Jadwal Ok
Jadwal Ok
08-Jul 15-Jul 22-Jul 29-Jul 05-Agt 12-Agt 19-Agt 26-Agt 02-Sep 09-Sep 16-Sep 23-Sep 30-Sep 07-Okt 14-Okt 21-Okt 28-Okt 04-Nov 11-Nov 18-Nov 25-Nov 02-Des 08-Des
-
A PEKERJAAN AWAL - 100
A.1 Pembersihan Awal Lokasi Ls 1.00 700,000 700,000.00 0.23% 0.11 0.11
A.2 Pengkuruan dan Pemasangan Bowplank Ls 1.00 1,300,000 1,300,000.00 0.43% 0.43
A.4 Penyediaan Air Kerja/Listrik Kerja Ls 1.00 725,000 725,000.00 0.24% 0.24
SUB TOTAL PEKERJAAN AWAL - 2,925,000.00 0.96%
B PEKERJAAN TANAH -
B.1 Galian Tanah untuk Pondasi m3 42.57 60,280 2,566,119.60 0.84% 0.24 0.47 0.13
B.2 Urugan Tanah Galian Kembali m3 10.64 39,050 415,492.00 0.14% 0.14
B.3 Urugan Sirtu Peninggi Lantai m3 63.94 128,432 8,211,916.50 2.69% 1.16 1.52
B.4 Urugan Pasir di Bawah Pondasi m3 3.28 146,850 481,668.00 0.16% 0.16
B.5 Urugan Pasir di Bawah Lantai m3 16.15 146,850 2,371,627.50 0.78% 0.78
SUB TOTAL PEKERJAAN TANAH - 14,046,823.60 4.60%
C PEKERJAAN PASANGAN DAN PLESTERAN -
C.1 Aanstamping m3 12.20 294,534 3,593,320.41 1.18% 1.18
C.2 Pasangan Pondasi Batu Kali (1 Pc : 4 Psr) m3 33.89 578,793 19,615,277.83 6.42% 6.42
C.3 Pasangan Pondasi Rolag & Tangga (1 Pc : 4 Psr) m3 6.92 578,793 4,005,244.10 1.31% 1.31
C.4 Pasangan Tembok Bata Merah (1 Pc : 5 Psr) m2 173.34 150,189 26,033,846.20 8.52% 0.42 4.41 1.48 1.08 1.13
C.5 Plesteran (1 Pc : 5 Psr) Tebal 15 mm m2 403.12 49,013 19,758,265.68 6.46% 3.21 3.25
D.2 Pek. Beton Bertulang untuk Kolom praktis m3 1.52 7,118,037 10,819,415.69 3.54% 3.54
D.3 Pek. Beton Bertulang untuk Sloof m3 1.85 4,297,497 7,950,368.53 2.60% 2.60
D.4 Pek. Beton Bertulang untuk Ringbalk 15/40 m3 0.33 5,495,951 1,813,663.80 0.59% 0.59
D.5 Pek. Beton Bertulang untuk Ringbalk m3 1.38 5,495,951 7,584,412.24 2.48% 2.48
D.6 Pek. Beton Bertulang untuk Balok Latei m3 0.81 5,495,951 4,451,720.23 1.46% 1.46
D.7 Pek. Beton Bertulang untuk Plat Level m3 1.14 5,041,554 5,747,371.67 1.88% 1.88
D.8 Pek. Beton Bertulang untuk Plat m3 0.14 5,041,554 705,817.57 0.23% 0.23
D.9 Pek. Beton Tidak Bertulang untuk Rabat m3 4.15 825,416 3,425,476.22 1.12% 1.12
SUB TOTAL PEKERJAAN BETON - 44,135,394.38 14.44%
E PEKERJAAN KUSEN, PINTU/JENDELA, KACA, KUNCI DAN PENGANTUNG -
E.1 Kusen Kayu Jati m3 0.34 7,797,020 2,650,986.80 0.87% 0.87
E.2 Kusen + Daun Pintu PVC Beserta Perlengkapannya Unit 1.00 570,000 570,000.00 0.19% 0.19
E.3 Daun Pintu Panil Kayu Jati m2 11.24 477,932 5,371,950.28 1.76% 1.76
E.4 Daun Jendela Panil Kaca Rangka Kayu Jati m2 6.30 425,810 2,682,603.00 0.88% 0.88
E.6 Pasang Kunci Tanam 2 x Putar Bh 7.00 250,349 1,752,443.00 0.57% 0.57
SUB TOTAL PEKERJAAN KUSEN, PINTU/JENDELA, KACA, KUNCI DAN PENGANTUNG 17,070,362.76 5.58%
F PEKERJAAN PLAFOND, PENUTUP LANTAI DAN DINDING
F.1 Pasang Lantai Keramik 40/40 cm m2 87.32 152,807 13,343,063.58 4.37% 4.37
F.2 Pasang Lantai Keramik 20/20 cm m2 4.31 162,289 699,463.44 0.23% 0.23
F.3 Pasang Dinding Keramik 20/25 cm m2 10.08 145,019 1,461,786.48 0.48% 0.48
F.4 Pasang Plint Keramik 10/40 cm m2 67.15 93,023 6,246,467.59 2.04% 2.04
F.5 Rangka Plafond Kayu Klas. II m2 110.97 106,381 11,805,099.57 3.86% 3.86
F.7 List Plafond Kayu Profil m1 173.20 18,832 3,261,702.40 1.07% 1.07
F.8 Pasang Dinding Batu Alam m2 29.88 282,601 8,444,117.88 2.76% 2.76
SUB TOTAL PEKERJAAN PLAFOND, PENUTUP LANTAI DAN DINDING - 49,671,371.31 16.25%
G PEKERJAAN KUDA-KUDA DAN PENUTUP ATAP -
G.1 Pekerjaan Konstruksi Kuda-kuda Kayu Klas II m3 1.41 5,119,400 7,218,354.01 2.36% 2.36
G.2 Pekerjaan Konstruksi Gording Kayu Klas II m3 1.43 6,252,785 8,941,482.55 2.93% 2.93
G.3 Pekerjaan Atap Seng Gelombang BJLS 0.30 m2 143.37 65,164 9,342,562.68 3.06% 3.06
G.4 Pekerjaan Seng Licin Bubungan m1 32.80 34,551 1,133,272.80 0.37% 0.37
G.5 Pekerjaan Lisplank Kayu Klas II Ukuran (2 x 2,5 x 18) cm m1 44.40 71,610 3,179,484.00 1.04% 1.04
SUB TOTAL PEKERJAAN KUDA-KUDA DAN PENUTUP ATAP - 29,815,156.04 9.75%
H PEKERJAAN PENGECATAN -
H.1 Pengecatan Tembok m2 403.12 25,809 10,403,956.07 3.40% 3.40 40
MATI
H.2 Pengecatan Plafond m2 110.97 25,809 2,863,979.23 0.94% 0.94
I.5 Pasang Lampu LED 13 Watt Bh 6.00 81,686 490,116.00 0.16% 0.16
I.6 Pasang Lampu LED 7 Watt Bh 7.00 72,873 510,109.60 0.17% 0.17
J.5 Pasang Kictchen Zinc 1 Lubang Bh 1.00 607,761 607,761.00 0.20% 0.20 20
J.6 Pasang Pipa PVC Dia 4" + acc m1 4.00 128,774 515,094.80 0.17% 0.17
J.7 Pasang Pipa PVC Dia 2" + acc m1 4.00 58,375 233,499.20 0.08% 0.08
J.8 Pasang Pipa GIP Dia 0,5" + acc m1 12.00 61,414 736,969.20 0.24% 0.24
J.9 Septiktank dan Peresapan Unit 1.00 2,250,000 2,250,000.00 0.74% 0.74
K.2 Pompa Air + Instalasi Pipa + acc Ls 1.00 2,000,000 2,000,000.00 0.65% 0.65
K.4 Huruf Nama Kantor Tinggi 20 cm Bh 15.00 200,000 3,000,000.00 0.98% 0.98
K.5 Huruf Nama Kantor Tinggi 15 cm Bh 25.00 150,000 3,750,000.00 1.23% 1.23
K.6 Biaya Pengadaan Genset 5 KVA Ls 1.00 11,500,000 11,500,000.00 3.76% 3.76
K.7 Pek. Tiang Bendera + acc Ls 1.00 1,500,000 1,500,000.00 0.49% JADWAL REALISASI 0.49
SUB TOTAL PEKERJAAN BAK PENAMPUNG DAN LAIN - LAIN - 32,532,601.03 10.64% LAPANGAN
L PEKERJAAN AKHIR -
L.1 Pembersihan Akhir Lokasi Ls 1.00 1,000,000 1,000,000.00 0.33% 0.33
L.2 Biaya Administrasi, Pelaporan, As Built Brawing & Dokumentasi Ls 1.00 1,000,000 1,000,000.00 0.33% 0.33 0.00
SUB TOTAL PEKERJAAN AKHIR - 2,000,000.00 0.65%
08-Jul 15-Jul 22-Jul 29-Jul 05-Agt 12-Agt 19-Agt 26-Agt 02-Sep 09-Sep 16-Sep 23-Sep 30-Sep 07-Okt 14-Okt 21-Okt 28-Okt 04-Nov 11-Nov 18-Nov 25-Nov 02-Des 08-Des
-
A PEKERJAAN AWAL - 100
A.1 Pembersihan Awal Lokasi Ls 1.00 700,000 700,000.00 0.23% 0.11 0.11
A.2 Pengkuruan dan Pemasangan Bowplank Ls 1.00 1,300,000 1,300,000.00 0.43% 0.43
A.3 Papan Nama Proyek Ls 1.00 200,000 200,000.00 0.07% 0.07
A.4 Penyediaan Air Kerja/Listrik Kerja Ls 1.00 725,000 725,000.00 0.24% 0.24
SUB TOTAL PEKERJAAN AWAL - 2,925,000.00 0.96%
B PEKERJAAN TANAH -
B.1 Galian Tanah untuk Pondasi m3 42.57 60,280 2,566,119.60 0.84% 0.24 0.47 0.13
B.2 Urugan Tanah Galian Kembali m3 10.64 39,050 415,492.00 0.14% 0.14
B.3 Urugan Sirtu Peninggi Lantai m3 63.94 128,432 8,211,916.50 2.69% 1.16 1.52
B.4 Urugan Pasir di Bawah Pondasi m3 3.28 146,850 481,668.00 0.16% 0.16
B.5 Urugan Pasir di Bawah Lantai m3 16.15 146,850 2,371,627.50 0.78% 0.78
SUB TOTAL PEKERJAAN TANAH - 14,046,823.60 4.60%
C PEKERJAAN PASANGAN DAN PLESTERAN -
C.1 Aanstamping m3 12.20 294,534 3,593,320.41 1.18% 1.18
C.2 Pasangan Pondasi Batu Kali (1 Pc : 4 Psr) m3 33.89 578,793 19,615,277.83 6.42% 6.42
C.3 Pasangan Pondasi Rolag & Tangga (1 Pc : 4 Psr) m3 6.92 578,793 4,005,244.10 1.31% 1.31
C.4 Pasangan Tembok Bata Merah (1 Pc : 5 Psr) m2 173.34 150,189 26,033,846.20 8.52% 0.42 4.41 1.48 1.08 1.13
C.5 Plesteran (1 Pc : 5 Psr) Tebal 15 mm m2 403.12 49,013 19,758,265.68 6.46% 3.21 3.25
D.2 Pek. Beton Bertulang untuk Kolom praktis m3 1.52 7,118,037 10,819,415.69 3.54% 3.54
D.3 Pek. Beton Bertulang untuk Sloof m3 1.85 4,297,497 7,950,368.53 2.60% 2.60
D.4 Pek. Beton Bertulang untuk Ringbalk 15/40 m3 0.33 5,495,951 1,813,663.80 0.59% 0.59
D.5 Pek. Beton Bertulang untuk Ringbalk m3 1.38 5,495,951 7,584,412.24 2.48% 2.48
D.6 Pek. Beton Bertulang untuk Balok Latei m3 0.81 5,495,951 4,451,720.23 1.46% 1.46
D.7 Pek. Beton Bertulang untuk Plat Level m3 1.14 5,041,554 5,747,371.67 1.88% 1.88
D.8 Pek. Beton Bertulang untuk Plat m3 0.14 5,041,554 705,817.57 0.23% 0.23
D.9 Pek. Beton Tidak Bertulang untuk Rabat m3 4.15 825,416 3,425,476.22 1.12% 1.12
SUB TOTAL PEKERJAAN BETON - 44,135,394.38 14.44%
E PEKERJAAN KUSEN, PINTU/JENDELA, KACA, KUNCI DAN PENGANTUNG -
E.1 Kusen Kayu Jati m3 0.34 7,797,020 2,650,986.80 0.87% 0.87
E.2 Kusen + Daun Pintu PVC Beserta Perlengkapannya Unit 1.00 570,000 570,000.00 0.19% 0.19
E.3 Daun Pintu Panil Kayu Jati m2 11.24 477,932 5,371,950.28 1.76% 1.76
E.4 Daun Jendela Panil Kaca Rangka Kayu Jati m2 6.30 425,810 2,682,603.00 0.88% 0.88
E.6 Pasang Kunci Tanam 2 x Putar Bh 7.00 250,349 1,752,443.00 0.57% 0.57
SUB TOTAL PEKERJAAN KUSEN, PINTU/JENDELA, KACA, KUNCI DAN PENGANTUNG 17,070,362.76 5.58%
F PEKERJAAN PLAFOND, PENUTUP LANTAI DAN DINDING
F.1 Pasang Lantai Keramik 40/40 cm m2 87.32 152,807 13,343,063.58 4.37% 4.37
F.2 Pasang Lantai Keramik 20/20 cm m2 4.31 162,289 699,463.44 0.23% 0.23
F.3 Pasang Dinding Keramik 20/25 cm m2 10.08 145,019 1,461,786.48 0.48% 0.48
F.4 Pasang Plint Keramik 10/40 cm m2 67.15 93,023 6,246,467.59 2.04% 2.04
F.5 Rangka Plafond Kayu Klas. II m2 110.97 106,381 11,805,099.57 3.86% 3.86
F.6 Plafond Tripleks 3 mm m2 110.97 39,738 4,409,670.38 1.44% JADWAL RENCANA 1.44
F.7 List Plafond Kayu Profil m1 173.20 18,832 3,261,702.40 1.07% TERKONTRAK 1.07
F.8 Pasang Dinding Batu Alam m2 29.88 282,601 8,444,117.88 2.76% 2.76
SUB TOTAL PEKERJAAN PLAFOND, PENUTUP LANTAI DAN DINDING - 49,671,371.31 16.25%
G PEKERJAAN KUDA-KUDA DAN PENUTUP ATAP -
G.1 Pekerjaan Konstruksi Kuda-kuda Kayu Klas II m3 1.41 5,119,400 7,218,354.01 2.36% 2.36
G.2 Pekerjaan Konstruksi Gording Kayu Klas II m3 1.43 6,252,785 8,941,482.55 2.93% 2.93
G.3 Pekerjaan Atap Seng Gelombang BJLS 0.30 m2 143.37 65,164 9,342,562.68 3.06% 3.06
G.4 Pekerjaan Seng Licin Bubungan m1 32.80 34,551 1,133,272.80 0.37% 0.37
G.5 Pekerjaan Lisplank Kayu Klas II Ukuran (2 x 2,5 x 18) cm m1 44.40 71,610 3,179,484.00 1.04% 1.04
SUB TOTAL PEKERJAAN KUDA-KUDA DAN PENUTUP ATAP - 29,815,156.04 9.75%
H PEKERJAAN PENGECATAN -
H.1 Pengecatan Tembok m2 403.12 25,809 10,403,956.07 3.40% 3.40 40
MATI
H.2 Pengecatan Plafond m2 110.97 25,809 2,863,979.23 0.94% 0.94
I.5 Pasang Lampu LED 13 Watt Bh 6.00 81,686 490,116.00 0.16% 0.16
I.6 Pasang Lampu LED 7 Watt Bh 7.00 72,873 510,109.60 0.17% 0.17
J.5 Pasang Kictchen Zinc 1 Lubang Bh 1.00 607,761 607,761.00 0.20% 0.20 20
J.6 Pasang Pipa PVC Dia 4" + acc m1 4.00 128,774 515,094.80 0.17% 0.17
J.7 Pasang Pipa PVC Dia 2" + acc m1 4.00 58,375 233,499.20 0.08% 0.08
J.8 Pasang Pipa GIP Dia 0,5" + acc m1 12.00 61,414 736,969.20 0.24% 0.24
J.9 Septiktank dan Peresapan Unit 1.00 2,250,000 2,250,000.00 0.74% 0.74
K.2 Pompa Air + Instalasi Pipa + acc Ls 1.00 2,000,000 2,000,000.00 0.65% JADWAL REALISASI 0.65
K.3 Tralis Besi Hollow 5 cm m2 3.51 365,413 1,282,601.03 0.42% LAPANGAN 0.42
K.4 Huruf Nama Kantor Tinggi 20 cm Bh 15.00 200,000 3,000,000.00 0.98% 0.98
K.5 Huruf Nama Kantor Tinggi 15 cm Bh 25.00 150,000 3,750,000.00 1.23% 1.23
K.6 Biaya Pengadaan Genset 5 KVA Ls 1.00 11,500,000 11,500,000.00 3.76% 3.76
K.7 Pek. Tiang Bendera + acc Ls 1.00 1,500,000 1,500,000.00 0.49% 0.49
SUB TOTAL PEKERJAAN BAK PENAMPUNG DAN LAIN - LAIN - 32,532,601.03 10.64%
L PEKERJAAN AKHIR -
L.1 Pembersihan Akhir Lokasi Ls 1.00 1,000,000 1,000,000.00 0.33% 0.33
L.2 Biaya Administrasi, Pelaporan, As Built Brawing & Dokumentasi Ls 1.00 1,000,000 1,000,000.00 0.33% 0.33 0.00
SUB TOTAL PEKERJAAN AKHIR - 2,000,000.00 0.65%
08-Jul 15-Jul 22-Jul 29-Jul 05-Agt 12-Agt 19-Agt 26-Agt 02-Sep 09-Sep 16-Sep 23-Sep 30-Sep 07-Okt 14-Okt 21-Okt 28-Okt 04-Nov 11-Nov 18-Nov 25-Nov 02-Des 08-Des
-
A PEKERJAAN AWAL - 100
A.1 Pembersihan Awal Lokasi Ls 1.00 700,000 700,000.00 0.23% 0.11 0.11
A.2 Pengkuruan dan Pemasangan Bowplank Ls 1.00 1,300,000 1,300,000.00 0.43% 0.43
A.3 Papan Nama Proyek Ls 1.00 200,000 200,000.00 0.07% 0.07
A.4 Penyediaan Air Kerja/Listrik Kerja Ls 1.00 725,000 725,000.00 0.24% 0.24
SUB TOTAL PEKERJAAN AWAL - 2,925,000.00 0.96%
B PEKERJAAN TANAH -
B.1 Galian Tanah untuk Pondasi m3 42.57 60,280 2,566,119.60 0.84% 0.24 0.47 0.13
B.2 Urugan Tanah Galian Kembali m3 10.64 39,050 415,492.00 0.14% 0.14
B.3 Urugan Sirtu Peninggi Lantai m3 63.94 128,432 8,211,916.50 2.69% 1.16 1.52
B.4 Urugan Pasir di Bawah Pondasi m3 3.28 146,850 481,668.00 0.16% 0.16
B.5 Urugan Pasir di Bawah Lantai m3 16.15 146,850 2,371,627.50 0.78% 0.78
SUB TOTAL PEKERJAAN TANAH - 14,046,823.60 4.60%
C PEKERJAAN PASANGAN DAN PLESTERAN -
C.1 Aanstamping m3 12.20 294,534 3,593,320.41 1.18% 1.18
C.2 Pasangan Pondasi Batu Kali (1 Pc : 4 Psr) m3 33.89 578,793 19,615,277.83 6.42% 6.42
C.3 Pasangan Pondasi Rolag & Tangga (1 Pc : 4 Psr) m3 6.92 578,793 4,005,244.10 1.31% 1.31
C.4 Pasangan Tembok Bata Merah (1 Pc : 5 Psr) m2 173.34 150,189 26,033,846.20 8.52% 0.42 4.41 1.48 1.08 1.13
C.5 Plesteran (1 Pc : 5 Psr) Tebal 15 mm m2 403.12 49,013 19,758,265.68 6.46% 3.21 3.25
E.4 Daun Jendela Panil Kaca Rangka Kayu Jati m2 6.30 425,810 2,682,603.00 0.88% 0.88
E.6 Pasang Kunci Tanam 2 x Putar Bh 7.00 250,349 1,752,443.00 0.57% 0.57
F.2 Pasang Lantai Keramik 20/20 cm m2 4.31 162,289 699,463.44 0.23% 0.23
F.3 Pasang Dinding Keramik 20/25 cm m2 10.08 145,019 1,461,786.48 0.48% 0.48
F.4 Pasang Plint Keramik 10/40 cm m2 67.15 93,023 6,246,467.59 2.04% 2.04
F.5 Rangka Plafond Kayu Klas. II m2 110.97 106,381 11,805,099.57 3.86% 3.86
F.6 Plafond Tripleks 3 mm m2 110.97 39,738 4,409,670.38 1.44% JADWAL RENCANA 1.44
F.7 List Plafond Kayu Profil m1 173.20 18,832 3,261,702.40 1.07% TERKONTRAK 1.07
F.8 Pasang Dinding Batu Alam m2 29.88 282,601 8,444,117.88 2.76% 2.76
SUB TOTAL PEKERJAAN PLAFOND, PENUTUP LANTAI DAN DINDING - 49,671,371.31 16.25%
G PEKERJAAN KUDA-KUDA DAN PENUTUP ATAP -
G.1 Pekerjaan Konstruksi Kuda-kuda Kayu Klas II m3 1.41 5,119,400 7,218,354.01 2.36% 2.36
G.2 Pekerjaan Konstruksi Gording Kayu Klas II m3 1.43 6,252,785 8,941,482.55 2.93% 2.93
G.3 Pekerjaan Atap Seng Gelombang BJLS 0.30 m2 143.37 65,164 9,342,562.68 3.06% 3.06
G.4 Pekerjaan Seng Licin Bubungan m1 32.80 34,551 1,133,272.80 0.37% 0.37
G.5 Pekerjaan Lisplank Kayu Klas II Ukuran (2 x 2,5 x 18) cm m1 44.40 71,610 3,179,484.00 1.04% 1.04
SUB TOTAL PEKERJAAN KUDA-KUDA DAN PENUTUP ATAP - 29,815,156.04 9.75%
H PEKERJAAN PENGECATAN -
H.1 Pengecatan Tembok m2 403.12 25,809 10,403,956.07 3.40% 3.40 40
MATI
H.2 Pengecatan Plafond m2 110.97 25,809 2,863,979.23 0.94% 0.94
I.5 Pasang Lampu LED 13 Watt Bh 6.00 81,686 490,116.00 0.16% 0.16
I.6 Pasang Lampu LED 7 Watt Bh 7.00 72,873 510,109.60 0.17% 0.17
J.5 Pasang Kictchen Zinc 1 Lubang Bh 1.00 607,761 607,761.00 0.20% 0.20 20
J.6 Pasang Pipa PVC Dia 4" + acc m1 4.00 128,774 515,094.80 0.17% 0.17
J.7 Pasang Pipa PVC Dia 2" + acc m1 4.00 58,375 233,499.20 0.08% 0.08
J.8 Pasang Pipa GIP Dia 0,5" + acc m1 12.00 61,414 736,969.20 0.24% 0.24
J.9 Septiktank dan Peresapan Unit 1.00 2,250,000 2,250,000.00 0.74% 0.74
K.2 Pompa Air + Instalasi Pipa + acc Ls 1.00 2,000,000 2,000,000.00 0.65% 0.65
K.4 Huruf Nama Kantor Tinggi 20 cm Bh 15.00 200,000 3,000,000.00 0.98% 0.98
K.5 Huruf Nama Kantor Tinggi 15 cm Bh 25.00 150,000 3,750,000.00 1.23% 1.23
K.6 Biaya Pengadaan Genset 5 KVA Ls 1.00 11,500,000 11,500,000.00 3.76% 3.76
K.7 Pek. Tiang Bendera + acc Ls 1.00 1,500,000 1,500,000.00 0.49% 0.49
SUB TOTAL PEKERJAAN BAK PENAMPUNG DAN LAIN - LAIN - 32,532,601.03 10.64%
L PEKERJAAN AKHIR -
L.1 Pembersihan Akhir Lokasi Ls 1.00 1,000,000 1,000,000.00 0.33% 0.33
L.2 Biaya Administrasi, Pelaporan, As Built Brawing & Dokumentasi Ls 1.00 1,000,000 1,000,000.00 0.33% 0.33 0.00
SUB TOTAL PEKERJAAN AKHIR - 2,000,000.00 0.65%
08-Jul 15-Jul 22-Jul 29-Jul 05-Agt 12-Agt 19-Agt 26-Agt 02-Sep 09-Sep 16-Sep 23-Sep 30-Sep 07-Okt 14-Okt 21-Okt 28-Okt 04-Nov 11-Nov 18-Nov 25-Nov 02-Des 08-Des
-
A PEKERJAAN AWAL - 100
A.1 Pembersihan Awal Lokasi Ls 1.00 700,000 700,000.00 0.23% 0.11 0.11
A.2 Pengkuruan dan Pemasangan Bowplank Ls 1.00 1,300,000 1,300,000.00 0.43% 0.43
A.3 Papan Nama Proyek Ls 1.00 200,000 200,000.00 0.07% 0.07
A.4 Penyediaan Air Kerja/Listrik Kerja Ls 1.00 725,000 725,000.00 0.24% 0.24
SUB TOTAL PEKERJAAN AWAL - 2,925,000.00 0.96%
B PEKERJAAN TANAH -
B.1 Galian Tanah untuk Pondasi m3 42.57 60,280 2,566,119.60 0.84% 0.24 0.47 0.13
B.2 Urugan Tanah Galian Kembali m3 10.64 39,050 415,492.00 0.14% 0.14
B.3 Urugan Sirtu Peninggi Lantai m3 63.94 128,432 8,211,916.50 2.69% 1.16 1.52
B.4 Urugan Pasir di Bawah Pondasi m3 3.28 146,850 481,668.00 0.16% 0.16
B.5 Urugan Pasir di Bawah Lantai m3 16.15 146,850 2,371,627.50 0.78% 0.78
SUB TOTAL PEKERJAAN TANAH - 14,046,823.60 4.60%
C PEKERJAAN PASANGAN DAN PLESTERAN -
C.1 Aanstamping m3 12.20 294,534 3,593,320.41 1.18% 1.18
C.2 Pasangan Pondasi Batu Kali (1 Pc : 4 Psr) m3 33.89 578,793 19,615,277.83 6.42% 6.42
C.3 Pasangan Pondasi Rolag & Tangga (1 Pc : 4 Psr) m3 6.92 578,793 4,005,244.10 1.31% 1.31
C.4 Pasangan Tembok Bata Merah (1 Pc : 5 Psr) m2 173.34 150,189 26,033,846.20 8.52% 0.42 4.41 1.48 1.08 1.13
C.5 Plesteran (1 Pc : 5 Psr) Tebal 15 mm m2 403.12 49,013 19,758,265.68 6.46% 3.21 3.25
C.6 Acian m2 403.12 21,802 8,788,822.24 2.88% 0.96 1.92
SUB TOTAL PEKERJAAN PASANGAN DAN PLESTERAN - 81,794,776.46 26.76%
D PEKERJAAN BETON - 80
D.1 Pek. Beton Bertulang untuk Kolom 15/60 m3 0.23 7,118,037 1,637,148.43 0.54% 0.54
D.2 Pek. Beton Bertulang untuk Kolom praktis m3 1.52 7,118,037 10,819,415.69 3.54% 3.54
D.3 Pek. Beton Bertulang untuk Sloof m3 1.85 4,297,497 7,950,368.53 2.60% 2.60
D.4 Pek. Beton Bertulang untuk Ringbalk 15/40 m3 0.33 5,495,951 1,813,663.80 0.59% 0.59
D.5 Pek. Beton Bertulang untuk Ringbalk m3 1.38 5,495,951 7,584,412.24 2.48% 2.48
D.6 Pek. Beton Bertulang untuk Balok Latei m3 0.81 5,495,951 4,451,720.23 1.46% 1.46
D.7 Pek. Beton Bertulang untuk Plat Level m3 1.14 5,041,554 5,747,371.67 1.88% 1.88
D.8 Pek. Beton Bertulang untuk Plat m3 0.14 5,041,554 705,817.57 0.23% 0.23
D.9 Pek. Beton Tidak Bertulang untuk Rabat m3 4.15 825,416 3,425,476.22 1.12% 1.12
SUB TOTAL PEKERJAAN BETON - 44,135,394.38 14.44%
E PEKERJAAN KUSEN, PINTU/JENDELA, KACA, KUNCI DAN PENGANTUNG -
E.1 Kusen Kayu Jati m3 0.34 7,797,020 2,650,986.80 0.87% 0.87
E.2 Kusen + Daun Pintu PVC Beserta Perlengkapannya Unit 1.00 570,000 570,000.00 0.19% 0.19
E.3 Daun Pintu Panil Kayu Jati m2 11.24 477,932 5,371,950.28 1.76% 1.76
E.4 Daun Jendela Panil Kaca Rangka Kayu Jati m2 6.30 425,810 2,682,603.00 0.88% 0.88
E.6 Pasang Kunci Tanam 2 x Putar Bh 7.00 250,349 1,752,443.00 0.57% 0.57
F.2 Pasang Lantai Keramik 20/20 cm m2 4.31 162,289 699,463.44 0.23% 0.23
F.3 Pasang Dinding Keramik 20/25 cm m2 10.08 145,019 1,461,786.48 0.48% 0.48
F.4 Pasang Plint Keramik 10/40 cm m2 67.15 93,023 6,246,467.59 2.04% 2.04
F.5 Rangka Plafond Kayu Klas. II m2 110.97 106,381 11,805,099.57 3.86% 3.86
F.6 Plafond Tripleks 3 mm m2 110.97 39,738 4,409,670.38 1.44% JADWAL RENCANA 1.44
F.7 List Plafond Kayu Profil m1 173.20 18,832 3,261,702.40 1.07% TERKONTRAK 1.07
F.8 Pasang Dinding Batu Alam m2 29.88 282,601 8,444,117.88 2.76% 2.76
SUB TOTAL PEKERJAAN PLAFOND, PENUTUP LANTAI DAN DINDING - 49,671,371.31 16.25%
G PEKERJAAN KUDA-KUDA DAN PENUTUP ATAP -
G.1 Pekerjaan Konstruksi Kuda-kuda Kayu Klas II m3 1.41 5,119,400 7,218,354.01 2.36% 2.36
G.2 Pekerjaan Konstruksi Gording Kayu Klas II m3 1.43 6,252,785 8,941,482.55 2.93% 2.93
G.3 Pekerjaan Atap Seng Gelombang BJLS 0.30 m2 143.37 65,164 9,342,562.68 3.06% 3.06
G.4 Pekerjaan Seng Licin Bubungan m1 32.80 34,551 1,133,272.80 0.37% 0.37
G.5 Pekerjaan Lisplank Kayu Klas II Ukuran (2 x 2,5 x 18) cm m1 44.40 71,610 3,179,484.00 1.04% 1.04
SUB TOTAL PEKERJAAN KUDA-KUDA DAN PENUTUP ATAP - 29,815,156.04 9.75%
H PEKERJAAN PENGECATAN -
H.1 Pengecatan Tembok m2 403.12 25,809 10,403,956.07 3.40% 3.40 40
MATI
H.2 Pengecatan Plafond m2 110.97 25,809 2,863,979.23 0.94% 0.94
H.6 Residu Rangka Atap Ls 1.00 500,000 500,000.00 0.16% 0.16 LAPANGAN
SUB TOTAL PEKERJAAN PENGECATAN - 16,282,110.62 5.33%
I PEKERJAAN INSTALASI LISTRIK -
I.1 Instalasi Titik Lampu Ttk 13.00 561,193 7,295,505.36 2.39% 2.39
I.5 Pasang Lampu LED 13 Watt Bh 6.00 81,686 490,116.00 0.16% 0.16
I.6 Pasang Lampu LED 7 Watt Bh 7.00 72,873 510,109.60 0.17% 0.17
J.8 Pasang Pipa GIP Dia 0,5" + acc m1 12.00 61,414 736,969.20 0.24% 0.24
J.9 Septiktank dan Peresapan Unit 1.00 2,250,000 2,250,000.00 0.74% 0.74
SUB TOTAL PEKERJAAN INSTALASI AIR DAN SANITAIR - 6,011,182.70 1.97%
K PEKERJAAN BAK PENAMPUNG DAN LAIN - LAIN -
K.1 Bak Penampung 5000 L + acc Unit 1.00 9,500,000 9,500,000.00 3.11% 1.55 1.55
K.2 Pompa Air + Instalasi Pipa + acc Ls 1.00 2,000,000 2,000,000.00 0.65% 0.65
K.4 Huruf Nama Kantor Tinggi 20 cm Bh 15.00 200,000 3,000,000.00 0.98% 0.98
K.5 Huruf Nama Kantor Tinggi 15 cm Bh 25.00 150,000 3,750,000.00 1.23% 1.23
K.6 Biaya Pengadaan Genset 5 KVA Ls 1.00 11,500,000 11,500,000.00 3.76% 3.76
K.7 Pek. Tiang Bendera + acc Ls 1.00 1,500,000 1,500,000.00 0.49% 0.49
SUB TOTAL PEKERJAAN BAK PENAMPUNG DAN LAIN - LAIN - 32,532,601.03 10.64%
L PEKERJAAN AKHIR -
L.1 Pembersihan Akhir Lokasi Ls 1.00 1,000,000 1,000,000.00 0.33% 0.33
L.2 Biaya Administrasi, Pelaporan, As Built Brawing & Dokumentasi Ls 1.00 1,000,000 1,000,000.00 0.33% 0.33 0.00
SUB TOTAL PEKERJAAN AKHIR - 2,000,000.00 0.65%
08-Jul 15-Jul 22-Jul 29-Jul 05-Agt 12-Agt 19-Agt 26-Agt 02-Sep 09-Sep 16-Sep 23-Sep 30-Sep 07-Okt 14-Okt 21-Okt 28-Okt 04-Nov 11-Nov 18-Nov 25-Nov 02-Des 08-Des
-
A PEKERJAAN AWAL - 100
A.1 Pembersihan Awal Lokasi Ls 1.00 700,000 700,000.00 0.23% 0.11 0.11
A.2 Pengkuruan dan Pemasangan Bowplank Ls 1.00 1,300,000 1,300,000.00 0.43% 0.43
A.3 Papan Nama Proyek Ls 1.00 200,000 200,000.00 0.07% 0.07
A.4 Penyediaan Air Kerja/Listrik Kerja Ls 1.00 725,000 725,000.00 0.24% 0.24
SUB TOTAL PEKERJAAN AWAL - 2,925,000.00 0.96%
B PEKERJAAN TANAH -
B.1 Galian Tanah untuk Pondasi m3 42.57 60,280 2,566,119.60 0.84% 0.24 0.47 0.13
B.2 Urugan Tanah Galian Kembali m3 10.64 39,050 415,492.00 0.14% 0.14
B.3 Urugan Sirtu Peninggi Lantai m3 63.94 128,432 8,211,916.50 2.69% 1.16 1.52
B.4 Urugan Pasir di Bawah Pondasi m3 3.28 146,850 481,668.00 0.16% 0.16
B.5 Urugan Pasir di Bawah Lantai m3 16.15 146,850 2,371,627.50 0.78% 0.78
SUB TOTAL PEKERJAAN TANAH - 14,046,823.60 4.60%
C PEKERJAAN PASANGAN DAN PLESTERAN -
C.1 Aanstamping m3 12.20 294,534 3,593,320.41 1.18% 1.18
C.2 Pasangan Pondasi Batu Kali (1 Pc : 4 Psr) m3 33.89 578,793 19,615,277.83 6.42% 6.42
C.3 Pasangan Pondasi Rolag & Tangga (1 Pc : 4 Psr) m3 6.92 578,793 4,005,244.10 1.31% 1.31
C.4 Pasangan Tembok Bata Merah (1 Pc : 5 Psr) m2 173.34 150,189 26,033,846.20 8.52% 0.42 4.41 1.48 1.08 1.13
C.5 Plesteran (1 Pc : 5 Psr) Tebal 15 mm m2 403.12 49,013 19,758,265.68 6.46% 3.21 3.25
C.6 Acian m2 403.12 21,802 8,788,822.24 2.88% 0.96 1.92
SUB TOTAL PEKERJAAN PASANGAN DAN PLESTERAN - 81,794,776.46 26.76%
D PEKERJAAN BETON - 80
D.1 Pek. Beton Bertulang untuk Kolom 15/60 m3 0.23 7,118,037 1,637,148.43 0.54% 0.54
D.2 Pek. Beton Bertulang untuk Kolom praktis m3 1.52 7,118,037 10,819,415.69 3.54% 3.54
D.3 Pek. Beton Bertulang untuk Sloof m3 1.85 4,297,497 7,950,368.53 2.60% 2.60
D.4 Pek. Beton Bertulang untuk Ringbalk 15/40 m3 0.33 5,495,951 1,813,663.80 0.59% 0.59
D.5 Pek. Beton Bertulang untuk Ringbalk m3 1.38 5,495,951 7,584,412.24 2.48% 2.48
D.6 Pek. Beton Bertulang untuk Balok Latei m3 0.81 5,495,951 4,451,720.23 1.46% 1.46
D.7 Pek. Beton Bertulang untuk Plat Level m3 1.14 5,041,554 5,747,371.67 1.88% 1.88
D.8 Pek. Beton Bertulang untuk Plat m3 0.14 5,041,554 705,817.57 0.23% 0.23
D.9 Pek. Beton Tidak Bertulang untuk Rabat m3 4.15 825,416 3,425,476.22 1.12% 1.12
SUB TOTAL PEKERJAAN BETON - 44,135,394.38 14.44%
E PEKERJAAN KUSEN, PINTU/JENDELA, KACA, KUNCI DAN PENGANTUNG -
E.1 Kusen Kayu Jati m3 0.34 7,797,020 2,650,986.80 0.87% 0.87
E.2 Kusen + Daun Pintu PVC Beserta Perlengkapannya Unit 1.00 570,000 570,000.00 0.19% 0.19
E.3 Daun Pintu Panil Kayu Jati m2 11.24 477,932 5,371,950.28 1.76% 1.76
E.4 Daun Jendela Panil Kaca Rangka Kayu Jati m2 6.30 425,810 2,682,603.00 0.88% 0.88
E.5 Pasang Kaca Jendela 5 mm m2 4.03 88,536 356,798.87 0.12% 0.12
E.6 Pasang Kunci Tanam 2 x Putar Bh 7.00 250,349 1,752,443.00 0.57% 0.57
E.7 Pasang Engsel Pintu Bh 21.00 36,467 765,811.20 0.25% 0.25
E.8 Pasang Engsel Jendela Bh 20.00 26,142 522,830.00 0.17% 0.17
E.9 Pasang Kait Angin Bh 20.00 31,955 639,100.00 0.21% 0.21
E.10 Pasang Grendel Bh 11.00 64,757 712,327.00 0.23% 0.23 60
E.11 Boven Batu Angin/Roster Bh 22.00 47,523 1,045,512.60 0.34% 0.34
SUB TOTAL PEKERJAAN KUSEN, PINTU/JENDELA, KACA, KUNCI DAN PENGANTUNG 17,070,362.76 5.58%
F PEKERJAAN PLAFOND, PENUTUP LANTAI DAN DINDING
F.1 Pasang Lantai Keramik 40/40 cm m2 87.32 152,807 13,343,063.58 4.37% 4.37
F.2 Pasang Lantai Keramik 20/20 cm m2 4.31 162,289 699,463.44 0.23% 0.23
F.3 Pasang Dinding Keramik 20/25 cm m2 10.08 145,019 1,461,786.48 0.48% 0.48
F.4 Pasang Plint Keramik 10/40 cm m2 67.15 93,023 6,246,467.59 2.04% 2.04
F.5 Rangka Plafond Kayu Klas. II m2 110.97 106,381 11,805,099.57 3.86% 3.86
F.6 Plafond Tripleks 3 mm m2 110.97 39,738 4,409,670.38 1.44% JADWAL RENCANA 1.44
F.7 List Plafond Kayu Profil m1 173.20 18,832 3,261,702.40 1.07% TERKONTRAK 1.07
F.8 Pasang Dinding Batu Alam m2 29.88 282,601 8,444,117.88 2.76% 2.76
SUB TOTAL PEKERJAAN PLAFOND, PENUTUP LANTAI DAN DINDING - 49,671,371.31 16.25%
G PEKERJAAN KUDA-KUDA DAN PENUTUP ATAP -
G.1 Pekerjaan Konstruksi Kuda-kuda Kayu Klas II m3 1.41 5,119,400 7,218,354.01 2.36% 2.36
G.2 Pekerjaan Konstruksi Gording Kayu Klas II m3 1.43 6,252,785 8,941,482.55 2.93% 2.93
G.3 Pekerjaan Atap Seng Gelombang BJLS 0.30 m2 143.37 65,164 9,342,562.68 3.06% 3.06
G.4 Pekerjaan Seng Licin Bubungan m1 32.80 34,551 1,133,272.80 0.37% 0.37
G.5 Pekerjaan Lisplank Kayu Klas II Ukuran (2 x 2,5 x 18) cm m1 44.40 71,610 3,179,484.00 1.04% 1.04
SUB TOTAL PEKERJAAN KUDA-KUDA DAN PENUTUP ATAP - 29,815,156.04 9.75%
H PEKERJAAN PENGECATAN -
H.1 Pengecatan Tembok m2 403.12 25,809 10,403,956.07 3.40% 3.40 40
MATI
H.2 Pengecatan Plafond m2 110.97 25,809 2,863,979.23 0.94% 0.94
H.3 Pengecatan Atap m2 143.37 11,052 1,584,482.23 0.52%
KONTRAK 0.52
H.4 Pengecatan Kayu m2 30.82 12,302 379,148.26 0.12% 0.12
H.5 Teakoil m2 27.01 20,383 550,544.83 0.18% 0.18
H.6 Residu Rangka Atap Ls 1.00 500,000 500,000.00 0.16% 0.16
SUB TOTAL PEKERJAAN PENGECATAN - 16,282,110.62 5.33%
I PEKERJAAN INSTALASI LISTRIK -
I.1 Instalasi Titik Lampu Ttk 13.00 561,193 7,295,505.36 2.39% 2.39
I.2 Pasang MCB + Box Bh 1.00 74,800 74,800.00 0.02% 0.02
I.3 Pasang Saklar Ganda Bh 3.00 72,600 217,800.00 0.07% JADWAL REALISASI 0.07
I.4 Pasang Saklar Tunggal Bh 5.00 67,100 335,500.00 0.11% LAPANGAN 0.11
I.5 Pasang Lampu LED 13 Watt Bh 6.00 81,686 490,116.00 0.16% 0.16
I.6 Pasang Lampu LED 7 Watt Bh 7.00 72,873 510,109.60 0.17% 0.17
I.7 Pasang Stop Kontak Bh 9.00 50,006 450,054.00 0.15% 0.15
SUB TOTAL PEKERJAAN INSTALASI LISTRIK - 9,373,884.96 3.07%
J PEKERJAAN INSTALASI AIR DAN SANITAIR -
J.1 Pasang Closed Duduk Bh 1.00 621,610 621,610.00 0.20% 0.20
J.2 Pasang Bak Air Bh 1.00 819,390 819,390.00 0.27% 0.27
J.3 Pasang Kran Air Bh 2.00 75,386 150,771.50 0.05% 0.05
J.4 Pasang Floor Drain Bh 1.00 76,087 76,087.00 0.02% 0.02
J.5 Pasang Kictchen Zinc 1 Lubang Bh 1.00 607,761 607,761.00 0.20% 0.20 20
J.6 Pasang Pipa PVC Dia 4" + acc m1 4.00 128,774 515,094.80 0.17% 0.17
J.7 Pasang Pipa PVC Dia 2" + acc m1 4.00 58,375 233,499.20 0.08% 0.08
J.8 Pasang Pipa GIP Dia 0,5" + acc m1 12.00 61,414 736,969.20 0.24% 0.24
J.9 Septiktank dan Peresapan Unit 1.00 2,250,000 2,250,000.00 0.74% 0.74
SUB TOTAL PEKERJAAN INSTALASI AIR DAN SANITAIR - 6,011,182.70 1.97%
K PEKERJAAN BAK PENAMPUNG DAN LAIN - LAIN -
K.1 Bak Penampung 5000 L + acc Unit 1.00 9,500,000 9,500,000.00 3.11% 1.55 1.55
K.2 Pompa Air + Instalasi Pipa + acc Ls 1.00 2,000,000 2,000,000.00 0.65% 0.65
K.4 Huruf Nama Kantor Tinggi 20 cm Bh 15.00 200,000 3,000,000.00 0.98% 0.98
K.5 Huruf Nama Kantor Tinggi 15 cm Bh 25.00 150,000 3,750,000.00 1.23% 1.23
K.6 Biaya Pengadaan Genset 5 KVA Ls 1.00 11,500,000 11,500,000.00 3.76% 3.76
K.7 Pek. Tiang Bendera + acc Ls 1.00 1,500,000 1,500,000.00 0.49% 0.49
SUB TOTAL PEKERJAAN BAK PENAMPUNG DAN LAIN - LAIN - 32,532,601.03 10.64%
L PEKERJAAN AKHIR -
L.1 Pembersihan Akhir Lokasi Ls 1.00 1,000,000 1,000,000.00 0.33% 0.33
L.2 Biaya Administrasi, Pelaporan, As Built Brawing & Dokumentasi Ls 1.00 1,000,000 1,000,000.00 0.33% 0.33 0.00
SUB TOTAL PEKERJAAN AKHIR - 2,000,000.00 0.65%
08-Jul 15-Jul 22-Jul 29-Jul 05-Agt 12-Agt 19-Agt 26-Agt 02-Sep 09-Sep 16-Sep 23-Sep 30-Sep 07-Okt 14-Okt 21-Okt 28-Okt 04-Nov 11-Nov 18-Nov 25-Nov 02-Des 08-Des
-
A PEKERJAAN AWAL - 100
A.1 Pembersihan Awal Lokasi Ls 1.00 700,000 700,000.00 0.23% 0.11 0.11
A.2 Pengkuruan dan Pemasangan Bowplank Ls 1.00 1,300,000 1,300,000.00 0.43% 0.43
A.3 Papan Nama Proyek Ls 1.00 200,000 200,000.00 0.07% 0.07
A.4 Penyediaan Air Kerja/Listrik Kerja Ls 1.00 725,000 725,000.00 0.24% 0.24
SUB TOTAL PEKERJAAN AWAL - 2,925,000.00 0.96%
B PEKERJAAN TANAH -
B.1 Galian Tanah untuk Pondasi m3 42.57 60,280 2,566,119.60 0.84% 0.24 0.47 0.13
B.2 Urugan Tanah Galian Kembali m3 10.64 39,050 415,492.00 0.14% 0.14
B.3 Urugan Sirtu Peninggi Lantai m3 63.94 128,432 8,211,916.50 2.69% 1.16 1.52
B.4 Urugan Pasir di Bawah Pondasi m3 3.28 146,850 481,668.00 0.16% 0.16
B.5 Urugan Pasir di Bawah Lantai m3 16.15 146,850 2,371,627.50 0.78% 0.78
SUB TOTAL PEKERJAAN TANAH - 14,046,823.60 4.60%
C PEKERJAAN PASANGAN DAN PLESTERAN -
C.1 Aanstamping m3 12.20 294,534 3,593,320.41 1.18% 1.18
C.2 Pasangan Pondasi Batu Kali (1 Pc : 4 Psr) m3 33.89 578,793 19,615,277.83 6.42% 6.42
C.3 Pasangan Pondasi Rolag & Tangga (1 Pc : 4 Psr) m3 6.92 578,793 4,005,244.10 1.31% 1.31
C.4 Pasangan Tembok Bata Merah (1 Pc : 5 Psr) m2 173.34 150,189 26,033,846.20 8.52% 0.42 4.41 1.48 1.08 1.13
C.5 Plesteran (1 Pc : 5 Psr) Tebal 15 mm m2 403.12 49,013 19,758,265.68 6.46% 3.21 3.25
C.6 Acian m2 403.12 21,802 8,788,822.24 2.88% 0.96 1.92
SUB TOTAL PEKERJAAN PASANGAN DAN PLESTERAN - 81,794,776.46 26.76%
D PEKERJAAN BETON - 80
D.1 Pek. Beton Bertulang untuk Kolom 15/60 m3 0.23 7,118,037 1,637,148.43 0.54% 0.54
D.2 Pek. Beton Bertulang untuk Kolom praktis m3 1.52 7,118,037 10,819,415.69 3.54% 3.54
D.3 Pek. Beton Bertulang untuk Sloof m3 1.85 4,297,497 7,950,368.53 2.60% 2.60
D.4 Pek. Beton Bertulang untuk Ringbalk 15/40 m3 0.33 5,495,951 1,813,663.80 0.59% 0.59
D.5 Pek. Beton Bertulang untuk Ringbalk m3 1.38 5,495,951 7,584,412.24 2.48% 2.48
D.6 Pek. Beton Bertulang untuk Balok Latei m3 0.81 5,495,951 4,451,720.23 1.46% 1.46
D.7 Pek. Beton Bertulang untuk Plat Level m3 1.14 5,041,554 5,747,371.67 1.88% 1.88
D.8 Pek. Beton Bertulang untuk Plat m3 0.14 5,041,554 705,817.57 0.23% 0.23
D.9 Pek. Beton Tidak Bertulang untuk Rabat m3 4.15 825,416 3,425,476.22 1.12% 1.12
SUB TOTAL PEKERJAAN BETON - 44,135,394.38 14.44%
E PEKERJAAN KUSEN, PINTU/JENDELA, KACA, KUNCI DAN PENGANTUNG -
E.1 Kusen Kayu Jati m3 0.34 7,797,020 2,650,986.80 0.87% 0.87
E.2 Kusen + Daun Pintu PVC Beserta Perlengkapannya Unit 1.00 570,000 570,000.00 0.19% 0.19
E.3 Daun Pintu Panil Kayu Jati m2 11.24 477,932 5,371,950.28 1.76% 1.76
E.4 Daun Jendela Panil Kaca Rangka Kayu Jati m2 6.30 425,810 2,682,603.00 0.88% 0.88
E.5 Pasang Kaca Jendela 5 mm m2 4.03 88,536 356,798.87 0.12% 0.12
E.6 Pasang Kunci Tanam 2 x Putar Bh 7.00 250,349 1,752,443.00 0.57% 0.57
E.7 Pasang Engsel Pintu Bh 21.00 36,467 765,811.20 0.25% 0.25
E.8 Pasang Engsel Jendela Bh 20.00 26,142 522,830.00 0.17% 0.17
E.9 Pasang Kait Angin Bh 20.00 31,955 639,100.00 0.21% 0.21
E.10 Pasang Grendel Bh 11.00 64,757 712,327.00 0.23% 0.23 60
E.11 Boven Batu Angin/Roster Bh 22.00 47,523 1,045,512.60 0.34% 0.34
SUB TOTAL PEKERJAAN KUSEN, PINTU/JENDELA, KACA, KUNCI DAN PENGANTUNG 17,070,362.76 5.58%
F PEKERJAAN PLAFOND, PENUTUP LANTAI DAN DINDING
F.1 Pasang Lantai Keramik 40/40 cm m2 87.32 152,807 13,343,063.58 4.37% 4.37
F.2 Pasang Lantai Keramik 20/20 cm m2 4.31 162,289 699,463.44 0.23% 0.23
F.3 Pasang Dinding Keramik 20/25 cm m2 10.08 145,019 1,461,786.48 0.48% 0.48
F.4 Pasang Plint Keramik 10/40 cm m2 67.15 93,023 6,246,467.59 2.04% 2.04
F.5 Rangka Plafond Kayu Klas. II m2 110.97 106,381 11,805,099.57 3.86% 3.86
F.6 Plafond Tripleks 3 mm m2 110.97 39,738 4,409,670.38 1.44% JADWAL RENCANA 1.44
F.7 List Plafond Kayu Profil m1 173.20 18,832 3,261,702.40 1.07% TERKONTRAK 1.07
F.8 Pasang Dinding Batu Alam m2 29.88 282,601 8,444,117.88 2.76% 2.76
SUB TOTAL PEKERJAAN PLAFOND, PENUTUP LANTAI DAN DINDING - 49,671,371.31 16.25%
G PEKERJAAN KUDA-KUDA DAN PENUTUP ATAP -
G.1 Pekerjaan Konstruksi Kuda-kuda Kayu Klas II m3 1.41 5,119,400 7,218,354.01 2.36% 2.36
G.2 Pekerjaan Konstruksi Gording Kayu Klas II m3 1.43 6,252,785 8,941,482.55 2.93% 2.93
G.3 Pekerjaan Atap Seng Gelombang BJLS 0.30 m2 143.37 65,164 9,342,562.68 3.06% 3.06
G.4 Pekerjaan Seng Licin Bubungan m1 32.80 34,551 1,133,272.80 0.37% 0.37
G.5 Pekerjaan Lisplank Kayu Klas II Ukuran (2 x 2,5 x 18) cm m1 44.40 71,610 3,179,484.00 1.04% 1.04
SUB TOTAL PEKERJAAN KUDA-KUDA DAN PENUTUP ATAP - 29,815,156.04 9.75%
H PEKERJAAN PENGECATAN -
H.1 Pengecatan Tembok m2 403.12 25,809 10,403,956.07 3.40% 3.40 40
MATI
H.2 Pengecatan Plafond m2 110.97 25,809 2,863,979.23 0.94% 0.94
H.3 Pengecatan Atap m2 143.37 11,052 1,584,482.23 0.52%
KONTRAK 0.52
H.4 Pengecatan Kayu m2 30.82 12,302 379,148.26 0.12% 0.12
H.5 Teakoil m2 27.01 20,383 550,544.83 0.18% 0.18
H.6 Residu Rangka Atap Ls 1.00 500,000 500,000.00 0.16% 0.16
SUB TOTAL PEKERJAAN PENGECATAN - 16,282,110.62 5.33%
I PEKERJAAN INSTALASI LISTRIK -
I.1 Instalasi Titik Lampu Ttk 13.00 561,193 7,295,505.36 2.39% 2.39
I.2 Pasang MCB + Box Bh 1.00 74,800 74,800.00 0.02% 0.02
I.3 Pasang Saklar Ganda Bh 3.00 72,600 217,800.00 0.07% 0.07
I.4 Pasang Saklar Tunggal Bh 5.00 67,100 335,500.00 0.11% 0.11
I.5 Pasang Lampu LED 13 Watt Bh 6.00 81,686 490,116.00 0.16% JADWAL REALISASI 0.16
I.6 Pasang Lampu LED 7 Watt Bh 7.00 72,873 510,109.60 0.17% LAPANGAN 0.17
I.7 Pasang Stop Kontak Bh 9.00 50,006 450,054.00 0.15% 0.15
SUB TOTAL PEKERJAAN INSTALASI LISTRIK - 9,373,884.96 3.07%
J PEKERJAAN INSTALASI AIR DAN SANITAIR -
J.1 Pasang Closed Duduk Bh 1.00 621,610 621,610.00 0.20% 0.20
J.2 Pasang Bak Air Bh 1.00 819,390 819,390.00 0.27% 0.27
J.3 Pasang Kran Air Bh 2.00 75,386 150,771.50 0.05% 0.05
J.4 Pasang Floor Drain Bh 1.00 76,087 76,087.00 0.02% 0.02
J.5 Pasang Kictchen Zinc 1 Lubang Bh 1.00 607,761 607,761.00 0.20% 0.20 20
J.6 Pasang Pipa PVC Dia 4" + acc m1 4.00 128,774 515,094.80 0.17% 0.17
J.7 Pasang Pipa PVC Dia 2" + acc m1 4.00 58,375 233,499.20 0.08% 0.08
J.8 Pasang Pipa GIP Dia 0,5" + acc m1 12.00 61,414 736,969.20 0.24% 0.24
J.9 Septiktank dan Peresapan Unit 1.00 2,250,000 2,250,000.00 0.74% 0.74
SUB TOTAL PEKERJAAN INSTALASI AIR DAN SANITAIR - 6,011,182.70 1.97%
K PEKERJAAN BAK PENAMPUNG DAN LAIN - LAIN -
K.1 Bak Penampung 5000 L + acc Unit 1.00 9,500,000 9,500,000.00 3.11% 1.55 1.55
K.2 Pompa Air + Instalasi Pipa + acc Ls 1.00 2,000,000 2,000,000.00 0.65% 0.65
K.4 Huruf Nama Kantor Tinggi 20 cm Bh 15.00 200,000 3,000,000.00 0.98% 0.98
K.5 Huruf Nama Kantor Tinggi 15 cm Bh 25.00 150,000 3,750,000.00 1.23% 1.23
K.6 Biaya Pengadaan Genset 5 KVA Ls 1.00 11,500,000 11,500,000.00 3.76% 3.76
K.7 Pek. Tiang Bendera + acc Ls 1.00 1,500,000 1,500,000.00 0.49% 0.49
SUB TOTAL PEKERJAAN BAK PENAMPUNG DAN LAIN - LAIN - 32,532,601.03 10.64%
L PEKERJAAN AKHIR -
L.1 Pembersihan Akhir Lokasi Ls 1.00 1,000,000 1,000,000.00 0.33% 0.33
L.2 Biaya Administrasi, Pelaporan, As Built Brawing & Dokumentasi Ls 1.00 1,000,000 1,000,000.00 0.33% 0.33 0.00
SUB TOTAL PEKERJAAN AKHIR - 2,000,000.00 0.65%