WEEKLY TIME SHEET

CLIENT : PT ONE ( P Chusnu ) PROJECT NAME : Modification P


PO NUMBER DRAWING NO :
HARMONI ENERGY SEMESTA WEEK : 01 PERIODE : 31 Des 201
Man Man Total
Start-Stop
No Description Process Part Power Hours Day
( Orang )( Jam )
1 Furnace
Pembongkaran Castabe 2 8 1 08.00 -17.00
2 8 1 08.00 -17.00

Review / Approve by : Prepare by :


Yoyok

(…………………………………………) (…………………………………………)
PT ONE PT HIE
Rev :
PROJECT NAME : Modification Plant Date :
Page
PERIODE : 31 Des 2018- 5 Jan-2019

Remark

Kamis, 3 jan- 2019


Jum'at, 4 jan- 2019

(…………………………………………)
PT HIE
WEEKLY TIME SHEET Rev :
CLIENT : PT ONE ( P Chusnu ) PROJECT NAME : Modification Plant Date :
PO NUMBER DRAWING NO : Page
HARMONI ENERGY SEMESTA WEEK : 02 PERIODE : 7 - 12 Jan-2019
Man Man Total
Start-Stop
No Description Process Part Power Hours Day Remark
( Orang )( Jam )
1 Furnace
Pembongkaran Castabe 2 8 1 08.00 -20.00 senin, 7 jan - 2019
2 Screw Conveyo
Pembongkaran 2 12.5 2 08.00 -20.00 Rabu, Kamis ( 9 s/d 10 Jan-2019
Screw Conveyor 2 8 2 08.00 -17.00 Jum'at,sabtu ( 11 s/d 12 Jan-20

Review / Approve by : Prepare by :


Yoyok

(…………………………………………) (…………………………………………)
PT ONE PT HIE