Chapter 4
Fall 2018
10/23/2018
Engineering Economy
Chap 4: Present Worth Analysis
1. Capital (C):
the funds that finance engineering projects
2. Cost of Capital (COC):
the interest rate paid on capital funds
3. Minimum Attractive Rate of Return (MARR):
a reasonable ROR established for the evaluation/selection of alternatives
how much it costs to obtain the needed capital funds
for an accepted project: ROR ≥ MARR > COC
10/23/2018
Engineering Economy
Chap 4: Present Worth Analysis
Revenue
Cash Flow Estimates:
Cost
6. Revenue:
alternatives include estimates of costs (outflows) and revenues (inflows)
7. Cost:
alternatives include only costs
revenues and savings assumed equal for all alternatives
Costs are also called service alternatives
Present Worth (PW) Analysis of Alternatives:
Using MARR for converting all cash flows to PW
Preceding costs by minus sign; receipts by plus sign
10/23/2018
Engineering Economy
Chap 4: Present Worth Analysis
Progression
from Proposals
much of the emphasis
in professional
engineering practice is
on
Economic Evaluation
ME & cost alternatives
to selection
10/23/2018
Engineering Economy
Chap 4: Present Worth Analysis
Example 2
A project is defined by the following economical data:
MARR = 10%, first cost P = $-2500, Annual revenue A = $2000 per year
Annual cost AOC = $-900 per year, Salvage value S = $200, Life n = 6 years
Check whether this project is justified?
i = MARR = 0.1; 2 x P/A; 1 x P/F; n = 6
PW = P + A (P/A, 10%, 6) + AOC (P/A, 10%, 6) + S (P/F, 10%, 6)
= -2500 + 2000 (P/A, 10%, 6) – 900 (P/A, 10%, 6) + 200 (P/F, 10%, 6)
= -2500 + 8711 – 3920 + 113
= + $2,404
PW > 0; project is
economically justified
10/23/2018
Engineering Economy
Chap 4: Present Worth Analysis
Example 3
Example 4
The operations of two machines with following data must be compared.
Using Present Worth Analysis at an MARR of 10% per year find out which
machine is economically acceptable.
Machine A Machine B
1st cost $20,000 $30,000
Annual cost per year $9,000 $7,000
Salvage value $4,000 $6,000
Life, year 3 6
Example 4
0 1 2 3 4 5 6
PWB = -30,000 – 7000 (P/A, 10%, 6) +
6000 (P/F, 10%, 6)
$7000 / year = $-57,100
$30000 Machine B machine B would be selected
10/23/2018
Engineering Economy
Chap 4: Present Worth Analysis
Example 5
Example 5
LCM of 6 & 9 = 18 years
Example 5
(a) with an LCM = 18:
10/23/2018
Engineering Economy
Chap 4: Present Worth Analysis
Evaluation approach:
determining FW value from cash flows or PW with an n value in F/P factor
Least Common Multiple (LCM)
ways of comparing equal-service:
Study Period
10/23/2018
Engineering Economy
Chap 4: Present Worth Analysis
Example 6
Compare the machines shown below on the basis of their capitalized cost.
Use i = 10% per year.
Machine 1 Machine 2
1st cost $20,000 $100,000
Annual cost per year $9,000 $7,000
Salvage value $4,000 -------------
Life, year 3 ∞
Converting machine 1 cash flows into A and then divide by i:
A1 = -20,000 (A/P, 10%, 3) – 9000 + 4000 (A/F, 10%, 3) = $-15,834
CC1 = A1 / i = -15,834 / 0.1 = $-158,340 machine 1 is selected
n2→∞, CC2 = -100,000 – (7000) / 0.1 = $-170,000
10/23/2018
Engineering Economy
Chap 4: Present Worth Analysis
13. Procedure to find CC for an infinite sequence of cash flows:
1. Draw diagram for 2 cycles of recurring (periodic) cash flows and any
nonrecurring (one-time) cash flows,
2. Calculate PW (or CC) for all nonrecurring amounts,
3. Find AW for 1 cycle of recurring amounts; then add these to all A
series applicable for all years 1 to ∞ (or long life),
4. Find CC for amount above using CC = AW / i,
5. Add all CC values (steps 2 and 4).
Example 7
Find CC and A values at i = 5% of long-term public project with cash flows
below. Cycle time is 13 years.
Nonrecurring costs: first $150,000; then one-time of $50,000 in year 10
Recurring costs: annual maintenance of $5000 (years 1-4) and $8000
thereafter; upgrade costs $15,000 each 13 years
10/23/2018
Engineering Economy
Chap 4: Present Worth Analysis
Example 7
Step 1
recurring
nonrecurring
cycle time
Step 2
nonrecurring costs CC1 = -150,000 – 50,000 (P/F, 5%, 10) = $-180,695
Step 3
recurring $15,000 upgrade AW = -15,000 (A/F, 5%, 13) = $-847 / year
recurring maintenance costs years 1 to ∞ AW = $-5000 / year forever
10/23/2018
Engineering Economy
Chap 4: Present Worth Analysis
Example 7
Step 4
CC of extra $3000 (=8000-5000) maintenance for years 5 to ∞:
CC2 = -3000 (P/F, 5%, 4) / 0.05 = $-49,362
CC for recurring upgrade and maintenance costs:
CC3 = (-847-5000) / 0.05 = $-116,940
Step 5
Total CC obtained by adding all three CC components:
CCT = -180,695 – 49,362 – 116,940 = $-346,997
The AW value is the annual cost forever:
AW = CC × i = -346,997 (0.05) = $-17,350
10/23/2018