Peñasquito Pyrite Leach Project Execution Stage October 2018
Project Number: A9PPS511 Client Doc. No. PLP-FL-PM-115-0014
Goldcorp
Pyrite Leach Project Execution Stage
Issued: 21-November-2018
CONFIDENTIAL
(DO NOT COPY OR DISTRIBUTE)
Page i
Goldcorp Monthly Progress Report No. 035
Peñasquito Pyrite Leach Project Execution Stage October 2018
Project Number: A9PPS511 Client Doc. No. PLP-FL-PM-115-0014
DISTRIBUTION LIST
Name
Copies
Goldcorp Electronic Hardcopy
Daniel Arvayo 1
Pablo Balsamo 1
Brian Berney 1
Luis Chaman 1
Luis Cornejo 1
Kim Hackney 1
Philip Jutten 1
David Moll 1
Nelson Nunez 1
Jeannie Troung 1
Dale Tweed 1
Bruce Knight 1
Fluor
Marcel Bittel 1
ICA Fluor
Eduardo Baran 1
Project
Victor Caro 1
Fabian Servin 1
Vijay Parasram 1
Alejandro Rangel 1
Brendan Macken 1
Total 21 1
Page ii
Goldcorp Monthly Progress Report No. 035
Peñasquito Pyrite Leach Project Execution Stage October 2018
Project Number: A9PPS511 Client Doc. No. PLP-FL-PM-115-0014
TABLE OF CONTENTS
Page
1. DASHBOARD .................................................................................................................. 1
2. PROJECT DESCRIPTION............................................................................................... 1
2.1 General Description ................................................................................................... 1
2.2 General Layout .......................................................................................................... 1
3. SAFETY ........................................................................................................................... 2
4. QUALITY.......................................................................................................................... 2
5. NARRATIVES .................................................................................................................. 2
5.1 Major Milestones/Finished Activities and In Progress Activities ................................ 2
5.2 Major Milestones/ Scheduled Activities for Upcoming Period.................................... 5
6. ISSUES AND CONCERNS.............................................................................................. 7
7. PROGRESS ..................................................................................................................... 7
7.1 Engineering ................................................................................................................ 7
7.2 Procurement............................................................................................................... 7
7.3 Construction ............................................................................................................... 7
7.4 Pre-Commissioning and Commissioning ................................................................... 7
8. SCHEDULE ..................................................................................................................... 8
8.1 Master Schedule ........................................................................................................ 8
8.2 Critical Path ................................................................................................................ 8
9. PAYMENT SCHEDULE AND COST REPORT ............................................................... 8
9.1 Billing Status .............................................................................................................. 8
9.2 Incurred Cost by FBS Table ....................................................................................... 8
9.3 Forecast Cost Flow by FBS ....................................................................................... 8
9.4 Forecast Cost Flow by Current .................................................................................. 8
10. CHANGE MANAGEMENT .............................................................................................. 8
11. APPENDICES .................................................................................................................. 9
Page iii
Goldcorp Monthly Progress Report No. 035
Peñasquito Pyrite Leach Project Execution Stage October 2018
Project Number: A9PPS511 Client Doc. No. PLP-FL-PM-115-0014
1. DASHBOARD
Monthly report for October 2018 addresses the period from October 1st to October 28th, 2018
The past October 15, 2018 was achieved of PLP Practical Completion; additionally Goldcorp issued
the Certificate of Transfer of Care, Custody and Control (TCCC) of the entire Project based on
Terms & Conditions of the EPC Agreement, Section 25.10.
As a result of the above, we continue strongly working to close the list of exceptions attach to the
TCCC certificate issued by Goldcorp.
Page 1
Goldcorp Monthly Progress Report No. 035
Peñasquito Pyrite Leach Project Execution Stage October 2018
Project Number: A9PPS511 Client Doc. No. PLP-FL-PM-115-0014
3. SAFETY
Reached 7,869,311 man-hours without LTI from Sep 14, 2016, to Oct 16th, 2018.
Daily meetings with construction and Pre-commissioning continue to review the activities to
be carried out each day.
After having obtained the TCCC for PLP (Transfer Care, Custody and Control certificate)
we have closed the safety Statistics with October 16, 2018 Date.
I. Environmental
The month of October was destined to carry out the removal and disposal of all the materials
and waste that were stored in the yards and general store. In this way, the cleaning and
rehabilitation of the patio of workshops and other storage yards is carried out.
4. QUALITY
Workflow tracking for CWP and TOP'S acceptance and compilation of key documents to be
sent to Goldcorp the project data book
Support Construction & Precommissioning team to address the issues and concerns that
arise in the daily follow-up meeting with client to final TCCC.
5. NARRATIVES
5.1 Major Milestones/ Finished Activities and In Progress Activities (Current Period)
I. Field Engineering
Got final dictum from Electrical Verification (UVIE) and Mechanical Verification Units.
Expediting and closing out document review with vendor GE Prime 6 Electrical.
Expediting last I/O Manuals from Vendor GE
Working with PID´s As-built.
II. Procurement
Page 2
Goldcorp Monthly Progress Report No. 035
Peñasquito Pyrite Leach Project Execution Stage October 2018
Project Number: A9PPS511 Client Doc. No. PLP-FL-PM-115-0014
III. Subcontracts
Close out has been initiated for contract PEN-071-18 Gratings and handrails supply and
installation with Industrial Batagonza, SA.
Close out has been initiated for contract K-019 for the services of Labor Bussing with
Servicios Coordinados Piolín, SA
Close out has been initiated for contract PEN-064-17 for the Supply and Installation of
Insulation in Pipelines and equipment with Company Fervaz Construcciones e
Instalaciones, SA.
Close out has been initiated for contract PEN-044-17 for the Scaffolding Services on
Tanks with company Andamios In–Situ, SA
Close out has been initiated for contract K-109C Rubber lining Spools adjustments wth
ANVI Mexicana, SA.
Close out has been initiated for contract K-120B for Permanent Buildings (COMMOSA).
Close out has been initiated for contract PEN-001 for Forms leasing (UNISPAN).
Close out has been achieved of contract K-001 for Ready-Mix concrete supply with
Concretos Cemex, SA; since negotiations had been finalized, and all close-out documents
are now executed by Parties.
IV. Construction
Page 3
Goldcorp Monthly Progress Report No. 035
Peñasquito Pyrite Leach Project Execution Stage October 2018
Project Number: A9PPS511 Client Doc. No. PLP-FL-PM-115-0014
VI. Safety
a) Security
b) Environmental
Verification of sanitation of the yards, where materials and equipment were stored.
Disposal of all the recoverable residues those were stored in the different fronts.
The cleaning of the general store is carried out, for delivery to the UMP.
The hazardous waste generated in the work is sent to final disposal.
The information referring to the environmental management system is concentrated, for
the preparation of the client delivery dossier.
Page 4
Goldcorp Monthly Progress Report No. 035
Peñasquito Pyrite Leach Project Execution Stage October 2018
Project Number: A9PPS511 Client Doc. No. PLP-FL-PM-115-0014
VII. Quality
I. Field Engineering
II. Procurement
III. Subcontracts
Continue with the close out of Subcontracts whose work has been finalized.
IV. Construction
Page 5
Goldcorp Monthly Progress Report No. 035
Peñasquito Pyrite Leach Project Execution Stage October 2018
Project Number: A9PPS511 Client Doc. No. PLP-FL-PM-115-0014
d) Mechanical Works
Will be finish the exception list activities in PLP.
f) Electrical Works
Will be finish the exception list activities in PLP.
Close final punch list items, B sheets and complete transfer of remaining subsystems to
GC Operations.
VI. Safety
a) Security
VII. Quality
Page 6
Goldcorp Monthly Progress Report No. 035
Peñasquito Pyrite Leach Project Execution Stage October 2018
Project Number: A9PPS511 Client Doc. No. PLP-FL-PM-115-0014
7. PROGRESS
8. SCHEDULE
On October 15, 2018 was achieved of Practical Completion and the Transfer Care, Custody and
Control (TCCC), so this Critical Path section no longer applies.
Page 7
Goldcorp Monthly Progress Report No. 035
Peñasquito Pyrite Leach Project Execution Stage October 2018
Project Number: A9PPS511 Client Doc. No. PLP-FL-PM-115-0014
Page 8