QUANTITY
ITEM DESCRIPTION OF WORK UNIT REMARKS
AS-PLANNED AS-STAKED AS-BUILT
EARTHWORKS
102(2) SURPLUS COMMON EXCAVATION CU. M. 5,095.00 5,215.00 5,215.00 Please refer to V.O. # 1
103(5)b SHORING, CRIBBING AND RELATED WORKS CU. M. 1.00 - - Item was deleted, refer to V.O. # 1
103(6)a PIPE CULVERTS AND DRAIN EXCAVATION CU. M. 108.00 108.00 108.00 Common Soil
104(1)a EMBANKMENT FROM ROADWAY EXCAVATION CU. M. 1,320.00 1,411.00 1,411.00 Please refer to V.O. # 1
105(1)a SUB - GRADE PREPARATION SQ. M. 6,162.00 6,943.75 6,943.75 Please refer to V.O. # 1
200(1) AGGREAGATE SUBBASE COURSE CU. M. 1,368.00 1,541.55 1,541.55 Please refer to V.O. # 1
SURFACE COURSES
311(1)a.5 PCC PAVEMENT (UNREINFORCED) SQ.M. 6,097.00 6,788.60 6,788.60 Please refer to V.O. # 1
DRAINAGE AND SLOPE PROTECTION STRUCTURES (including Road Safety & GAD)
404(1)a REINFORCING STEEL BARS, GRADE 40 KG. 18,397.00 18,397.00 18,397.00 Grade 40
405(1)a3 STRUCTURAL CONCRETE CU. M. 267.00 267.00 267.00 f 'c = 20.68 Mpa 28 days
407(8) LEAN CONCRETE CU. M. 5.00 5.00 5.00 Class B (16.50 Mpa) (0.05 m thk)
505 GROUTED RIPRAP CU. M. 160.00 160.00 160.00 Class A 0.30 m thk.
508(1) HAND LAID ROCK EMBANKMENT CU. M. 30.00 30.00 30.00 0.30 m thk.