ID Task Task Name DurationStart Finish % Work Resource Names Jan 20, '19

Mode Complete S
1 Count Fixed Asset and Stamp Code 2 days Mon 1/21/19 Tue 1/22/19 0% Sophath,Chouy Soph
2 Count Raws Materials and Other Overhead 2 days Wed 1/23/19 Thu 1/24/19 0% Stock Controller,Chouy,Head of Department,Sophath
3 Count Semi-Finished Goods and Finished Goods 2 days Fri 1/25/19 Mon 1/28/190% Chouy,Head of Department,Sophath,Stock Controller
4 Confirm with Cash on hand, Cash in Bank, Account Receivable, Account 1 day Tue 1/29/19 Tue 1/29/19 0% Sophath,AR Controller,AP Controller
Payable, and Capital Investment
5 Verify Data and key into System 2 days Wed 1/30/19 Thu 1/31/19 0% Sophath

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Manual Schedul for Op
Summary Manual Summary Rollup Progress
Date: Fri 1/4/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
Jan 20, '19 Jan 27, '19 Feb 3, '19 Feb 10, '19 Feb 17, '19 Feb 24, '19 Mar 3, '19 Mar 10, '19
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
Sophath,Chouy
Stock Controller,Chouy,Head of Department,Sophath
Chouy,Head of Department,Sophath,Stock Controller
Sophath,AR Controller,AP Controller

Sophath

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Manual Schedul for Op
Summary Manual Summary Rollup Progress
Date: Fri 1/4/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2