Jurnal Tugas Akhir PDF
Jurnal Tugas Akhir PDF
DISUSUN OLEH:
ABSTRACT : Along with the development of more advanced in time, some progress
has been achieved by humans. Included in the construction world, especially in the use of
materials building materials. New building materials that are widely used by the public is
beginning to replace timber into mild steel in terms of its use as a roof truss construction
material. This study aims to determine the magnitude of the difference in the cost to make the
roof construction between using lightweight steel material and using wood materials in the area
of Makassar.
Using the example of the case of a building, the cost (RAB) in the manufacture of
construction of the timber roof truss obtained from the calculation of the volume of each
material that is based on the design drawing mild steel truss and wooden horses as well as the
unit price of each material and work force in the area of Makassar.
Based on the research results, obtained by the difference between the percentage of
construction lightweight steel truss construction job with timber truss job ranging from 29.23%
to the cost of the timber truss. Where the cost of making the mild steel truss is cheaper than
manufacturing of timber truss.
2
1. PENDAHULUAN Meskipun tipis, baja ringan memiliki
derajat kekuatan tarik 550 MPa,
Latar Belakang sementara baja biasa sekitar 300 MPa.
Atap adalah salah satu bagian yang Berdasarkan pembahasan diatas,
penting pada suatu bangunan. Tugas pekerjaan atap dapat dibuat dengan
atap adalah untuk melindungi penghuni menggunakan material kayu maupun
bangunan dari sinar matahari yang dapat menggunakan material baja
terik, air hujan, dan cuaca yang ringan. Pemilihan bahan antara kayu
berubah-ubah sesuai musimnya. Salah atau baja ringan, jelas mempengaruhi
satu bagian dari konstruksi atap adalah biaya yang harus disediakan. Untuk itu,
kuda-kuda. Kuda-kuda merupakan penulis mengadakan penelitian untuk
bagian yang penting daripada atap, mengetahui perbedaan biaya dalam
karena semua beban atap ditanggung memasang kerangka atap berbahan
oleh kuda-kuda. kayu dengan kerangka atap berbahan
Material kuda-kuda yang paling baja ringan, dengan mengangkat judul
sering dijumpai orang adalah kayu. “Analisa Perbandingan Biaya Pada
Kayu sudah menjadi material kuda- Kuda-Kuda Baja Ringan Dengan
kuda sejak lama, dikarenakan karena Kuda-Kuda Kayu” dengan mengambil
kayu mempunyai daya dukung yang contoh kasus sebuah gedung dengan
memadai, dan juga kayu cukup tahan desain atap berbentuk pelana dan
terhadap lingkungan sekitarnya, memiliki luas atap 488 M².
termasuk cuaca selama kayu tetap
dijaga dalam kondisi kering. Meskipun Tujuan Penulisan
demikian, kayu merupakan bagian Tujuan penulisan ini adalah untuk
daripada alam dimana umurnya dapat mengetahui perbedaan biaya konstruksi
dipengaruhi dengan kondisi alam kuda-kuda kayu dengan biaya
disekitarnya seperti kehadiran rayap, konstruksi kuda-kuda baja ringan.
tikus, atau lumut yang dapat saja
timbul pada permukaan kayu. Apalagi
sekarang ini, hutan yang tadinya lebat 2. METODOLOGI PENELITIAN
mulai menjadi gundul karena
meningkatnya permintaan manusia Langkah Pelaksanaan Penelitian
terhadap kayu, sehingga mengancam Langkah yang dilakukan dalam
ekosistem alam. pelaksanaan penelitian ini, dapat
Karena melihat keberadaan kayu dijelaskan pada bagan di bawah ini :
yang mulai tidak tentu, maka dianggap Mulai
perlu untuk mencari material lain yang Studi Pustaka
juga memadai. Salah satu material Pengumpulan Data
yang mumpuni untuk digunakan adalah
baja ringan. Baja ringan merupakan Baja
Kayu
baja profil yang dibentuk dalam Ringan
4
Sedangkan untuk menghitung atap, kualitas material, lokasi proyek,
volume paku digunakan perhitungan; dan volume pekerjaan. Dari sisi bisnis,
Kebutuhan paku = volume pekerjaan x harga produksi ditentukan oleh factor
koefisien paku seperti overhead, harga baja dunia,
*Untuk koefisien paku diperoleh dari biaya promosi dan pemasaran, biaya
SNI 3434-2008 tentang “Tata Cara sewa kantor, dan biaya-biaya lain.
Perhitungan Harga Satuan Pekerjaan Perlu diketahui bahwa standar harga
Kayu untuk Konstruksi Bangunan konstruksi atap baja ringan dihitung
Gedung dan Perumahan” permeter persegi miring (luasan
genteng). (Wicaksono, 2014).
Pekerjaan Atap dari Baja Ringan
Dalam tahap pelaksanaan 4. HASIL DAN PEMBAHASAN
pemasangan atap baja ringan ini sudah
tentunya Data Teknis Bangunan
dilakukan oleh pekerja yang Luas bangunan : 435 m² (30m x
didatangkan langsung oleh pihak 14,5m)
supplier baja ringan Luas atap : 488,43 m²
karena untuk pekerjaan atap baja a) Atap utama : 421,45 m²
ringan tidak bisa dikerjakan oleh b) Atap depan : 25,52 m²
tukang-tukang c) Atap belakang : 41,46 m²
biasa. Pekerja untuk memasang atap Kemiringan atap : 30º
baja ringan haruslah bersertifikat baik Jenis penutup atap : Genteng
pernah metal (770mm x 800mm)
mengikuti pelatihan atau biasanya Desain bentuk atap : Atap
bersertifikat dari pihak supplier dan Pelana
kontraktor Beban yang bekerja pada atap
baja ringan. a) Beban mati : Beban rangka
Setelah kuda-kuda siap untuk atap dan penutup atap
diletakan pada posisinya sesuai dengan b) Beban hidup : Berat manusia
gambar desain selanjutnya pekerja saat pemasangan
tinggal memasangkannya dengan c) Beban angin : Beban angin
melihat aturan atau prosedur sesuai tekan dan angin hisap
gambar yang telah dihitung dengan out
Konsultan baja ringan : Cv.
put softwere khusus baja ringan, Cheeqal Baldan Utama
dimana ukuran dan jumlah batang-
Suplier Baja Ringan : PT.
batang lain selain kuda-kuda serta
Kepuh Kencana Arum
jumlah self drilling screw ( SDS )
sudah tertera dalam out put hasil Material kuda-kuda
a) Kuda-kuda kayu : Kayu
analisa software. Dengan dibantu alat-
kelas I (kayu besi/bayam)
alat pembantu lainnya seperti bor listrik
b) Kuda-kuda baja ringan :
dengan kontrol torsi untuk memasang
Kencana truss
SDS dan grinda untuk memotong
kelebihan-kelebihan material baja
ringan agar presisi dan hasilnya rapih. Analisa Biaya
Untuk denah kuda-kuda baja ringan,
Dengan demikian rangka atap baja
ringan pun dapat dikerjakan. dapat dilihat pada gambar dibawah ini;
Harga ditentukan oleh berbagai
macam faktor, seperti merek, desain
5
Tabel 2. Rincian Biaya upah tenaga
kerja pekerjaan rangka baja ringan dan
reng untuk genteng metal
Volume
Total Harga
No Uraian Satuan Koef Harga Satuan Pekerjaan
(Rp)
(m²)
Pekerja
1 OH 0,247 Rp 70.000
8.444.954,70
Tukang
2 OH 0,176 Rp 90.000
Besi 7.736.731,20
488,43
Gambar 2. denah kuda-kuda baja Kepala
ringan 3 OH 0,117 Rp 140.000
Tukang 8.000.483,40
Berdasarkan gambar diatas
Mandor
kemudian kemudian dibuatkan tabel 4 OH 0,050
untuk membuat rincian biaya kuda- Rp 150.000 3.663.225,00
kuda baja ringan. TOTAL HARGA 27.845.394,30
Tabel 1. Rincian Biaya Material
Rangka Atap Baja Ringan Untuk denah kuda-kuda baja ringan,
KUDA-KUDA BAJA RINGAN
dapat dilihat pada gambar dibawah ini;
Jumlah material
No Nama Material Satuan Harga satuan Harga total
total
Rangka Baja
1 Bottom chord Profil C75.75 110 Batang 72500 Rp 7.975.000,00
2 Top chord Profil C75.75 162 Batang 72500 Rp 11.745.000,00
3 Web Profil C75.75 417 Batang 72500 Rp 30.232.500,00
Batang
4 Profil C75.75 125 Batang 12000 Rp 1.500.000,00
Penyambung
5 Batang pengaku Profil C75.75 72 Batang 72500 Rp 5.220.000,00
6 Baut-12 12-14x20 HEX 4451 Pcs 200 Rp 890.200,00
7 Footplate Bracket L 50 Pcs 1800 Rp 90.000,00
8 Dynabolt M10x100 mm 100 Pcs 1500 Rp 150.000,00
Rangka Atap
9 Reng Profil R30.45 245 Batang 31900 Rp 7.815.500,00
10 Baut-10 10-16x16 HEX 5402 Pcs 130 Rp 702.260,00
6
Tabel 3. Rincian Biaya Material
Rangka Atap Baja Ringan Tabel 5. Menghitung upah tenaga kerja
KUDA-KUDA KAYU
Harga per
pemasangan konstruksi gording dan
No Pekerjaan Uraian Volume Total Satuan
kubik atau Jumlah harga nok
harga satuan (Rp)
Volume
(Rp)
Total Harga
Rangka Kuda-Kuda Kebutuhan Satuan Koefisien Harga Satuan Pekerjaan
1 Balok Tarik Kayu 5/10 x 400 cm 1,7821 m3 10000000 Rp 17.821.000 (Rp)
2 Kaki kuda-kuda Kayu 5/10 x 400 cm 0,97136 m3 10000000 Rp 9.713.600 (
(m³)
3 Balok Tengah Kayu 5/10 x 300 cm 0,22935 m3 10000000 Rp 2.293.500 Pekerja OH 2,4 Rp70.000 554.694
4 Balok skor Kayu 5/10 x 400 cm 1,1258 m3 10000000 Rp 11.258.000
5 Balok skor angin Kayu 5/10 x 400 cm 0,435 m3 10000000 Rp 4.350.000 Tukang
6 Balok gapit Kayu 5/10 x 400 cm 1,60368 m3 10000000 Rp 16.036.800 OH 7,2 Rp85.000 2.020.671
Tenaga Kayu
7 Balok kunci Kayu 5/10 x 100 cm 0,12089 m3 10000000 Rp 1.208.900 3,30175
8 klos kayu 5/10 x 15 cm 0 m3 10000000 Rp - Kerja Kepala
OH 0,72 Rp140.000 332.816,40
Rangka Atap Tukang
9 Gording Kayu 5/10 x 300 cm 3,09 m3 10000000 Rp 30.900.000 Mandor OH 0,12 Rp150.000 495.262,50
10 Nok Kayu 5/10 x 400 cm 0,15075 m3 10000000 Rp 1.507.500
11 Kasau Kayu 5/7 x 400 cm 4,04285 m3 9000000 Rp 36.385.650 Total Harga 3.403.443,90
12 Reng Kayu 3/4 x 300 cm 1,666656 m3 7000000 Rp 11.666.592
7
Grafik 1. Perbandingan Biaya Total
Kuda-Kuda
Berdasarkan grafik diatas, diperoleh
selisih biaya material kuda-kuda
kuda kayu
dengan kuda-kuda
kuda baja ringan sebesar
Rp. 83.766.682,00, dimana material
baja ringan lebih murah dibanding
dengan material kayu. Persentase
selisihnya sebesar 37% terhadap kayu. erbandingan biaya kuda
Grafik 3. Perbandingan kuda-
Sedangkan selisih biaya upah tenaga kuda kayu dengan baja ringan
kerja diperoleh sebesar Rp.14.552.377,
dimana upah tenaga kerja kudakuda-kuda
kayu lebih murah dibanding upah Berdasarkan grafik diatas, diperoleh
tenaga kerja baja ringan. Persentase selisih biaya sebesar Rp 69.214.305,22
selisihnya sebesar 52% terhadap baja (enam puluh sembilan juta dua ratus
ringan. empat belas ribu tiga ratus lima koma
dua puluh dua rupiah). Dimana
penggunaan baja ringan lebih murah
dibandingkan penggunaan kuda kuda-kuda
kayu pada gedung. Persentase
selisihnya
sihnya sekitar 29,23 % terhadap
biaya kuda-kuda kayu.
Kesimpulan
1. Berdasarkan hasil perhitungan,
Grafik 2. Perbandingan Biaya Kuda-
Kuda diperoleh biaya total pekerjaan
Kuda Per m² konstruksi kuda-kuda kuda baja
ringan pada gedung sebesar Rp
Jumlah biaya per m² diperoleh dari 167.605.854,30
jumlah biaya dibagi dengan luas atap 2. Berdasarkan hasil perhitungan,
488,43 m². Berdasarkan grafik diatas, diperoleh biaya total pekerjaan
diperoleh selisih biaya material kuda- konstruksi kuda-kudakuda kayu
kuda kayu dengan kuda-kuda kuda baja pada gedung sebesar Rp
ringan sebesar Rp 171.502. Sedangkan 236.820.159,52.
selisih biaya upah tenaga kerja 3. Diperoleh selisih antara
diperoleh sebesar Rp 29.794. pekerjaan konstruksi kuda
kuda-kuda
baja ringan dengan pekerjaan
Untuk biaya keseluruhanuruhan total konstruksi kuda-kudakuda kayu
pekerjaan kuda-kuda
kuda (biaya material + sebesar Rp 69.214.305,22.
upah tenaga kerja) pada kuda kuda-kuda Dimana pekerjaan kosntruksi
kosnt
kayu dan kuda-kuda
kuda baja ringan dapat kuda-kuda
kuda baja ringan lebih
dilihat pada grafik 3 dibawah ini; murah dibandingkan pekerjaan
kuda-kuda
kuda kayu. Persentase
selisihnya sekitar 29,23 %
terhadap biaya kuda-kuda
kuda kayu.
8
4. Berdasarkan hasil perhitungan, konstruksi kuda-kuda, maka
diperoleh sisa material pada ada baiknya jika meminta
pekerjaan kuda-kuda baja rekomendasi dari pihak-pihak
ringan sebanyak 72 Pcs yang yang mengerti industri
berasal dari sisa pemotongan konstruksi, seperti konsultan
batang reng. Sedangkan sisa atau arsitek bangunan.
material pada pekerjaan kuda- Mengingat semakin banyaknya
kuda kayu sebanyak 92 Pcs. rangka atap baja ringan yang
5. Material baja ringan merupakan dipasarkan maka semakin
sebuah solusi untuk mengganti banyak pula pilihan yang
material kayu sebagai beragam bagi konsumen.
pembuatan kuda-kuda. Selain
harganya yang lebih murah, sisa
material yang dihasilkan di
lapangan tidak terlalu banyak DAFTAR PUSTAKA
dibandingkan dengan kayu.
Selain itu, dengan Agustinus, W. (2011). Panduan
menggunakan baja ringan dapat Konsumen Memilih Konstruksi
mengurangi eksploitasi kayu Baja Ringan. Yogyakarta: CV.
secara berlebihan sehingga Andi Offset.
dapat melestarikan hutan. Frick, Heinz., & Moediartianto. (
2003). Ilmu Konstruksi
Saran Bangunan Kayu, Yogyakarta:
1. Analisa perhitungan biaya ini Penerbit Kanisius.
dilakukan pada tahun 2014, Hesna, Yervi. (2009). Komparasi
dengan harga yang berlaku saat Penggunaan Kayu dan Baja
itu. Oleh karena itu untuk Ringan Sebagai Konstruksi
peneliti selanjutnya, perlu Rangka Atap. Jurnal Teknik Sipil
dianalisia kembali biaya dengan Universitas Andalas. Vol 1: hal
melakukan penyesuaian harga 1-7
upah dan bahan yang berlaku. Ibrahim, H. Bachtiar. (2001). Rencana
2. Perlu diadakan penelitian lebih dan Estimate Real of Cost,
lanjut untuk menentukan indeks Jakarta: PT. Bumi Aksara.
tenaga kerja pekerjaan baja Sutersman, Nobel. (2003). Analisa
ringan, mengingat belum Baja Ringan Sebagai Konstruksi
adanya standarisasi untuk Kuda-Kuda. Skripsi. Makassar:
pekerjaan kuda-kuda baja Universitas Hasanuddin.
ringan. Sehingga akan SNI 3434-2008, Tata Cara Perhitungan
diperoleh biaya yang lebih riil Harga Satuan Pekerjaan Kayu
dalam menyusun rencana Untuk Konstruksi Bangunan
anggaran biaya kuda-kuda baja Gedung dan Perumahan.
ringan.
3. Untuk konsumen, jika memilih
rangka baja ringan sebagai