In this phase Project Management Team prepares abbreviated Project
Execution Plan which basically states how the project is going to be executed
the project can be handled in-kingdom or out of kingdom, whether the project
will be handled as one package or more than one. All of this is determined
proponent and Project Management Team. This will secure TC-68 funding.
TC-68 Funds are Funds allotted to project management personnel only for the
and contract. This funding is usually 5% to 10% of the project cost, and is
determined in the Study and Development Phase, based on the nature of the
project, and how and where the preliminary engineering to be done (6).
design contractor to prepare the Project Proposal. The purpose of the project
accurate Expenditure Request estimate of the actual cost of the project. This
will enable management to deicide whether to proceed with the project or not.
Project Management Team and General Engineering Service Unit, one of the
Project Support and Controls Department units, develop the Bid slate. The bid
bid for doing the project proposal. The Bid slate is taken to Service Review
12
• Any Sole Source Service Authorization anticipated
established at the initial procurement was under $2 Million, but the final
submit their bids on the project proposal. Bidders are required to submit
(where applicable) provide sufficient information to obtain Lump Sum Turn Key
will open the bid box and the lowest cost contractor is selected to do the
project proposal. Project Management Team will direct and monitor the design
Team initiates a formal value engineering study. The value engineering study
is coordinated with the Value Engineering Unit of the Project Support and
Controls Department.
representative to develop the construction contract, bid slate, and the bid
13
review program. The Contracting Department representative sends the
contract to the Law Department and Contract Review and Cost compliance
representative will agree on the construction contractors who will be in the bid
slate. Also, they would prepare the bid review program that will identify the
bidders understand the specific scope of work and whether their proposals
meet the requirement of the scope of work. The technical evaluation should
reveal cases where an otherwise capable contractor has failed to plan the use
commercial evaluation is to identify the bid representing the lowest overall cost
14
2.3 PHASE III – FUNDING PHASE:
15
After the Expenditure Request estimate is prepared, Project
Management Team and Project Support and Controls Department will prepare
approved and the project can move to the next phases (9).
16
2.4 PHASE IV – DETAILED ENGINEERING:
Includes:
packages.
17
Upon Expenditure Request Approved (ERA), the Contracting
the bid slate to a clarification meeting in which the scope of the project will be
explained. A site visit may be conducted. The contractors get a copy of the bid
package to bid on. Each contractor will submit a technical and a commercial
bid.
The technical bid will contain the technical and management aspects of
the work, and may include the following, depending on the contract:
• Manpower plan
• Equipment schedule.
• Equipment Rental.
• Subcontract Plan.
18
The commercial bid will be based on:
The technical bid will be opened first by the Technical Review Team,
rated against a scale with an agreed pass score. The overall passing score is
70% of the total points. Any bidder which does not achieve this passing score
After the technical evaluation, the commercial bid will be opened by the
those bidders whose Technical proposals have been approved. List the
19
The lowest of the Total cost will be ranked with number 1 and will be
the kind of contract, the detailed engineering will be done by the construction
the facility. Issued for Construction package is developed for the procurement
attend a kick off meeting. In the meeting the contractor meets the
especially at 60% and 90% design completion stages. During this time,
several Saudi Aramco organizations are involved in the reviews like Project
Department.
to make sure that designed facility meets Saudi Aramco standards and
20
As the job progresses, monthly reports are prepared by the contractor to
Aramco drawing management system, which is drawing database for all the
company drawings.