 25,575.00 1,536.00 (5.64)
15 0.99 1,606.55 27,181.55 1,536.00 (70.55)
16 0.96 1,557.87 28,739.42 1,536.00 (21.87)
17 1.07 1,736.37 30,475.79 1,536.00 (200.37)
18 1.33 2,158.30 32,634.09 1,536.00 (622.30)
19 1.36 2,206.98 34,841.07 1,536.00 (670.98)
20 0.87 1,411.82 36,252.88 1,536.00 124.18
21 0.64 1,038.58 37,291.46 1,536.00 497.42
22 0.54 876.30 38,167.76 1,536.00 659.70
23 0.42 681.57 38,849.33 1,536.00 854.43
0 0.38 616.66 39,465.99 1,536.00 919.34

The storage capacity required is the sum of the positive storage variation and negative
variation
Total Capacity in liters
Total Capacity in cubic meters

6) Reservoir dimension

Dimension (r.cap.)^1/3 = 2.17 cum


use
Length 2.17 = 2.17 m. 2.20 m.
Breadth 2.17 = 2.17 m. 2.20 m.
Height 2.17 = 2.47 m. 2.50 m.
Freeboard 0.20
Dead vol. Ht. 0.10

Therefore width length height


Use reservoir dimension = 2.20 2.20 2.50
Actual reservoir capacity = 10.65 cu.m.
Note: Computed dimension is INSIDE DIMENSION. 0.39 if + answer the size is OK

ECONOMICAL STORAGE CAPACITY


Simple Ratio Method
Calculate the ratio (R) of the average source flow (ASF) (for spring sources) over the
Average Day Demand and refer to the table below:
R = ASF ÷ ADD

Ratio Storage Capacity Ratio


< 1.0 inadequate source
1.0-2.0 ½ of the average daily used
2.0-3.0 ¼ of the average daily used
3.0-4.0 1/8
of the average daily used
> 4.0 no storage facility required 0.94652

Note: The source above in the sample is inadequate and to balance the demand and supply-the minimum
required hours to fill a balancing reservoir is 6.93 hours

2.5

1.5
Ratio to ADD

1 TI
C
C
0.5 A

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Ratio to A
1 TI
C
C
0.5 A

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Time (Hours)

TYPICAL WATER DEMAND VARIATION

MASS DIAGRAM METHOD OF RESERVOIR SIZING (8 hours pumping) (Fill and Draw Operation)

ADD 38,946.70 lit/day

Average Hourly Demand 1,622.78 lit/hour 0.45 lps


Pump Discharge 1.28 lit/sec
HOURLY CUMULATIVE
DEMAND HOURLY DEMAND SUPPLY FROM PUMP SUPPLY MINUS
TIME TI ADD RATIO (liters) (liters) (liters/hour) DRAFT (liters)
1 0.32 519.29 519.29 (519.29)
2 0.38 616.66 1,135.95 (616.66)
3 0.39 632.88 1,768.83 (632.88)
4 0.33 535.52 2,304.35 (535.52)
5 0.48 778.93 3,083.28 (778.93)
6 0.95 1,541.64 4,624.92 (1,541.64)
7 1.93 3,131.96 7,756.88 (3,131.96)
8 2.06 3,342.92 11,099.81 4,608.00 1,265.08
9 1.98 3,213.10 14,312.91 4,608.00 1,394.90
10 1.58 2,563.99 16,876.90 4,608.00 2,044.01
11 1.89 3,067.05 19,943.95 4,608.00 1,540.95
12 1.29 2,093.38 22,037.34 4,608.00 2,514.62
13 1.23 1,996.02 24,033.36 4,608.00 2,611.98
14 0.95 1,541.64 25,575.00 4,608.00 3,066.36
15 0.99 1,606.55 27,181.55 4,608.00 3,001.45
16 0.96 1,557.87 28,739.42 (1,557.87)
17 1.07 1,736.37 30,475.79 (1,736.37)
18 1.33 2,158.30 32,634.09 (2,158.30)
19 1.36 2,206.98 34,841.07 (2,206.98)
20 0.87 1,411.82 36,252.88 (1,411.82)
21 0.64 1,038.58 37,291.46 (1,038.58)
22 0.54 876.30 38,167.76 (876.30)
23 0.42 681.57 38,849.33 (681.57)
0 0.38 616.66 39,465.99 (616.66)

The storage capacity required is the sum of the positive storage variation and negative
variation
Total Capacity in liters
Total Capacity in cubic meters

6) Reservoir dimension

Dimension (r.cap.)^1/3 = 4.97 cum


use
Length 4.97 = 4.97 m. 5.00 m.
Breadth 4.97 = 4.97 m. 5.00 m.
Height 4.97 = 5.27 m. 5.30 m.
Freeboard 0.20
Dead vol. Ht. 0.10

Therefore width length height


Use reservoir dimension = 5.00 5.00 5.30
Actual reservoir capacity = 125.00 cu.m.
Note: Computed dimension is INSIDE DIMENSION. 2.17 if + answer the size is OK

Time to Fill Reservoir if distribution gatevalve is fully closed 27.13 hours


from 8PM to 3AM
System (Gravity Driven)

ve, settling or point of

1.28m dropdown into level 0 from max. level

Data Unit
161 HH
6 No.
966 No.
0.03 %
10 Years
1298 No.
30 Liter

38,947 Liter
0.451 LPS
if + answer the size is OK

Time Factor Analysis

Minimum Time to Fill


Balancing Reservoir
(in hours)

6.93

the minimum

DEFICIT(__)
SURPLUS REMARKS
17,662.60
16,767.12
15,844.77
14,894.75
13,916.24
12,908.36
11,870.26
10,801.00
9,699.67
8,565.30
7,396.90
6,193.45
4,953.89
3,677.15
2,362.10

read over 24 hours)

SUPPLY MINUS STORAGE


DRAFT (liters) VARIATION (liters)
1,016.71 1,016.71
919.34 1,936.05
903.12 2,839.17
1,000.48 3,839.65
757.07 4,596.72
(5.64) 4,591.08
(1,595.96) 2,995.12
(1,806.92) 1,188.19
(1,677.10) (488.91)
(1,027.99) (1,516.90)
(1,531.05) (3,047.95)
(557.38) (3,605.34)
(460.02) (4,065.36)
(5.64) (4,071.00)
(70.55) (4,141.55)
(21.87) (4,163.42)
(200.37) (4,363.79)
(622.30) (4,986.09)
(670.98) (5,657.07)
124.18 (5,532.88)
497.42 (5,035.46)
659.70 (4,375.76)
854.43 (3,521.33)
919.34 (2,601.99)

4,596.72 Extreme positive variation


5,657.07 Extreme negative variation
10,253.79
10.25

if + answer the size is OK

Time Factor Analysis

Minimum Time to Fill


Balancing Reservoir
(in hours)

6.93

the minimum

TIME
Column B
Column C
ADD RATIO

21 22 23 24
TIME
Column B
Column C
ADD RATIO

21 22 23 24

w Operation)

SUPPLY MINUS STORAGE


DRAFT (liters) VARIATION (liters)
(519.29) (519.29)
(616.66) (1,135.95)
(632.88) (1,768.83)
(535.52) (2,304.35)
(778.93) (3,083.28)
(1,541.64) (4,624.92)
(3,131.96) (7,756.88)
1,265.08 (6,491.81)
1,394.90 (5,096.91)
2,044.01 (3,052.90)
1,540.95 (1,511.95)
2,514.62 1,002.66
2,611.98 3,614.64
3,066.36 6,681.00
3,001.45 9,682.45
(1,557.87) 8,124.58
(1,736.37) 6,388.21
(2,158.30) 4,229.91
(2,206.98) 2,022.93
(1,411.82) 611.12
(1,038.58) (427.46)
(876.30) (1,303.76)
(681.57) (1,985.33)
(616.66) (2,601.99)

74,235.90 Positive Variation


48,592.22 Negative Variation
122,828.12
122.83

if + answer the size is OK


Pipeline Hydraulic Analysis
Planning and Design WS

ANNEX 1

II -PIPELINE DESIGN ANALYSIS:

Design criteria

The pipeline must be designed to handle the maximum hour demand or Peak Flow (PF)=2.5ADD of the area to be
Minimun pressure at the remotest end of the system should be 3.0 meters (Approx. 4.26 psi) and 7.0 meters at th
mainline
Maximum Velocity of flow in the pipes:
a. Main pipes… 3.0 meters per second
b. Distribution pipes… 1.5 meters per second
Water flow per tapstand ranges from 0.125 lps to 0.225 lps

Additional: Consider most economical pipe size and layout

Additonal: Best location of tank ( if any)

A. Pipeline Design Input/Output


Pipeline Section Household Peak Node Pipe Pipe
Section Node Length Served Flow Elev. Diameter Diameter
from to Difference Option
(m) (no.) (lps) (m) (mm) (mm)
a b c d e f g h i

0
B. Pipeline Analysis
Branch Node Remarks
No. of Household Total Headloss Compare Elev Head

KALAHI-CIDSS PROJECT Pipeline Hydraulic Analysis for Annex 1 20of 4


Pipeline Hydraulic Analysis
Planning and Design WS

Recommendation:
For all the branch nodes, the total headloss is greater than the elevation head. It is therefore
recommended to increase the diameter of pipe to effect efficient flow in the system.(?) reject

Column Description:
Column Description
a Pipe section under consideration
b-c Node section under consideration
d Length of pipe section under consideration (meter)
e Number of household served
f Computed Peak Flow (liter per second)
g Difference in elevation between nodes under consideration (meter)
h Computed Pipe Diameter (mm), using the Darcy Weisbach Formula
i Nominal Diameter available in the market (mm)
j Headloss per 100 meters (refer to table 9.1 or 9.2)
k Actual Headloss

KALAHI-CIDSS PROJECT Pipeline Hydraulic Analysis for Annex 1 21of 4


Pipeline Hydraulic Analysis
Planning and Design WS

Formula:

Column f:

PF = 2.5 x GRF x N x Average Household Size x PCWC / 86,400

Where:

PF = Peak flow.
GRF = Growth rate factor (1+GR)^life span
N = Total number of household served by the pipe section.
PCWC = Per capita water consumption.

Column h:

HF = (8)(f)(L)(Q)^2/D^5(g)(pi)^2
D^5 =(8)(f)(L)(Q)^2/HF(g)(pi)^2

Where:

HF = Headloss or the difference in elevation between the pipe in


consideration.
F = Coefficient of friction (approximately 0.02).
L = Length of pipe section in consideration.
Q = Water discharge.
D =Pipe diameter (mm).
g =gravitational value (9.81)
pi =3.1415

Simplifying:

D^5 = (0.00165(L)(Q/1000)^2/HF)(1000)(mm)
= (0.00165(Column d)(Column f/1000)^2/(Column g))(1000)

Column j:

From table 9.1 or 9.2, (interpolate when necessary).

Column k:

Actual Headloss = (Headloss per 100 M)(Section Length)/100


= (Column j)(Column d)/100

KALAHI-CIDSS PROJECT Pipeline Hydraulic Analysis for Annex 1 22of 4


Pipeline Hydraulic Analysis
Planning and Design WS

III -PIPELINE DESIGN ADJUSTMENT:

A. Pipeline Design Input/Output


Pipeline Section Household Peak Node Pipe Pipe
Section Node Length Served Flow Elev. Diameter Diameter
from to Difference Option
(m) (no.) (lps) (m) (mm) (mm)
a b c d e f g h i
a 1 2 30 15 0.105 0.3 17.8633 32
b 2 3 37.6 30 0.210 0.3 24.6597 32
c 3 4 47.6 30 0.210 0.3 25.8506 32
d 4 5 26.7 20 0.140 0.31 19.4521 32
e 4 6 51.5 50 0.350 0.92 25.7464 32
f 6 7 9.67 70 0.490 0 0.0000 32
g 7 8 53.84 40 0.280 0 0.0000 32
h 8 9 94.2 20 0.140 0.31 25.0308 32
i 9 10 43.06 20 0.140 0.3 21.5441 32
j 10 11 31.39 10 0.070 0.3 15.3271 25
k 7 12 21.2 90 0.630 7.70 17.8316 38
l 12 13 11.43 161 0.464 8.00 13.8387 50
m 12 14 54.76 71 0.497 8.61 19.1743 63
n 14 15 861.86 71 0.497 2.43 42.8543 63
o 15 16 108.42 46 0.322 0 0.0000 38
p 16 17 57.48 10 0.070 1.52 12.5043 38
q 16 18 48.4 26 0.285 0.92 19.5761 38
r 18 19 35.99 11 0.077 0.61 14.1992 25
s 15 20 20.23 25 0.175 0.62 17.5155 38
t 20 21 171.93 15 0.105 3.05 15.9284 25

B. Pipeline Analysis (checking by comparing the Total HL and Elevation Head and check Minimum Res
Branch Node Remarks
No. of Household Total Headloss Compare Elev Head
1-2 15 0.0165 < 7.98
2-3 30 0.132 < 7.87
3-4 30 0.168 < 7.83
1-2-3-4 30 0.316 < 7.68
4-5 20 0.045 < 7.95
4-6 50 0.469 < 7.53
6-7 70 0.163 < 7.84
4-5-6 50 0.514 < 7.49
4-5-6-7 70 0.677 < 7.32
4-5-6-7-8 70 0.997 < 7.00
1-2-3-4-6 50 0.786 < 7.21
1-2-3-4-6-7 70 0.949 < 7.05
1-2-3-4-6-7-12 70 1.181 < 6.82
3-4-6 50 0.637 < 7.36
3-4-6-7 70 0.800 < 7.20
3-4-6-7-12 70 1.033 < 6.97
10-11 10 0.041 < 7.96
9-10 20 0.073 < 7.93
8-9 20 0.160 < 7.84
7-8 40 0.320 < 7.68
7-12 90 0.233 < 7.77
9-10-11 20 0.114 < 7.89
8-9-10-11 20 0.274 < 7.73
7-8-9-10-11 40 0.594 < 7.41

KALAHI-CIDSS PROJECT Pipeline Hydraulic Analysis for Annex 1 23of 4


Pipeline Hydraulic Analysis
Planning and Design WS

7-8-9-10-11-12 90 0.827 < 7.17


16-17 10 0.000 < 8.00
18-19 11 0.057 < 7.94
16-18 26 0.050 < 7.95
15-16 46 0.307 < 7.69
20-21 15 0.490 < 7.51
15-20 25 0.015 < 7.98
14-15 71 0.000 < 8.00
12-14 71 0.000 < 8.00
12-13 161 0.018 < 7.98
15-20-21 25 0.505 < 7.49
16-18-19 46 0.107 < 7.89
15-16-17 71 0.307 < 7.69
15-16-18-19 71 0.364 < 7.64
14-15-20-21 71 0.505 < 7.49
12-14-15-20-21 71 0.505 < 7.49
14-15-16-18-19 71 0.414 < 7.59
12-14-15-16-18-19 71 0.414 < 7.59
14-15-16-17 71 0.307 < 7.69
12-14-15-16-17 71 0.307 < 7.69
The total headloss is less than the elevation head and therefore accept adjusted size but there are still critical node
with < 3m residual head (Hr)

KALAHI-CIDSS PROJECT Pipeline Hydraulic Analysis for Annex 1 24of 4


Pipeline Hydraulic Analysis
Planning and Design WS

Graph of Hydraulic Gradeline of Mainline, Pipeline and Ground Elevation

Pipeline Section Household Peak Node Pipe Pipe


Section Node Length Served Flow Elev. Diameter Diameter
from to Difference Option
(m) (no.) (lps) (m) (mm) (mm)
a b c d e f g h i
a 1 2 30 15 0.105 0.3 17.8633 32
b 2 3 37.6 30 0.210 0.3 24.6597 32
c 3 4 47.6 30 0.210 0.3 25.8506 32
d 4 5 26.7 20 0.140 0.31 19.4521 32
e 4 6 51.5 50 0.350 0.92 25.7464 32
f 6 7 9.67 70 0.490 0 0.0000 32
g 7 8 53.84 40 0.280 0 0.0000 32
h 8 9 94.2 20 0.140 0.31 25.0308 32
i 9 10 43.06 20 0.140 0.3 21.5441 32
j 10 11 31.39 10 0.070 0.3 15.3271 25
k 7 12 21.2 90 0.630 7.70 17.8361 38
l 12 13 11.43 161 0.464 8.00 13.8387 50
m 12 14 54.76 71 0.497 8.61 19.1743 63
n 14 15 861.86 71 0.497 2.43 42.8543 63
o 15 16 108.42 46 0.322 0 0.0000 38
p 16 17 57.48 10 0.070 1.52 12.5043 38
q 16 18 48.4 26 0.182 0.92 19.5761 38
r 18 19 35.99 11 0.077 0.61 14.1992 25
s 15 20 20.23 25 0.175 0.62 17.5155 38
t 20 21 171.93 15 0.105 3.05 15.9284 25
18.00
17.50
17.00 Reservoir
16.50
16.00
15.50
15.00
14.50 Pip
14.00 ma
13.50
13.00 Hyd
12.50 Gra
12.00 Elev
11.50 ma
11.00
10.50 Gro
10.00 Elev
9.50 ma
9.00
8.50
8.00
7.50
7.00
6.50
6.00
5.50
5.00
4.50
4.00
3.50
KALAHI-CIDSS PROJECT
3.00 Pipeline Hydraulic Analysis for Annex 1 25of 4
2.50
7.00
6.50
6.00
5.50 Analysis
Pipeline Hydraulic
Planning and Design WS
5.00
4.50
4.00
3.50
3.00
2.50
2.00
1.50
1.00
0.50
-
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

KALAHI-CIDSS PROJECT Pipeline Hydraulic Analysis for Annex 1 26of 4


Pipeline Hydraulic Analysis
Planning and Design WS

k Flow (PF)=2.5ADD of the area to be served


Approx. 4.26 psi) and 7.0 meters at the

Headloss Actual
per Headloss
100 m.
(m) (m)
j k

not the exact data refer downward for brgy. 7

Remarks Residual Remarks


Accept Head (Hr)

KALAHI-CIDSS PROJECT Pipeline Hydraulic Analysis for Annex 1 27of 4


Pipeline Hydraulic Analysis
Planning and Design WS

KALAHI-CIDSS PROJECT Pipeline Hydraulic Analysis for Annex 1 28of 4


Pipeline Hydraulic Analysis
Planning and Design WS

(m)

KALAHI-CIDSS PROJECT Pipeline Hydraulic Analysis for Annex 1 29of 4


Pipeline Hydraulic Analysis
Planning and Design WS

Headloss Actual
per Headloss
100 m.
(m) (m)
j k
0.055 0.0165
0.352 0.132
0.352 0.168
0.170 0.045
0.910 0.469
1.681 0.163
0.594 0.320
0.170 0.160
0.170 0.073
0.130 0.041
1.099 0.233
0.158 0.018 reservoir
0.000 0.000
0.000 0.000
0.283 0.307
0.000 0.000
0.103 0.050
0.158 0.057
0.075 0.015
0.285 0.490

tion Head and check Minimum Residual Head)


Remarks Residual Remarks
Accept Head (Hr)
okey 7.96 Pass
okey 7.74 Pass
okey 7.66 Pass
okey 7.36 Pass
okey 7.91 Pass
okey 7.06 Pass
okey 7.68 Pass
okey 6.98 Pass
okey 6.64 Pass
okey 6.00 Pass
okey 6.42 Pass
okey 6.10 Pass
okey 5.64 Pass
okey 6.72 Pass
okey 6.40 Pass
okey 5.94 Pass
okey 7.92 Pass
okey 7.86 Pass
okey 7.68 Pass
okey 7.36 Pass
okey 7.54 Pass
okey 7.78 Pass
okey 7.46 Pass
okey 6.82 Pass

KALAHI-CIDSS PROJECT Pipeline Hydraulic Analysis for Annex 1 30of 4


Pipeline Hydraulic Analysis
Planning and Design WS

okey 6.34 Pass


okey 8.00 Pass
okey 7.88 Pass
okey 7.90 Pass
okey 7.38 Pass
okey 7.02 Pass
okey 7.97 Pass
okey 8.00 Pass
okey 8.00 Pass
okey 7.96 Pass
okey 6.99 Pass
okey 7.78 Pass
okey 7.38 Pass
okey 7.28 Pass
okey 6.99 Pass
okey 6.99 Pass
okey 7.18 Pass
okey 7.18 Pass
okey 7.38 Pass
okey 7.38 Pass
sted size but there are still critical nodes

KALAHI-CIDSS PROJECT Pipeline Hydraulic Analysis for Annex 1 31of 4


Pipeline Hydraulic Analysis
Planning and Design WS

Headloss Actual Hydraulic


per Headloss Gradeline
100 m. Pipe Point Ground Available
(m) (m) Elevation Elevation Elevation Head
j k masl masl masl
0.055 0.0165 8.34 15.30 8.84 6.96
0.352 0.132 8.64 15.19 9.14 6.550
0.352 0.168 8.34 15.15 8.84 6.810
0.170 0.045 8.04 15.27 8.54 7.230
0.910 0.469 8.04 14.85 8.54 6.810
1.681 0.163 7.12 15.16 7.62 8.040
0.594 0.320 7.12 15.00 7.62 7.880
0.170 0.160 7.43 15.16 7.62 7.730
0.170 0.073 7.73 15.25 7.93 7.520
0.130 0.041 7.73 15.28 8.23 7.550
1.099 0.233 7.12 15.09 7.62 7.970
0.158 0.018 6.82 15.30 7.32 8.480
0.000 0.000 6.82 15.32 7.32 8.500
0.000 0.000 6.21 15.32 6.71 9.110
0.283 0.307 8.64 15.01 9.14 6.370
0.000 0.000 8.64 15.32 9.14 6.680
0.103 0.050 8.64 15.27 9.14 6.630
0.158 0.057 9.56 15.26 10.06 5.700
0.075 0.015 8.64 15.30 9.14 6.660
0.285 0.490 9.26 14.83 9.76 5.570

Pipe Elevation
masl

Hydraulic
Gradeline Point
Elevation
masl

Ground
Elevation
masl

KALAHI-CIDSS PROJECT Pipeline Hydraulic Analysis for Annex 1 32of 4


Pipeline Hydraulic Analysis
Planning and Design WS

15 16 17 18 19 20

KALAHI-CIDSS PROJECT Pipeline Hydraulic Analysis for Annex 1 33of 4


Planning and Design WS
Schematic Diagram/Project Area Map

ANNEX 1

Schematic Diagram of
Poblacion 7, Can avid Eastern Samar

Q= 0.464 lps
elev. 7.32
Dug well
13 elev. 7.62 8 elev.
94.2 m
11.43 m h
F5
Elevated tank to l g 9
8.00 m 12 53.84 m HH= 10
elev 7.32 elev
RESERVOIR Tank k elev. 7.62
m 21.2 F6 7 8.23
6.71 54.76 HH=20 F3 5
14 9.67 f HH=20
elev. 7.62 6
861.86 51.5 26.7 d
n elev. 8.54
e 4 c
47.6 3
15 8.84 F2
9.14 108.42 16 HH=10 HH=15 37.6
o 9.14 b elev
F9
20.23 57.48 17 2
s q p F10 HH=10
20 48.4 7.62
F7 HH=10 18
9.76 F11 10.06
HH=15
t r
171.93 35.99

19
21 F12 9.45 m
F8 HH=15 HH=11
6.71

Preparation of schematic diagram as basis for pipeline design:


Steps:
1. Locate tapstand and name it F1…n starting from farthest
to the reservoir and or water source.
2. Determine the number of nodes and name it in numbers
starting from farthest to the reservoir and or water source.
3. Determine the number of sections and name it in letters
starting from farthest to the reservoir and or water source.
4. Indicate the number of HH per tapstand, the elevation of
the nodes, the length of the sections from survey results.
5. Design for the pipe diameter of the sections (see pipeline analysis)
and indicate final pipe sizes in the schematic diagram.
F1

KALAHI-CIDSS
Planning and Design WS
Schematic Diagram/Project Area Map
F1

KALAHI-CIDSS Subproject Name Prepared Drawing Title


PROJECT SCHEMATIC DIAGRAM
Sheet Title
Location Checked Schematic Diagram
Scale
NTS

KALAHI-CIDSS
Planning and Design WS
Schematic Diagram/Project Area Map

R
ANNEX 1

PROJECT AREA MAP

Prepare a map showing the area to be served and the location of the source(s) of water. It should be drawn to a
convenient scale or with measurements of distance between important structures along roads and pathways.
Include elevation. Indicate houses, schools, churches, markets, existing water systems, public faucets, reservoir
and other important land features.

Legend

House
School
Church

Public faucet
Existing pipeline
Proposed pipeline
R Reservoir
Gate valve
Check Valve

KALAHI-CIDSS
Planning and Design WS
Schematic Diagram/Project Area Map

Reducer
Clinic
Contours
º123 Elevations
S Spring Box

KALAHI-CIDSS Subproject Name Prepared Drawing Title


PROJECT Project Area Map
Sheet Title
Location Checked Project Area Map
Scale
NTS

KALAHI-CIDSS
Planning and Design WS
Schematic Diagram/Project Area Map

Samar

11
HH=10 F4
7.93
7.93
31.39
F5
43.06
i j
8.23
10

8.84
HH=15
F1
F3 1
30.00
a

9.14

KALAHI-CIDSS
Planning and Design WS
Schematic Diagram/Project Area Map

Sub-Project No.

ematic Diagram
Sheet No.

KALAHI-CIDSS
Planning and Design WS
Schematic Diagram/Project Area Map

ce(s) of water. It should be drawn to a


uctures along roads and pathways.
ater systems, public faucets, reservoir

KALAHI-CIDSS
Planning and Design WS
Schematic Diagram/Project Area Map

Sub-Project No.

Sheet No.

KALAHI-CIDSS
PUMP DESIGN
Water
Pump
Design Horse Brake
Data Capacity
Paramet Power Horse
Parameters lps
ers Power
a b c d e

1.Drawdown (m) 1.28


2.Static Water Level (SWL) (m) 2.38
3.Pumping Water Level (drawdown+SWL) (m) 3.66
4.Height of Discharge Point Level (m) 8.5
5.Suction and transmission Discharge Friction
3.77
Headloss (HL) (meters)
TDH (3+4+5) 15.93 1.74 0.36 0.90
Pump operation (hours) 12
Number of Household 103
Ave. person per HH 6
Growth Rate Factor 0.03
Design Period 15
Design Population 962.82
Water Consumption per capita per day 60
Average Daily Demand (ADD) (lit/day) 57,769.20
Maximum day demand (lps) * 1.3 0.87

Data from Georesistivity Survey or from Pumping Test Result of Existing Wells or from Newly Bored Well:

1. Target Well Discharge (lps) 0.464


2. Total Dynamic Head (m) 15.93
3. Well depth (m) 4.94

Design Consideration:
Case I : Fixed maximum well yield and target household, adjust pumping hour.
Case II: Fixed maximum pumping hour to 12 and target household, locate sufficient well yield on site.
Case III: Fixed maximum well yield and 12 hour pumping, adjust target household.
Formula:
1. Pump Capacity: Q=maximum day demand* 24 hours / 12 hours pumping
2. Break Horsepower: BHP= Q * TDH * g/ e / 0.746 / 1000
3. Actual Discharge: Qactual= BHP * e * .746 *1000 / g / TDH

Where : g = gravitational factor 9.81


e = pump efficiency 40%

4. Height of discharge point is the difference in elevation of reservoir (maximum water level) and the pump

5. The headloss computation will be referred to table 9.1 & 9.2


Solve for initial size of transmission pipe Q=AV
assume V= 3 m/s
A=1/4 (pi()) d^2

d= ((4*Q/3.14)*V)^.5

Q (lps) V (m/s) d (mm)


1.74 3 28
Refer to headloss table per 100 meters and equivalent length of connection accessories:
Headlos
Length of
Q (lps) d (mm) s/ 100
Pipe (m)
(m)
1.75 28 7.9 25.59

Note: insert for the other sizes

Analysis:
Compare the Design Pump Discharge and the Well Capacity if there is a need for reservoir.

Equivalent Length of Connections for the Computation of Headlosses


Nominal
Dia.
Elbow, 45 Gate Valve,
(mm.) of Elbow, 90 deg Tee
deg Fully Open
Accessori
es
32 Equivalent Length per pc 1.14 0.52 2.29 0.24
Number 2 1 4
Equivalent Length 2.28 0.52 9.16 -
50 Equivalent Length per pc 1.62 0.76 3.66 0.38
Number 2 1
Equivalent Length 3.24 0.76 - -
75 Equivalent Length per pc 2.50 1.16 4.88 0.53
Number 2 1
Equivalent Length 5.00 1.16 - -
Total
Equivalen 22.12 10.52 2.44 9.16
t Length

\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\
Type of
Pump
f g h
Q
BHP
TDH (m) (actual)
(HP)
(lps)

11.43 m
ground level elev. 7.32

2.38 m Pump discharge


15.93 1.72 0.90 1.00 HP SWL
drawdown = Consumption per
1.28 m capita per day
PWL pop. Growth rate
design period
1.28 m

wly Bored Well:

1000 gal/1 cu.m


1000 =

yield on site.

vel) and the pump


Equivale
Total
nt Total HL
Length
Length (m)
(m)
(elbows)
22.12 47.71 3.76909

the Computation of Headlosses

Globe Angle Foot Check


Faucet,
Valve, Valve, Valve, Valve,
Fully Strainer
Fully Fully Fully Fully
Open
Open Open Open Open

11.28 5.49 - 2.13 4.88 2.74

- - - - - -
16.76 8.54 - 2.74 6.10 4.27

- - - - - -
25.90 12.80 - 3.66 7.62 5.79

- - - - - -

Design: Capacity Q (gpm) 25.80


Brake Power (HP)
Head (ft) 52.25
Efficiency (%) 40%
2.00

2.50 m
to Brgy. Maliunao
8.00 m
m
elev. 7.32 m

Pump discharge 2.5 lps.


HH 161 ?
Consumption per to Pob. 7
capita per day 30 lps
pop. Growth rate 3%
design period 10 years
Name of Sub-Project Construction of Pinanag-an Level I Water System (Gravity Driven)
Sub-project Type Groundwater Source
Municipality Borongan City
Province Eastern Samar
Region VIII

PUMPING TEST

Pump Specification Used Size of Dugwell constructed per info from the installer

Pump : SPERONI
HP : 0.75 0.69m NGL
Type Cam 50
v : 230 2.38 m
Hz : 60 max. water level
rpm : 3400 4.94m
1 PH ~ A 3.4 1.28m

0.90 m

A. Container Vol. 20 Liters


Time
1 39.6 sec.
2 40.3 sec.
3 40.9 sec.
4 41.6 sec.
5 41.8 sec.
40.84 sec. Average

Q1 = 0.489716

Qave. = 0.489716 lps QA

Start 10:43
3:25 Pumping Time till drained t1 12300
Stop 14:08
Recharge period t2 300
Start 14:13
1:30 Pumping Time till drained t3 5400
Stop 15:43

Vol = QA x t1
Vol = 0.489716 x 205 x 60
= 6023.506 liters Pump out volume

Let QA= Discharge rate of water pump used


QB= Recharge rate of the ground water

t1= Pumping period till drained


t2= Recharge period
t3= Second pumping period till drained

V1= Volume water pump out at t3


V2= Volume recharge from t2 and t3

V1= V2
QA x (t3) = QB x (t2+t3)
0.48972 x 5400 = QB x ( 300 + 5400
2644.46621 = 5700 QB

QB = 0.464 lps ground recharge

Volume of existing ground cistern

V = (QA-QB) X t1
V= ( 0.489716 - 0.464 ) X 12300
V= 316.31 Liters

V= 0.31631 = Pi()*D^2/4

Diameter=[4V/pi()]^0.5
Diameter= 0.634616735 m. Confirmed that 1 pc of 0.61 m. diameter of RCPC was installed

QB = 0.464 lps Source Discharge to be used


info from the installer

0.69m NGL

max. water level

1.28m

Sec.

Sec.

Sec.
)

RCPC was installed


Fricstion Headloss Table Planning and Design WS

Q PIPE SIZE (mm)


LPS 13 19 25 32 38 50 63
0.01 0.10
0.02 0.40
0.03 0.80 0.11
0.04 1.40 0.19
0.05 2.10 0.30
0.06 3.00 0.41 0.10
0.07 4.00 0.50 0.13
0.08 5.00 0.65 0.17
0.09 6.30 0.82 0.22
0.10 7.60 1.06 0.26
0.11 9.10 1.18 0.31 0.11
0.12 10.70 1.50 0.36 0.13
0.14 2.00 0.48 0.17
0.15 2.10 0.55 0.18
0.16 2.50 0.62 0.22
0.18 3.10 0.77 0.27 0.10
0.20 3.80 0.94 0.32 0.13
0.25 5.80 1.42 0.48 0.20
0.30 2.00 0.67 0.23
0.40 3.40 1.15 0.47 0.12
0.50 5.10 1.74 0.71 0.18
0.60 7.20 2.40 1.00 0.25
0.70 3.20 1.33 0.33 0.11
0.80 4.10 1.70 0.42 0.14
1.00 6.30 2.60 0.64 0.21
1.20 8.80 3.60 0.89 0.30
1.40 4.40 1.20 0.40
1.50 4.90 1.35 0.44
1.60 5.50 1.52 0.51
1.80 7.35 1.88 0.64
2.00 8.40 2.30 0.77
2.50 3.50 1.20
3.00 4.95 1.65
3.50 6.95 2.19
4.00 9.20 3.00
4.50 11.85 3.60
5.00 4.50
6.00 6.20
7.00 8.60
8.00
10.00

FRICTION HEAD LOSS IN METERS PER 100 METERS


PLASTIC PIPE - PVC, PE, PB

TABLE 9.1 FRICTION HEAD LOSS IN PLASTIC PIPES

Q PIPE SIZE (mm)


LPS 13 19 25 32 38 50 63
0.01 0.20
0.02 0.80
0.03 1.60 0.22

KALAHI-CIDSS PROJECT Reference for Annex 1-----54of 3


Fricstion Headloss Table Planning and Design WS

0.04 2.80 0.38


0.05 4.20 0.60
0.06 6.00 0.82 0.20
0.07 8.00 1.00 0.26
0.08 10.00 1.30 0.34
0.09 12.60 1.64 0.44 0.15
0.10 15.20 2.12 0.52 0.18
0.11 18.20 2.36 0.62 0.22
0.12 21.40 3.00 0.72 0.26
0.14 4.00 0.96 0.34 0.13
0.15 4.20 1.10 0.36 0.15
0.16 5.00 1.24 0.44 0.16
0.18 6.20 1.54 0.54 0.20
0.20 7.60 1.88 0.64 0.26 0.70
0.25 11.60 2.84 0.96 0.40 0.10
0.30 4.00 1.34 0.46 0.14
0.40 6.80 2.30 0.94 0.24
0.50 10.20 3.48 1.42 0.36 0.12
0.60 14.40 4.80 2.00 0.50 0.17
0.70 6.40 2.66 0.66 0.22
0.80 8.20 3.40 0.84 0.28
1.00 12.60 5.20 1.28 0.42
1.20 17.60 7.20 1.78 0.60
1.40 8.80 2.40 0.80
1.50 9.80 2.70 0.88
1.60 11.00 3.04 1.02
1.80 14.70 3.76 1.28
2.00 16.80 4.60 1.54
2.50 7.00 2.40
3.00 9.90 3.30
3.50 13.90 4.38
4.00 18.40 6.00
4.50 23.70 7.20
5.00 9.00
6.00 12.40
7.00 17.20
8.00
10.00

FRICTION HEAD LOSS IN METERS PER 100 METERS


GALVANIZED IRON PIPE (GIP)

TABLE 9.2
FRICTION HEAD LOSS IN GI PIPES

KALAHI-CIDSS PROJECT Reference for Annex 1-----55of 3


Fricstion Headloss Table Planning and Design WS

RESISTANCE OF VALVE AND FITTINGS*

Gate Globe Angle


Nominal Elbow, 90 Elbow, 45 Faucet,
Tee Valve, Valve, Valve,
Dia. (mm.) deg deg Fully Open
Fully Open Fully Open Fully Open
13 0.55 0.24 1.04 0.11 4.88 2.56 4.88
19 0.69 0.3 1.37 0.14 6.4 3.66 6.4
25 0.84 0.41 `1.77 0.18 8.23 4.57
32 1.14 0.52 2.29 0.24 11.28 5.49
38 1.36 0.61 2.74 0.29 13.71 6.71
50 1.62 0.76 3.66 0.38 16.76 8.54
63 1.98 0.91 4.27 0.43 19.61 10.06
75 2.5 1.16 4.88 0.53 25.9 12.8
100 3.35 1.52 6.71 0.7 33.54 12.8
150 5.03 2.04 9.76 1.01 48.78 24.39
EQUIVQLENT LENGTH STRAIGHT PIPE METERS

*WHEN THE LENGTH OF PIPE IS GREATER THAN 1000 TIMES ITS DIAMETER, THE LOSS OF HEAD DUE TO VALVE
AND FITTINGS MAYBE DISREGARDED.

EQUIVALENT LENGTH OF PIPE FITTINGS, VALVES, ETC.

KALAHI-CIDSS PROJECT Reference for Annex 1-----56of 3


Fricstion Headloss Table Planning and Design WS

(mm)
75 100 150

INTERPOLATION

Discharge Friction Headloss per 100 meters


Upper
Middle x
Lower

0.09
0.12
0.17
0.19
0.21
0.26
0.32 0.08
0.48 0.12
0.68 0.17
0.90 0.22
1.15 0.28
1.43 0.35
1.74 0.43 0.06
2.44 0.60 0.09
3.20 0.80 0.11
4.15 1.20 0.14
6.50 1.55 0.21

(mm)
75 100 150

KALAHI-CIDSS PROJECT Reference for Annex 1-----57of 3


Fricstion Headloss Table Planning and Design WS

INTERPOLATION

Discharge Friction Headloss per 100 meters


Upper
Middle
Lower

0.70
0.91
0.12
0.18
0.25
0.33
0.37
0.42 0.10
0.52 0.13
0.64 0.16
0.96 0.24
1.36 0.33
1.80 0.44
2.30 0.37
2.86 0.71
3.48 0.86 0.12
4.88 1.20 0.17
6.40 1.60 0.22
8.30 2.40 0.28
13.00 3.10 0.42

KALAHI-CIDSS PROJECT Reference for Annex 1-----58of 3


Fricstion Headloss Table Planning and Design WS

Foot Check
Valve, Strainer Valve,
Fully Open Fully Open
1.22 3.05 1.16
1.52 3.66 1.58
1.83 4.27 1.98
2.13 4.88 2.74
2.44 5.49 3.35
2.74 6.1 4.27
3.05 6.71 5.18
3.66 7.62 5.79
4.57 9.15 7.62
6.42 12.21 11.59
E METERS

AMETER, THE LOSS OF HEAD DUE TO VALVES AND

KALAHI-CIDSS PROJECT Reference for Annex 1-----59of 3


Fricstion Headloss Table Planning and Design WS

RPOLATION

riction Headloss per 100 meters

KALAHI-CIDSS PROJECT Reference for Annex 1-----60of 3


Fricstion Headloss Table Planning and Design WS

RPOLATION

riction Headloss per 100 meters

KALAHI-CIDSS PROJECT Reference for Annex 1-----61of 3


Fricstion Headloss Table Planning and Design WS

KALAHI-CIDSS PROJECT Reference for Annex 1-----62of 3


Fricstion Headloss Table Planning and Design WS

KALAHI-CIDSS PROJECT Reference for Annex 1-----63of 3


Fricstion Headloss Table Planning and Design WS

KALAHI-CIDSS PROJECT Reference for Annex 1-----64of 3


CONSTANT DISCHARGE AQUIFER PUMPING TEST DATA

Name of Sub-project : Construction of Pinanag-an Level I Water System (Gravity D


Location : Poblacion 7, Can avid Eastern Samar
Well No./Name : Dugwel
Well Depth : 4.94m
Pump Type : Type Cam 50
Pump Setting : 2.38m (orig. ground/top of the well)
Static Water Level : 1.28
Time Pump Started : 12:02 AM
Time Pump Stopped : 3:37 PM
Q ave. 0.49 lps

CLOCK Time After FLOW WATER DRAW SPECIFIC


READING Pump Started (Q) LEVEL DOWN CAPACITY
min. lps m m lps/m
12:02 0 0 2.38 0 0
12:07 5 0.49 2.15 0.23 2.13
12:12 10 0.49 1.99 0.16 1.26
12:17 15 0.49 1.92 0.07 1.06
12:22 20 0.49 1.86 0.06 0.94
12:27 25 0.49 1.8 0.06 0.84
12.32 30 0.49 1.75 0.05 0.78
12:37 35 0.49 1.71 0.04 0.73
12:42 40 0.49 1.67 0.04 0.69
12:47 45 0.49 1.64 0.03 0.66
12:52 50 0.49 1.61 0.04 0.63
12:57 55 0.49 1.59 0.02 0.62
1:02 60 0.49 1.57 0.03 0.60
1:07 65 0.49 1.55 0.02 0.59
1:12 70 0.49 1.53 0.02 0.58
1:17 75 0.49 1.52 0.02 0.57
1:22 80 0.49 1.51 0.01 0.56
1:27 85 0.49 1.50 0.01 0.55
1:32 90 0.49 1.49 0.01 0.55
1:37 95 0.49 1.48 0.01 0.54
1:42 100 0.49 1.47 0.01 0.54
1:47 105 0.49 1.46 0.01 0.53
1:52 110 0.49 1.44 0.02 0.52
1:57 115 0.49 1.42 0.02 0.51
2:02 120 0.49 1.41 0.01 0.51
2:07 125 0.49 1.40 0.01 0.50
2:12 130 0.49 1.39 0.02 0.49
2:17 135 0.49 1.38 0.01 0.49
2:22 140 0.49 1.37 0.01 0.49
2:27 145 0.49 1.36 0.01 0.48
2.32 150 0.49 1.34 0.03 0.47
2:37 155 0.49 1.33 0.01 0.47
2:42 160 0.49 1.32 0.01 0.46
2:47 165 0.49 1.31 0.01 0.46
2:52 170 0.49 1.30 0.01 0.45
2:57 175 0.49 1.29 0.01 0.45
3:02 180 0.49 1.29 0.01 0.45
3.07 185 0.49 1.28 0.01 0.44
3:12 190 0.49 1.28 0.00 0.44
3:17 195 0.49 1.28 0 0.44
3:22 200 0.49 1.28 0 0.44
3:27 205 0.49 1.28 0 0.44
3:32 210 0.49 1.28 0 0.44
3:37 215 0.49 1.28 0 0.44
3:42 220 0.49 1.28 0 0.44
3:47 225 0.49 1.28 0 0.44
3:52 230 0.49 1.28 0 0.44
3:57 235 0.49 1.28 0 0.44
4:02 240 0.49 1.28 0 0.44
4:07 245 0.49 1.28 0 0.44
4:12 250 0.49 1.28 0 0.44
4:17 255 0.49 1.28 0 0.44
4:22 260 0.49 1.28 0 0.44
4:27 265 0.49 1.28 0 0.44
4:32 270 0.49 1.28 0 0.44
4:37 275 0.49 1.28 0 0.44
4:42 280 0.49 1.28 0 0.44

Pumping Test Conducted by: Noted:


RECOVERY TEST DATA

Name of Project : Construction of Level II Water System (Pump Driven)


Location : Poblacion 7, Can avid Eastern Samar
Well No./Name : Dugwel
Well Depth : 4.94m
Static Water Level : Type Cam 50
Recovery Started : 4.94 (orig. ground/top of the well)
Recovery Stopped : 2.38 m

CLOCK Time AfterTime After WATER RESIDUAL


RATIO
TIME Pump Started Pump Stopped LEVEL DDOWN
t(minutes) t' (minutes) (t/t') m m
2:08 0
2:13 5
Recovery Test Conducted by: Noted:
NT DISCHARGE AQUIFER PUMPING TEST DATA

Construction of Pinanag-an Level I Water System (Gravity Driven)

(orig. ground/top of the well)

REMARKS

0
0.23
0.16
0.07
0.06
0.06
0.05
0.04
0.04
0.03
0.04
0.02
0.03
0.02
0.02
0.02
0.01
0.01
0.01
0.01
0.01
0.01
0.02
0.02
0.01
0.01
0.02
0.01
0.01
0.01
0.03
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.00
0
0
0
RECOVERY TEST DATA

Construction of Level II Water System (Pump Driven)

(orig. ground/top of the well)

REMARKS
Detailed Estimates

ANNEX 1a
FORMAT OF DETAILED COST ESTIMATES

The presentation of the materials, labor and equipment in details is helpful when implementing the subproject by c
account.
ITEM RESERVOIR ( 8 cu.m. )

A. MATERIALS
1) Computation of Quantities and Costing
Particular Compu Material Quantity
Description Specs. Factor ted Compu- Say Unit
Volume ted

B. LABOUR COST

Particular Quantity Gang Activity Duration Rate


Description Manpower Required Output Compu- Say per Day
ted

C. SUMMARY OF ITEM COST


Work No. of No. of Funding TOTAL
Particular Duration Manpower MD Inkind CASH
(P)

KALAHI-CIDSS PROJECT 73 of 7
Detailed Estimates

Note: cost not current

KALAHI-CIDSS PROJECT 74 of 7
Detailed Estimates

ITEM SPRING BOX ( Improvement )

A. MATERIALS
1) Computation of Quantities and Costing
Particular Compu Material Quantity
Description Specs. Factor ted Compu- Say Unit
Volume ted

B. LABOUR COST
Particular Quantity Gang Activity Duration Rate
Description Manpower Required Output Compu- Say per Day
ted

C. SUMMARY OF ITEM COST


Work No. of No. of Funding TOTAL
Particular Duration Manpower MD Inkind CASH
(P)

KALAHI-CIDSS PROJECT 75 of 7
Detailed Estimates

ITEM PIPELINE

A. MATERIALS
1) Computation of Quantities and Costing
Particular Pipeline Section Quantity
Unit Section/ Length Compu-
Description Specs. Location ted Say
(m)
Pipes and fittings
G.I. Pipe, sched. 40 31 mm x 6 m pc. a 500
G.I. Union patente 31 mm pc. a
G.I. Coupling 31 mm pc. a
G.I. Tee 31 x 31 mm pc. a
G.I. Reducer Bushing 31 x 13 mm pc. a
G.I. Plug 31 mm pc. a
G.I. Pipe, sched. 40 13 mm x 6 m pc. a
G.I. Coupling 13 mm pc. a
G.I. Elbow, 90 degrees13 mm pc. a
Brass Gate valve 13 mm pc. a

G.I. Reducer Bushing 31 x 19 mm pc. b


G.I. Pipe, sched. 40 19 mm x 6 m pc. b 10
G.I. Coupling 19 mm pc. b
G.I. Union patente 19 mm pc. b
G.I. Tee 19 x 19 mm pc. b
G.I. Plug 19 mm pc. b
G.I. Reducer Bushing 19 x 13 mm pc. b
G.I. Pipe, sched. 40 13 mm x 6 m pc. b
G.I. Coupling 13 mm pc. b
G.I. Elbow, 90 degrees13 mm pc. b
Brass Gate valve 13 mm pc. b

G.I. Pipe, sched. 40 31 mm x 6 m pc. c 1,200


G.I. Union patente 31 mm pc. c
G.I. Coupling 31 mm pc. c
G.I. Tee 31 x 31 mm pc. c

G.I. Reducer Bushing 31 x 25 mm pc. d


G.I. Pipe, sched. 40 25 mm x 6 m pc. d 20
G.I. Union patente 25 mm pc. d
G.I. Coupling 25 mm pc. d
G.I. Tee 25 x 25 mm pc. d
G.I. Plug 25 mm pc. d
G.I. Reducer Bushing 25 x 13 mm pc. d
G.I. Pipe, sched. 40 13 mm x 6 m pc. d
G.I. Coupling 13 mm pc. d
G.I. Elbow, 90 degrees13 mm pc. d
Brass Gate valve 13 mm pc. d

G.I. Reducer Bushing 38 x 31 mm pc. e


G.I. Pipe, sched. 40 31 mm x 6 m pc. e 240
G.I. Union patente 31 mm pc. e
G.I. Coupling 31 mm pc. e
G.I. Tee 31 x 31 mm pc. e

G.I. Reducer Bushing 38 x 25 mm pc. f

KALAHI-CIDSS PROJECT 76 of 7
Detailed Estimates

G.I. Pipe, sched. 40 25 mm x 6 m pc. f 320


G.I. Union patente 25 mm pc. f
G.I. Coupling 25 mm pc. f
G.I. Tee 31 x 31 mm pc. f
G.I. Reducer Bushing 31 x 25 mm pc. f
G.I. Reducer Bushing 31 x 13 mm pc. f
G.I. Pipe, sched. 40 13 mm x 6 m pc. f
G.I. Coupling 13 mm pc. f
G.I. Elbow, 90 degrees13 mm pc. f
Brass Gate valve 13 mm pc. f

KALAHI-CIDSS PROJECT 77 of 7
Detailed Estimates

G.I. Pipe, sched. 40 31 mm x 6 m pc. g 200


G.I. Union patente 31 mm pc. g
G.I. Coupling 31 mm pc. g
G.I. Tee 31 x 31 mm pc. g
G.I. Plug 31 mm pc. g
G.I. Reducer Bushing 31 x 13 mm pc. g
G.I. Pipe, sched. 40 13 mm x 6 m pc. g
G.I. Coupling 13 mm pc. g
G.I. Elbow, 90 degrees13 mm pc. g
Brass Gate valve 13 mm pc. g

Brass Gate valve 38 mm pc. h


G.I. Pipe, sched. 40 38 mm x 6 m pc. h 60
G.I. Union patente 38 mm pc. h
G.I. Coupling 38 mm pc. h
G.I. Tee 38 x 38 mm pc. h

Brass Gate valve 25 mm pc. i


G.I. Pipe, sched. 40 25 mm x 6 m pc. i 100
G.I. Union patente 25 mm pc. i
G.I. Coupling 25 mm pc. i
G.I. Tee 25 x 25 mm pc. i
G.I. Plug 25 mm pc. i
G.I. Reducer Bushing 25 x 13 mm pc. i
G.I. Pipe, sched. 40 13 mm x 6 m pc. i
G.I. Coupling 13 mm pc. i
G.I. Elbow, 90 degrees13 mm pc. i
G.I. Elbow, 45 degrees25 mm pc. i
Brass Gate valve 13 mm pc. i

Brss Gate valve 25 mm pc. j


G.I. Pipe, sched. 40 25 mm x 6 m pc. j 710
G.I. Union patente 25 mm pc. j
G.I. Coupling 25 mm pc. j
G.I. Elbow, 90 degrees25 mm pc. j

G.I. Elbow, 90 degrees38 mm pc. at reservoir overflow


Brass Gate valve 50 mm pc. drain at spring box & res.
G.I.Nipple, sched. 40 50 mm x 0.3 m pc. drain at spring box & res.
Perforated PVC Pipe 25 mm x 0.3 m pc. strainer at inlet of spring box
Brass Faucet 13 mm pc. faucet at tap stands

Others (tools to be turned-over to the (BWSA) association)


Teflon seal tape 3/4 inch roll accessories
Pipe wrench 12 inches long unit tools
Pipe wrench 14 inches long unit tools
Pipe threader 13, 19, 25, set tools
31, 38 mm
Hack saw unit tools
Hack saw blade pc. tools
TOTAL 3,360

KALAHI-CIDSS PROJECT 78 of 7
Detailed Estimates

B. LABOUR COST
Particular Quantity Gang Activity Duration Rate
Description Manpower Required Output Compu- Say per Day
ted

TOTAL 0

C. SUMMARY OF ITEM COST


Work No. of No. of Funding TOTAL
Particular Duration Manpower MD In Kind CASH
(P)

KALAHI-CIDSS PROJECT 79 of 7
Detailed Estimates

ITEM CREEK / RIVER CROSSING ( 2-Suspended type, 2-Submerged type)

A. MATERIALS
1) Computation of Quantities and Costing
Particular Compu Material Quantity
Description Specs. Factor ted Compu- Say Unit
Volume ted

TOTAL

B. LABOUR COST
Particular Quantity Gang Activity Duration Rate
Description Manpower Required Output Compu- Say per Day
ted

C. SUMMARY OF ITEM COST


Work No. of No. of Funding TOTAL
Particular Duration Manpower MD Inkind CASH
(P)

KALAHI-CIDSS PROJECT 80 of 7
Detailed Estimates

ITEM TAP STAND ( 6 Units )

A. MATERIALS
1) Computation of Quantities and Costing
Particular Compu Material Quantity
Description Specs. Factor ted Compu- Say Unit
Volume ted

B. LABOUR COST
Particular Quantity Gang Activity Duration Rate
Description Manpower Required Output Compu- Say per Day
ted

C. SUMMARY OF ITEM COST


Work No. of No. of Funding TOTAL
Particular Duration Manpower MD Inkind CASH
(P)

KALAHI-CIDSS PROJECT 81 of 7
Detailed Estimates

n implementing the subproject by community force

Unit TOTAL
Cost Cost
(P) (P)

Total
Labour
Cost

Percent
Weight
(%)

KALAHI-CIDSS PROJECT 82 of 7
Detailed Estimates

KALAHI-CIDSS PROJECT 83 of 7
Detailed Estimates

Unit TOTAL
Cost Cost
(P) (P)

Total
Labour
Cost

Percent
Weight
(%)

KALAHI-CIDSS PROJECT 84 of 7
Detailed Estimates

Unit Total
Cost Cost

(P) (P)

KALAHI-CIDSS PROJECT 85 of 7
Detailed Estimates

KALAHI-CIDSS PROJECT 86 of 7
Detailed Estimates

KALAHI-CIDSS PROJECT 87 of 7
Detailed Estimates

Total
Labour
Cost

Percent
Weight
(%)

KALAHI-CIDSS PROJECT 88 of 7
Detailed Estimates

d type, 2-Submerged type)

Unit TOTAL
Cost Cost
(P) (P)

Total
Labour
Cost

Percent
Weight
(%)

KALAHI-CIDSS PROJECT 89 of 7
Detailed Estimates

Unit TOTAL
Cost Cost
(P) (P)

Total
Labour
Cost

Percent
Weight
(%)

KALAHI-CIDSS PROJECT 90 of 7
KALAHI-CID
Project

Sub-Project Name

Elevation and Reinforcement of Spring Box


Location

Drawing Title
SPRING BOX

Sheet Title
Elevation and Reinforc

Scale
1 : 20 meters

Prepared

Checked

Sub-Project No.
KALAHI-CID
Project

Project Name

Plan and Reinforcement of Spring Box

Location

Drawing Title
SPRING BOX

Sheet Title
Plan and Reinforceme

Scale
1 : 20 meters

Prepared

Checked

Sub-Project No.
KALAHI-CID
Project

Sub-Project NameSub-

Manhole cover

Location

Drawing Title
SPRING BOX

Sheet Title
Manhole Cover

Scale
1 : 20 meters

Prepared

Checked

Sub-Project No.
KALAHI-CIDSS
Project

Elevation and Reinforcement

Concrete Mix
"A" (1:2:4)

Sheet No.
1 of 4
KALAHI-CIDSS
Project

Plan and Reinforcement

Concrete Mix
"A" (1:2:4)

Sheet No.
2 of 4
KALAHI-CIDSS
Project

Sub-Project NameSub-

Manhole Cover

Concrete Mix
"A" (1:2:4)

Sheet No.
3 of 4
BAR SCHEDULE-SPRING BOX
Total Quantity of 6-meter KALAHI-CIDSS
Bar Diagram Dia. Spacing Length Quantity Length lenght Bar Project
10 mm 12 mm
(mm) (m) (m) (m) (pcs.) (pcs.)

B Sub-Project Name

D Location

E Drawing Title
SPRING BOX

TOTAL Sheet Title


Elevation and Reinforcem

TABLE OF QUANTITIES Scale


Particular Unit Quantity Remarks
Description Specs.
Prepared

Checked

Sub-Project No.
KALAHI-CIDSS
Project

Elevation and Reinforcement

Concrete Mix
"A" (1:2:4)

Sheet No.
4 of 4
KALAHI-CIDSS Sub-Project Name Prepared Drawing Title
Project CREEK / RIVER CROSSING
Sheet Title
Location Checked Profile (Suspended type)
Scale
NTS
KALAHI-CIDSS Sub-Project Name Prepared Drawing Title
Project CREEK / RIVER CROSSING
Sheet Title
Location Checked Profile (Submerged type)
Scale
NTS
KALAHI-CIDSS Sub-Project Name Prepared Drawing Title
Project CREEK / RIVER CROSSING
Sheet Title
Location Checked Concrete Post Reinforcement Detail
Scale
NTS
TABLE OF QUANTITIES
Particular Unit Quantity Remarks
Description Specs.

Suspended crossing
Concrete Class "A" (1:2:4) cu.m. 0.48 For the two concrete posts
Portland cement 40 kg. bag 5
Sand cu.m. 0.25 (13 cans)
Gravel cu.m. 0.5 (25 cans)
RSB 12 mm x 6 m pc. 6 For stirrups
16 mm x 6 m pc. 8 For vertical bars
G.I. Wire Gauge # 16 kg. 2 As tie wire
Gauge # 4 roll 1 As suspension wire
Steel angle bar 1-1/2 x 1-1/2 x pc. 2 To hold the pipeline and where the
1/8 x 6 m suspension wire is attached to
Marine plywood 1/4" x 4' x 8' sheet 0 Re-use from reservoir
Rough lumber 2" x 2' x 8' pc. 0 Re-use from reservoir
Common nails kg. 0 Re-use from reservoir
Submerged crossing
RSB 12 mm x 6 m pc. 4 To anchor pipeline to river bed when
crossing under water. (One hook = 1 m)

KALAHI-CIDSS Sub-Project Name Prepared Drawing Title


Project CREEK / RIVER CROSSING
Sheet Title
Location Checked Table of Quantities
Scale
Sub-Project No.

Sheet No.
1 of 4
Sub-Project No.

Sheet No.
2 of 4
Sub-Project No.

Concrete Post Reinforcement Detail


Sheet No.
3 of 4
Sub-Project No.

Sheet No.
4 of 4
(REHABILITATION / IMPROVEMENT)

PANURAN SPRING DEVELOMENT


PROGRAM OF WORK

PANURAN SPRING DEVELOMENT


DETAILED ESTIMATE

PANURAN SPRING DEVELOMENT


SCHEMATIC DIAGRAM

PANURAN SPRING DEVELOMENT


DRAWINGS

PANURAN SPRING DEVELOMENT


RESERVOIR CAPACITY DESIGN
and
PIPELINE DESIGN and ANALYSIS

PANURAN SPRING DEVELOMENT


SPRING BOX

PANURAN SPRING DEVELOMENT


RESERVOIR

PANURAN SPRING DEVELOMENT


TAPSTAND

PANURAN SPRING DEVELOMENT


RIVER / CREEK CROSSING

PANURAN SPRING DEVELOMENT


BAR CHART

PANURAN SPRING DEVELOMENT


SUMMARY OF MATERIALS

PANURAN SPRING DEVELOMENT


UNIT COST OF MATERIALS

PANURAN SPRING DEVELOMENT


SUMMARY OF MATERIALS

Particular
Description Specs. Unit Qty. Remarks

A. Pipes and fittings


G.I. Pipe, sched. 40 38 mm x 6 m pc. 10
31 mm x 6 m pc. 358
25 mm x 6 m pc. 194
19 mm x 6m pc. 2
13 mm x 6 m pc. 3
G.I. Union patente 38 mm pc. 1
31 mm pc. 33
25 mm pc. 18
19 mm pc. 1
G.I. Coupling 38 mm pc. 8
31 mm pc. 321
25 mm pc. 171
19 mm pc. 1
13 mm pc. 6
G.I. Elbow, 90 degrees 38 mm pc. 2
25 mm pc. 3
13 mm pc. 12
G.I. Elbow, 45 degrees 25 mm pc. 2
G.I. Tee 38 x 38 mm pc. 1
31 x 31 mm pc. 5
25 x 25 mm pc. 2
19 x 19 mm pc. 1
G.I. Reducer Bushing 38 x 31 mm pc. 1
38 x 25 mm pc. 1
31 x 25 mm pc. 2
31 x 19 mm pc. 1
31 x 13 mm pc. 3
25 x 13 mm pc. 2
19 x 13 mm pc. 1
G.I. Plug 31 mm pc. 2
25 mm pc. 2
19 mm pc. 1
Brass Gate valve 50 mm pc. 2
38 mm pc. 1
25 mm pc. 1
13 mm pc. 6
Brass Faucet 13 mm pc. 6
G.I. Nipple sched. 40 50 mm x 0.3 m pc. 4
Perforated PVC pipe 31 mm x 0.3m pc. 1

B. Accessories
Teflon sealing tape 3/4 inch roll 100

KALAHI-CIDSS PROJECT Summary of Materials - page 128 of 142


C. Tools
Pipe Wrench 12 inches long pc. 1
14 inches long pc. 2
Pipe Threader 13, 19, 25, set 1
31, 38 mm
Hacksaw pc. 1
Hacksaw blade pc. 5

D. Others
Portland cement 40 kg. bag 55
Sahara compound pack 37
Marine plywood 1/4" x 4' x 8' sheet 18
Rough lumber 2" x 2' x 8' pc. 50
Steel angle bar 1-1/2 x 1-1/2 x 1/8 x 6 m pc. 2
RSB 10 mm x 6 m pc. 62
12 mm x 6 m pc. 33
16 mm x 6 m pc. 8
G.I. Wire Gauge # 16 kg. 7
Gauge # 4 roll 1
Common nails #4 kg. 25
# 1-1/2 kg. 3
Sand cu.m. 3.23
Gravel cu.m. 5.35

KALAHI-CIDSS PROJECT Summary of Materials - page 129 of 142


UNIT COST OF MATERIALS

Particular Unit Unit Remarks


Description Specs. Cost

A. Pipes and Fittings


G.I. Pipe sched. 40 38 mm x 6 m pc. 550.00
do 31 mm x 6 m pc. 468.00
do 25 mm x 6 m pc. 332.00
do 19 mm x 6 m pc. 285.00
do 13 mm x 6 m pc. 184.00
G.I. Union patente 38 mm pc. 116.00
do 31 mm pc. 88.00
do 25 mm pc. 62.00
do 19 mm pc. 47.00
G.I. Coupling 38 mm pc. 41.00
do 31 mm pc. 32.00
do 25 mm pc. 24.00
do 19 mm pc. 20.00
do 13 mm pc. 12.00
G.I. Elbow, 90 degrees 38 mm pc. 60.00
do 25 mm pc. 35.00
do 13 mm pc. 15.00
G.I. Elbow, 45 degrees 25 mm pc. 35.00
G.I. Tee 38 x 38 mm pc. 52.00
do 31 x 31 mm pc. 42.00
do 25 x 25 mm pc. 32.00
do 19 x 19 mm pc. 24.00
G.I. Reducer Bushing 38 x 31 mm pc. 32.00
do 38 x 25 mm pc. 34.00
do 31 x 25 mm pc. 26.00
do 31 x 19 mm pc. 28.00
do 31 x 13 mm pc. 30.00
do 25 x 13 mm pc. 25.00
do 19 x 13 mm pc. 20.00
G.I. Plug 31 mm pc. 20.00
do 25 mm pc. 12.00
do 19 mm pc. 8.00
Brass Gate valve 50 mm pc. 245.00
do 38 mm pc. 205.00
do 25 mm pc. 102.00
do 13 mm pc. 65.00
Brass Faucet 13 mm pc. 65.00
G.I. Nipple, sched. 40 50 mm x 0.3 m pc. 44.00
Perforated PVC Pipe 25 mm x 0.3 m pc. 27.00

B. Accessories
Teflon sealing tape 3/4 inch wide roll 20.00

KALAHI CIDSS PROJECT Unit Cost of Materials - page 130 of 142


C. Tools
Pipe Wrench 12 inches long unit 550.00
do 14 inches long unit 650.00
Pipe Threader Set (one handle, set 6,000.00
one 13 mm (1/2),
one 19 mm (3/4),
one 25 mm (1),
one 31 mm (1-1/4),
one 38 mm (1-1/2))
Hacksaw unit 85.00
Hacksaw Blade pc. 40.00

D. Others
Portland cement 40 kg. bag 140.00
Sahara compound pack 22.00
Marine plywood 1/4" x 4' x 8' sheet 375.00
Rough lumber 2"x 2' x 8' pc. 53.00
Steel angle bar 1-1/2 x 1-1/2 x 1/8 x 6 m pc. 250.00
RSB 10 mm x 6 m pc. 70.00
12 mm x 6 m pc. 77.00
16 mm x 6 m pc. 103.00
G.I.Wire Gauge # 16 kg. 43.00
Gauge # 4 roll 1,500.00
Common nail #4 kg. 30.00
# 1-1/2 kg. 35.00

KALAHI CIDSS PROJECT Unit Cost of Materials - page 131 of 142


PROGRAM OF WORK WS

OFFICE OF THE BARANGAY SUB-PROJECT MANAGEMENT COMMITTEE


Barangay ____________________________
Municipality of __________________________
Province of ____________________________

SUB-PROJECT PROGRAM OF WORKs

Sub-Project Title
Category
Physical Target
Total Sub-Project Cost

Project Description: Sub-Project Duration


Equipment Needed
Technical Personnel
Scope of Work %
Item No. Quantity Unit Unit Price Total
(Direct Cost) Wt.

Total
Breakdown Estimated Sources of Fund
Project Cost KALAHI-
Community Local Gov't.Units Other Source Total Cost
CIDSS Grant
A. Direct Cost

KALAHI CIDSS PROJECT 1 of 2


PROGRAM OF WORK WS

Materials Cost
Equipment Rental
Labor Cost:
a. Skilled
b. Unskilled
Sub-Total A

KALAHI CIDSS PROJECT 1 of 2


PROGRAM OF WORK WS

B. Indirect Cost
Pre-Engineering
Supervision
Contractor's Profit
Taxes
Hand Tools
Material Testing
Admin and Overhead
Sub-Total B
TOTAL (A+B)
ADD: Contingency
%
Total Estimated Cost
ADD: O&M (Other amenities)
Grand Total
Prepared by: Approved by:

Sevice Provider/Municipal Engineer BSPMC Chairperson

Reviewed by: Concurred by:

Deputy Area Coordinator Barangay Chairperson

Noted:
Municipal Mayor
Regional Infrastructure Engineer

Note: Costing to be used on the MIBF will be the Total Estimated Cost

KALAHI CIDSS PROJECT 1 of 2


IMPLEMENTATION SCHEDULE WS

BARANGAY SUB-PROJECT WORK SCHEDULE & PHYSICAL PROGRESS REPORT


For the Month of __________________, 200___

Name of Sub-project: ___________________________________ Total Sub-Project Cost:_______________________


Physical Target: _____________________________ Direct Cost:
Region: __________________________________ Indirect cost:
Province : __________________________________ Date Started:________________________________
Municipality : _______________________________ Target Completion Date: ______________________
Barangay: __________________________________ Mode of Implementation:

I. To be filled up by Deputy Area Coordinator


WEIGHT Physical Previous
ITEM No. DESCRIPTION QTY UNIT AMOUNT
(%) Target Cumm. Month 1
Planned
Actual
Planned
Actual
Planned
Actual
Planned
Actual
Planned
Actual
Planned
Actual
Planned
Actual
Planned
Actual
TOTAL 0 0

II To be filled up by Deputy Area Coordinator


PERIODIC
% PROGRESS (PLANNED)
CUMULATIVE
PHYSICAL

KALAHI CIDSS PROJECT 135 of 1


IMPLEMENTATION SCHEDULE WS

PHYSICAL
PERIODIC
% PROGRESS (ACTUAL)
CUMULATIVE
PERIODIC
% PROGRESS (PLANNED)
CUMULATIVE
CASH FLOW
PERIODIC
% PROGRESS (ACTUAL)
CUMULATIVE

III. Major Issues Encountered: IV. Recommendations

Prepared by: _____________________________ Concurred by:


PIT Chair/Skilled Person/Contractor Monitoring Team Leader

Approved by: _____________________________ _____________________


BSPMC Chairperson Deputy Area Coordinator

Note: Attach Material Records Sheet if physical accomplishment lags behind financial disbursements.

KALAHI CIDSS PROJECT 136 of 1


IMPLEMENTATION SCHEDULE WS

CAL PROGRESS REPORT


200___

Labor Ave.
Generat Total No. of Days Rate/Da
ed S-Curve

y
Male
Skilled
Female
Male
Unskilled
Female
TOTAL

DURATION
Month 1 Month 2 Month 3 Month 4

0 0 0 0 0 0 0 0 0 0 0 0 0 0

KALAHI CIDSS PROJECT 137 of 1


IMPLEMENTATION SCHEDULE WS

Recommendations

_____________________
Monitoring Team Leader Municipal Engineer

Noted:

Regional Infrastructure Engineer

KALAHI CIDSS PROJECT 138 of 1

Anda mungkin juga menyukai