APPENDIX A: ARP Weekly Work Plan Date:

Name, Program: Xxxxx Xxxxxxxx, XXX2


ARP Progress Report #__
Project Title: Boiler Plant Piping Modifications at SJ Foods Inc.
Sponsor: SJ Foods Inc., Saint John

All AR Project *DELIVERABLES* are mentioned at appropriate times in the following Work Plan.

JANUARY 7-11

o Establish structured daily Logbook


o Meet with Project sponsor on-site—take notes on proposed work-plan schedule/restrictions…
o Review plant rules and production schedule
o Establish CAD requirements
o Gather background information on topic/company
o Begin review of background data on problem
o Prepare draft Progress Report #1
o Consult with Technical Advisor re proposed work plan

JANUARY 14-18

o Complete review of background information


o Gather field data for project schematics, including sketch of compressor room, receivers, and piping
o Begin calculations to indicate air flow, velocities, and head loss
o Submit Progress Report #1 with Work Plan to Tech Advisor (with Logbook) and to Comm Instructor

JANUARY 21-25

o Complete project schematic showing compressor specifications, line type/size/length/condition, system


arrangement, operation details
o Finalize calculations indicating airflow, velocities, and head loss (*DELIVERABLE*)
o Verify flow calculations with actual field measurements
o Prepare and submit formal ARP Proposal--memo format with all required Appendices

JANUARY 28-FEBRUARY 1

o Meet with Project Sponsor to approve project schematic and review data
o Begin literature review
o Meet G Jenkins (Plant Suptd) at SJ Foods Inc. with air equipment vendor re specs and prices: 31 Jan @ 4:00
o Discuss project solutions with Tech Advisor
o Begin to compile list of options and recommendations

FEBRUARY 4-8

o Finalize existing project schematic on CAD


o Prepare draft list of recommendations/options for discussion with Project Sponsor (*DELIVERABLE*)
o Meet with G Jenkins of SJ Foods Inc. to review possible options and recommendations
o Learn SolidWorks and begin to model the design

FEB…MARCH…APRIL… [Continue week by week until AR Project submission date]

APRIL 23 (First Day of Term 6)

o Submit copies of Applied Research Report: 1 bound / 1 unbound / 1 on usb drive (*DELIVERABLE*)
o Prepare and practice ARP Presentation
o Invite Sponsor to attend Presentation (date/time/location)