Anda di halaman 1dari 1

ANALISA HARGA SATUAN PEKERJAAN

PROJECT :
LOCATE :
JOB : Structure
ongkos kirim/rit (Rp) 700,000
max 8 ton/rit 8000 kg
PEKERJAAN : BESI BETON (SNI) biaya perkilonya (Rp) 87.50
SATUAN : KG
HARGA KONSULTAN
NO. URAIAN PEKERJAAN UNIT VOL
SATUAN TOTAL MATERIAL TOTAL JASA
###
Rp Rp Rp
###
1 Bahan ###
Besi Beton Ulir kg 1.05 6,685 7,019 ###
Kawat Bendrat kg 0.02 13,000 260 ###
ongkos kirim kg 1.00 88 88 ###
###
3 Upah ###
Upah pembesian + alat bantu Kg 1.00 1,000 1,000 ###
###
SUB TOTAL 7,366 1,000
###
PROFIT 10% 737 100
###
TOTAL 8,103 1,100
TOTAL MATERIAL + JASA 9,203
###
Harga Penawaran 9,300
###
###
###
PEKERJAAN : BESI PROFIL Marking MS ###
SATUAN : KG ###
HARGA KONSULTAN ###
NO. URAIAN PEKERJAAN UNIT VOL
SATUAN TOTAL MATERIAL TOTAL JASA###
Rp Rp Rp ###
###
1 Bahan ###
Besi Struktur <WF 300 kg 1.05 6948 7,296 ###
ongkos kirim kg 1.00 88 88 ###
Siku 50.50.5
2 Upah HB 150 x 150 x 7 x 10mm 12Mtr
Upah Erection + potong + welded + alat bantu kg 1.00 5,500 5,500

SUB TOTAL 7,383 5,500


PROFIT 10% 738 550
TOTAL 8,121 6,050
TOTAL MATERIAL + JASA 14,171
Harga Penawaran 14,200
PEKERJAAN : BESI PROFIL Marking MS
SATUAN : KG
HARGA KONSULTAN
NO. URAIAN PEKERJAAN UNIT VOL
SATUAN TOTAL MATERIAL TOTAL JASA
Rp Rp Rp

1 Bahan

Besi Struktur >WF 300 kg 1.05 6,950 7,297


ongkos kirim kg 1.00 88 88

2 Upah

Upah Erection + potong + welded + alat bantu kg 1.00 5,500 5,500

SUB TOTAL 7,385 5,500


PROFIT 10% 738 550

TOTAL 8,123 6,050


TOTAL MATERIAL + JASA 14,173
Harga Penawaran 14,200

PEKERJAAN : BESI PROFIL Marking MS


SATUAN : KG
HARGA KONSULTAN
NO. URAIAN PEKERJAAN UNIT VOL
SATUAN TOTAL MATERIAL TOTAL JASA
Rp Rp Rp

1 Bahan
Besi Struktur HB kg 1.05 6,950 7,297
ongkos kirim kg 1.00 88 88

2 Upah
Upah Erection + potong + welded + alat bantu kg 1.00 5,500 5,500

SUB TOTAL 7,385 5,500


PROFIT 10% 738 550
TOTAL 8,123 6,050
TOTAL MATERIAL + JASA 14,173
Harga Penawaran 14,200

PEKERJAAN : BESI PROFIL Marking MS


SATUAN : KG
0
NO. URAIAN PEKERJAAN UNIT VOL
SATUAN TOTAL MATERIAL TOTAL JASA
Rp Rp Rp

1 Bahan
Besi Struktur SIKU kg 1.05 7099 7,454
ongkos kirim kg 1.00 88 88

2 Upah
Upah Erection + potong + welded + alat bantu kg 1.00 5,500 5,500

SUB TOTAL 7,541 5,500


PROFIT 10% 754 550
TOTAL 8,295 6,050
TOTAL MATERIAL + JASA 14,345
Harga Penawaran 14,400

PEKERJAAN :CAT BAJA Ex. IP


SATUAN : M²
HARGA KONSULTAN
NO. URAIAN PEKERJAAN UNIT VOL
SATUAN TOTAL MATERIAL TOTAL JASA
Rp Rp Rp

1 Bahan
Cat dasar 1 kali (50µ) m2 1.00 26,376 26,376
Cat Finish 2 kali (150µ) m2 1.00 22,007 22,007
Cat finish 1 kali (50µ) m2 1.00 15,049 15,049
Ongkos kirim kg 0.32 0 0

2 Upah
Cat m2 1.00 18,000 18,000
Sandblast m2 1.00 40,000 40,000

SUB TOTAL 63,432 58,000


PROFIT 10% 6,343 5,800
TOTAL 69,775 63,800
TOTAL MATERIAL + JASA 133,575
Harga Penawaran 133,600

PEKERJAAN : CHAQUERPLATE BAJA 4'x8'


SATUAN : KG 2.4384 1.2192 2.973 m2
SATUAN
NO. URAIAN PEKERJAAN UNIT VOL
SATUAN TOTAL MATERIAL TOTAL JASA
Rp Rp Rp

1 Bahan
Besi Struktur CHAQUERPLATE BAJA kg 1.10 7,492 8,241
ongkos kirim kg 1.00 88 88

2 Upah
Upah Potong + Pasang + Alat bantu kg 1.00 5,500 5,500

SUB TOTAL 8,328 5,500


PROFIT 10% 833 550
TOTAL 9,161 6,050
TOTAL MATERIAL + JASA 15,211
Harga Penawaran 15,300

PEKERJAAN : PLAT HITAM BAJA 4'x8'


SATUAN : KG 2.4384 1.2192 2.973 m2
HARGA KONSULTAN
NO. URAIAN PEKERJAAN UNIT VOL
SATUAN TOTAL MATERIAL TOTAL JASA
Rp Rp Rp

1 Bahan
Besi Struktur kg 1.10 7,011 7,712
ongkos kirim kg 1.00 88 88

2 Upah
Upah Potong + Pasang + Alat bantu kg 1.00 5,500 5,500

SUB TOTAL 7,799 5,500


PROFIT 10% 780 550
TOTAL 8,579 6,050
TOTAL MATERIAL + JASA 14,629
Harga Penawaran 14,700

PEKERJAAN : PLAT BAJA with Rolled


SATUAN : KG
HARGA KONSULTAN
NO. URAIAN PEKERJAAN UNIT VOL
SATUAN TOTAL MATERIAL TOTAL JASA
Rp Rp Rp

1 Bahan
Besi Struktur kg 1.10 9,700 10,670
ongkos kirim kg 1.00 0 0

2 Upah
Upah Potong + Pasang + Alat bantu+ Rolled kg 1.00 5,500 5,500

SUB TOTAL 10,670 5,500


PROFIT 10% 1,067 550
TOTAL 11,737 6,050
TOTAL MATERIAL + JASA 17,787
Harga Penawaran 17,800

PEKERJAAN : PLAT STRIP


SATUAN : KG
0
NO. URAIAN PEKERJAAN UNIT VOL
SATUAN TOTAL MATERIAL TOTAL JASA
Rp Rp Rp

1 Bahan
Besi Struktur kg 1.10 8,551 9,406
ongkos kirim kg 1.00 88 88

2 Upah
Upah Potong + Pasang + Alat bantu kg 1.00 4,500 4,500

SUB TOTAL 9,494 4,500


PROFIT 10% 949 450
TOTAL 10,443 4,950
TOTAL MATERIAL + JASA 15,393
Harga Penawaran 15,400

Anda mungkin juga menyukai