Anda di halaman 1dari 20

REKAPITULASI RENCANA ANGGARAN BIAYA

PEMBANGUNAN JARINGAN IRIGASI TERSIER COT TRIENG


KOTA LHOKSEUMAWE

JUMLAH BIAYA TOTAL


NO PEKERJAAN JUMLAH BIAYA
( Rp.) (Rp.)
I PEKERJAAN PERSIAPAN 45,000,000.00
A. Pembersihan Lapangan 4,000,000.00
B. Pemasangan profil dan Pengukuran Awal (MC.0) 30,000,000.00
C. Direksi Keets, Los Kerja dan Gudang 10,000,000.00
D. Pembuatan Papan Nama Proyek 1,000,000.00
II PEKERJAAN SALURAN TERSIER COT TRIENG KIRI 2,793,875,801.07
A. Pembangunan Saluran Tersier (L = 2553 m) 2,762,608,061.35
B. Pekerjaan Box Tersier Tipe - II (2 unit) 10,289,298.54
C. Pekerjaan Box Tersier Tipe - III (2 uit) 10,231,272.39
D. Pekerjaan Box Kuarter (3 unit) 10,747,168.80
III PEKERJAAN SALURAN TERSIER COT TRIENG KANAN 3,134,238,767.67
A. Pembangunan Saluran Tersier (L = 2057 m) 2,846,499,486.39
B. Bangunan Bagi Sadap (4 unit) 152,190,023.45
C. Pekerjaan Gorong-gorong/box culvert (1 unit) 18,542,229.98
D. Pekerjaan Talang Air (1 unit) 91,557,027.84
E. Pintu sorong rangka baja (13 buah) 25,450,000.00
IV PEKERJAAN SALURAN TERSIER COT TRIENG KANAN A 1,141,596,165.16
A. Pembangunan Saluran Tersier (L = 1047 m) 1,123,629,257.95
B. Pekerjaan Box Tersier Tipe - II (3 unit) 14,776,318.11
C. Pekerjaan Box Kuarter (1 unit) 3,190,589.10
V PEKERJAAN SALURAN TERSIER COT TRIENG KANAN B 1,050,547,101.04
A. Pembangunan Saluran Tersier (L = 846 m) 1,035,419,086.41
B. Pekerjaan Box Tersier Tipe - I (1 unit) 11,937,425.52
C. Pekerjaan Box Kuarter ( 1 unit) 3,190,589.10
VI PEKERJAAN SALURAN TERSIER COT TRIENG KANAN C 1,324,717,844.85
A. Pembangunan Saluran Tersier (L = 1080 m) 1,309,589,830.22
B. Pekerjaan Box Tersier Tipe - I (1 unit) 11,937,425.52
C. Pekerjaan Box Kuarter (1 unit) 3,190,589.10
VII PEKERJAAN LAIN-LAIN 35,000,000.00
A. Administrasi, Progress dan Pelaporan 8,000,000.00
B. Pengukuran dan Pembuatan Mutual Check (MC) 20,000,000.00
C. Foto Dokumentasi 2,000,000.00
D. P3K dan Obat -obatan 5,000,000.00
JUMLAH 9,524,975,679.78
DIBULATKAN 9,524,970,000.00
Terbilang : " Sembilan Milyar Lima Ratus Dua Puluh Empat Juta Sembilan Ratus Tujuh Puluh Ribu Rupiah"

Lhokseumawe, Desember 2008


Menyetujui,
Kepala Dinas Pekerjaan Umum PT. Citra Rancang Global
Kota Lhokseumawe

IR. KAMARUZZAMAN MUSTAFA UMAR ST


Nip. 110045829 Direktur Utama

Mengetahui, Menyetujui,
Pengguna Anggaran Pejabat Pembuat Komitmen
Bappeda Kota Lhokseumawe Bappeda Kota Lhokseumawe

DRS. T. SOFYANSYAH TAUFIK S.Sos


PEMBINA TK. I/Nip. 010092878 Nip. 010281789
RENCANA ANGGARAN BIAYA
PEMBANGUNAN JARINGAN TERSIER COT TRIENG KIRI (L = 2351 meter)
DESA COT TRIENG - KOTA LHOKSEUMAWE

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN STN VOLUME ANALISA (Rp.) (Rp.)

I PEKERJAAN SALURAN IRIGASI


Saluran Tersier Cot Trieng Kiri m 2,351.00
1. Galian tanah m3 1,747.62 Anl A1 27,675.00 48,365,311.55
2. Timbunan tanah m3 3,605.47 Anl D2 99,190.00 357,626,346.12
3. Striping/kupasan m2 8,544.70 Anl B1 2,035.00 17,388,462.06
4. Beton K-175 m3 1,290.83 Anl Supl 1a 1,812,192.10 2,339,227,941.62
JUMLAH I 2,762,608,061.35
II PEKERJAAN BANGUNAN IRIGASI
A. Pekerjaan Box Tersier Tipe - II Unit 2.00
1. Galian tanah m3 7.09 Anl A1 27,675.00 196,160.40
2. Timbunan tanah m3 4.42 Anl D2 99,190.00 438,419.80
3. Beton K-175 m3 4.66 Anl. Supl 1a 1,812,192.10 8,437,566.42
4. Pas. Batu 1:4 m3 1.66 Anl E2 561,700.00 932,983.70
5. Plasteran 1:2 m2 6.44 Anl G.50h 44,125.50 284,168.22
Jumlah A 10,289,298.54
B. Pekerjaan Box Tersier Tipe - III Unit 2.00
1. Galian tanah m3 7.09 Anl A1 27,675.00 196,160.40
2. Timbunan tanah m3 3.84 Anl D2 99,190.00 380,393.65
3. Beton K-175 m3 4.66 Anl. Supl 1a 1,812,192.10 8,437,566.42
4. Pas. Batu 1:4 m3 1.66 Anl E2 561,700.00 932,983.70
5. Plasteran 1:2 m2 6.44 Anl G.50h 44,125.50 284,168.22
Jumlah B 10,231,272.39
C. Pekerjaan Box Karter Unit 3.00
1. Galian tanah m3 4.87 Anl A1 27,675.00 134,832.60
2. Timbunan tanah m3 11.85 Anl D2 99,190.00 1,175,401.50
3. Beton K-175 m3 4.20 Anl. Supl 1a 1,812,192.10 7,611,206.82
4. Pas. Batu 1:4 m3 2.49 Anl E2 561,700.00 1,399,475.55
5. Plasteran 1:2 m2 9.66 Anl G.50h 44,125.50 426,252.33
Jumlah C 10,747,168.80
JUMLAH II (A+B+C) 31,267,739.73

JUMLAH ( I + II ) 2,793,875,801.07

Lhokseumawe, Desember 2008

PT. Citra Rancang Global

MUSTAFA UMAR ST
Direktur Utama
RENCANA ANGGARAN BIAYA
PEMBANGUNAN JARINGAN TERSIER COT TRIENG KANAN (2057 meter)
DESA COT TRIENG - KOTA LHOKSEUMAWE

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN STN VOLUME ANALISA
(Rp.) (Rp.)

I PEKERJAAN SALURAN IRIGASI


Saluran Tersier Cot Trieng Kanan m 2,057.00
1. Pembongkaran Saluran dan Bangunan Lama m 1,243.00 Ls 10,000.00 12,430,000.00
2. Galian tanah m3 1,488.83 Anl A1 27,675.00 41,203,370.25
3. Timbunan tanah m3 3,972.34 Anl D2 99,190.00 394,015,908.65
4. Striping/kupasan m2 78.75 Anl B1 2,035.00 160,256.25
5. Beton K-175 m3 1,323.64 Anl Supl 1a 1,812,192.10 2,398,689,951.24
JUMLAH I 2,846,499,486.39
II PEKERJAAN BANGUNAN IRIGASI
A. Bangunan Bagi Sadap unit 4.00
1. Galian tanah m3 99.80 Anl A1 27,675.00 2,762,092.31
2. Timbunan tanah m3 105.17 Anl D2 99,190.00
3. Beton K-175 m3 49.30 Anl. Supl 1a 1,812,192.10 89,345,057.35
4. Beton K-225 m3 11.94 Anl. Supl 1b 3,590,848.48 42,863,958.25
5. Pas. Batu 1:4 m3 28.72 Anl E2 561,700.00 16,133,428.25
6. Plasteran 1:2 m2 24.60 Anl G.50h 44,125.50 1,085,487.30
Jumlah A 152,190,023.45
B. Pekerjaan Gorong-gorong/box culvert unit 1.00
1. Galian tanah m3 8.80 Anl A1 27,675.00 243,540.00
2. Beton K-225 m3 2.80 Anl. Supl 1b 3,590,848.48 10,054,375.73
3. Pas. Batu 1:4 m3 12.36 Anl E2 561,700.00 6,942,612.00
4. Plasteran 1:2 m2 29.50 Anl G.50h 44,125.50 1,301,702.25
Jumlah B 18,542,229.98
C. Pekerjaan Talang Air unit 1.00
1. Galian tanah m3 123.89 Anl A1 27,675.00 3,428,655.75
2. Pas. Batu 1:4 m3 56.88 Anl E2 561,700.00 31,949,496.00
3. Plasteran 1:2 m2 132.16 Anl G.50h 44,125.50 5,831,626.08
4. Beton tumbuk 1:3:5 m3 11.04 Anl G.44 657,610.00 7,263,170.93
5. Beton K-175 m3 0.43 Anl. Supl 1a 1,812,192.10 784,679.18
6. Beton K-225 m3 9.90 Anl. Supl 1b 3,590,848.48 35,549,399.90
7. Cerucuk Kayu m 30.00 Ls 125,000.00 3,750,000.00
8. Perancah Ls 1.00 Ls 3,000,000.00 3,000,000.00
Jumlah C 91,557,027.84
D. Pintu sorong rangka baja BH 13.00
1. Pintu Uk. B = 1.3 H = 0.8 BH 1.00 Ls 2,500,000.00 2,500,000.00
2. Pintu Uk. B = 1.0 H = 0.65 BH 1.00 Ls 2,200,000.00 2,200,000.00
3. Pintu Uk. B = 0.9 H = 0.55 BH 1.00 Ls 2,100,000.00 2,100,000.00
4. Pintu Uk. B = 0.8 H = 0.55 BH 1.00 Ls 2,000,000.00 2,000,000.00
5. Pintu Uk. B = 0.8 H = 0.5 BH 4.00 Ls 1,900,000.00 7,600,000.00
6. Pintu Uk. B = 0.5 H = 0.5 BH 4.00 Ls 1,800,000.00 7,200,000.00
7. Pintu Uk. B = 0.5 H = 0.8 BH 1.00 Ls 1,850,000.00 1,850,000.00
Jumlah D 25,450,000.00
JUMLAH II (A+B+C+D) 287,739,281.27
JUMLAH TOTAL ( I + II ) 3,134,238,767.67

Lhokseumawe, Desember 2008

PT. Citra Rancang Global

MUSTAFA UMAR ST
Direktur Utama
RENCANA ANGGARAN BIAYA
PEMBANGUNAN JARINGAN TERSIER COT TRIENG KANAN A (L = 1047 meter)
DESA COT TRIENG - KOTA LHOKSEUMAWE

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN STN VOLUME ANALISA (Rp.) (Rp.)

I PEKERJAAN SALURAN IRIGASI


Saluran Tersier Cot Trieng Kanan A m 1,047.00
1. Galian tanah m3 430.40 Anl A1 27,675.00 11,911,320.00
2. Timbunan tanah m3 1,534.23 Anl D2 99,190.00 152,180,273.70
3. Striping/kupasan m2 4,418.76 Anl B1 2,035.00 8,992,166.43
4. Beton K-175 m3 524.53 Anl Supl 1a 1,812,192.10 950,545,497.83
JUMLAH I 1,123,629,257.95
II PEKERJAAN BANGUNAN IRIGASI
A. Box Tersier TIPE-II unit 3.00
1. Galian tanah m3 10.63 Anl A1 27,675.00 294,240.60
2. Timbunan tanah m3 6.63 Anl D2 99,190.00
3. Beton K-175 m3 6.98 Anl. Supl 1a 1,812,192.10 12,656,349.63
4. Pas. Batu 1:4 m3 2.49 Anl E2 561,700.00 1,399,475.55
5. Plasteran 1:2 m2 9.66 Anl G.50h 44,125.50 426,252.33
Jumlah A 14,776,318.11
B. Box Kuarter unit 1.00
1. Galian tanah m3 1.62 Anl A1 27,675.00 44,944.20
2. Timbunan tanah m3 3.95 Anl D2 99,190.00
3. Beton K-175 m3 1.40 Anl. Supl 1a 1,812,192.10 2,537,068.94
4. Pas. Batu 1:4 m3 0.83 Anl E2 561,700.00 466,491.85
5. Plasteran 1:2 m2 3.22 Anl G.50h 44,125.50 142,084.11
Jumlah B 3,190,589.10

JUMLAH II (A+B) 17,966,907.21

JUMLAH ( I + II ) 1,141,596,165.16

Lhokseumawe, Desember 2008

PT. Citra Rancang Global

MUSTAFA UMAR ST
Direktur Utama
RENCANA ANGGARAN BIAYA
PEMBANGUNAN JARINGAN TERSIER COT TRIENG KANAN B (L = 846 meter)
DESA COT TRIENG - KOTA LHOKSEUMAWE

NO URAIAN PEKERJAAN STN VOLUME ANALISA HARGA SATUAN JUMLAH HARGA


(Rp.) (Rp.)

I PEKERJAAN SALURAN IRIGASI


Saluran Tersier Cot Trieng Kanan B m 846.00
1. Galian tanah m3 158.51 Anl A1 27,675.00 4,386,764.25
2. Timbunan tanah m3 2,277.60 Anl D2 99,190.00 225,915,144.00
3. Striping/kupasan m2 3,952.14 Anl B1 2,035.00 8,042,604.90
4. Beton K-175 m3 439.84 Anl Supl 1a 1,812,192.10 797,074,573.26
JUMLAH I 1,035,419,086.41
II PEKERJAAN BANGUNAN IRIGASI
A. Box Tersier TIPE-I unit 1.00
1. Galian tanah m3 3.18 Anl A1 27,675.00 88,117.20
2. Timbunan tanah m3 3.25 Anl D2 99,190.00
3. Beton K-175 m3 5.69 Supl 1a 1,812,192.10 10,307,748.66
4. Pas. Batu 1:4 m3 2.49 Anl E2 561,700.00 1,399,475.55
5. Plasteran 1:2 m2 3.22 Anl G.50h 44,125.50 142,084.11
Jumlah A 11,937,425.52
B. Box Kuarter unit 1.00
1. Galian tanah m3 1.62 Anl A1 27,675.00 44,944.20
2. Timbunan tanah m3 3.95 Anl D2 99,190.00
3. Beton K-175 m3 1.40 Supl 1a 1,812,192.10 2,537,068.94
4. Pas. Batu 1:4 m3 0.83 Anl E2 561,700.00 466,491.85
5. Plasteran 1:2 m2 3.22 Anl G.50h 44,125.50 142,084.11
Jumlah B 3,190,589.10

JUMLAH II (A+B) 15,128,014.62

JUMLAH ( I + II ) 1,050,547,101.04

Lhokseumawe, Desember 2008

PT. Citra Rancang Global

MUSTAFA UMAR ST
Direktur Utama
RENCANA ANGGARAN BIAYA
PEMBANGUNAN JARINGAN TERSIER COT TRIENG KANAN B (L = 1080 meter)
DESA COT TRIENG - KOTA LHOKSEUMAWE

NO URAIAN PEKERJAAN STN VOLUME ANALISA HARGA SATUAN JUMLAH HARGA


(Rp.) (Rp.)

I PEKERJAAN SALURAN IRIGASI


Saluran Tersier Cot Trieng Kanan C m 1,080.00
1. Galian tanah m3 100.18 Anl A1 27,675.00 2,772,481.50
2. Timbunan tanah m3 2,906.32 Anl D2 99,190.00 288,277,880.80
3. Striping/kupasan m2 5,101.11 Anl B1 2,035.00 10,380,758.85
4. Beton K-175 m3 556.32 Anl Supl 1a 1,812,192.10 1,008,158,709.07
JUMLAH I 1,309,589,830.22
II PEKERJAAN BANGUNAN IRIGASI
A. Box Tersier TIPE-I unit 1.00
1. Galian tanah m3 3.18 Anl A1 27,675.00 88,117.20
2. Timbunan tanah m3 3.25 Anl D2 99,190.00
3. Beton K-175 m3 5.69 Supl 1a 1,812,192.10 10,307,748.66
4. Pas. Batu 1:4 m3 2.49 Anl E2 561,700.00 1,399,475.55
5. Plasteran 1:2 m2 3.22 Anl G.50h 44,125.50 142,084.11
Jumlah A 11,937,425.52
B. Box Kuarter unit 1.00
1. Galian tanah m3 1.62 Anl A1 27,675.00 44,944.20
2. Timbunan tanah m3 3.95 Anl D2 99,190.00
3. Beton K-175 m3 1.40 Supl 1a 1,812,192.10 2,537,068.94
4. Pas. Batu 1:4 m3 0.83 Anl E2 561,700.00 466,491.85
5. Plasteran 1:2 m2 3.22 Anl G.50h 44,125.50 142,084.11
Jumlah B 3,190,589.10

JUMLAH II (A+B) 15,128,014.62

JUMLAH ( I + II ) 1,324,717,844.85

Lhokseumawe, Desember 2008

PT. Citra Rancang Global

MUSTAFA UMAR ST
Direktur Utama
DAFTAR HARGA SATUAN PEKERJAAN
PEMBANGUNAN JARINGAN IRIGASI TERSIER COT TRIENG
KOTA LHOKSEUMAWE

NO URAIAN PEKERJAAN SATUAN ANALISA HARGA SATUAN

I PEKERJAAN TANAH

1 1 m2 Pembersihan dan striping/kosrekan m2 Anl B.1 2,035.00


2 1 m Galian tanah h > 1-2 m dan membuang hasil galian
3
m 3
Anl. A.1 27,675.00
3 1 m3 Timbunan tanah untuk tanggul saluran m 3
Anl D.2 99,190.00

II PEKERJAAN BETON DAN PASANGAN

1 Beton 1 pc : 1,5 ps : 2,5 kr (Beton Non-Struktural) m3 Anl F.2 607,010.00


2 Beton Cor K-225 (Beton Struktural) m3 Anl G.41 927,610.00
3 Pekerjaan Bekisting (cetakan) m 2
Anl F.8 145,620.00
4 Pasangan Batu Kali (1 : 4) m 3
Anl E.2 561,700.00
5 Plesteran (1 pc : 2 ps, tebal 1 cm) m2 Anl G.50h 44,125.50
6 Pekerjaan Beton Cor m 3
Anl. G.44 657,610.00
7 Beton Lining Saluran dan Bangunan Air (K-175) m 3
Supl. 1a 1,812,192.10
8 Beton Talang Air (K-225) m 3
Supl. 1b 3,590,848.48

Lhokseumawe, Desember 2008

PT. Citra Rancang Global

MUSTAFA UMAR ST
Direktur Utama
ANALISA HARGA SATUAN
PEMBANGUNAN JARINGAN IRIGASI TERSIER
DESA COT TRIENG - KOTA LHOKSEUMAWE

1. Pekerjaan Kupasan/Striping
Anl B.1 1 M2 Pembersihan dan striping/kosrekan
0.05 Org Pekerja @ Rp.
0.005 Org Mandor @ Rp.

2. Pekerjaan Galian Tanah


Anl. A.1 1 M3 Galian tanah h > 1-2 m dan membuang hasil galian
0.75 Org Pekerja @ Rp.
0.025 Org Mandor @ Rp.

3. Pekerjaan Timbunan Tanah


Anl D.2 1 M3 Timbunan tanah untuk tanggul saluran
a. Bahan
1.0 Tanah Timbun @ Rp.

b. 1 M3 Upah Angkutan
0.33 Org Pekerja @ Rp.
0.01 Org Mandor @ Rp.

c. 1 M3 Upah Pemadatan Tanah


0.5 Org Pekerja @ Rp.
0.01 Org Mandor @ Rp.

4. Pekerjaan Beton Non Struktural K-175


Anl F.2 1 M3 Beton 1 pc : 1,5 ps : 2,5 kr)
a. Bahan beton
8.0 Zak PC (40 kg) @ Rp.
0.82 M3 Kerikil @ Rp.
0.54 M3 Pasir Beton @ Rp.

b. Upah kerja beton


0.41 Org Pekerja @ Rp.
0.02 Org Mandor @ Rp.
0.7 Org Tukang Batu @ Rp.
0.07 Org Kepala Tukang @ Rp.
5. Pekerjaan Beton Struktural K-225
Anl G.41 1 M3 Beton Cor K-225
a. Bahan beton
10.0 Zak PC (40 kg) @ Rp.
0.54 Pasir Beton @ Rp.
0.82 Batu Kerikil @ Rp.

b. Upah kerja beton


6.0 Org Pekerja @ Rp.
1.0 Org Tukang Batu @ Rp.
0.1 Org Kepala Tukang @ Rp.
0.3 Org Mandor @ Rp.

6. Pekerjaan Pembesian
Anl F.10 100 kg Pekerjaan besi beton
a. Bahan
110 kg besi beton @ Rp.
2.0 kg kawat ikat @ Rp.

b. Upah kerja besi beton


2.25 Org Kepala Tukang @ Rp.
6.75 Org Tukang Besi @ Rp.
6.75 Org Pekerja @ Rp.

Untuk 1 Kg Pekerjaan Besi (1/100)

7. Pekerjaan Bekisting
Anl F.8 1 M2 Pekerjaan bekisting/cetakan
a. Bahan
0.34 Kayu Bekisting @ Rp.
4.0 Paku Kayu @ Rp.

b. Upah kerja bekisting


0.5 Org Kepala Tukang @ Rp.
0.1 Org Mandor @ Rp.
5.0 Org Tukang Kayu @ Rp.
2.0 Org Pekerja @ Rp.
4.0 Org Bongkar Bekisting @ Rp.

Untuk 1 M2 (1/10)

8. Lain-lain: Membongkar Cetakan Beton


0.400 Pekerja @ Rp.

9. Pekerjaan Pasangan Batu kali 1:4


Anl E.2 1 M3 Pas. Batu kali 1 pc : 4 ps
a. Bahan
1.20 M3 Batu Kali @ Rp.
3.30 Zak PC (50 kg) @ Rp.
0.41 M3 Pasir @ Rp.

b. Upah kerja pas. Batu 1:4


0.600 Org Tukang Batu @ Rp.
0.060 Org Kepala Tukang @ Rp.
1.500 Org Pekerja @ Rp.
0.015 Org Mandor @ Rp.

10. Pekerjaan Plasteran 1:2


Anl G.50h 1 M2 Plesteran campuran 1 pc : 2 ps, tebal 1 cm
a. Bahan
0.315 Zak PC (40 kg) @ Rp.
0.017 M3 Pasir @ Rp.

b. Upah kerja plasteran 1:2


0.2 Org Tukang @ Rp.
0.02 Org Kepala Tukang @ Rp.
0.4 Org Pekerja @ Rp.
0.02 Org Mandor @ Rp.

11. Pekerjaan Beton Cor


Anl. G.44 1M3 Beton Cor 1:3:5
a. Bahan
0.91 M3 Kerikil Bersih @ Rp.
0.54 M3 Pasir Beton @ Rp.
4.54 Zak PC (40 kg) @ Rp.

b. Tenaga Kerja
6.0 Org Pekerja @ Rp.
0.2 Org Mandor @ Rp.
0.05 Org Kepala Tukang @ Rp.
0.5 Org Tukang @ Rp.

12. Pekerjaan Beton Saluran dan Bangunan Bagi/Sadap


Anl Supl. 1a 1 M3 Beton Lining Saluran/Bang. Air K-175
1.0 M3 Beton K175 Rp.
21.8 Kg Besi Rp.
4.18 M2 Pekerjaan Bekisting Rp.
4.18 M2 Membongkar Cetakan Rp.

13. Pekerjaan Beton Talang


Anl Supl. 1b 1 M3 Beton Talang Air K-225
1.0 M3 Beton K225 Rp.
62.45 Kg Besi Rp.
7.03 M2 Pekerjaan Bekisting Rp.
7.03 M2 Membongkar Cetakan Rp.
35,000.00 Rp. 1,750.00
57,000.00 Rp. 285.00
Jumlah Rp. 2,035.00

buang hasil galian


35,000.00 Rp. 26,250.00
57,000.00 Rp. 1,425.00
Jumlah Rp. 27,675.00

69,000.00 Rp. 69,000.00


Jumlah Rp. 69,000.00

35,000.00 Rp. 11,550.00


57,000.00 Rp. 570.00
Jumlah Rp. 12,120.00

35,000.00 Rp. 17,500.00


57,000.00 Rp. 570.00
Jumlah Rp. 18,070.00
Jlh Total Rp. 99,190.00

45,000.00 Rp. 360,000.00


145,000.00 Rp. 118,900.00
126,500.00 Rp. 68,310.00
Jumlah Rp. 547,210.00

35,000.00 Rp. 14,350.00


57,000.00 Rp. 1,140.00
57,000.00 Rp. 39,900.00
63,000.00 Rp. 4,410.00
Jumlah Rp. 59,800.00
Jlh Total Rp. 607,010.00

45,000.00 Rp. 450,000.00


126,500.00 Rp. 68,310.00
145,000.00 Rp. 118,900.00
Jumlah Rp. 637,210.00

35,000.00 Rp. 210,000.00


57,000.00 Rp. 57,000.00
63,000.00 Rp. 6,300.00
57,000.00 Rp. 17,100.00
Jumlah Rp. 290,400.00
Jumlah Total Rp. 927,610.00

15,200.00 Rp. 1,672,000.00


16,500.00 Rp. 33,000.00
Jumlah Rp. 1,705,000.00

63,000.00 Rp. 141,750.00


57,000.00 Rp. 384,750.00
35,000.00 Rp. 236,250.00
Jumlah Rp. 762,750.00
Jumlah Total Rp. 2,467,750.00
Rp. 24,677.50

2,600,000.00 Rp. 884,000.00


10,000.00 Rp. 40,000.00
Jumlah Rp. 924,000.00

63,000.00 Rp. 31,500.00


57,000.00 Rp. 5,700.00
57,000.00 Rp. 285,000.00
35,000.00 Rp. 70,000.00
35,000.00 Rp. 140,000.00
Jumlah Rp. 532,200.00
Jumlah Total Rp. 1,456,200.00
Rp. 145,620.00

35,000.00 Rp. 14,000.00


Jumlah Rp. 14,000.00

183,750.00 Rp. 220,500.00


60,000.00 Rp. 198,000.00
126,500.00 Rp. 51,865.00
Jumlah Rp. 470,365.00

57,000.00 Rp. 34,200.00


63,000.00 Rp. 3,780.00
35,000.00 Rp. 52,500.00
57,000.00 Rp. 855.00
Jumlah Rp. 91,335.00
Jumlah Total Rp. 561,700.00

45,000.00 Rp. 14,175.00


126,500.00 Rp. 2,150.50
Jumlah Rp. 16,325.50

57,000.00 Rp. 11,400.00


63,000.00 Rp. 1,260.00
35,000.00 Rp. 14,000.00
57,000.00 Rp. 1,140.00
Jumlah Rp. 27,800.00
Jlh Total Rp. 44,125.50

145,000.00 Rp. 131,950.00


126,500.00 Rp. 68,310.00
45,000.00 Rp. 204,300.00
Jumlah Rp. 404,560.00

35,000.00 Rp. 210,000.00


57,000.00 Rp. 11,400.00
63,000.00 Rp. 3,150.00
57,000.00 Rp. 28,500.00
Jumlah Rp. 253,050.00
Jlh Total Rp. 657,610.00

607,010.00 Rp. 607,011.00


24,677.50 Rp. 537,969.50
145,620.00 Rp. 608,691.60
14,000.00 Rp. 58,520.00
Jumlah Rp. 1,812,192.10

927,610.00 Rp. 927,610.00


24,677.50 Rp. 1,541,109.88
145,620.00 Rp. 1,023,708.60
14,000.00 Rp. 98,420.00
Jumlah Rp. 3,590,848.48

Lhokseumawe, Desember 2008

PT. Citra Rancang Global

MUSTAFA UMAR ST
Direktur Utama
DAFTAR HARGA BAHAN DAN UPAH
PEMBANGUNAN JARINGAN IRIGASI TERSIER
DESA COT TRIENG - KOTA LHOKSEUMAWE

A. UPAH

NO UPAH SATUAN HARGA SATUAN (Rp.)

1 Pekerja Org/Hari 35,000.00


2 Tukang Org/Hari 57,000.00
3 Kepala Tukang Org/Hari 63,000.00
4 Mandor Org/Hari 57,000.00

B. BAHAN / MATERIAL

NO BAHAN/MATERIAL SATUAN HARGA SATUAN (Rp.)

1 Pasir M3 126,500.00
2 Kerikil M3 145,000.00
3 Semen (PC) 40 kg Zak 45,000.00
4 Semen (PC) 50 kg Zak 60,000.00
5 Tanah Timbun M3 69,000.00
6 Besi Polos Kg 15,200.00
7 Kawat Kg 16,500.00
8 Paku Kg 10,000.00
9 Kayu Bekisting M 3
2,600,000.00
10 Batu Kali M3 183,750.00

Lhokseumawe, Desember 2008

PT. Citra Rancang Global

MUSTAFA UMAR ST
Direktur Utama
PERHITUNGAN JUMLAH PEMBESIAN (1 M3 Beton K-175)
PEMBANGUNAN JARINGAN IRIGASI TERSIER
DESA COT TRIENG - KOTA LHOKSEUMAWE

No. Pias Saluran B (m) H (m) T (m) A (m2) L/M3 (m)

1 BCT.1 - BCT.2 1.30 1.25 0.20 0.76 1.32


2 BCT.2 - BCT.3 1.00 1.10 0.20 0.64 1.56
3 BCT.3 - BCT.4 0.80 1.00 0.20 0.56 1.79
4 BT.2.1 - BT.2.2 0.75 0.97 0.20 0.54 1.86
5 BT.2.2 - BT.2.3 0.70 0.95 0.20 0.52 1.92
6 BT.2.3 - BK.2.1 0.70 0.95 0.20 0.52 1.92
7 BCT.3 - BT.3 0.80 1.10 0.20 0.60 1.67
8 BT.3 - BK.2 0.50 0.85 0.20 0.44 2.27
9 BCT.4 - BT.4 ki 0.80 1.00 0.20 0.56 1.79
10 BT.4 ki - BK.4.2 0.50 0.85 0.20 0.44 2.27
11 BCT.1 - BT.1.1 0.90 0.95 0.20 0.56 1.79
12 BT.1.1 - BT.1.2 0.90 0.95 0.20 0.56 1.79
13 BT.1.2 - BT.1.3 0.80 0.90 0.20 0.52 1.92
14 BT.1.3 - BK.1.2 0.50 0.85 0.20 0.44 2.27
15 BT.1.3 - BT.1.4 0.70 0.95 0.20 0.52 1.92
16 BT.1.4 - BK.1.3 0.50 0.85 0.20 0.44 2.27
17 BT.1.4 - BK.1.4 0.50 0.85 0.20 0.44 2.27
12.65 16.32 32.60
0.74 0.96 1.92
Bekisting (M2/M3) 4.18
Besi Dia. 10 Besi Dia. 8 Besi Dia. 10 Besi Dia. 8 Berat Total
(bh) (bh) (kg) (kg) Besi (kg/M3)

17.00 4.76 13.80 7.33 21.13


14.60 5.46 14.08 7.34 21.41
13.00 6.10 14.32 7.23 21.55
12.56 6.31 14.40 7.20 21.61
12.20 6.49 14.48 7.41 21.89
12.20 6.49 14.48 7.18 21.66
12.60 5.76 12.96 6.60 19.56
10.60 7.49 14.86 7.10 21.97
13.00 6.10 14.32 7.23 21.55
10.60 7.49 14.86 7.10 21.97
13.80 6.10 15.20 7.71 22.92
13.80 6.10 15.20 7.71 22.92
13.00 6.49 15.43 7.70 23.12
10.60 7.49 14.86 7.10 21.97
12.20 6.49 14.48 7.18 21.66
10.60 7.49 14.86 7.10 21.97
10.60 7.49 14.86 7.10 21.97
94.15 370.82
6.48
Rata-rata 21.81