Anda di halaman 1dari 79

1

Governmentof Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction

Federal Project Implementation Unit


Janakpurdham, Dhanusha
BASIC LABOUR & MATERIAL RATE
DISTRICT : Dhanusha F / Y : 2075/076
Transportation @ 3 %
S.No. Description Unit District Rate Rate Remarks District Rate Code

1 Aggrigate >10 mm-Crushed Cum. 2,900.00 100.00 3,000.00 100.00 tax per 27-KHA
2 Aggrigate >10 mm-River bed Cum. 1,650.00 113.75 1,763.75 75.00 tax per 26-KHA
3 Aggrigate 10 mm-Crushed Cum. 3,000.00 100.00 3,100.00 100.00 tax per 27-KHA
4 Aggrigate 10 mm-River bed Cum. 1,750.00 113.75 1,863.75 75.00 tax per 26-KA
5 Aggrigate 12 mm-Crushed Cum. 2,900.00 100.00 3,000.00 100.00 tax per 27-KHA
6 Aggrigate 12 mm-River bed Cum. 1,650.00 113.75 1,763.75 75.00 tax per 26-KHA
7 Aggrigate 20 mm-Crushed Cum. 2,900.00 100.00 3,000.00 100.00 tax per 27-kha
8 Aggrigate 20 mm-River bed Cum. 1,650.00 113.75 1,763.75 75.00 tax per 26-kha
9 Aggrigate 40 mm-Crushed Cum. 2,850.00 100.00 2,950.00 100.00 tax per 27-ga
10 Aggrigate 40 mm-River bed Cum. 1,600.00 113.75 1,713.75 75.00 tax per 26-ga
11 Aluminium paint Ltr. 490.00 14.70 504.70 152
12 Asbestos cement ridge cover Rmtr. 355.00 10.65 365.65 67.00
13 Asbestos cement sheet Sqm. 700.00 21.00 721.00 66.00
14 ASO Joint Tape laying Work. Rmtr. 720.00 21.60 741.60 UD-13-01
Assistant lab equipment with
2,000.00
15 agar Hour 60.00 2,060.00 Ktm rate
16 Bamboo No. 275.00 8.25 283.25 30-40ft 74
17 Barbed wire 12 Bwg. Rmtr. 105.00 3.15 108.15 93/6 48
18 Barbed wire 14 Bwg. Rmtr. 115.00 3.45 118.45 93/10 47
19 Bhush Kg. 6.50 0.19 6.69 UD-09-19
20 Binding wire Kg. 120.00 3.60 123.60 31
21 Bitumen Kg. 110.00 3.30 113.30 167
22 Bitumen paint Ltr. 160.00 4.80 164.80 156
23 Bitumen washer Nos. 3.00 0.09 3.09 35/100 65
24 Brick Aggrigate Cum. 66.36 2,278.36 load Udayapur
unload
2212.00
0.60/10 Km.*30 km
distance*2.50 kg
13.50 Cons.m-3
25 Brick Nos. 0.40 13.90 for one brick wt
26 Brick Machine Nos. - - -
Carborundam
185.00 UD-28-10
27 Stone(Sharpenning Stone) Nos. 5.55 190.55 Udayapur
28 Cement MT 17,000.00 510.00 17,510.00 Nepali other (OPC) Cons.m-12
29 Cement primer Ltr. 450.00 13.50 463.50 UD-27-02
30 Cement tile No. 165.00 4.95 169.95 2000/100 70
31 Cement tile ridge cover No. 180.00 5.40 185.40 3000/100 71
32 CGI Ridge Cover Rmtr. 196.80 5.90 202.70 UD-14-07
33 CGI Ridge Cover colour Rmtr. 325.00 9.75 334.75
CGI sheet 26 (H) 0.41 mm thick 770.00 61-ga
34 coloured Sqm. 23.10 793.10 9390 /bandal
CGI sheet 26 (H) 0.41 mm thick
650.00 63-ga
35 Plain Sqm. 19.50 669.50 7410/bandal
CGI sheet 26 (L) 0.38 mm thick
367.77 UD-14-03
36 plain Sqm. 11.03 378.80 6460 /bandal
CGI sheet 26 (M) 0.38 mm
493.59 UD-14-05
37 thick colour Sqm. 14.80 508.39 8670 /bandal
CGI sheet 26 (M) 0.38 mm
384.85 UD-14-02
38 thick Plane Sqm. 11.54 396.39 6760/bandal
CGI sheet 26 (M) 0.38 mm
384.85 UD-14-02
39 thick plane Sqm. 11.54 396.39 6760/bandal
CGI sheet 28 (H) 0.30 mm thick
700.00 61-gha
40 colour Sqm. 21.00 721.00 7470/bandal
CGI sheet 28 (H) 0.30 mm thick
600.00 61-nga
41 plane Sqm. 18.00 618.00 5830/bandal
42 CGI sheet Ridge Cover Rmtr. 196.80 5.90 202.70 60/rft UD-14-07
Chain Link 2"x2" mesh (10 SWG
517.00
43 G. I.) Sqm. 15.51 532.51 Ktm rate
44 Chapra paint Kg. 570.00 17.10 587.10 165
45 Chattai Sqm. 130.00 3.90 133.90 78

Prepared By : Checked By : Approved By :


2

Governmentof Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction

Federal Project Implementation Unit


Janakpurdham, Dhanusha
BASIC LABOUR & MATERIAL RATE
DISTRICT : Dhanusha F / Y : 2075/076
46 Clay tile No. 33.00 0.99 33.99 68
47 Clay tile ridge cover No. 34.00 1.02 35.02 69
48 Clip no 58.00 1.74 59.74 ktm Rate 2072-2073
49 Collapisible gate (60 kg/sqm.) Sqm. 5,080.00 152.40 5,232.40 125*60 52
50 Collection bag Nos. 22.00 0.66 22.66 Empity plastic bag 138
51 Crystallization seal Sqm. 551.45 16.54 567.99 previous year
52 Damp proof grade tarfelt Sqm. 140.00 4.20 144.20
53 Diesel Ltr. 101.50 3.04 104.54 73.5/1.13
54 Distemper Primer Ltr. 350.00 10.50 360.50 149
55 Distemper Washable Kg. 280.00 8.40 288.40 150
56 Door spring No. 300.00 9.00 309.00 42
57 Dori Kg. 140.00 4.20 144.20 naribal 76
58 Enamel Paint Ltr. 580.00 17.40 597.40 159
59 Enamel Primer Ltr. 350.00 10.50 360.50 149
60 Engineer Nos. 1,100.00 - 1,100.00 23
61 Expansion joint materials Sqm. 6,665.00 199.95 6,864.95 211-i
62 Expanded metal Sqm. 170.00 5.10 175.10 SI-06-17
Fiber glass 1.20 mm thick
965.00 62
63 corgated Sqm. 28.95 993.95
Fiber glass 1.20 mm thick ridge
581.33 62
64 cover (0.60m width) Rmtr. 17.44 598.77 width=0.60m
65 Fire wood Kg. 16.50 0.49 16.99 93
66 Flooring stone 37mm thick Sqm. 850.00 25.50 875.50 28-kha
G. I. plane sheet Gutter 0.50mm
202.31
67 thick Rmtr. 6.06 208.37 Ktm rate
G. I.Colour plane sheet Gutter
242.66
68 0.50mm thick Rmtr. 7.27 249.93 Ktm rate
69 Gavion wire commercial Kg. 85.00 2.55 87.55 UD-05-01
70 Gavion wire Heavy coated Kg. 95.00 2.85 97.85 UD-05-02
71 Gavion wire Light coated Kg. 85.00 2.55 87.55 Udayapur SA-07-09
72 Gavion wire Medium coated Kg. 92.00 2.76 94.76 SA-07-08
73 GI plane sheet 26 gauge Sqm. 450.00 13.50 650.00 63-ga
CGI sheet 26 (L) 0.35 mm thick
469.68 UD-14-06
74 colour Rmtr. 14.09 483.77
CGI sheet 26 (L) 0.35 mm thick 367.77 UD-14-03
75 Plane Sqm. 11.03 378.80
CGI sheet 26(H) 0.31 mm thick
421.86 UD-14-01
76 plane Sqm. 12.65 434.51
77 Glass 3 mm thick-Plane Sqm. 680.00 20.40 700.40 110-ka
78 Glass 4 mm thick-Plane Sqm. 760.00 22.80 782.80 110-kha
79 Glass 6 mm thick-Plane Sqm. 1,180.00 35.40 1,215.40 110-gha
80 Gobar Kg. 3.60 0.10 3.70 144
81 Gravel (sand mixed) Cum. 1450.00 43.50 1,493.50 (800+450)/2 24
82 Granite 20mm thick Sqm. 3,690.00 110.70 3,800.70 136
83 Gum Kg. 165.00 4.95 169.95 146
84 Handle No. 75.00 2.25 77.25 simple 39
85 Helper Nos. 650.00 - 650.00 Worker D-1
86 Hinge 75 mm No. 40.00 1.20 41.20 36-ka
87 Hinge 100 mm No. 45.00 1.35 46.35 36-kha
88 Hinge 150 mm No. 60.00 1.80 61.80 36-gha
89 Hold fast No. 50.00 1.50 51.50 35
90 Hydrolic Excavetor 0.35 Cum. Hour 1,200.00 36.00 1,236.00 Udayapur
91 Hydrolic Excavetor 0.63 Cum. Hour 2,600.00 78.00 2,678.00 16-i
92 Hydrolic Excavetor 0.80 Cum. Hour 3,100.00 93.00 3,193.00 16-ii
93 Hydrolic Excavetor 1.32 Cum. Hour 5,200.00 156.00 5,356.00 16-iii
94 Iron bolt Kg. 180.00 5.40 185.40 previous year 133
95 Iron strips Kg. 120.00 3.60 123.60
96 J-hook Nos. 58.00 1.74 59.74 140 /8 64
97 Khar Bdl. 27.00 0.81 27.81 73
98 Killa Kg. 110.00 3.30 113.30 32

Prepared By : Checked By : Approved By :


3

Governmentof Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction

Federal Project Implementation Unit


Janakpurdham, Dhanusha
BASIC LABOUR & MATERIAL RATE
DISTRICT : Dhanusha F / Y : 2075/076
lastocret cementious
516.48
99 elastomeric water proofing Sqm. 15.49 531.97 previous year Ktm rate
100 Linseed oil paint Ltr. 130.00 3.90 133.90 158
101 Lockingset 250-300mm. No. 2,100.00 63.00 2,163.00 12" UD-11-08
102 Main Polish Kg. 430.00 12.90 442.90 119
103 Marble chips 3 mm Cum. 15,750.00 472.50 16,222.50 38*2560 117
104 Marble power Kg. 50.00 1.50 51.50 UD-18-07
105 Marble tile 15mm Sqm. 3,550.00 106.50 3,656.50 126
106 Marble tile 25mm Sqm. 3,690.00 110.70 3,800.70 127
107 Micro silica Kg. 289.00 8.67 297.67 Ktm rate
Mixture Machine (0.20-0.28
475.00 18
108 Cum.) Hr 14.25 489.25
109 Mortice lock(Brass) No. 990.00 29.70 1,019.70 41
Mosquito proof net 18 mess
465.00 58-ii
110 good(steel) quality Sqm. 13.95 478.95 w=.90m
111 MS angle Kg. 120.00 3.60 123.60 54
112 MS Black pipe 0.75" to 2" dia. Kg. 100.00 3.00 103.00 255
113 MS Black pipe(MNB 50-M) no 1,540.00 46.20 1,586.20 Udayapur rate
114 MS grill Kg. 160.00 4.80 164.80 49

160.00 49-ka
115 MS grill 3*20 mm (15 kg/sqm) Kg. 4.80 164.80

160.00 49--kha
116 MS grill 4.5*20 mm (21 kg/sqm) Kg. 4.80 164.80
MS grill gate 5*20 mm(35
3,750.00 51
117 kg/sqm) Kg. 112.50 3,862.50
MS grill gate 5*25 mm(40
3,750.00 51
118 kg/sqm) M. sheet Kg. 112.50 3,862.50
119 Different size MS plate Kg. 139.00 4.17 143.17 Ktm rate 2075-2075

10,004.00
120 MS Spiral Staircase Readymade Rmtr. 300.12 10,304.12 Ktm rate 2075-2076
121 Mud Cum. 400.00 12.00 412.00 14
122 Mud tile No. 33.00 0.99 33.99 previous year 68
123 Mud tile ridge cover No. 34.00 1.02 35.02 previous year 69
124 Nutbolt 8 mm. Nos. 18.00 0.54 18.54 180/10 33
125 Oxalic acid powder Kg. 115.00 3.45 118.45 118.00
126 Paint brush 100 mm Nos. 240.00 7.20 247.20 60 per inch UD-27-24
127 Pech killas No. 2.25 0.06 2.31 40,50,60mm avg 34
128 Petrol Ltr. 110.50 3.31 113.81 100/1.13 5/8/2073
129 Plaster of Paris Kg. 21.00 0.63 21.63 160
130 Plastic emulsion paint Ltr. 650.00 19.50 669.50 154
Ply wood 12 mm thick 510.00
131 commercial Sqm. 15.30 525.30
Ply board 19 mm thick
1,260.00 112-ga
132 waterproof Sqm. 37.80 1,297.80
Ply wood 3 mm thick
260.00 111-ka
133 commercial Sqm. 7.80 267.80
134 Ply wood 3 mm thick Teak Sqm. 600.00 18.00 618.00 113-ka
Ply wood 4 mm thick
315.00 111-kha
135 commercial Sqm. 9.45 324.45
136 Ply wood 4 mm thick Teak Sqm. 630.00 18.90 648.90 113-kha
Ply wood 6 mm thick water
575.00 112-ka
137 proof Sqm. 17.25 592.25
138 Polythine sheet 500 gauge Sqm. 50.00 1.50 51.50 183
Porecelain glazed/non glazed
1030.00 122
139 tile Sqm. 30.90 1,060.90
140 Pre-leminated board Sqm. 645.60 19.36 664.96 6 mm Ktm rate

3,444.00 (Vertical post Udayapur


Railing with 40 mm Ø ms pipe 2",Hand rail
141 handrail Rmtr. 103.32 3,547.32 1.5",Horizontal 1")

Prepared By : Checked By : Approved By :


4

Governmentof Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction

Federal Project Implementation Unit


Janakpurdham, Dhanusha
BASIC LABOUR & MATERIAL RATE
DISTRICT : Dhanusha F / Y : 2075/076
Railing with sisham wood
-
142 handrail - -
143 Rain seal paint Kg. - - -
Readymade colour concrete tile
I,,bambai,cadbari design floor 27.55
144 tile(10"x10"x1.5"=40.00rs no 0.82 28.37 previous year gaighat
145 Red oxide Paint Ltr. 350.00 10.50 360.50 UD-27-14
146 Red oxide Primer Ltr. 450.00 13.50 463.50 UD UD-24-58
147 Road roller 8-10 M.T. hr 900.00 27.00 927.00 UD UDAYAPUR
148 Road hand roller 1.0 M.T. hr 300.00 9.00 300.00 UD
149 Rolling Shutter Sqm. 3,750.00 112.50 3,862.50 315.00 sft 50
150 Roofing nail Kg. 150.00 4.50 154.50 UD-15-14
151 Rubber bidding -
152 Sand aurhi khola Cum. 1,200.00 107.25 1,307.25 75.00 tax per cons.m-2
153 Sand crusher(Badahari khola) Cum. 1,500.00 107.25 1,607.25 75.00 tax per cons.m-1
154 Sand mixed gravel Cum. 1,450.00 43.50 1,493.50 (450+800)/2 24
155 Sand paper Nos. 12.00 0.36 12.36 UD-27-25
156 Self Taping Screw 3" Nos. 8.50 0.25 8.75 previous year SI-21-21
157 Silica cement Kg. 325.00 9.75 334.75 189
158 Skilled Nos. 940.00 - 940.00 3
159 Spartik non glazed tile Sqm. 980.00 29.40 1,009.40 124
160 Spiral stair case Rmtr. 10,004.00 300.12 10,304.12 previous year Ktm rate
161 Sprit Ltr. 80.00 2.40 82.40 166
162 Square pipe1"x1" Kg. 73.00 2.19 75.19 UD-05-10
73.00 UD-05-09
163 Square rod 12mm Ø solid core Kg. 2.19 75.19

Stainless Steel 50mm dia


Handrail in 2.00m.distance with
50mm dia.vertical post & 3 layer
Horizontal 25mm dia.stainless
steel member ,2.5' to 3' height
164 Railing with Painting & fixing. Rmtr. 4,090.00 122.70 4,212.70 215
164A Stainless steel pipe 25 mm Ø Rmtr. 243.00 7.29 250.29 Ktm rate
165 Stainless steel pipe 30 mm Ø Rmtr. 310.00 9.30 319.30 Ktm rate 2072-2073
166 Stainless steel pipe 38 mm Ø Rmtr. 376.00 11.28 387.28 Ktm rate 2072-2073
167 Stone block Cum. 2,350.00 70.50 2,420.50 100.00 tax 20
168 Stone bond Cum. 2,000.00 60.00 2,060.00 100.00 tax 21
169 Sub engineer Nos. 800.00 - 800.00 24
170 Sunmica board Sqm. 460.00 13.80 473.80 8*4=32.00sqft 79
171 Super plasticiser Ltr. - - - 187

172 Surkhee Cum. 2,200.00 66.00 2,266.00 C0NS.M.-6


173 Tarfelt Sqm. 140.00 4.20 144.20 2200/18 185
174 Tarpaintain oil Ltr. 130.00 3.90 133.90 120
175 Terrazo tile 20 mm thick Sqm. 690.00 20.70 710.70 121
176 Teak ply 12mm Sqm. 1050.00 31.50 1,081.50 UD-17-17
177 TOR/TMT reinforcement bar M.T. 86000.00 2,580.00 88,580.00 (70+72+73)/3 29-30
178 Towerbolt 100 mm No. 60.00 1.80 61.80 UD-11-06
179 Towerbolt 150 mm No. 100.00 3.00 103.00 UD-11-06
180 Towerbolt 300 mm No. 180.00 5.40 185.40 UD-11-06
181 U-nail Nos. 1.79 0.05 1.84 125/70 UD-05-04
182 Unskilled Nos. 650.00 - 650.00 Worker D-1
1,650.00 196-i
183 UPVC roofing sheet 3 mm thick Sqm. 49.50 1,699.50

916.48 SI-21-26
184 UPVC roofing sheet ridge cover Rmtr. 27.49 943.97 previous year
185 Varnish paint Ltr. 325.00 9.75 334.75 155
186 Vibrator Hour 275.00 8.25 283.25 19

Prepared By : Checked By : Approved By :


5

Governmentof Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction

Federal Project Implementation Unit


Janakpurdham, Dhanusha
BASIC LABOUR & MATERIAL RATE
DISTRICT : Dhanusha F / Y : 2075/076
187 W.P.Compound Kg. 100.00 3.00 103.00 116
188 Water Ltr. 0.35 0.01 0.36 15
189 Water proof cement paint Kg. 85.00 2.55 87.55 asian 151
190 Water pump Hour 330.00 9.90 339.90 5 H.P. 14
191 Weather proof paint Kg. 830.00 24.90 854.90 UD-27-30
192 Weather proof primer Kg. 450.00 13.50 463.50
193 White cement M.T. 55000.00 1,650.00 56,650.00 40kg/ bag 147
194 White lime Kg. 22.00 0.66 22.66 5kg/ bag 148
195 Wood Gamhair Cum. 62,507.55 1,875.22 64,382.77 previous year siraha
196 Wood Local Cum. 55000.00 1,650.00 56,650.00 35.31*1000 84
197 Wood preservative paint Ltr. 350.00 10.50 360.50 149
198 Wood Sal Cum. 214500.00 6,435.00 220,935.00 35.31*4000 81
199 Wood Sisham Cum. 116600.00 3,498.00 120,098.00 35.31*1500 82
200 Wooden listies ½" Rmtr. 7.35 0.22 7.57 114-ka
201 Wooden listies ¾" Rmtr. 13.65 0.40 14.05 114-kha
202 Wooden listies 1" Rmtr. 15.75 0.47 16.22 114-ga
203 Wooden listies 1½" Rmtr. 25.25 0.75 26.00 114-gha
204 white putting Kg. 60.00 1.80 61.80 Ktm rate
25 mm thick roofing tile butta
plaster in cement sand (1:4) 623.00
205 work Sqm. 18.69 641.69 Ktm rate

Prepared By : Checked By : Approved By :


Governmentof Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Federal Project Implementation Unit
Janakpurdham, Dhanusha
BASIC LABOUR & MATERIAL RATE

S.No. Description Unit Easy Uneasy Remarks


charge by potter Rs/kg/km 0.00 0.00
loading/unloading Rs/kg 0 0.0000
charge for transportation in
gravelled road Rs/kg/km 0.065 0.0650
charge for transportation in
Black topped road Rs/kg/km 0.060 0.060

S.No. Materials Unit Market Coloading ch unloading cha Transport By vehicle per unit rate
Transportation Total cost at sRemarks
per unit raper unit rate (Gravel Road) (Black topped)
1 OPC Cement MT 17000.00 0.00 0.00 1040.00 0.00 0.00 18040.00 902.00
2 Reinforcement bar Kg 86.00 0.00 0.00 1.040 0.000 0.00 87.04 87040
3 Water tank ( 1000 lt) 1 nos 13500.00 0.00 0.00 500.00 0.00 0.00 14000.00 14.00
4 Grill Angle Kg 73.00 0.00 0.00 1.04 0.00 0.00 74.04
5 CGI Sheet Sqm 550.61 0.00 0.00 3.847 0.000 0.00 554.46 1 bundle=65 kg
3 M.S. pipe fabricated Kg 115.00 0.00 0.00 1.040 0.960 0.00 117.000
7 Sand (Local) Cum 1200.00 0.00 0.00 107.25 0.00 0.00 1307.25 1 Cum=1650kg
9 Brick per 1000 13.50 0.00 0.00 2600 3150.00 0.00 5763.50 1 Brick=2.5kg
10 Stone Cum 2,420.50 0.00 0.00 117.000 0.00 0.00 2537.50 1 Cum=1800 Kg
11 Aggregate (10-12)mm (River b Cum 1,650.00 0.00 0.00 113.750 0.00 0.00 1763.75 1 Cum=1750 Kg
12 Aggregate (20-40)mm (River bCum 1,600.00 0.00 0.00 113.750 0.00 0.00 1713.75 1 Cum=1750 Kg
Nurms used in this is derieved from DoLIDAR used for Trail bridge

220 Local Material Collection


221 Chisel Dressed Stones per m3
Labour
Collection and Dressing Skilled md 8.00 0.00 0.00
Unskilled md 3.00 0.00 0.00
Transportation Tractor ( 17.5qtlX12kmX1.2Rs)
m3 1.00 0.00
Cost per m3 for collecting and chisel dressing stones 0.00
222 Hammer Dressed Stone per m3
Labour
Collection and Dressing Skilled md 4.00 0 0.00
Unskilled md 3.00 0 0.00
Transportation Tractor ( 17.5qtlX12kmX1.2Rs)
m3 1.00 0.00
Cost per m3 for collecting and hammer dressing stones 0.00
223 Broken Stones per m3
Labour
Collection and breaking Unskilled md 5.00 480 2400.00
Transportation Truck (1tru m3 1.00 0.00
Cost per m for collecting and breaking stones
3
2400.00

1
Apply District Rates

COST ESTIMATE: Rate Analysis (page 3)

Unit
Description Unit Rate1 Unit Cost
Quantity
224 Sand pe m3
Labour Unskilled md 3.00 0 0.00
Transportation Tractor ( 17.5qtlX60kmX1.2Rs)
m3 1.00 0.00
Cost per m3 for collecting and hauling sand 0.00
225 Gravel (Broken)
Labour Unskilled md 7.00 0 0.00
Transportation Truck (1tru m3 1.00 0.00
Cost per m3 for breaking gravel 0.00
8 of 79
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :DHANUSHA 2075/2076


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract

A - SITE PREPARATION WORK

Cutting of tree, branch & log etc. (12-30 cm. girth above 1.00
1.01 A1 (1-1A) Nos. 84.50 97.17
mtr. From G.L.) with lead upto 15 mtr.
Cutting of tree, branch & log etc. (31-60 cm. girth above 1.00
1.02 A1 (1-1B) Nos. 253.50 291.52
mtr. From G.L.) with lead upto 15 mtr.
Cutting of tree, branch & log etc. (61-120 cm. girth above
1.03 A1 (1-1C) Nos. 637.00 732.55
1.00 mtr. From G.L.) with lead upto 15 mtr.
Removing of tree root (12-30 cm. girth above 1.00 mtr. From
1.04 A2 (1-2A) Nos. 260.00 299.00
G.L.) with lead upto 15 mtr.
Removing of tree root (31-60 cm. girth above 1.00 mtr. From
1.05 A2 (1-2B) Nos. 344.50 396.17
G.L.) with lead upto 15 mtr.
Removing of tree root (61-120 cm. girth above 1.00 mtr. From
1.06 A2 (1-2C) Nos. 1,638.00 1,883.70
G.L.) with lead upto 15 mtr.
Cutting of grass, taking of root & brocken of uplecutting of
1.07 A3 Sqm. 14.95 17.19
raised soil & site leveling with all complete
Surface dressing work with cutting of raised soil & filling the
1.08 A4 sqm. 6.50 7.47
ditches.

B - EARTH & SAND WORK


Earth work excavation in foundation in clay & silty soft soil
2.01 B1 (2-1) Cum. 468.65 538.94
lead upto 10 mtr. & lift 1.5 mtr.
Earth work excavation in foundation in clay & soft murram
2.02 B1 (2-2) Cum. 535.60 615.94
stone (30 cm.) hard soil lead upto 10 mtr. & lift 1.5 mtr.
Earth filling work in every 15-15 cm. layer with watering & lead
2.03 B2 (2-25A) Cum. 325.00 373.75
upto 1o.00 mtr. & proper manual compaction.
Earth filling (Earth transported from 5 Km. surronding) work in
2.04 B2 (2-25A) every 15-15 cm. layer with watering & proper manual Cum. 944.80 1,086.52
compaction.
Earth filling work in every 15-15 cm. layer without watering &
2.05 B2 (2-25B) Cum. 162.50 186.87
proper manual compaction.
Earth filling (Earth transported from 5 Km. surronding) work in
2.06 B2 (2-25B) every 15-15 cm. layer without watering & proper manual Cum. 698.10 802.81
compaction.

2.07 B3 (2-42A) Sand filling work with watering & proper manual compaction. Cum. 2,224.77 2,558.48

Gravel Sand mixed (agg-50% + sand 50%) filling work with


2.08 B3 (2-42B) Cum. 2,130.35 2,449.90
proper manual compaction.
2.09 B4 (2-34) Pumping of water from foundation or trench Hrs 33.99 39.08
Removing of tree root (12-30 cm. girth above 1.00 mtr. From
2.11 A2 (1-2A) Nos. 15.48 17.80
G.L.) with lead upto 15 mtr.
Removing of tree root (12-30 cm. girth above 1.00 mtr. From
2.12 A2 (1-2A) Nos. 5.01 5.76
G.L.) with lead upto 15 mtr.
Removing of tree root (12-30 cm. girth above 1.00 mtr. From
2.13 A2 (1-2A) Nos. 46.24 53.17
G.L.) with lead upto 15 mtr.
Removing of tree root (12-30 cm. girth above 1.00 mtr. From
2.14 A2 (1-2A) Nos. 55.59 63.92
G.L.) with lead upto 15 mtr.
Removing of tree root (12-30 cm. girth above 1.00 mtr. From
2.15 A2 (1-2A) Nos. 55.59 63.92
G.L.) with lead upto 15 mtr.
Removing of tree root (12-30 cm. girth above 1.00 mtr. From
2.16 A2 (1-2A) Nos. 14.77 16.98
G.L.) with lead upto 15 mtr.

Prepared by Checked by Approved by


9 of 79
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :DHANUSHA 2075/2076


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract
Earth work excavation in foundation in HARD SOIL Used
2.17 B7 Cum. 17.99 20.68
1.32Cum capecity Hydraulic excavator

C - MASONRY WORK
C2(5-1-B1 & First class chimney brick masonry work in (1:3) cement sand
3.01 Cum. 12,354.55 14,207.73
5-2A) mortar in G. F.
C2(5-1-B1 First class chimney brick masonry work in (1:3) cement sand
3.02 Cum. 12,689.30 14,592.69
& 5-2B) mortar in F. F.
C2(5-1-B1 First class chimney brick masonry work in (1:3) cement sand
3.03 Cum. 13,157.95 15,131.64
& 5-2B) mortar in S. F.
C2( 5-1-B2 First class chimney brick masonry work in (1:4) cement sand
3.04 Cum. 11,838.13 13,613.84
& 5-2A) mortar in G. F.
C25-1-B2 First class chimney brick masonry work in (1:4) cement sand
3.05 Cum. 12,172.88 13,998.81
& 5-2B) mortar in F. F.
C2(5-1-B2 First class chimney brick masonry work in (1:4) cement sand
3.06 Cum. 12,641.53 14,537.75
& 5-2B) mortar in S. F.
C2(5-1-B3 First class chimney brick masonry work in (1:6) cement sand
3.07 Cum. 11,334.17 13,034.29
& 5-2A) mortar in G. F.
C2(5-1-B3 First class chimney brick masonry work in (1:6) cement sand
3.08 Cum. 11,668.92 13,419.25
& 5-2B) mortar in F. F.
C2( 5-1-B3 First class chimney brick masonry work in (1:6) cement sand
3.09 Cum. 12,137.57 13,958.20
& 5-2B) mortar in S F.
C2(5-1-B6 &
3.1 First class chimney brick masonry work in mud mortar in G. F. Cum. 9,004.34 10,354.99
5-2A)
C2( 5-1-B6
3.11 First class chimney brick masonry work in mud mortar in F. F. Cum. 9,339.09 10,739.95
& 5-2B)
C2(5-1-B6
3.12 First class chimney brick masonry work in mud mortar in S. F. Cum. 9,807.74 11,278.90
& 5-2B)
3.13 C6( 6-1-1A) R.R. stone masonry work in cement sand (1:3) mortar Cum. 11,401.68 13,111.93
3.14 C6( 6-1-1B) R.R. stone masonry work in cement sand (1:4) mortar Cum. 10,829.85 12,454.32
Aslar (Crused stone) stone masonry work in cement sand
3.14a C6( 6-1-1B) #N/A 10,334.35 11,884.50
(1:4) mortar
3.15 C6( 6-1-1C) R.R. stone masonry work in cement sand (1:6) mortar Cum. 9,923.16 11,411.63
Aslar (Crused stone)stone masonry work in cement sand (1:6)
3.15a C6( 6-1-1C) #N/A 9,421.66 10,834.90
mortar
3.16 C6( 6-2-1) R.R. stone masonry work for dry wall Cum. 4,866.50 5,596.47
3.17 C6( 6-2-2) R.R. stone masonry work in mud mortar Cum. 5,202.04 5,982.34
3.18 C10( 6-5) Stone filling in trench with proper leveling Cum. 3,807.50 4,378.62

D - CEMENT CONCRETE WORK

4.01 D1(7-2B) P.C.C. (1:4:8) work in foundation, wall (River bed) Cum. 8,704.33 10,009.97
4.02 D1(7-2C) P.C.C. (1:3:6) work in foundation, wall (River bed) Cum. 9,587.03 11,025.08
4.03 D1(7-2D) P.C.C. (1:2:4) work in foundation, wall (River bed) Cum. 11,263.10 12,952.56
4.04 D2(7-4A) P.C.C. (1:2:4) for R.C.C. work in slab, beam etc (River bed) Cum. 13,025.10 14,978.86

4.05 D2(7-4B) P.C.C. (1:1½:3) for R.C.C. work in slab, beam etc (River bed) Cum. 14,479.39 16,651.29

4.06 D2(7-4C) P.C.C. (1:1:2) for R.C.C. work in slab, beam etc (River bed) Cum. 18,166.86 20,891.88

Prepared by Checked by Approved by


10 of 79
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :DHANUSHA 2075/2076


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract
P.C.C. (1:3:6) work (USED MACHINE) in foundation, wall
4.07 D3(A) Cum. 9,415.37 10,827.67
(River bed)
P.C.C. (1:2:4) work (USED MACHINE) in foundation, wall
4.08 D3(B) Cum. 11,139.26 12,810.14
(River bed)
P.C.C. (1:1½:3) for R.C.C. work(USED MACHINE) in slab,
4.09 D4(A) Cum. 12,611.75 14,503.51
beam etc (River bed)
P.C.C. (1:1:2) for R.C.C. work(USED MACHINE) in slab, beam
4.10 D4(B) Cum. 16,299.22 18,744.10
etc (River bed)
P.C.C. (1:1:2) for R.C.C. work in slab (River bed) with micro
4.11 D(5) Cum. 27,894.83 32,079.05
silica & super plasticiser
P.C.C. (1:4:8) work in foundation, wall (crushed or stone
4.12 D1(7-2B) Cum. 9,945.60 11,437.44
ballast)
P.C.C. (1:3:6) work in foundation, wall (crushed or stone
4.13 D1(7-2C) Cum. 10,828.30 12,452.54
ballast)
P.C.C. (1:2:4) work in foundation, wall (crushed or stone
4.14 D1(7-2D) Cum. 12,447.42 14,314.53
ballast)
P.C.C. (1:2:4) for R.C.C. work in slab, beam etc (crushed or
4.15 D2(7-4A) Cum. 13,937.44 16,028.05
stone ballast)
P.C.C. (1:1½:3) for R.C.C. work in slab, beam etc (crushed or
4.16 D2(7-4B) Cum. 15,670.08 18,020.59
stone ballast)
P.C.C. (1:1:2) for R.C.C. work in slab, beam etc (crushed or
4.17 D2(7-4C) Cum. 19,345.18 22,246.95
stone ballast)
P.C.C. (1:3:6) work (USED MACHINE) in foundation, wall
4.18 D3(A) Cum. 10,643.14 12,239.61
(crushed or stone ballast)
P.C.C. (1:2:4) work (USED MACHINE) in foundation, wall
4.19 D3(B) Cum. 12,323.58 14,172.11
(crushed or stone ballast)
P.C.C. (1:1½:3) for R.C.C. work(USED MACHINE) in slab,
4.20 D4(A) Cum. 13,802.44 15,872.80
beam etc (crushed or stone ballast)
P.C.C. (1:1:2) for R.C.C. work(USED MACHINE) in slab, beam
4.21 D4(B) Cum. 17,477.54 20,099.17
etc (crushed or stone ballast)
P.C.C. (1:1:2) for R.C.C. work in slab (crushed or stone
4.22 D(5) Cum. 29,038.34 33,394.09
ballast) with micro silica & super plasticiser
Torsteel reinforcement bar for R.C.C. work with cutting,
4.23 D9(7-5) Kg. 113.32 130.32
bending, binding & laying with all complete.

E - FORM & PROPS WORK


Form work shuttering & centering (COLUMN) with (USED
5.01 E1(8-3A) Sqm. 1,142.61 1,314.00
LOCAL WOOD) all complete.
Form work shuttering & centering (COLUMN) with (USED PLY
5.02 E2(51B) Sqm. 612.97 704.91
WOOD) all complete.
Form work shuttering & centering (BEAM-0.30 Mtr) with
5.03 E3(8-4A) Sqm. 1,190.87 1,369.50
(USED LOCAL WOOD) all complete.
Form work shuttering & centering (BEAM-0.30-0.80 Mtr) with
5.04 E4(8-4B) Sqm. 935.85 1,076.23
(USED LOCAL WOOD) all complete.
Form work shuttering & centering (COLUMN) with (USED PLY
5.05 E5(51A) Sqm. 1,199.95 1,379.94
WOOD) all complete.
Form work shuttering & centering with MS pipe (prop),
5.06 E6(8-4A) Sqm. 954.89 1,098.12
plyboard for slab etc
Form work shuttering & centering with Bamboo, plyboard for
5.06(A) E6(8-4A) Sqm. 454.65 522.85
slab etc
5.07 E12(8-13A) Trench work open type form work (up to 1.50 Mtr.) Sqm. 207.20 238.28
5.08 E12(8-13B) Trench work open type form work ( 1.50 to 3.00 Mtr.) Sqm. 214.43 246.59
5.09 E13(8-13C) Trench work open type form work (above 3.00 Mtr.) Sqm. 224.00 257.60

Prepared by Checked by Approved by


11 of 79
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :DHANUSHA 2075/2076


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract

F - ROOFING WORK
26 (H) 0.41 mm thick colored C.G.I. sheet roofing work
6.01 F1( 9-1) Sqm. 1,358.33 1,562.08
(65kg/bandal)
26 (H) 0.41mm thick plane C.G.I. sheet roofing work
6.02 F1( 9-1) Sqm. 1,210.01 1,391.51
(62kg/bandal)
26 (L) 0.35mm thick plane C.G.I. sheet roofing work
6.03 F1( 9-1) Sqm. 861.17 990.35
(55kg/bandal)
26 (H) 0.41 mm thick colour C.G.I. sheet roofing work
6.04 F3( 9-1) Sqm. 808.31 929.56
(65kg/bandal)
26 (M) 0.38mm thick colour C.G.I. sheet roofing work
6.05 F3( 9-1) Sqm. 1,016.68 1,169.18
(62kg/bandal)
6.08 F2( 9-2) 28 (H) G.I. plane ridge cover Rmtr. 631.24 725.92
6.09 F4( 9-2) 26 (L) C.G.I. colour ridge cover Rmtr. 789.70 908.15
6.11 F5 26 (M) 0.41 mm thick plane G.I. sheet roofing work Rmtr. 948.62 1,090.92
6.12 F5 26 (L) 0.35 mm thick plane G.I. sheet roofing work Rmtr. 881.77 1,014.04
6.13 F6 26 (H) 0.50 mm thick Colour G.I. sheet roofing work Rmtr. 1,271.81 1,462.58
6.14 F6 26 (M) 0.41 mm thick Colour G.I. sheet roofing work Rmtr. 948.62 1,090.92

150 mm breadth upto 450 mm G. I. plane sheet Gutter fixing


6.16 F7 Rmtr. 1,137.76 1,308.43
work with 3x40 mm M.S. bracke,t nut bolt & washer .

150 mm breadth upto 450 mm G. I. colour sheet Gutter fixing


6.17 F7 Rmtr. 1,193.87 1,372.95
work with 3x40 mm M.S. bracke,t nut bolt & washer .

6.18 F10( 9-6) Clay tile roofing work Rmtr. 569.37 654.78
6.19 F11( 9-7) Clay tile ridge cover Rmtr. 359.66 413.60
6.2 F12( 9-8) 100 mm lime concrete (1:1:3) work Sqm. 1,016.77 1,169.29
6.21 F13( 9-9A) 80 mm thick khar roof with bamboo frame Sqm. 1,530.22 1,759.75
6.22 F13( 9-9B) 150 mm thick khar roof with bamboo frame Sqm. 2,065.92 2,375.81
6.23 F14 1.20 mm thick fiber glass corgated sheet roofing work Sqm. 1,599.35 1,839.25
6.24 F15 1.20 mm thick fiber glass ridge cover Rmtr. 1,106.51 1,272.49
Readymade colour concrete tile laying work on cement sand
6.25 F18 Sqm. 774.26 890.40
(1:4) screeding
6.26 F19( 10-17) Making and fixing of Sal wood beam, lintel, etc Cum. 249,816.75 287,289.26
6.27 F20(10-19) Making and fixing of 25 mm sal wood eaves board Sqm. 6,229.42 7,163.84
6.28 F22 2 mm thick UPVC roofing sheet roofing work Sqm. - -
6.29 F23 3 mm thick UPVC roofing sheet roofing work Sqm. 2,353.53 2,706.56

G - DOOR & WINDOW WORK


7.01 G1(10-1) Sal wood works for chaukhats with all complete. Cum. 282,361.54 324,715.77
7.02 G1(10-1) Local wood works for chaukhats with all complete. Cum. 101,648.04 116,895.24

38 mm thick sal wood fully paneled shutter fixing work with all
7.03 G2(10-2) Sqm. 14,932.61 17,172.50
complete. Size of shutter 1.07 x 1.982 =2.114 Sqm.

Prepared by Checked by Approved by


12 of 79
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :DHANUSHA 2075/2076


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract
38 x 75 mm thick sal wood frame with 4 mm thick fully glazed
7.04 G3(10-4) shutter fixing work with all complete. Size of shutter 1.829 x Sqm. 9,653.11 11,101.07
1.22 =2.23 Sqm.
38 x 75 mm thick sal wood frame with 3 mm thick fully glazed
7.04a G3(10-4) shutter fixing work with all complete. Size of shutter 1.829 x Sqm. 9,613.02 11,054.97
1.22 =2.23 Sqm.
38 x 75 mm thick Gamhair wood frame with 4 mm thick fully
7.05 G3(10-4) glazed shutter fixing work with all complete. Size of shutter Sqm. 6,213.17 7,145.14
1.829 x 1.22 =2.23 Sqm.
38 mm thick sal wood frame with 4 mm thick commercial
7.06 G4(10-7) plywood (bothside) flush shutter fixing with all comolete. Size Sqm. 7,840.88 9,017.01
of shutter 1.092 x 2.058 =2.245 Sqm.
38 mm thick sal wood frame with 3 mm thick TEAK plywood
7.07 G4(10-8) (Both side ) flush shutter fixing with all comolete. Size of Sqm. 7,840.88 9,017.01
shutter 1.092 x 2.058 =2.245 Sqm.
38 mm thick sal wood frame with 26 Bwg G.I. plane sheet
7.08 G4(10-9) (bothside) shutter fixing with all comolete. Size of shutter Sqm. 8,155.03 9,378.28
1.092 x 2.058 =2.245 Sqm.
38 mm thick sal wood frame with 24 Bwg G.I. mosquito proof
7.09 G4(10-10) & Expanded metal net net shutter fixing with all comolete. Size Sqm. 5,799.99 6,669.98
of shutter 1.092 x 2.058 =2.245 Sqm.
38 mm thick sal wood frame with 24 Bwg G.I. mosquito proof
7.10 G4(10-10) net shutter fixing with all comolete. Size of shutter 1.092 x Sqm. 5,633.86 6,478.93
2.058 =2.245 Sqm.
7.11 G5(10-11B) 4 mm thick plane glass fixing work with wooden listies. Sqm. 888.75 1,022.06

7.12 G5(10-11B) 26 Bwg plane sheet fixing work with wooden listies. Sqm. 782.20 899.53

7.13 G6(10-12) 4 mm thick ply wood fixing work with wooden listies. Sqm. 481.66 553.90

7.14 G5(10-11B) Mosquito proof net fixing work with wooden listies. Sqm. 3,153.09 3,626.05
Mosquito proof & Expanded metal net fixing work with
7.15 G5(10-11B) Sqm. 795.04 914.29
wooden listies.
False ceiling of 6 mm thick commerical plywood with 50 mm x
7.16 10-16-A 75 mm size local wood frame of box size 0.600 x 0.900 m and Sqm. 2,079.77 2,391.73
fixing of wooden listy in joints
Torsteel reinforcement bar fixing work in window frame with all
7.17 G7(10-21) Kg. 124.80 143.53
complete,
38 x100mm thick sal wood frame with 12 mm thick
G8(10-3 & commercial plywood paneled & one side 4 mm thick Teak
7.18 Sqm. 10,376.57 11,933.05
10-7) plywood paneled shutter fixing with all comolete. Size of
shutter 1.092 x 2.058 =2.245 Sqm.
38 x100mm thick sal wood frame with 12 mm thick
G9(10-3 & commercial plywood paneled & both side 4 mm thick Teak
7.19 Sqm. 13,050.61 15,008.20
10-7) plywood paneled shutter fixing with all comolete. Size of
shutter 1.092 x 2.058 =2.245 Sqm.
38 x100mm thick sal wood frame with 12 mm thick water proof
G10(10-3 & plywood paneled & one side 4 mm thick Teak plywood
7.20 Sqm. 10,376.57 11,933.05
10-7) paneled shutter fixing with all comolete. Size of shutter 1.092
x 2.058 =2.245 Sqm.

H - FLOORING WORK

Prepared by Checked by Approved by


13 of 79
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :DHANUSHA 2075/2076


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract
25 mm or 1" thick P.C.C. (1:2:4) work in floor with all complete.
8.01 H1(11-1A) Sqm. 414.74 476.95
38 mm or 1½" thick P.C.C. (1:2:4) work in floor with all
8.02 H1(11-1B) Sqm. 562.15 646.47
complete.
50 mm or 2" thick P.C.C. (1:2:4) work in floor with all complete.
8.03 H1(11-1C) Sqm. 688.86 792.19

8.04 H1(11-1D) 75 mm or 3" thick P.C.C. (1:2:4) work in floor with all complete. Sqm. 932.14 1,071.96

25 mm thick mosaic flooring with 20 mm thick P.C.C. (1:2:4) &


8.05 H2(11-2) 5 mm thick white cement marble chips1:1 rubbing & polishing Sqm. 1,892.63 2,176.52
work with all complete.
25 mm thick mosaic flooring with 19 mm thick cement sand
8.06 H3(11-3) plaster 1:2 & 6 mm thick white cement marble chips1:1 Sqm. 3,390.46 3,899.03
rubbing & polishing work with all complete.
20 mm thick mosaic flooring with 12.5mm thick cement sand
8.07 H4(11-4) plaster 1:2 & 6 mm thick white cement marble chips1:1 Sqm. 3,464.40 3,984.06
rubbing & polishing work with all complete.

20 mm thick Terrazo tile paving with 20 mm thick cement sand


8.08 H5(11-5) Sqm. 2,020.88 2,324.01
mortar 1:4 rubbing & polishing work with all complete.

15 mm thick marble tile 600x600 mm paving with 20 mm thick


8.09 11-6 cement sand mortar 1:2 rubbing & polishing work with all Sqm. 5,047.36 5,804.47
complete.
Porcelain glazed /non glazed tile paving work in cement sand
8.10 H6(11-7) Sqm. 2,822.26 3,245.60
(1:4) mortar
Spartik Non-glazed tile paving work in cement sand (1:4)
8.11 H6(11-7) Sqm. 2,765.61 3,180.45
mortar
8.12 H12(11-12) Flat Brick paving in 1:6 & cement sand pointing in1:2 in joints Sqm. 1,068.73 1,229.04
Edge Brick paving in 1:6 & cement sand pointing in1:2 in
8.13 H13(11-13) Sqm. 1,266.04 1,455.94
joints
H15(11-
8.14 Dry flat Brick paving work Sqm. 698.71 803.52
15A)
H15(11-
8.15 Dry flat Brick (Brick Bat ) paving work Sqm. 409.88 471.36
15A)
H15(11-
8.16 Dry edge Brickpaving work Sqm. 1,183.86 1,361.44
15B)
H15(11-
8.17 Dry edge Brick (Brick Bat ) paving work Sqm. 716.63 824.13
15B)
8.18 H16( 11-16) Stone filling in floor with sand lead up to 30 mtr. Cum. 6,776.64 7,793.13
Edge brick paving with sand packing in voids & cement sand
8.19 H17( 11-17) Sqm. 1,263.59 1,453.13
(1:3) flush pointing in top surface.
H19( 11-
8.20 Sand filling work Cum. 2,378.97 2,735.82
19A)
H19( 11-
8.21 15-15 cm. Brick bat filling work. Cum. 955.29 1,098.58
19B)
8.22 H20( 11-20) 3 mm thick neat cement punning work. Sqm. 252.15 289.97
25 mm thick Sal wood planking work with 50x75 mm sal
8.23 H21(11-21) Sqm. 9,974.61 11,470.80
wood frame in 600x600 mm
8.24 H24( 11-20) 3 mm thick neat Plaster of Paris punning work. Sqm. 274.07 315.18
Clay tile(Machine Made) paving work in cement sand (1:4)
8.25 H25(11-7) Sqm. 1,674.37 1,925.53
mortar

Prepared by Checked by Approved by


14 of 79
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :DHANUSHA 2075/2076


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract

Granite 16mm thick paving with 20 mm thick cement sand


8.26 H26(11-6) Sqm. 6,083.48 6,996.00
mortar 1:2 rubbing & polishing work with all complete.
I - PLASTER & POINTING WORK
9.01 I1(12-1B) 12.5 mm. thick cement sand plaster work 1:3 on wall. Sqm. 346.81 398.83
9.02 I1(12-1C) 12.5 mm. thick cement sand plaster work 1:4 on wall. Sqm. 334.46 384.64
9.03 I1(12-1D) 12.5 mm. thick cement sand plaster work 1:6 on wall. Sqm. 308.92 355.26
9.04 I4(12-4A) 20 mm. thick cement sand plaster work 1:3 on wall etc. Sqm. 454.53 522.71
9.05 I4(12-4B) 20 mm. thick cement sand plaster work 1:4 on wall etc. Sqm. 432.29 497.13
9.06 I4(12-4C) 20 mm. thick cement sand plaster work1:6 on wall etc. Sqm. 392.67 451.57
9.07 I5(12-5) 25 mm. thick mud plaster on wall etc. Sqm. 367.96 423.16
9.08 I5(12-6) 12.5 mm. thick mud plaster on wall etc. Sqm. 282.74 325.15
9.09 I7(12-1B) 12.5 mm. thick cement sand plaster work (1:3 ) on ceilling Sqm. 401.01 461.16
9.10 I7(12-1C) 12.5 mm. thick cement sand plaster work 1:4 on ceilling Sqm. 388.66 446.97
Flush pointing works in 1:1 Cement sand mortar on Brick
9.11 I8(14-1A) Sqm. 235.56 270.90
masonry wall
Flush pointing works in 1:2 Cement sand mortar on Brick
9.12 I8(14-1B) Sqm. 218.13 250.85
masonry work
Flush pointing works in 1:3 Cement sand mortar on Brick
9.13 I8(14-1C) Sqm. 208.98 240.33
masonry wall
Rulled pointing works in 1:1 Cement sand mortar on Brick
9.14 I8(14-1A) Sqm. 323.91 372.50
masonry wall
Ruled pointing works in 1:2 Cement sand mortar on Brick
9.15 I8(14-1B) Sqm. 306.48 352.45
masonry work
Ruled pointing works in 1:3 Cement sand mortar on Brick
9.16 I8(14-1C) Sqm. 297.33 341.93
masonry wall
Flush/Rulled pointing works in 1:1 Cement sand mortar on
9.17 I9(14-2A) Sqm. 299.07 343.93
Stone masonry wall
Flush/Rulled pointing works in 1:2 Cement sand mortar on
9.18 I9(14-2B) Sqm. 265.60 305.44
Stone masonry work
Flush/Rulled pointing works in 1:3 Cement sand mortar on
9.19 (14-2C) Sqm. 248.70 286.01
Stone masonry work
Flush/Rulled pointing works in 1:3 Cement sand mortar on
9.20 I10(14-3) Sqm. 162.67 187.07
Aslar Stone masonry work
1:3 Cement sand pointing on 450 mm x 450 mm flat stone
9.21 I11(14-4) Sqm. 87.33 100.43
paving joints.
9.22 I12(14-5) 1:1 Cement sand pointing on Teliya brick paving joints. Sqm. 186.87 214.90
9.23 (14-6) 3 mm thick Cement sand 1:1 flushing plaster Sqm. 221.53 254.75
9.24 I13(14-7) 3 mm thick lime flushing plaster Sqm. 159.03 182.89
9.25 I14(14-8) 3 mm thick Cement flushing plaster Sqm. 249.70 287.15
9.26 I15 20 mm thick Jhalar/pani patti making over cement plaster Sqm. 169.29 194.68
25 mm thick roofing tile butta plaster in cement sand (1:4)
9.27 I16 Sqm. 641.69 737.94
work
9.28 I17 2 mm thick plane white putting plaster work in wall &ceilling Sqm. 224.75 258.46

13. PAINTING WORK


10.01 J1(13-1B) Two coat white washing work on wall. Sqm. 27.73 31.89

Prepared by Checked by Approved by


15 of 79
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :DHANUSHA 2075/2076


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract
10.02 J1(13-1B) Two coat white washing work on ceilling. Sqm. 33.04 37.99
10.03 J1(13-1C) Three coat white washing work on wall. Sqm. 55.17 63.45
10.04 J1(13-1C) Three coat white washing work on ceilling. Sqm. 66.61 76.60
10.05 J2(13-2) white washing work in old surface. Sqm. 15.01 17.26
10.06 J3(13-3AB) One coat distemper painting work over primer coat. Sqm. 111.18 127.86
J3(13-
10.07 Two coat distemper painting work over primer coat. Sqm. 154.22 177.35
3ABC)
10.08 J3(13-3B) One coat distemper painting work without primer coat. Sqm. 50.54 58.12
10.09 J3(13-3BC) Two coat distemper painting work without primer coat. Sqm. 93.58 107.62
10.10 J3(13-3AB) One coat weather proof painting work over primer coat. Sqm. 156.24 179.68
J3(13-
10.11 Two coat weather proof painting work over primer coat. Sqm. 227.61 261.75
3ABC)
10.12 J3(13-3B) One coat weather proof painting work without primer coat. Sqm. 87.36 100.47
10.13 J3(13-3BC) Two coat weather proof painting work without primer coat. Sqm. 158.73 182.54
One coat water proof cement paint painting work in old
10.14 J4(13-4A) Sqm. 53.29 61.28
surface
Two coat water proof cement paint painting work in old
10.15 J4(13-4B) Sqm. 121.96 140.25
surface
10.16 J4(13-4A) One coat white cement paint painting work . Sqm. 44.02 50.62
10.17 J4(13-4B) Two coat white cement paint painting work . Sqm. 106.97 123.02
One coat enamel painting work over primer coat in wooden
10.18 J5(13-5AB) Sqm. 190.66 219.26
surface.
J5(13- Two coat enamel painting work over primer coat in wooden
10.19 Sqm. 289.58 333.02
5ABC) surface.
10.20 J5(13-5AB) One coat plastic emulsion painting work over primer coat. Sqm. 197.15 226.72
10.21 J5(13-5AB) Two coat plastic emulsion painting work over primer coat. Sqm. 301.12 346.28
Two coat aluminium painting work over primer coat in metal
10.22 J6(13-6) Sqm. 263.26 302.75
surface.
10.23 J7(13-8AB) Two coat double boiled Linseed oil painting work . Sqm. 78.32 90.07
Two coat aluminium painting work over primer coat in metal
10.24 J6(13-6) Sqm. 263.26 302.75
surface.
10.25 J7(13-8A) One coat double boiled Linseed oil painting work . Sqm. 39.83 45.80
10.25(A) #N/A #N/A #N/A #N/A #N/A
10.26 J9(13-10A) One coat Bitumen painting work . Sqm. 32.13 36.95
10.27 J9(13-10B) Two coat Bitumen painting work . Sqm. 56.27 64.71
10.28 J10(13-11) Three coat chapra painting work . Sqm. 146.48 168.45
10.29 J11(13-4C) One coat RED OXIDE painting work . Sqm. 135.18 155.45
10.30 J11(13-4C) Two coat RED OXIDE painting work . Sqm. 230.49 265.06
One coat water proof cement paint painting work in plastered
10.31 J12(13-12A) Sqm. 81.91 94.20
surface
J12(13- Two coat water proof cement paint painting work in plastered
10.32 Sqm. 147.12 169.19
12AB) surface
10.33 J15(5-5) ENAMEL paint painting work over linceed oil in face brick wall Sqm. 189.16 217.53
One coat enamel painting work without primer coat in wooden
10.34 J16(13-5B) Sqm. 113.76 130.83
surface.
Two coat enamel painting work without primer coat in wooden
10.35 J17(13-5BC) Sqm. 212.68 244.58
surface.
10.36 J18(13-5B) One coat plastic emulsion painting work without primer coat. Sqm. 120.25 138.29

Prepared by Checked by Approved by


16 of 79
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :DHANUSHA 2075/2076


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract
10.37 J19(13-5BC) Two coat plastic emulsion painting work without primer coat. Sqm. 224.22 257.85
One coat aluminium painting work without primer coat in metal
10.38 J20(13-6) Sqm. 87.14 100.22
surface.
Two coat aluminium painting work without primer coat in metal
10.39 J21(13-6) Sqm. 178.02 204.72
surface.
10.40 J22(13-7) One coat RED OXIDE painting work without primer coat Sqm. 93.73 107.80
10.41 J23(13-7) Two coat RED OXIDE painting work without primer coat Sqm. 187.57 215.70

10.44 J26 Two coat washable distemper painting work over primer coat. Sqm. 167.20 192.28

K - Damp proofing work

20 mm thick D.P.C. work in cement sand mortar in 1:2 with


11.01 K1(18-7) Sqm. 415.62 477.96
W.P.Compound.
25 mm thick D.P.C. work in cement concrete in 1:1½:3
11.02 K2(18-8) Sqm. 460.16 529.19
withwith W.P.Compound.
38 mm thick D.P.C. work in cement concrete in 1:2:4 with with
11.03 18-9 Sqm. 554.47 637.64
W.P.Compound.
11.05 K4(18-11) 500 gauge polythine sheet laying work Sqm. 152.05 174.85

11.06 K5(18-12A) One layer tarfelt laying work. Sqm. 826.68 950.68

11.07 K5(18-12B) Two layer tarfelt laying work. Sqm. 1,327.18 1,526.26

11.08 K6(18-13A) One layer damp proof grade tarfelt laying work. Sqm. 1,040.40 1,196.46

11.09 K6(18-13B) Two layer damp proof grade tarfelt laying work. Sqm. 1,926.20 2,215.13
Two coat elastocret cementious elastomeric water proofing
11.10 K7 Sqm. 531.97 611.76
work
One coat rain Crystallization seal paint or equivalent paint
11.11 K8(18-14) Sqm. 139.15 160.02
work.
Expansion Joint Works: - Chipping and laying thermocol in
the hole, masking tape on the thermocol and plaster with
11.12 0 Sqm. 6,864.95 7,894.69
mixing Perma Bond SBR or eqv. modified mortar up to 40
mm wide and levelling all complete.

L - MAINTAINANCE & DISMANTLING WORK

Dismantling work of mud masonry wall & removing of material


12.01 L1(19-1) Cum. 689.00 792.35
upto 10 mtr lead.
Dismantling work of cement masonry wall & removing of
12.02 L2(19-2) Cum. 1,378.00 1,584.70
material upto 10 mtr lead.
Dismantling work of R.C.C. / R.B.C. & removing of material
12.03 L3(19-3) Cum. 7,150.00 8,222.50
upto 10 mtr lead.
Dismantling work of P.C.C. / L.C.C. & removing of material
12.04 L4(19-4) Cum. 2,600.00 2,990.00
upto 10 mtr lead.
Dismantling work of cement sand / lime surkhee plaster &
12.05 L5(19-5) Sqm. 70.20 80.73
removing of material upto 10 mtr lead.
Dismantling work of tile roof & removing of all material wood,
12.06 L6(19-6) Sqm. 103.41 118.92
tile upto 10 mtr lead.
12.07 L7 Wood preservative paint painting work Sqm. 360.12 414.13
Clearance work of old existing marble floor with Oxalic acid &
12.08 L11 Sqm.. 240.62 276.71
carborendum stone

Prepared by Checked by Approved by


17 of 79
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :DHANUSHA 2075/2076


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract
12.09 L12 Clearance work of old existing parket & polishing work Sqm.. 219.37 252.28
Clearance work of old existing mosaic floor with Oxalic acid ,
12.10 L13 Sqm.. 255.24 293.52
main polish , terpantain oil & carborendum stone
Clearance work of brick from mud masonry wall & stacking of
12.11 L14(A) Nos. 2.82 3.25
brick for re-used
Clearance work of brick from cement masonry wall &
12.12 L14(C) Nos. 4.70 5.41
stacking of brick for re-used
Clearance work of stone from cement masonry wall &
12.13 L15(B) Cum. 1,002.01 1,152.31
stacking of stone for re-used
Clearance work of stone from mud masonry wall & stacking
12.13a Cum. 813.90 935.98
of stone for re-used
Dismantling work of R. C. C. barbed wire fencing work with
12.14 L19(A) Sqm. 292.50 336.37
earthwork excavation filling & leveling
Dismantling work of IRON. barbed wire fencing work with
12.15 L19(B) Sqm. 273.00 313.95
earthwork excavation filling & leveling
Dismantling work of WOODEN. barbed wire fencing work with
12.16 L19(C) Sqm. 260.00 299.00
earthwork excavation filling & leveling
Dismantling work of M.S. bar from R.C.C./R.B.C.& stacking
12.17 L19(C) Sqm. 874.00 1,005.10
upto 10 mtr.
12.18 L21 Dismantling work of Gavian work Sqm. 946.50 1,088.47
Dismantling work of cgi sheet roof & removing of all material
12.19 L22 Sqm. 51.38 59.08
wood, cgi sheet upto 10 mtr lead.

24 IRON WORK
3 x 20mm Metal Grill including manufacturing, fitting, painting
13.01 M1(24-1A) Sqm. 2,472.00 2,842.80
with Aluminium paint, sand papering all complete
4 x 20mm Metal Grill including manufacturing, fitting, painting
13.02 M2(24-1B) Sqm. 3,543.20 4,074.68
with Aluminium paint, sand papering all complete
12x12 mm solid core square rod M. S. grill with 4 x 20mm
13.03 M3 Sqm. 2,125.69 2,444.55
Metal frame
13.04 M4 Fabricating, supplying & fixing of different size M.S. angle Kg. 189.77 218.24

13.05 M5 Spiral stair case 3.00 mtr height 90 cm. width Rmtr. 10,304.12 11,849.73

Providing & fixing MS folded sheet rolling shutters with iron


13.06 M6(24-2) clamps, spring and axle of good quality finish with one coat Sqm. 3,862.50 4,441.87
red- oxide paint on shutter and oiling on spring and axle.
Collapsible shutter including manufacturing, welding, supply
13.07 M7(24-4) Sqm. 5,232.40 6,017.26
of material, painting and fixing
Providing and fixing MS gate as per drawing with 50 mm X 50
mm X 3 mm MS angle, 25 mm X 25 mm MS square pipe, 16
gauge MS flat sheet, 12 mm X 3 mm MS flat , ready made
13.08 M8(24-3) Sqm. 4,362.50 5,016.87
pivot hing welded to 175 mm long angle hold fast embedded
in concrete and iron locking arrangement over one coat primer
.
Providing and fixing MS gate as per drawing with 50 mm X 50
mm X 3 mm MS angle, 25 mm X 25 mm MS square pipe,
13.09 M8(24-3) ready made pivot hing welded to 175 mm long angle hold fast Sqm. 4,362.50 5,016.87
embedded in concrete and iron locking arrangement over one
coat primer.
Supplying and fixing of Barbed wire 14 gauge including hooks,
13.10 M9(24-6) Rmtr. 175.87 202.26
nails etc

Prepared by Checked by Approved by


18 of 79
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :DHANUSHA 2075/2076


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract

Supplying and fixing of Barbed wire 12 gauge including hooks,


13.11 M10(24-7) Rmtr. 2,379.88 2,736.86
nails etc 5 H+2D with 75x100 mm sal wood 2100 mm long .

Fabricating, supplying & fixing of different size M.S. black pipe


13.12 M11 Kg. 169.17 194.55
Truss with metal primer
Supplying & fixing work of 50 mm Ø MS black pipe @ 2.0 mtr
with 10 S.W.G.G. I. Chain Link 2"x2" mesh size fixing in
13.13 M12 Sqm. 3,172.26 3,648.10
4x20x20 mm & 4x25x25 mm ms angle frame & top 3x20 mm
MS grill 15 cm height with primer coat..
Supplying & fixing work of 50 mm Ø MS black pipe @ 2.0 mtr
with 7 mm Ø TMT bar mesh 62x62 mm size 4x25x25 mm ms
13.14 M13 Sqm. 2,816.35 3,238.81
angle frame & top 3x20 mm MS grill 15 cm height with primer
coat..
13.15 M14 900 mm height stainless steel staircase railing work Sqm. 4,212.70 4,844.60
Supplying & fixing work of 38 mm Ø stainless steel pipe post
@ 2.0 mtr , 8 mm Ø stainless steel pipe hand rail with two
13.16 M15 Sqm. 3,308.24 3,804.48
rows 25 mm Ø stainless steel pipe in between ground & hand
rail.
Supplying & fixing work of 150x150 mm size sisham wood
13.17 M16 ornamental post , 75x75 mm size bluster with 75x100 mm Sqm. - -
hand rail.
13.18 M17 Hand rail 3"x4" size sisham wood supplying & fixing work Rmtr. 1,095.76 1,260.12
Supplying & fixing work of 20x20 mm square pipe railing two
13.19 M18 nos. every trade 900 to 1000 mm height with 3"x4" sisham Rmtr. 2,190.87 2,519.50
wood hand rail
Supplying & fixing work of 20x20 mm square pipe railing two
13.20 M19 nos. every trade 900 to 1000 mm height with 40 mm MS Rmtr. 1,607.31 1,848.40
black pipe hand rail

25 ROAD WORK

Subgrade prepairing work with simple mud cutting 10 mtr.


15.01 O1 Sqm. 100.42 115.48
lead
15.02 O2 Rolling work Sqm. 8.05 9.25
10 cm. compact sub base laying work with sand mixed gravel,
15.03 O3(15-9A) Sqm. 291.36 335.06
load unload & proper levelling.

15 cm. compact sub base laying work with sand mixed gravel,
15.04 O3(15-9C) Sqm. 414.15 476.27
load unload & proper levelling.

20 cm. compact sub base laying work with sand mixed gravel,
15.05 O3(15-9D) Sqm. 524.23 602.86
load unload & proper levelling.

26 Misclenious WORK

Alluminium fixed panel window With ventilation but without fly


25.01 mesh shutter from section( 88mmx38.1mm x1.3mm , Glass Sqm. 6,386.00 7,343.90
5mm)

Alluminium fixed panel window With Ventilation with fly mesh


25.02 Sqm. 6,798.00 7,817.70
shutter from section(88mmx38.1mm x1.3mm , Glass 5mm )

Prepared by Checked by Approved by


19 of 79
SUMMARY OF RATE ANALYSIS, CIVIL

DISTRICT :DHANUSHA 2075/2076


RATE
S. No. N.C.N. DESCRIPTION OF WORKS UNIT
Dept Contract
Alluminium framed Sliding window Without ventilator
25.03 ( Aluminium :- Natural anodised 101mmx45mm x1.50mm , Sqm. 6,695.00 7,699.25
Glass 5mm clear)
Alluminium framed Sliding window With ventilator ( Aluminium
25.04 :- Natural anodised 101mmx45mm x1.5mm , Glass 5mm Sqm. 7,210.00 8,291.50
clear)
Alluminium framed Sliding Door ( Aluminium :- Natural
25.05 anodised 101mmx45mm x1.5mm ,) with sash 40*45*1.5mm Sqm. 7,622.00 8,765.30
and 5mm glass
Casement double panel aluminium window With ventilator
25.06 section of ( 54mmx33mm x1.5)mm with sash 38*34*1.5mm Sqm. 7,210.00 8,291.50
with Glass 5mm
Alluminium Casement Door section of ( 101mmx45mm
25.07 Sqm. 12,360.00 14,214.00
x1.1)mm sash 40*45*1.1mm & Glass 5mm

Alluminium framed Swing Door section of (101mmx45mm


25.08 Sqm. 7,879.50 9,061.42
x1.5)mm & Glass 5mm clear

Alluminium framed Sliding window 2 track section of


25.09 Sqm. 6,180.00 7,107.00
(88mmx38mm x1.5)mm & Glass 5mm
Alluminium fixed window and partition with fixed ventilator
25.10 Sqm. 6,180.00 7,107.00
from 9mm bord and section (101mmx45mm x1.5)mm
Aluminum framed Sliding window With ventilator and with
25.11 0 Mosquito Net ( Aluminium :- Natural anodised 78mmx35mm Sqm. 6,180.00 7,107.00
x1.2mm , Glass 5mm clear)
25.12 0 False ceiling by Gypsum ,Gypsum Board : 12mm Sqm. 906.40 1,042.36
11.09 0 ASO Joint Tape laying Work. Rm - -

Prepared by Checked by Approved by


Rate_Analysis_Dhanusha_Civil_2075/076 Page 20 of 79

A - SITE PREPARATION WORK

Cutting of tree, branch & log etc. (12-30 cm. girth above
1.01 A1 (1-1A) Nos. 84.50 97.17
1.00 mtr. From G.L.) with lead upto 15 mtr.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.130 Nos. 650.00 84.50
Total 84.50
Rate analysis for : 1.00 No. 15 % Contractor overhead 12.67
Grand Total 97.17

Cutting of tree, branch & log etc. (31-60 cm. girth above
1.02 A1 (1-1B) Nos. 253.50 291.52
1.00 mtr. From G.L.) with lead upto 15 mtr.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.390 Nos. 650.00 253.50
Total 253.50
Rate analysis for : 1.00 No. 15 % Contractor overhead 38.02
Grand Total 291.52

Cutting of tree, branch & log etc. (61-120 cm. girth above
1.03 A1 (1-1C) Nos. 637.00 732.55
1.00 mtr. From G.L.) with lead upto 15 mtr.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.980 Nos. 650.00 637.00
Total 637.00
Rate analysis for : 1.00 No. 15 % Contractor overhead 95.55
Grand Total 732.55

Removing of tree root (12-30 cm. girth above 1.00 mtr.


1.04 A2 (1-2A) From G.L.) with lead upto 15 mtr. Nos. 260.00 299.00

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.400 Nos. 650.00 260.00
Total 260.00
Rate analysis for : 1.00 No. 15 % Contractor overhead 39.00
Grand Total 299.00

Removing of tree root (31-60 cm. girth above 1.00 mtr.


1.05 A2 (1-2B) From G.L.) with lead upto 15 mtr. Nos. 344.50 396.17

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.530 Nos. 650.00 344.50
Total 344.50
Rate analysis for : 1.00 No. 15 % Contractor overhead 51.67
Grand Total 396.17

Removing of tree root (61-120 cm. girth above 1.00 mtr.


1.06 A2 (1-2C) From G.L.) with lead upto 15 mtr. Nos. 1,638.00 1,883.70

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 2.520 Nos. 650.00 1,638.00
Total 1,638.00
Rate analysis for : 1.00 No. 15 % Contractor overhead 245.70
Grand Total 1,883.70

Cutting of grass, taking of root & brocken of uplecutting


1.07 A3 of raised soil & site leveling with all complete Sqm. 14.95 17.19

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.230 Nos. 650.00 149.50
Total 149.50
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 22.42
Grand Total 171.92

Surface dressing work with cutting of raised soil & filling


1.08 A4 sqm. 6.50 7.47
the ditches.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.010 Nos. 650.00 6.50
Total 6.50
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 0.97
Grand Total 7.47

B - EARTH & SAND WORK

Earth work excavation in foundation in clay & silty soft


2.01 B1 (2-1) Cum. 468.65 538.94
soil lead upto 10 mtr. & lift 1.5 mtr.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.700 Nos. 650.00 455.00
Materials T&P 3 % of labour 13.65

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 21 of 79

Total 468.65
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 70.29
Grand Total 538.94

Earth work excavation in foundation in clay & soft murram


2.02 B1 (2-2) stone (30 cm.) hard soil lead upto 10 mtr. & lift 1.5 mtr. Cum. 535.60 615.94

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.800 Nos. 650.00 520.00
Materials T&P 3 % of labour 15.60
Total 535.60
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 80.34
Grand Total 615.94

Earth filling work in every 15-15 cm. layer with watering &
2.03 B2 (2-25A) lead upto 1o.00 mtr. & proper manual compaction. Cum. 325.00 373.75

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.500 Nos. 650.00 325.00
Total 325.00
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 48.75
Grand Total 373.75

Earth filling (Earth transported from 5 Km. surronding)


2.04 B2 (2-25A) work in every 15-15 cm. layer with watering & proper Cum. 944.80 1,086.52
manual compaction.
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.500 Nos. 650.00 325.00
Mud 1.500 Cum. 412.00 618.00
Materials
Water 5.000 Ltr. 0.36 1.80
Total 944.80
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 141.72
Grand Total 1,086.52

Earth filling work in every 15-15 cm. layer without


2.05 B2 (2-25B) watering & proper manual compaction. Cum. 162.50 186.87

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.250 Nos. 650.00 162.50
Total 162.50
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 24.37
Grand Total 186.87

Earth filling (Earth transported from 5 Km. surronding)


2.06 B2 (2-25B) work in every 15-15 cm. layer without watering & proper Cum. 698.10 802.81
manual compaction.

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.250 Nos. 650.00 162.50
Materials Mud 1.300 Cum. 412.00 535.60
Total 698.10
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 104.71
Grand Total 802.81

Sand filling work with watering & proper manual


2.07 B3 (2-42A) compaction. Cum. 2,224.77 2,558.48

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.700 Nos. 650.00 455.00
Sand local 1.100 Cum. 1,607.25 1,767.97 with tax
Materials
Water 5.000 Cum. 0.36 1.80
Total 2,224.77
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 333.71
Grand Total 2,558.48

Gravel Sand mixed (agg-50% + sand 50%) filling work with


2.08 B3 (2-42B) proper manual compaction. Cum. 2,130.35 2,449.90

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.750 Nos. 650.00 487.50
Materials Gravel (sand mixed) 1.100 Cum. 1,493.50 1,642.85 with tax
Total 2,130.35
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 319.55
Grand Total 2,449.90

Pumping of water from foundation or trench


2.09 B4 (2-34) Hrs 33.99 39.08

Resources Level/Type Quantity Unit Rate Amount Remarks


Materials Water pump 0.500 Hour 339.90 169.95

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 22 of 79

Total 169.95
Rate analysis for : 5000.00 Ltr. 15 % Contractor overhead 25.49
Grand Total 195.44

Compaction of filled earth by 8-10 M.T. roller in 20/20 cm


2.11 B5 layer Cum. 15.48 17.80

Resources Level/Type Quantity Unit Rate Amount Remarks


Equipment Road roller 8-10 M.T. 1.670 Hour 927.00 1,548.09
Total 1,548.09
Rate analysis for : 100.00 Cum. 15 % Contractor overhead 232.21
Grand Total 1,780.30

Compaction of filled earth by 1.00 M.T. Hand roller in 20/20


2.12 B5 cm layer Cum. 5.01 5.76

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 53.000 Nos 650.00 34,450.00
Equipment Road hand roller 1.00 M.T. 1.670 Hour 300.00 501.00
Total 501.00
Rate analysis for : 100.00 Cum. 15 % Contractor overhead 75.15
Grand Total 576.15

Earth work excavation in foundation in SOFT SOIL(USED 0.80


2.13 B7 CUM. CAPACITY Hydraulic EXCAVATOR) Cum. 46.24 53.17

Resources Level/Type Quantity Unit Rate Amount Remarks


Materials Diesel 0.1248 Ltr. 104.54 13.04
Equipment Hydraulic Excavator 0.80 Cum. 0.0104 Hour 3,193.00 33.20
Total 46.24
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 6.93
Grand Total 53.17

Earth work excavation in foundation in HARD SOIL USED 0.80


2.14 B7 CUM. CAPACITY Hydraulic EXCAVATOR) Cum. 55.59 63.92

Resources Level/Type Quantity Unit Rate Amount Remarks


Materials Diesel 0.1500 Ltr. 104.54 15.68
Equipment Hydraulic Excavator 0.80 Cum. 0.0125 Hour 3,193.00 39.91
Total 55.59
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 8.33
Grand Total 63.92

Earth work excavation in foundation in HARD SOIL Used 0.80


2.15 B7 Cum capecity Hydraulic excavator Cum. 55.59 63.92

Resources Level/Type Quantity Unit Rate Amount Remarks


Materials Diesel 0.1500 Ltr. 104.54 15.68
Equipment Hydraulic Excavator 0.80 Cum. 0.0125 Hour 3,193.00 39.91
Total 55.59
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 8.33
Grand Total 63.92

Earth work excavation in foundation in SOFT SOILUsed


2.16 B7 1.32Cum capecity Hydraulic excavator Cum. 14.77 16.98

Resources Level/Type Quantity Unit Rate Amount Remarks


Materials Diesel 0.1380 Ltr. 104.54 14.42
Hydraulic Excavator 1.32 Cum. 0.0069 Hour 51.50 0.35
Total 14.77
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2.21
Grand Total 16.98

Earth work excavation in foundation in HARD SOIL Used


2.17 B7 1.32Cum capecity Hydraulic excavator Cum. 17.99 20.68

Resources Level/Type Quantity Unit Rate Amount Remarks


Materials Diesel 0.1680 Ltr. 104.54 17.56
Hydraulic Excavator 1.32 Cum. 0.0084 Hour 51.50 0.43
Total 17.99
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2.69
Grand Total 20.68

C - MASONRY WORK

C2(5-1-B1 & First class chimney brick masonry work in (1:3) cement
3.01 Cum. 12,354.55 14,207.73
5-2A) sand mortar in G. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 940.00 1,410.00
Labour Unskilled 2.200 Nos. 650.00 1,430.00
Unskilled ( for Scaffolding ) 0.200 Nos. 650.00 130.00
Brick chimney 476.000 Nos. 13.90 6,616.40

Materials
-------------------Prepared by : -----------------Checked by : --------------------Approved by :
Rate_Analysis_Dhanusha_Civil_2075/076 Page 23 of 79

with
Cement 0.130 M.T. 17,510.00 2,276.30 transportation
Materials
Sand 0.270 Cum. 1,607.25 433.95
Water 150.000 Ltr. 0.36 54.00
Scaffolding material 3 % of Scaffolding labour 3.90
Total 12,354.55
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,853.18
Grand Total 14,207.73

C2(5-1-B1 & First class chimney brick masonry work in (1:3) cement
3.02 Cum. 12,689.30 14,592.69
5-2B) sand mortar in F. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 940.00 1,410.00
Labour Unskilled 2.200 Nos. 650.00 1,430.00
Unskilled 0.700 Nos. 650.00 455.00
Brick chimney 476.000 Nos. 13.90 6,616.40
with
Cement 0.130 M.T. 17,510.00 2,276.30 transportation
Materials
Sand 0.270 Cum. 1,607.25 433.95
Water 150.000 Ltr. 0.36 54.00
Scaffolding material 3 % of Scaffolding labour 13.65
Total 12,689.30
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,903.39
Grand Total 14,592.69

C2(5-1-B1 & First class chimney brick masonry work in (1:3) cement
3.03 Cum. 13,157.95 15,131.64
5-2B) sand mortar in S. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 940.00 1,410.00
Labour Unskilled 2.200 Nos. 650.00 1,430.00
Unskilled 1.400 Nos. 650.00 910.00
Brick chimney 476.000 Nos. 13.90 6,616.40
with
Cement 0.130 M.T. 17,510.00 2,276.30 transportation
Materials
Sand crusher 0.270 Cum. 1,607.25 433.95
Water 150.000 Ltr. 0.36 54.00
Scaffolding material 3 % of Scaffolding labour 27.30
Total 13,157.95
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,973.69
Grand Total 15,131.64

C2( 5-1-B2 & First class chimney brick masonry work in (1:4) cement
3.04 Cum. 11,838.13 13,613.84
5-2A) sand mortar in G. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 940.00 1,410.00
Labour Unskilled 2.200 Nos. 650.00 1,430.00
Unskilled ( for Scaffolding ) 0.200 Nos. 650.00 130.00
Brick chimney 476.000 Nos. 13.90 6,616.40
with
Cement 0.100 M.T. 17,510.00 1,751.00 transportation
Materials
Sand crusher 0.280 Cum. 1,607.25 450.03
Water 130.000 Ltr. 0.36 46.80
Scaffolding material 3 % of Scaffolding labour 3.90
Total 11,838.13
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,775.71
Grand Total 13,613.84

C25-1-B2 & First class chimney brick masonry work in (1:4) cement
3.05 Cum. 12,172.88 13,998.81
5-2B) sand mortar in F. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 940.00 1,410.00
Labour Unskilled 2.200 Nos. 650.00 1,430.00
Unskilled 0.700 Nos. 650.00 455.00
Brick chimney 476.000 Nos. 13.90 6,616.40
with
Cement 0.100 M.T. 17,510.00 1,751.00 transportation
Materials
Sand crusher 0.280 Cum. 1,607.25 450.03
Water 130.000 Ltr. 0.36 46.80
Scaffolding material 3 % of Scaffolding labour 13.65
Total 12,172.88
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,825.93
Grand Total 13,998.81

C2(5-1-B2 First class chimney brick masonry work in (1:4) cement


3.06 Cum. 12,641.53 14,537.75
& 5-2B) sand mortar in S. F.
Resources Level/Type Quantity Unit Rate Amount Remarks

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 24 of 79

Skilled 1.500 Nos. 940.00 1,410.00


Labour Unskilled 2.200 Nos. 650.00 1,430.00
Unskilled 1.400 Nos. 650.00 910.00
Brick chimney 476.000 Nos. 13.90 6,616.40
with
Cement 0.100 M.T. 17,510.00 1,751.00 transportation
Materials
Sand crusher 0.280 Cum. 1,607.25 450.03
Water 130.000 Ltr. 0.36 46.80
Scaffolding material 3 % of Scaffolding labour 27.30
Total 12,641.53
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,896.22
Grand Total 14,537.75

C2(5-1-B3 First class chimney brick masonry work in (1:6) cement


3.07 Cum. 11,334.17 13,034.29
& 5-2A) sand mortar in G. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.5000 Nos. 940.00 1,410.00
Labour Unskilled 2.2000 Nos. 650.00 1,430.00
Unskilled ( for Scaffolding ) 0.2000 Nos. 650.00 130.00
Brick chimney 476.0000 Nos. 13.90 6,616.40
with
Cement 0.0700 M.T. 17,510.00 1,225.70 transportation
Materials
Sand crusher 0.3000 Cum. 1,607.25 482.17
Water 100.0000 Ltr. 0.36 36.00
3 % of Scaffolding labour 3.90
Total 11,334.17
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,700.12
Grand Total 13,034.29

C2(5-1-B3 & First class chimney brick masonry work in (1:6) cement
3.08 Cum. 11,668.92 13,419.25
5-2B) sand mortar in F. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 940.00 1,410.00
Labour Unskilled 2.200 Nos. 650.00 1,430.00
Unskilled 0.700 Nos. 650.00 455.00
Brick chimney 476.000 Nos. 13.90 6,616.40
with
Cement 0.070 M.T. 17,510.00 1,225.70 transportation
Materials
Sand crusher 0.300 Cum. 1,607.25 482.17
Water 100.000 Ltr. 0.36 36.00
Scaffolding material 3 % of Scaffolding labour 13.65
Total 11,668.92
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,750.33
Grand Total 13,419.25

C2( 5-1-B3 & First class chimney brick masonry work in (1:6) cement
3.09 Cum. 12,137.57 13,958.20
5-2B) sand mortar in S F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 940.00 1,410.00
Labour Unskilled 2.200 Nos. 650.00 1,430.00
Unskilled 1.400 Nos. 650.00 910.00
Brick chimney 476.000 Nos. 13.90 6,616.40
with
Cement 0.070 M.T. 17,510.00 1,225.70 transportation
Materials
Sand crusher 0.300 Cum. 1,607.25 482.17
Water 100.000 Ltr. 0.36 36.00
Scaffolding material 3 % of Scaffolding labour 27.30
Total 12,137.57
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,820.63
Grand Total 13,958.20

C2(5-1-B6 & First class chimney brick masonry work in mud mortar in
3.10 Cum. 9,004.34 10,354.99
5-2A) G. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 940.00 940.00
Labour Unskilled 1.700 Nos. 650.00 1,105.00
Unskilled 0.200 Nos. 650.00 130.00
Brick chimney 476.000 Nos. 13.90 6,616.40
Mud 0.420 Cum. 412.00 173.04
Materials
Water 100.000 Ltr. 0.36 36.00
Scaffolding material 3 % of Scaffolding labour 3.90
Total 9,004.34
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,350.65
Grand Total 10,354.99

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 25 of 79

C2( 5-1-B6 & First class chimney brick masonry work in mud mortar in
3.11 Cum. 9,339.09 10,739.95
5-2B) F. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 940.00 940.00
Labour Unskilled 1.700 Nos. 650.00 1,105.00
Unskilled 0.700 Nos. 650.00 455.00
Brick chimney 476.000 Nos. 13.90 6,616.40
Mud 0.420 Cum. 412.00 173.04
Materials
Water 100.000 Ltr. 0.36 36.00
Scaffolding material 3 % of Scaffolding labour 13.65
Total 9,339.09
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,400.86
Grand Total 10,739.95

C2(5-1-B6 & First class chimney brick masonry work in mud mortar in
3.12 Cum. 9,807.74 11,278.90
5-2B) S. F.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 940.00 940.00
Labour Unskilled 1.700 Nos. 650.00 1,105.00
Unskilled 1.400 Nos. 650.00 910.00
Brick chimney 476.000 Nos. 13.90 6,616.40
Mud 0.420 Cum. 412.00 173.04
Materials
Water 100.000 Ltr. 0.36 36.00
Scaffolding material 3 % of Scaffolding labour 27.30
Total 9,807.74
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,471.16
Grand Total 11,278.90

R.R. stone masonry work in cement sand (1:3) mortar


3.13 C6( 6-1-1A) Cum. 11,401.68 13,111.93

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.500 Nos. 940.00 1,410.00
Labour
Unskilled 5.000 Nos. 650.00 3,250.00
Cement 0.194 M.T. 17,510.00 3,396.94
Sand crusher 0.420 Cum. 1,607.25 675.04
Materials Stone block 1.000 Cum. 2,420.50 2,420.50
Stone bond 0.100 Cum. 2,060.00 206.00
Water 120.000 Ltr. 0.36 43.20
Total 11,401.68
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,710.25
Grand Total 13,111.93

3.14 C6( 6-1-1B) R.R. stone masonry work in cement sand (1:4) mortar Cum. 10,829.85 12,454.32
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 940.00 1,410.00
Labour
Unskilled 5.000 Nos. 650.00 3,250.00
Cement 0.159 M.T. 17,510.00 2,784.09
Sand crusher 0.450 Cum. 1,607.25 723.26
Materials Stone block 1.000 Cum. 2,420.50 2,420.50
Stone bond 0.100 Cum. 2,060.00 206.00
Water 100.000 Ltr. 0.36 36.00
Total 10,829.85
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,624.47
Grand Total 12,454.32

3.15 C6( 6-1-1C) R.R. stone masonry work in cement sand (1:6) mortar Cum. 9,923.16 11,411.63
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 940.00 1,410.00
Labour
Unskilled 5.000 Nos. 650.00 3,250.00
Cement 0.106 M.T. 17,510.00 1,856.06
Sand crusher 0.470 Cum. 1,607.25 755.40
Materials
Stone block 1.000 Cum. 2,420.50 2,420.50
Stone bond 0.100 Cum. 2,060.00 206.00
Water 70.000 Ltr. 0.36 25.20
Total 9,923.16
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,488.47
Grand Total 11,411.63

Aslar (Crused stone) stone masonry work in cement sand


3.14a C6( 6-1-1B) (1:4) mortar Cum. 10,334.35 11,884.50

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.500 Nos. 940.00 1,410.00
Labour
Unskilled 5.000 Nos. 650.00 3,250.00
Cement 0.159 M.T. 17,510.00 2,784.09

Materials

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 26 of 79

Sand crusher 0.450 Cum. 1,307.25 588.26


Materials
Stone bond 1.100 Cum. 2,060.00 2,266.00
Water 100.000 Ltr. 0.36 36.00
Total 10,334.35
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,550.15
Grand Total 11,884.50

3.15a C6( 6-1-1C) Aslar (Crused stone)stone masonry work in cement sand Cum. 9,421.66 10,834.90
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 940.00 1,410.00 1.50
Labour
Unskilled 5.000 Nos. 650.00 3,250.00 3.00
Cement 0.106 M.T. 17,510.00 1,856.06 0.04
Materials Sand crusher 0.470 Cum. 1,307.25 614.40 0.42
Stone bond 1.100 Cum. 2,060.00 2,266.00 1.10
Water 70.000 Ltr. 0.36 25.20
Total 9,421.66
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,413.24
Grand Total 10,834.90

3.16 C6( 6-2-1) R.R. stone masonry work for dry wall Cum. 4,866.50 5,596.47
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 940.00 940.00
Labour
Unskilled 2.000 Nos. 650.00 1,300.00
Stone block 1.000 Cum. 2,420.50 2,420.50
Materials
Stone bond 0.100 Cum. 2,060.00 206.00
Total 4,866.50
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 729.97
Grand Total 5,596.47

3.17 C6( 6-2-2) R.R. stone masonry work in mud mortar Cum. 5,202.04 5,982.34
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 940.00 940.00
Labour
Unskilled 2.250 Nos. 650.00 1,462.50
Stone block 1.000 Cum. 2,420.50 2,420.50
Stone bond 0.100 Cum. 2,060.00 206.00
Materials
Mud 0.420 Cum. 412.00 173.04
Water 70.000 Ltr. 0.36 25.20
Total 5,202.04
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 780.30
Grand Total 5,982.34

3.18 C10( 6-5) Stone filling in trench with proper leveling Cum. 3,807.50 4,378.62
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 1.50 Nos. 650.00 975.00
Stone block 1.00 Cum. 2,420.50 2,420.50
Materials
Stone bond 0.20 Cum. 2,060.00 412.00
Total 3,807.50
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 571.12
Grand Total 4,378.62

D - CEMENT CONCRETE WORK

4.01 D1(7-2B) P.C.C. (1:4:8) work in foundation, wall (River bed) Cum. 8,704.33 10,009.97
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 940.00 940.00
Labour
Unskilled 4.000 Nos. 650.00 2,600.00
Cement 0.170 M.T. 17,510.00 2,976.70
Aggrigate 40 mm-River bed 0.650 Cum. 1,713.75 1,113.93
Materials Aggrigate 20 mm-River bed 0.240 Cum. 1,763.75 423.30
Sand crusher 0.470 Cum. 1,307.25 614.40
Water 100.000 Ltr. 0.36 36.00
Total 8,704.33
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,305.64
Grand Total 10,009.97

4.02 D1(7-2C) P.C.C. (1:3:6) work in foundation, wall (River bed) Cum. 9,587.03 11,025.08
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 940.00 940.00
Labour
Unskilled 4.000 Nos. 650.00 2,600.00
Cement 0.220 M.T. 17,510.00 3,852.20
Aggrigate 40 mm-River bed 0.650 Cum. 1,713.75 1,113.93
Materials Aggrigate 20 mm-River bed 0.240 Cum. 1,763.75 423.30
Sand crusher 0.470 Cum. 1,307.25 614.40
Water 120.000 Ltr. 0.36 43.20
Total 9,587.03
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,438.05
Grand Total 11,025.08

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 27 of 79

4.03 D1(7-2D) P.C.C. (1:2:4) work in foundation, wall (River bed) Cum. 11,263.10 12,952.56
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 940.00 940.00
Labour
Unskilled 4.000 Nos. 650.00 2,600.00
Cement 0.320 M.T. 17,510.00 5,603.20
Aggrigate 40 mm-River bed 0.520 Cum. 1,713.75 891.15
Aggrigate 20 mm-River bed 0.220 Cum. 1,763.75 388.02
Materials
Aggrigate 10 mm-River bed 0.110 Cum. 1,863.75 205.01
Sand crusher 0.445 Cum. 1,307.25 581.72
Water 150.000 Ltr. 0.36 54.00
Total 11,263.10
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,689.46
Grand Total 12,952.56

P.C.C. (1:2:4) for R.C.C. work in slab, beam etc (River bed)
4.04 D2(7-4A) Cum. 13,025.10 14,978.86
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.800 Nos. 940.00 752.00
Labour
Unskilled 7.000 Nos. 650.00 4,550.00
Cement 0.320 M.T. 17,510.00 5,603.20
Aggrigate 40 mm-River bed 0.520 Cum. 1,713.75 891.15
Aggrigate 20 mm-River bed 0.220 Cum. 1,763.75 388.02
Materials
Aggrigate 10 mm-River bed 0.110 Cum. 1,863.75 205.01
Sand crusher 0.445 Cum. 1,307.25 581.72
Water 150.000 Ltr. 0.36 54.00
Total 13,025.10
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,953.76
Grand Total 14,978.86

P.C.C. (1:1½:3) for R.C.C. work in slab, beam etc (River


4.05 D2(7-4B) bed) Cum. 14,479.39 16,651.29

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.800 Nos. 940.00 752.00
Labour
Unskilled 7.000 Nos. 650.00 4,550.00
Cement 0.400 M.T. 17,510.00 7,004.00
Aggrigate 20 mm-River bed 0.570 Cum. 1,763.75 1,005.33
Materials Aggrigate 10 mm-River bed 0.290 Cum. 1,863.75 540.48
Sand crusher 0.425 Cum. 1,307.25 555.58
Water 200.000 Ltr. 0.36 72.00
Total 14,479.39
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,171.90
Grand Total 16,651.29

P.C.C. (1:1:2) for R.C.C. work in slab, beam etc (River bed)
4.06 D2(7-4C) Cum. 18,166.86 20,891.88

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.800 Nos. 940.00 752.00
Labour
Unskilled 7.000 Nos. 650.00 4,550.00
Cement 0.610 M.T. 17,510.00 10,681.10
Aggrigate 20 mm-River bed 0.640 Cum. 1,763.75 1,128.80
Materials Aggrigate 10 mm-River bed 0.210 Cum. 1,863.75 391.38
Sand crusher 0.425 Cum. 1,307.25 555.58
Water 300.000 Ltr. 0.36 108.00
Total 18,166.86
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,725.02
Grand Total 20,891.88

P.C.C. (1:3:6) work (USED MACHINE) in foundation, wall


4.07 D3(A) (River bed) Cum. 9,415.37 10,827.67

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 940.00 470.00
Labour
Unskilled 3.500 Nos. 650.00 2,275.00
Cement 0.220 M.T. 17,510.00 3,852.20
Aggrigate 40 mm-River bed 0.650 Cum. 1,713.75 1,113.93
Aggrigate 20 mm-River bed 0.240 Cum. 1,763.75 423.30
Materials Sand crusher 0.425 Cum. 1,307.25 555.58
Water 100.000 Ltr. 0.36 36.00
Diesel 3.000 Ltr. 104.54 313.62
Petrol 0.100 Ltr. 113.81 11.38
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 489.25 293.55 Previous year
Equipment
Vibrator 0.250 Hour 283.25 70.81
Total 9,415.37
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,412.30
Grand Total 10,827.67

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 28 of 79

P.C.C. (1:2:4) work (USED MACHINE) in foundation, wall


4.08 D3(B) (River bed) Cum. 11,139.26 12,810.14

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 940.00 470.00
Labour
Unskilled 3.500 Nos. 650.00 2,275.00
Cement 0.320 M.T. 17,510.00 5,603.20
Aggrigate 40 mm-River bed 0.520 Cum. 1,713.75 891.15
Aggrigate 20 mm-River bed 0.330 Cum. 1,763.75 582.03
Materials Sand crusher 0.445 Cum. 1,307.25 581.72
Water 130.000 Ltr. 0.36 46.80
Diesel 3.000 Ltr. 104.54 313.62
Petrol 0.100 Ltr. 113.81 11.38
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 489.25 293.55
Equipment
Vibrator 0.250 Hour 283.25 70.81
Total 11,139.26
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,670.88
Grand Total 12,810.14

P.C.C. (1:1½:3) for R.C.C. work(USED MACHINE) in slab,


4.09 D4(A) beam etc (River bed) Cum. 12,611.75 14,503.51

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 940.00 470.00
Labour
Unskilled 3.500 Nos. 650.00 2,275.00
Cement 0.400 M.T. 17,510.00 7,004.00
Aggrigate 20 mm-River bed 0.570 Cum. 1,763.75 1,005.33
Aggrigate 10 mm-River bed 0.290 Cum. 1,863.75 540.48
Materials Sand crusher 0.425 Cum. 1,307.25 555.58
Water 200.000 Ltr. 0.36 72.00
Diesel 3.000 Ltr. 104.54 313.62
Petrol 0.100 Ltr. 113.81 11.38
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 489.25 293.55
Equipment
Vibrator 0.250 Hour 283.25 70.81
Total 12,611.75
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,891.76
Grand Total 14,503.51

P.C.C. (1:1:2) for R.C.C. work(USED MACHINE) in slab,


4.10 D4(B) beam etc (River bed) Cum. 16,299.22 18,744.10

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 940.00 470.00
Labour
Unskilled 3.500 Nos. 650.00 2,275.00
Cement 0.610 M.T. 17,510.00 10,681.10
Aggrigate 20 mm-River bed 0.640 Cum. 1,763.75 1,128.80
Aggrigate 10 mm-River bed 0.210 Cum. 1,863.75 391.38
Materials Sand crusher 0.425 Cum. 1,307.25 555.58
Water 300.000 Ltr. 0.36 108.00
Diesel 3.000 Ltr. 104.54 313.62
Petrol 0.100 Ltr. 113.81 11.38
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 489.25 293.55
Equipment
Vibrator 0.250 Hour 283.25 70.81
Total 16,299.22
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,444.88
Grand Total 18,744.10

P.C.C. (1:1:2) for R.C.C. work in slab (River bed) with micro
4.11 D(5) silica & super plasticiser Cum. 27,894.83 32,079.05

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 940.00 470.00
Labour
Unskilled 3.500 Nos. 650.00 2,275.00
Cement 0.600 M.T. 17,510.00 10,506.00
Aggrigate 20 mm-River bed 0.825 Cum. 1,763.75 1,455.09
Sand crusher 0.412 Cum. 1,307.25 538.58
Super plasticiser 12.000 Ltr. - -
Micro silica 40.000 Kg. 297.67 11,906.80
Materials Water 150.000 Ltr. 0.36 54.00
Diesel 3.000 Ltr. 104.54 313.62
Petrol 0.100 Ltr. 113.81 11.38
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 489.25 293.55
Vibrator 0.250 Hour 283.25 70.81
Total 27,894.83
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 4,184.22
Grand Total 32,079.05

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 29 of 79

P.C.C. (1:4:8) work in foundation, wall (crushed or stone


4.12 D1(7-2B) ballast) Cum. 9,945.60 11,437.44

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 940.00 940.00
Labour
Unskilled 4.000 Nos. 650.00 2,600.00
Cement 0.170 M.T. 17,510.00 2,976.70

Aggrigate 40 mm-crushed/ballast stone 0.650 Cum. 2,950.00 1,917.50


Materials
Aggrigate 20 mm-crushed/ballast stone 0.240 Cum. 3,000.00 720.00
Sand Crusher ( Badahari Khola) 0.470 Cum. 1,607.25 755.40
Water 100.000 Ltr. 0.36 36.00
Total 9,945.60
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,491.84
Grand Total 11,437.44

P.C.C. (1:3:6) work in foundation, wall (crushed or stone


4.13 D1(7-2C) ballast) Cum. 10,828.30 12,452.54

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 940.00 940.00
Labour
Unskilled 4.000 Nos. 650.00 2,600.00
Cement 0.220 M.T. 17,510.00 3,852.20

Aggrigate 40 mm-crushed/ballast stone 0.650 Cum. 2,950.00 1,917.50


Materials
Aggrigate 20 mm-crushed/ballast stone 0.240 Cum. 3,000.00 720.00
Sand Crusher ( Badahari Khola) 0.470 Cum. 1,607.25 755.40
Water 120.000 Ltr. 0.36 43.20
Total 10,828.30
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,624.24
Grand Total 12,452.54

P.C.C. (1:2:4) work in foundation, wall (crushed or stone


4.14 D1(7-2D) ballast) Cum. 12,447.42 14,314.53

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 940.00 940.00
Labour
Unskilled 4.000 Nos. 650.00 2,600.00
Cement 0.320 M.T. 17,510.00 5,603.20

Aggrigate 40 mm-crushed/ballast stone 0.520 Cum. 2,950.00 1,534.00

Materials Aggrigate 20 mm-crushed/ballast stone 0.220 Cum. 3,000.00 660.00

Aggrigate 10 mm-crushed/ballast stone 0.110 Cum. 3,100.00 341.00


Sand Crusher ( Badahari Khola) 0.445 Cum. 1,607.25 715.22
Water 150.000 Ltr. 0.36 54.00
Total 12,447.42
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,867.11
Grand Total 14,314.53

P.C.C. (1:2:4) for R.C.C. work in slab, beam etc (crushed or


4.15 D2(7-4A) Cum. 13,937.44 16,028.05
stone ballast)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.800 Nos. 940.00 752.00
Labour
Unskilled 7.000 Nos. 650.00 4,550.00
Cement 0.320 M.T. 17,510.00 5,603.20

Aggrigate 40 mm-crushed/ballast stone 0.520 Cum. 2,950.00 1,534.00

Materials Aggrigate 20 mmcrushed/ballast stone 0.220 Cum. 1,763.75 388.02

Aggrigate 10 mm-crushed/ballast stone 0.110 Cum. 3,100.00 341.00


Sand Crusher ( Badahari Khola) 0.445 Cum. 1,607.25 715.22
Water 150.000 Ltr. 0.36 54.00
Total 13,937.44
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,090.61
Grand Total 16,028.05

P.C.C. (1:1½:3) for R.C.C. work in slab, beam etc (crushed


4.16 D2(7-4B) or stone ballast) Cum. 15,670.08 18,020.59

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.800 Nos. 940.00 752.00
Labour
Unskilled 7.000 Nos. 650.00 4,550.00
Cement 0.400 M.T. 17,510.00 7,004.00

Aggrigate 20 mm-crushed/ballast stone 0.570 Cum. 3,000.00 1,710.00


Materials
Aggrigate 10 mm-crushed/ballast stone 0.290 Cum. 3,100.00 899.00

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 30 of 79
Materials

Sand Crusher ( Badahari Khola) 0.425 Cum. 1,607.25 683.08


Water 200.000 Ltr. 0.36 72.00
Total 15,670.08
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,350.51
Grand Total 18,020.59

P.C.C. (1:1:2) for R.C.C. work in slab, beam etc (crushed or


4.17 D2(7-4C) stone ballast) Cum. 19,345.18 22,246.95

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.800 Nos. 940.00 752.00
Labour
Unskilled 7.000 Nos. 650.00 4,550.00
Cement 0.610 M.T. 17,510.00 10,681.10

Aggrigate 20 mm-crushed/ballast stone 0.640 Cum. 3,000.00 1,920.00


Materials
Aggrigate 10 mm-crushed/ballast stone 0.210 Cum. 3,100.00 651.00
Sand Crusher ( Badahari Khola) 0.425 Cum. 1,607.25 683.08
Water 300.000 Ltr. 0.36 108.00
Total 19,345.18
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,901.77
Grand Total 22,246.95

P.C.C. (1:3:6) work (USED MACHINE) in foundation, wall


4.18 D3(A) (crushed or stone ballast) Cum. 10,643.14 12,239.61

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 940.00 470.00
Labour
Unskilled 3.500 Nos. 650.00 2,275.00
Cement 0.220 M.T. 17,510.00 3,852.20

Aggrigate 40 mm-crushed/ballast stone 0.650 Cum. 2,950.00 1,917.50

Materials Aggrigate 20 mm-crushed/ballast stone 0.240 Cum. 3,000.00 720.00


Sand Crusher ( Badahari Khola) 0.425 Cum. 1,607.25 683.08
Water 100.000 Ltr. 0.36 36.00
Diesel 3.000 Ltr. 104.54 313.62
Petrol 0.100 Ltr. 113.81 11.38
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 489.25 293.55
Equipment
Vibrator 0.250 Hour 283.25 70.81
Total 10,643.14
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,596.47
Grand Total 12,239.61

P.C.C. (1:2:4) work (USED MACHINE) in foundation, wall


4.19 D3(B) (crushed or stone ballast) Cum. 12,323.58 14,172.11

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 940.00 470.00
Labour
Unskilled 3.500 Nos. 650.00 2,275.00
Cement 0.320 M.T. 17,510.00 5,603.20

Aggrigate 40 mm-crushed/ballast stone 0.520 Cum. 2,950.00 1,534.00

Materials Aggrigate 20 mm-crushed/ballast stone 0.330 Cum. 3,000.00 990.00


Sand Crusher ( Badahari Khola) 0.445 Cum. 1,607.25 715.22
Water 130.000 Ltr. 0.36 46.80
Diesel 3.000 Ltr. 104.54 313.62
Petrol 0.100 Ltr. 113.81 11.38
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 489.25 293.55
Equipment
Vibrator 0.250 Hour 283.25 70.81
Total 12,323.58
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,848.53
Grand Total 14,172.11

P.C.C. (1:1½:3) for R.C.C. work(USED MACHINE) in slab,


4.20 D4(A) beam etc (crushed or stone ballast) Cum. 13,802.44 15,872.80

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 940.00 470.00
Labour
Unskilled 3.500 Nos. 650.00 2,275.00
Cement 0.400 M.T. 17,510.00 7,004.00

Aggrigate 20 mm-crushed/ballast stone 0.570 Cum. 3,000.00 1,710.00

Materials Aggrigate 10 mm-crushed/ballast stone 0.290 Cum. 3,100.00 899.00


Sand Crusher ( Badahari Khola) 0.425 Cum. 1,607.25 683.08
Water 200.000 Ltr. 0.36 72.00

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Materials Rate_Analysis_Dhanusha_Civil_2075/076 Page 31 of 79

Diesel 3.000 Ltr. 104.54 313.62


Petrol 0.100 Ltr. 113.81 11.38
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 489.25 293.55
Equipment
Vibrator 0.250 Hour 283.25 70.81
Total 13,802.44
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,070.36
Grand Total 15,872.80

P.C.C. (1:1:2) for R.C.C. work(USED MACHINE) in slab,


4.21 D4(B) beam etc (crushed or stone ballast) Cum. 17,477.54 20,099.17

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 940.00 470.00
Labour
Unskilled 3.500 Nos. 650.00 2,275.00
Cement 0.610 M.T. 17,510.00 10,681.10

Aggrigate 20 mm-crushed/ballast stone 0.640 Cum. 3,000.00 1,920.00

Materials Aggrigate 10 mm-crushed/ballast stone 0.210 Cum. 3,100.00 651.00


Sand Crusher ( Badahari Khola) 0.425 Cum. 1,607.25 683.08
Water 300.000 Ltr. 0.36 108.00
Diesel 3.000 Ltr. 104.54 313.62
Petrol 0.100 Ltr. 113.81 11.38
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 489.25 293.55
Equipment
Vibrator 0.250 Hour 283.25 70.81
Total 17,477.54
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,621.63
Grand Total 20,099.17

P.C.C. (1:1:2) for R.C.C. work in slab (crushed or stone


4.22 D(5) ballast) with micro silica & super plasticiser Cum. 29,038.34 33,394.09

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 940.00 470.00
Labour
Unskilled 3.500 Nos. 650.00 2,275.00
Cement 0.600 M.T. 17,510.00 10,506.00

Aggrigate 20 mm-crushed/ballast stone 0.825 Cum. 3,000.00 2,475.00


Sand Crusher ( Badahari Khola) 0.412 Cum. 1,607.25 662.18
Super plasticiser 12.000 Ltr. - -
Materials Micro silica 40.000 Kg. 297.67 11,906.80
Water 150.000 Ltr. 0.36 54.00
Diesel 3.000 Ltr. 104.54 313.62
Petrol 0.100 Ltr. 113.81 11.38
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 489.25 293.55

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Materials

Rate_Analysis_Dhanusha_Civil_2075/076 Page 32 of 79

Vibrator 0.250 Hour 283.25 70.81


Total 29,038.34
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 4,355.75
Grand Total 33,394.09

Torsteel reinforcement bar for R.C.C. work with cutting,


4.23 D9(7-5) bending, binding & laying with all complete. Kg. 113.32 130.32

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 12.000 Nos. 940.00 11,280.00
Labour
Unskilled 12.000 Nos. 650.00 7,800.00
TOR/TMT reinforcement bar 1.050 M.T. 88,580.00 93,009.00
Materials
Binding wire 10.000 Kg. 123.60 1,236.00
Total 113,325.00
Rate analysis for : 1.00 MT 15 % Contractor overhead 16,998.75
Grand Total 130,323.75
E - FORM & PROPS WORK

Form work shuttering & centering (COLUMN) with (USED


5.01 E1(8-3A) LOCAL WOOD) all complete. Sqm. 1,142.61 1,314.00

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 3.748 Nos. 940.00 3,523.12 Scrap value .
Labour
Unskilled 5.622 Nos. 650.00 3,654.30 75x.526/6=
Wood Local 0.070 Cum. 56,650.00 3,965.50 0.07
Materials
Killa 2.500 Kg. 113.30 283.25
Total 11,426.17
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 1,713.92
Grand Total 13,140.09

Form work shuttering & centering (COLUMN) with (USED


5.02 E2(51B) PLY WOOD) all complete. Sqm. 612.97 704.91

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.574 Nos. 940.00 1,479.56
Labour
Unskilled 2.361 Nos. 650.00 1,534.65
Ply board 19 mm thick 0.693 Sqm. 1,297.80 899.37
Wood Local 0.019 Cum. 56,650.00 1,076.35
Materials
MS Black pipe(MNB 50-M) 0.540 Nos. 1,586.20 856.54
Killa 2.500 Kg. 113.30 283.25
Total 6,129.72
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 919.45
Grand Total 7,049.17

Form work shuttering & centering (BEAM-0.30 Mtr) with


5.03 E3(8-4A) (USED LOCAL WOOD) all complete. Sqm. 1,190.87 1,369.50

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 4.000 Nos. 940.00 3,760.00
Labours
Unskilled 6.000 Nos. 650.00 3,900.00
Wood Local 0.070 Cum. 56,650.00 3,965.50
Materials
Killa 2.500 Kg. 113.30 283.25
Total 11,908.75
Rate analysis for : 10.00 Sqm. 15 % Contractor Overhead 1,786.31
Grand Total 13,695.06

Form work shuttering & centering (BEAM-0.30-0.80 Mtr)


5.04 E4(8-4B) with (USED LOCAL WOOD) all complete. Sqm. 935.85 1,076.23

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 2.670 Nos. 940.00 2,509.80
Labours
Unskilled 4.000 Nos. 650.00 2,600.00
Wood Local 0.070 Cum. 56,650.00 3,965.50
Materials
Killa 2.500 Kg. 113.30 283.25
Total 9,358.55
Rate analysis for : 10.00 Sqm. 15 % Contractor Overhead 1,403.78
Grand Total 10,762.33

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 33 of 79

Form work shuttering & centering (COLUMN) with (USED


5.05 E5(51A) PLY WOOD) all complete. Sqm. 1,199.95 1,379.94

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 2.670 Nos. 940.00 2,509.80
Labour
Unskilled 4.000 Nos. 650.00 2,600.00
Ply board 19 mm thick 1.650 Sqm. 669.50 1,104.67
Wood Local 0.040 Cum. 56,650.00 2,266.00
Materials
MS Black pipe(MNB 50-M) 2.040 Nos. 1,586.20 3,235.84 0.40*5.10
Killa 2.500 Kg. 113.30 283.25
Total 11,999.56
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 1,799.93
Grand Total 13,799.49

Form work shuttering & centering with MS pipe (prop),


5.06 E6(8-4A) plyboard for slab etc Sqm. 954.89 1,098.12

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 17.200 Nos. 940.00 16,168.00
Labours
Unskilled 25.700 Nos. 650.00 16,705.00
Ply board 19 mm thick 16.500 Sqm. 669.50 11,046.75
Wood Local 0.232 Cum. 56,650.00 13,142.80
Materials 4.40*5.10
MS Black pipe(MNB 50-M) 22.440 Nos. 1,586.20 35,594.32
Killa 25.000 Kg. 113.30 2,832.50
Total 95,489.37
Rate analysis for : 100.00 Sqm. 15 % Contractor Overhead 14,323.40
Grand Total 109,812.77

gf]6 M sf7 M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
1.6875x1.1x0.75/6= 0.232
M KNffO{ M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 !)Ü d"No afFsL /xg] lx;fan] ul/Psf]
100x1.1x0.9/6=16.5
M kfO{k M !% k6s;Dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
88/15x0.75 =4.4
gf]6 M sf7 M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
0.155/6x0.75=0.019
M KNffO{ M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 !)Ü d"No afFsL /xg] lx;fan] ul/Psf]
4.62/6x0.90=0.693
M kmnfd] af]N6 M !% k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
10.68/15x0.75=0.54
sf7 M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
33.33/6*0.75=4.16*0.0254=0.105
sf7 M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
2.03/6*0.75=0.25375

Form work shuttering & centering with Bamboo, plyboard


5.06(A) E6(8-4A) for slab etc Sqm. 454.65 522.85

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 10.560 Nos. 940.00 9,926.40 60% of17.2
Labours
Unskilled 10.380 Nos. 650.00 6,747.00 60% of17.3
Ply board 19 mm thick 16.500 Sqm. 669.50 11,046.75
Wood Local 0.232 Cum. 56,650.00 13,142.80
Materials
Bamboo 6.250 Nos. 283.25 1,770.31 6.25
Killa 25.000 Kg. 113.30 2,832.50
Total 45,465.76
Rate analysis for : 100.00 Sqm. 15 % Contractor Overhead 6,819.86
Grand Total 52,285.62

gf]6 M sf7 M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
1.6875x1.1x0.75/6= 0.232
M KNffO{ M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 !)Ü d"No afFsL /xg] lx;fan] ul/Psf]
100x1.1x0.9/6=16.5
af; M ^ k6s;dd k|of]u ug{ ;lsg] To;kl5 @%Ü d"No afFsL /xg] lx;fan] ul/Psf]
(100*3/6)/6*0.75 =6.25

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 34 of 79

5.07 E12(8-13A) Trench work open type form work (up to 1.50 Mtr.) Sqm. 207.20 238.28

Resources Quantity Unit Rate Amount Remarks


Level/Type
Skilled 0.250 Nos. 940.00 235.00
Labours
Unskilled 0.250 Nos. 650.00 162.50
Wood Local 0.105 Cum. 56,650.00 5,948.25
Materials
Wood Local 0.25375 Cum. 56,650.00 14,374.93
Total 20,720.68
Rate analysis for : 100.00 Sqm. 15 % Contractor Overhead 3,108.10
Grand Total 23,828.78

5.08 E12(8-13B) Trench work open type form work ( 1.50 to 3.00 Mtr.) Sqm. 214.43 246.59
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.500 Nos. 940.00 470.00
Labours
Unskilled 1.000 Nos. 650.00 650.00
Wood Local 0.105 Cum. 56,650.00 5,948.25 4.16*0.0254
Materials
Wood Local 0.25375 Cum. 56,650.00 14,374.93
Total 21,443.18
Rate analysis for : 100.00 Sqm. 15 % Contractor Overhead 3,216.47
Grand Total 24,659.65

5.09 E13(8-13C) Trench work open type form work (above 3.00 Mtr.) Sqm. 224.00 257.60
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 940.00 940.00
Labours
Unskilled 1.750 Nos. 650.00 1,137.50
Wood Local 0.105 Cum. 56,650.00 5,948.25 4.16*0.0254
Materials
Wood Local 0.25375 Cum. 56,650.00 14,374.93
Total 22,400.68
Rate analysis for : 100.00 Sqm. 15 % Contractor Overhead 3,360.10
Grand Total 25,760.78

gf]6 M !Æ j/fj/ @=%$ ;]=dL= kmn]ssf] lx;fj ul/Psf] sf7x? ^ k6s;Dd k|of]u u/L;s]kl5 @%Ü d"No afFsL x'g] u/L lx;
F - ROOFING WORK

26 (H) 0.41 mm thick colored C.G.I. sheet roofing work


6.01 F1( 9-1) Sqm. 1,358.33 1,562.08
(65kg/bandal)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.100 Nos. 940.00 1,034.00
Labour
Unskilled 1.250 Nos. 650.00 812.50
CGI sheet 26 (H) 0.41 mm thick Plane 12.000 Sqm. 793.10 9,517.20
Nutbolt 8 mm. 30.000 Nos. 18.54 556.20
Materials
J-hook 25.000 Nos. 59.74 1,493.50
Bitumen washer 55.000 Nos. 3.09 169.95
Total 13,583.35
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 2,037.50
Grand Total 15,620.85

26 (H) 0.41mm thick plane C.G.I. sheet roofing work


6.02 F1( 9-1) (62kg/bandal) Sqm. 1,210.01 1,391.51

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.100 Nos. 940.00 1,034.00
Labour
Unskilled 1.250 Nos. 650.00 812.50
CGI sheet 26 (H) 0.41 mm thick Plane 12.000 Sqm. 669.50 8,034.00
Nutbolt 8 mm. 30.000 Nos. 18.54 556.20
Materials
J-hook 25.000 Cum. 59.74 1,493.50
Bitumen washer 55.000 Nos. 3.09 169.95
Total 12,100.15
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 1,815.02
Grand Total 13,915.17

26 (L) 0.35mm thick plane C.G.I. sheet roofing work


6.03 F1( 9-1) Sqm. 861.17 990.35
(55kg/bandal)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.100 Nos. 940.00 1,034.00
Labour
Unskilled 1.250 Nos. 650.00 812.50
CGI sheet 26 (L) 0.35 mm thick Plane 12.000 Sqm. 378.80 4,545.60
Nutbolt 8 mm. 30.000 Nos. 18.54 556.20
Materials

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 35 of 79

Materials
J-hook 25.000 Nos. 59.74 1,493.50
Bitumen washer 55.000 Nos. 3.09 169.95
Total 8,611.75
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 1,291.76
Grand Total 9,903.51

26 (H) 0.41 mm thick colour C.G.I. sheet roofing work


6.04 F3( 9-1) Sqm. 808.31 929.56
(65kg/bandal)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.100 Nos. 940.00 1,034.00
Labour
Unskilled 1.250 Nos. 650.00 812.50
CGI sheet 26 (H) 0.41 mm thick colour 12.000 Sqm. 334.75 4,017.00
Nutbolt 8 mm. 30.000 Nos. 18.54 556.20
Materials
J-hook 25.000 Nos. 59.74 1,493.50
Bitumen washer 55.000 Nos. 3.09 169.95
Total 8,083.15
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 1,212.47
Grand Total 9,295.62

26 (M) 0.38mm thick colour C.G.I. sheet roofing work


6.05 F3( 9-1) (62kg/bandal) Sqm. 1,016.68 1,169.18

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.100 Nos. 940.00 1,034.00
Labour
Unskilled 1.250 Nos. 650.00 812.50
CGI sheet 26 (M) 0.38 mm thick colour 12.000 Sqm. 508.39 6,100.68
Nutbolt 8 mm. 30.000 Nos. 18.54 556.20
Materials
J-hook 25.000 Nos. 59.74 1,493.50
Bitumen washer 55.000 Nos. 3.09 169.95
Total 10,166.83
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 1,525.02
Grand Total 11,691.85

28 (H) G.I. plane ridge cover


6.08 F2( 9-2) Rmtr. 631.24 725.92

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 2.000 Nos. 940.00 1,880.00
Labour
Unskilled 3.000 Nos. 650.00 1,950.00
CGI Ridge Cover 12.000 Rmtr.. 202.70 2,432.40
Materials
Nutbolt L.S. 50.00
Total 6,312.40
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 946.86
Grand Total 7,259.26

6.09 F4( 9-2) 26 (L) C.G.I. colour ridge cover Rmtr. 789.70 908.15
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.000 Nos. 940.00 1,880.00
Labour
Unskilled 3.000 Nos. 650.00 1,950.00
CGI Ridge Cover colour 12.000 Rmtr.. 334.75 4,017.00
Materials
Nutbolt L.S. 50.00
Total 7,897.00
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 1,184.55
Grand Total 9,081.55

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 36 of 79

6.11 F5 26 (M) 0.41 mm thick plane G.I. sheet roofing work Rmtr. 948.62 1,090.92

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.100 Nos. 940.00 1,034.00
Labour
Unskilled 1.250 Nos. 650.00 812.50
GI sheet 26 (M) 0.41 mm thick plane 12.000 Sqm. 434.51 5,214.12
J-hook 30.000 Nos. 59.74 1,792.20
Materials
Nut bolt 8 mm 25.000 Nos. 18.54 463.50
Bitumen washer 55.000 Nos. 3.09 169.95
Total 9,486.27
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 1,422.94
Grand Total 10,909.21

6.12 F5 26 (L) 0.35 mm thick plane G.I. sheet roofing work Rmtr. 881.77 1,014.04

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.100 Nos. 940.00 1,034.00
Labour
Unskilled
CGI sheet 26 (L) 0.38 mm thick 1.250 Nos. 650.00 812.50
plain 12.000 Sqm. 378.80 4,545.60
J-hook 30.000 Nos. 59.74 1,792.20
Materials
Nut bolt 8 mm 25.000 Nos. 18.54 463.50
Bitumen washer 55.000 Nos. 3.09 169.95
Total 8,817.75
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 1,322.66
Grand Total 10,140.41

6.13 F6 26 (H) 0.50 mm thick Colour G.I. sheet roofing work Rmtr. 1,271.81 1,462.58

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.100 Nos. 940.00 1,034.00
Labour
Unskilled 1.250 Nos. 650.00 812.50
CGI sheet 26 (H) 0.50 mm thick
colour 12.000 Sqm. 669.50 8,034.00
Materials J-hook 30.000 Nos. 59.74 1,792.20
Nut bolt 8 mm 25.000 Nos. 35.02 875.50
Bitumen washer 55.000 Nos. 3.09 169.95
Total 12,718.15
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 1,907.72
Grand Total 14,625.87

6.14 F6 26 (M) 0.41 mm thick Colour G.I. sheet roofing work Rmtr. 948.62 1,090.92

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.100 Nos. 940.00 1,034.00
Labour
Unskilled 1.250 Nos. 650.00 812.50
GI sheet 26 (M) 0.41 mm thick Colour 12.000 Sqm. 434.51 5,214.12
J-hook 30.000 Nos. 59.74 1,792.20
Materials
Nut bolt 8 mm 25.000 Nos. 18.54 463.50
Bitumen washer 55.000 Nos. 3.09 169.95
Total 9,486.27
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 1,422.94
Grand Total 10,909.21

150 mm breadth upto 450 mm G. I. plane sheet Gutter


6.16 F7 fixing work with 3x40 mm M.S. bracke,t nut bolt & washer Rmtr. 1,137.76 1,308.43
.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.750 Nos. 940.00 1,645.00
Labour
Unskilled 2.000 Nos. 650.00 1,300.00
G. I. plane sheet Gutter 0.50mm thick 13.500 Rmtr 208.37 2,812.99
M.S. bracket 3*40 mm 32.000 Nos. 143.17 4,581.44
Materials
Nut bolt 48.000 Nos. 18.54 889.92
Bitumen washer 48.000 Nos. 3.09 148.32
Total 11,377.67
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 1,706.65
Grand Total 13,084.32

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 37 of 79

150 mm breadth upto 450 mm G. I. colour sheet Gutter


6.17 F7 fixing work with 3x40 mm M.S. bracke,t nut bolt & washer Rmtr. 1,193.87 1,372.95
.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.750 Nos. 940.00 1,645.00
Labour
Unskilled
G. I.Colour plane sheet Gutter 2.000 Nos. 650.00 1,300.00
0.50mm thick 13.500 Rmtr 249.93 3,374.05
M.S. bracket 3*40 mm 32.000 Nos. 143.17 4,581.44
Materials
Nut bolt 48.000 Nos. 18.54 889.92
Bitumen washer 48.000 Nos. 3.09 148.32
Total 11,938.73
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 1,790.81
Grand Total 13,729.54

6.18 F10( 9-6) Clay tile roofing work Rmtr. 569.37 654.78
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.500 Nos. 940.00 470.00
Labour
Unskilled 1.500 Nos. 650.00 975.00
Materials Clay tile 125.000 Nos. 33.99 4,248.75
Total 5,693.75
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 854.06
Grand Total 6,547.81

6.19 F11( 9-7) Clay tile ridge cover Rmtr. 359.66 413.60
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.500 Nos. 940.00 470.00
Labour
Unskilled 0.500 Nos. 650.00 325.00
Materials Clay tile ridge cover 80.000 Nos. 35.02 2,801.60
Total 3,596.60
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 539.49
Grand Total 4,136.09

6.20 F12( 9-8) 100 mm lime concrete (1:1:3) work Sqm. 1,016.77 1,169.29
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 940.00 1,410.00
Labour
Unskilled 12.000 Nos. 650.00 7,800.00
Brick Aggrigate 1.250 Cum. 13.90 17.37
Materials White lime 1.500 Kg. 22.66 33.99
Surkhee 0.400 Cum. 2,266.00 906.40
Total 10,167.76
Rate analysis for : 10.00 Sqm.. 15 % Contractor overhead 1,525.16
Grand Total 11,692.92

6.21 F13( 9-9A) 80 mm thick khar roof with bamboo frame Sqm. 1,530.22 1,759.75
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 940.00 1,410.00
Labour
Unskilled 1.500 Nos. 650.00 975.00
Khar 83.000 Bundle 27.81 2,308.23
Bamboo 30.000 Nos. 283.25 8,497.50
Materials
Dori 3.500 Kg. 144.20 504.70
Chattai 12.000 Sqm. 133.90 1,606.80
Total 15,302.23
Rate analysis for : 10.00 Sqm.. 15 % Contractor overhead 2,295.33
Grand Total 17,597.56

6.22 F13( 9-9B) 150 mm thick khar roof with bamboo frame Sqm. 2,065.92 2,375.81
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 940.00 1,410.00
Labour
Unskilled 1.500 Nos. 650.00 975.00
Khar 166.000 Bundle 27.81 4,616.46
Bamboo 40.000 Nos. 283.25 11,330.00
Materials
Dori 5.000 Kg. 144.20 721.00
Chattai 12.000 Sqm. 133.90 1,606.80
Total 20,659.26
Rate analysis for : 10.00 Sqm.. 15 % Contractor overhead 3,098.89
Grand Total 23,758.15

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 38 of 79

6.23 F14 1.20 mm thick fiber glass corgated sheet roofing work Sqm. 1,599.35 1,839.25
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.100 Nos. 940.00 1,034.00
Labour
Unskilled 1.250 Nos. 650.00 812.50
Fiber glass 1.20 mm thick corgated 12.000 Sqm. 993.95 11,927.40
Nutbolt 8 mm. 30.000 Nos. 18.54 556.20
Materials
J-hook 25.000 Nos. 59.74 1,493.50
Bitumen washer 55.000 Nos. 3.09 169.95
Total 15,993.55
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 2,399.03
Grand Total 18,392.58

6.24 F15 1.20 mm thick fiber glass ridge cover Rmtr. 1,106.51 1,272.49
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.00 Nos. 940.00 1,880.00
Labour
Unskilled
Fiber glass 1.20 mm thick ridge 3.00 Nos. 650.00 1,950.00
cover (0.60m width) 12.00 Rmtr. 598.77 7,185.18
Materials
Nutbolt L.S. 50.00
Total 11,065.18
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 1,659.77
Grand Total 12,724.95

Readymade colour concrete tile laying work on cement


6.25 F18 Sqm. 774.26 890.40
sand (1:4) screeding
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 940.00 940.00
Labour
Unskilled 2.000 Nos. 650.00 1,300.00
Cement 0.024 M.T. 17,510.00 420.24
Sand Crusher ( Badahari Khola) 0.090 Cum. 1,307.25 117.65
Materials Readymade colour concrete tile
I,,bambai,cadbari design floor
tile(10"x10"x1.5"=40.00rs 175.000 Nos. 28.37 4,964.75
Total 7,742.64
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 1,161.40
Grand Total 8,904.04

6.26 F19( 10-17) Making and fixing of Sal wood beam, lintel, etc Cum. 249,816.75 287,289.26
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 17.650 Nos. 940.00 16,591.00
Labour
Unskilled 1.760 Nos. 650.00 1,144.00
Wood Sal 1.050 Cum. 220,935.00 231,981.75
Materials
Killas L.S. 100.00
Total 249,816.75
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 37,472.51
Grand Total 287,289.26

6.27 F20(10-19) Making and fixing of 25 mm sal wood eaves board Sqm. 6,229.42 7,163.84
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.430 Nos. 940.00 1,344.20
Labour
Unskilled 0.143 Nos. 650.00 92.95
Wood Sal 0.275 Cum. 220,935.00 60,757.12
Materials
Killas L.S. 100.00
Total 62,294.27
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 9,344.14
Grand Total 71,638.41

6.28 F22 2 mm thick UPVC roofing sheet roofing work Sqm. - -


Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 940.00 1,410.00
Labour
Unskilled 1.000 Nos. 650.00 650.00
UPVC roofing sheet 2 mm thick 12.000 Sqm. - -
Materials Clip 14.000 Nos. 59.74 836.36
Self Taping Screw 3" 28.000 Nos. 8.75 245.00
Total -
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead -
Grand Total -

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 39 of 79

6.29 F23 3 mm thick UPVC roofing sheet roofing work Sqm. 2,353.53 2,706.56
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 940.00 1,410.00
Labour
Unskilled 1.000 Nos. 650.00 650.00
UPVC roofing sheet 3 mm thick 12.000 Sqm. 1,699.50 20,394.00
Materials Clip 14.000 Nos. 59.74 836.36
Self Taping Screw 3" 28.000 Nos. 8.75 245.00
Total 23,535.36
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 3,530.30
Grand Total 27,065.66

G - DOOR & WINDOW WORK

7.01 G1(10-1) Sal wood works for chaukhats with all complete. Cum. 282,361.54 324,715.77
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 34.000 Nos. 940.00 31,960.00
Labour
Unskilled 3.400 Nos. 650.00 2,210.00
Wood Sal 1.100 Nos. 220,935.00 243,028.50
Materials Hold fast 92.000 Nos. 51.50 4,738.00
pech killas 184.000 Nos. 2.31 425.04
Total 282,361.54
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 42,354.23
Grand Total 324,715.77

7.02 G1(10-1) Local wood works for chaukhats with all complete. Cum. 101,648.04 116,895.24
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 34.000 Nos. 940.00 31,960.00
Labour
Unskilled 3.400 Nos. 650.00 2,210.00
Wood Local 1.100 Nos. 56,650.00 62,315.00
Materials Hold fast 92.000 Nos. 51.50 4,738.00
pech killas 184.000 Nos. 2.31 425.04
Total 101,648.04
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 15,247.20
Grand Total 116,895.24

38 mm thick sal wood fully paneled shutter fixing work with all
7.03 G2(10-2) complete. Size of shutter 1.07 x 1.982 =2.114 Sqm. Sqm. 14,932.61 17,172.50

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 10.000 Nos. 940.00 9,400.00
Labour
Unskilled 1.000 Nos. 650.00 650.00
Wood Sal 0.084 Cum. 220,935.00 18,558.54
Hinge 100 mm 6.000 Nos. 46.35 278.10
Towerbolt 150 mm. 1.000 Nos. 103.00 103.00
Materials Towerbolt 300 mm. 1.000 Nos. 185.40 185.40
Lockingset 250-300mm. 1.000 Nos. 2,163.00 2,163.00
Handle 2.000 Nos. 77.25 154.50
Pech killas L.S. 75.00
Total 31,567.54
Rate analysis for : 2.114 Sqm. 15 % Contractor overhead 4,735.13
Grand Total 36,302.67

38 x 75 mm thick sal wood frame with 4 mm thick fully glazed


7.04 G3(10-4) shutter fixing work with all complete. Size of shutter 1.829 x Sqm. 9,653.11 11,101.07
1.22 =2.23 Sqm.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 9.000 Nos. 940.00 8,460.00
Labour
Unskilled 0.900 Nos. 650.00 585.00
Wood Sal 0.049 Cum. 220,935.00 10,825.81
Glass 4 mm thick-Plane 1.085 Sqm. 782.80 849.33
Hinge 75 mm 8.000 Nos. 41.20 329.60
Materials
Towerbolt 100 mm. 4.000 Nos. 61.80 247.20
Handle 2.000 Nos. 77.25 154.50
Pech killas L.S. 75.00
Total 21,526.44
Rate analysis for : 2.23 Sqm. 15 % Contractor overhead 3,228.96
Grand Total 24,755.40

38 x 75 mm thick sal wood frame with 3 mm thick fully glazed


7.04a G3(10-4) shutter fixing work with all complete. Size of shutter 1.829 x Sqm. 9,613.02 11,054.97
1.22 =2.23 Sqm.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 9.000 Nos. 940.00 8,460.00
Labour
Unskilled 0.900 Nos. 650.00 585.00
Wood Sal 0.049 Cum. 220,935.00 10,825.81
Glass 3 mm thick-Plane 1.085 Sqm. 700.40 759.93

Materials

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 40 of 79

Hinge 75 mm 8.000 Sqm. 41.20 329.60


Materials
Towerbolt 100 mm. 4.000 Cum. 61.80 247.20
Handle 2.000 Nos. 77.25 154.50
Pech killas L.S. 75.00
Total 21,437.04
Rate analysis for : 2.23 Sqm. 15 % Contractor overhead 3,215.55
Grand Total 24,652.59

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 41 of 79

38 x 75 mm thick Gamhair wood frame with 4 mm thick fully


7.05 G3(10-4) glazed shutter fixing work with all complete. Size of shutter Sqm. 6,213.17 7,145.14
1.829 x 1.22 =2.23 Sqm.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 9.000 Nos. 940.00 8,460.00
Labour
Unskilled 0.900 Nos. 650.00 585.00
Wood Gamhair 0.049 Cum. 64,382.77 3,154.75
Glass 4 mm thick-Plane 1.085 Sqm. 782.80 849.33
Hinge 75 mm 8.000 Nos. 41.20 329.60
Materials
Towerbolt 100 mm. 4.000 Nos. 61.80 247.20
Handle 2.000 Nos. 77.25 154.50
Pech killas L.S. 75.00
Total 13,855.38
Rate analysis for : 2.23 Sqm. 15 % Contractor overhead 2,078.30
Grand Total 15,933.68

38 mm thick sal wood frame with 4 mm thick commercial


7.06 G4(10-7) plywood (bothside) flush shutter fixing with all comolete. Sqm. 7,840.88 9,017.01
Size of shutter 1.092 x 2.058 =2.245 Sqm.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 7.000 Nos. 940.00 6,580.00
Labour
Unskilled 0.700 Nos. 650.00 455.00
Wood Sal 0.0346 Cum. 220,935.00 7,644.35
Ply wood 4 mm thick commercial 4.650 Sqm. 324.45 1,508.69
Hinge 100 mm 3.000 Nos. 46.35 139.05
Materials
Towerbolt 150 mm. 2.000 Nos. 103.00 206.00
Mortice lock(Brass) 1.000 Nos. 1,019.70 1,019.70
Pech killas L.S. 50.00
Total 17,602.79
Rate analysis for : 2.245 Sqm. 15 % Contractor overhead 2,640.41
Grand Total 20,243.20

38 mm thick sal wood frame with 3 mm thick TEAK


plywood (Both side ) flush shutter fixing with all comolete.
7.07 G4(10-8) Sqm. 7,840.88 9,017.01
Size of shutter 1.092 x 2.058 =2.245 Sqm.

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 7.000 Nos. 940.00 6,580.00
Labour
Unskilled 0.700 Nos. 650.00 455.00
Wood Sal 0.0346 Cum. 220,935.00 7,644.35
Ply wood 4 mm thick Teak 2.325 Sqm. 648.90 1,508.69
Hinge 100 mm 3.000 Nos. 46.35 139.05
Materials
Towerbolt 150 mm. 2.000 Nos. 103.00 206.00
Mortice lock(Brass) 1.000 Nos. 1,019.70 1,019.70
Pech killas L.S. 50.00
Total 17,602.79
Rate analysis for : 2.245 Sqm. 15 % Contractor overhead 2,640.41
Grand Total 20,243.20

38 mm thick sal wood frame with 26 Bwg G.I. plane sheet


7.08 G4(10-9) (bothside) shutter fixing with all comolete. Size of shutter Sqm. 8,155.03 9,378.28
1.092 x 2.058 =2.245 Sqm.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 7.000 Nos. 940.00 6,580.00
Labour
Unskilled 0.700 Nos. 650.00 455.00
Wood Sal 0.0346 Cum. 220,935.00 7,644.35
GI plane sheet 26 gauge 4.650 Sqm. 650.00 3,022.50
Hinge 100 mm 3.000 Nos. 46.35 139.05
Materials Towerbolt 150 mm. 2.000 Nos. 103.00 206.00
Handle 1.000 Nos. 77.25 77.25
Lockingset 250 mm. 1.000 Nos. 133.90 133.90
Pech killas L.S. 50.00
Total 18,308.05
Rate analysis for : 2.245 Sqm. 15 % Contractor overhead 2,746.20
Grand Total 21,054.25

38 mm thick sal wood frame with 24 Bwg G.I. mosquito


7.09 G4(10-10) proof & Expanded metal net net shutter fixing with all Sqm. 5,799.99 6,669.98
comolete. Size of shutter 1.092 x 2.058 =2.245 Sqm.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 5.000 Nos. 940.00 4,700.00
Labour
Unskilled 0.500 Nos. 650.00 325.00
Wood Sal 0.026 Cum. 220,935.00 5,744.31
Mosquito proof net 2.130 Sqm. 478.95 1,020.16
Expanded metal 2.130 Sqm. 175.10 372.96
Hinge 100 mm 3.000 Nos. 46.35 139.05
Materials

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 42 of 79

Materials
Towerbolt 150 mm. 2.000 Nos. 103.00 206.00
Handle 2.000 Nos. 77.25 154.50
Door spring 1.000 Nos. 309.00 309.00
Pech killas L.S. 50.00
Total 13,020.98
Rate analysis for : 2.245 Sqm. 15 % Contractor overhead 1,953.14
Grand Total 14,974.12

38 mm thick sal wood frame with 24 Bwg G.I. mosquito


7.10 G4(10-10) proof net shutter fixing with all comolete. Size of shutter Sqm. 5,633.86 6,478.93
1.092 x 2.058 =2.245 Sqm.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 5.000 Nos. 940.00 4,700.00
Labour
Unskilled 0.500 Nos. 650.00 325.00
Wood Sal 0.026 Cum. 220,935.00 5,744.31
Mosquito proof net 18 mess good(steel)
quality 2.130 Sqm. 478.95 1,020.16
Hinge 100 mm 3.000 Nos. 46.35 139.05
Materials
Towerbolt 150 mm. 2.000 Nos. 103.00 206.00
Handle 2.000 Nos. 77.25 154.50
Door spring 1.000 Nos. 309.00 309.00
Pech killas L.S. 50.00
Total 12,648.02
Rate analysis for : 2.245 Sqm. 15 % Contractor overhead 1,897.20
Grand Total 14,545.22

4 mm thick plane glass fixing work with wooden listies.


7.11 G5(10-11B) Sqm. 888.75 1,022.06

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.060 Nos. 940.00 56.40
Labour
Unskilled 0.006 Nos. 650.00 3.90
Glass 4 mm thick-Plane 1.000 Sqm. 782.80 782.80
Materials Wooden listies ½" 4.050 Rmtr. 7.57 30.65
Killas L.S. 15.00
Total 888.75
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 133.31
Grand Total 1,022.06

26 Bwg plane sheet fixing work with wooden listies.


7.12 G5(10-11B) Sqm. 782.20 899.53

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.060 Nos. 940.00 56.40
Labour
Unskilled 0.006 Nos. 650.00 3.90
GI plane sheet 26 gauge 1.000 Sqm. 650.00 650.00
Materials Wooden listies ¾" 4.050 Sqm. 14.05 56.90
Killas L.S. 15.00
Total 782.20
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 117.33
Grand Total 899.53

7.13 G6(10-12) 4 mm thick ply wood fixing work with wooden listies. Sqm. 481.66 553.90
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.060 Nos. 940.00 56.40
Labour
Unskilled 0.006 Nos. 650.00 3.90
Ply wood 4 mm thick commercial 1.050 Sqm. 324.45 340.67
Materials Wooden listies 1" 4.050 Sqm. 16.22 65.69
Killas L.S. 15.00
Total 481.66
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 72.24
Grand Total 553.90

7.14 G5(10-11B) Mosquito proof net fixing work with wooden listies. Sqm. 3,153.09 3,626.05
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.060 Nos. 940.00 56.40
Labour
Unskilled 0.006 Nos. 650.00 3.90
Mosquito proof net 1.000 Sqm. 478.95 478.95
Materials Wooden listies ¾" 4.050 Rmtr. 641.69 2,598.84
Killas L.S. 15.00
Total 3,153.09
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 472.96
Grand Total 3,626.05

Mosquito proof & Expanded metal net fixing work with


7.15 G5(10-11B) wooden listies. Sqm. 795.04 914.29

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.060 Nos. 940.00 56.40
Labour
Unskilled 0.006 Nos. 650.00 3.90

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 43 of 79

Mosquito proof net 1.000 Sqm. 478.95 478.95


Expanded metal 1.000 Sqm. 175.10 175.10
Materials
Wooden listies 1" 4.050 Rmtr. 16.22 65.69
Killas L.S. 15.00
Total 795.04
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 119.25
Grand Total 914.29

False ceiling of 6 mm thick commerical plywood with 50


7.16 10-16-A mm x 75 mm size local wood frame of box size 0.600 x Sqm. 2,079.77 2,391.73
0.900 m and fixing of wooden listy in joints
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 23.000 Nos. 940.00 21,620.00
Labour
Unskilled 2.300 Nos. 650.00 1,495.00
Wood Local 0.450 Cum. 56,650.00 25,492.50
Ply wood 6 mm thick commercial 37.500 Sqm. 648.90 24,333.75
Materials
Wooden listies 1½" 100.000 Rmtr. 7.57 757.00 L.S.
Killas Kg. 113.30 300.00 L.S.
Total 73,998.25
Rate analysis for : 35.58 Sqm. 15 % Contractor overhead 11,099.73
Grand Total 85,097.98

Torsteel reinforcement bar fixing work in window frame


7.17 G7(10-21) with all complete, Kg. 124.80 143.53

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 20.00 Nos. 940.00 18,800.00
Labour
Unskilled 20.00 Nos. 650.00 13,000.00
Materials TOR/TMT reinforcement bar 1.05 M.T. 88,580.00 93,009.00
Total 124,809.00
Rate analysis for : 1.00 M.T. 15 % Contractor overhead 18,721.35
Grand Total 143,530.35

38 x100mm thick sal wood frame with 12 mm thick


G8(10-3 & commercial plywood paneled & one side 4 mm thick Teak
7.18 plywood paneled shutter fixing with all comolete. Size of Sqm. 10,376.57 11,933.05
10-7)
shutter 1.092 x 2.058 =2.245 Sqm.

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 7.000 Nos. 940.00 6,580.00
Labour
Unskilled 0.700 Nos. 650.00 455.00
Wood Sal 0.0346 Cum. 220,935.00 7,644.35
Ply wood 12 mm thick commercial 1.900 Sqm. 525.30 998.07
Ply wood 4 mm thick Teak 1.900 Sqm. 648.90 1,232.91
Wooden listies ¾" 7.434 Rmtr. 641.69 4,770.32
Materials Fevicol L.S. 200.00
Hinge 100 mm 3.000 Nos. 46.35 139.05
Towerbolt 150 mm. 2.000 Nos. 103.00 206.00
Mortice lock(Brass) 1.000 Nos. 1,019.70 1,019.70
Pech killas L.S. 50.00
Total 23,295.40
Rate analysis for : 2.245 Sqm. 15 % Contractor overhead 3,494.31
Grand Total 26,789.71

38 x100mm thick sal wood frame with 12 mm thick


G9(10-3 & commercial plywood paneled & both side 4 mm thick Teak
7.19 plywood paneled shutter fixing with all comolete. Size of Sqm. 13,050.61 15,008.20
10-7)
shutter 1.092 x 2.058 =2.245 Sqm.

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 7.000 Nos. 940.00 6,580.00
Labour
Unskilled 0.700 Nos. 650.00 455.00
Wood Sal 0.0346 Cum. 220,935.00 7,644.35
Ply wood 12 mm thick commercial 1.900 Sqm. 525.30 998.07
Ply wood 4 mm thick Teak 3.800 Sqm. 648.90 2,465.82
Wooden listies ¾" 14.868 Rmtr. 641.69 9,540.64
Materials Fevicol L.S. 200.00
Hinge 100 mm 3.000 Nos. 46.35 139.05
Towerbolt 150 mm. 2.000 Nos. 103.00 206.00
Mortice lock(Brass) 1.000 Nos. 1,019.70 1,019.70
Pech killas L.S. 50.00
Total 29,298.63
Rate analysis for : 2.245 Sqm. 15 % Contractor overhead 4,394.79
Grand Total 33,693.42

38 x100mm thick sal wood frame with 12 mm thick water


G10(10-3 & proof plywood paneled & one side 4 mm thick Teak
7.20 plywood paneled shutter fixing with all comolete. Size of Sqm. 10,376.57 11,933.05
10-7)
shutter 1.092 x 2.058 =2.245 Sqm.

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 44 of 79

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 7.000 Nos. 940.00 6,580.00
Labour
Unskilled 0.700 Nos. 650.00 455.00
Wood Sal 0.0346 Cum. 220,935.00 7,644.35
Ply wood 12 mm thick water proof 1.900 Sqm. 525.30 998.07
Ply wood 4 mm thick Teak 1.900 Sqm. 648.90 1,232.91
Wooden listies ¾" 7.434 Rmtr. 641.69 4,770.32
Materials Fevicol L.S. 200.00
Hinge 100 mm 3.000 Nos. 46.35 139.05
Towerbolt 150 mm. 2.000 Nos. 103.00 206.00
Mortice lock(Brass) 1.000 Nos. 1,019.70 1,019.70
Pech killas L.S. 50.00
Total 23,295.40
Rate analysis for : 2.245 Sqm. 15 % Contractor overhead 3,494.31
Grand Total 26,789.71
H - FLOORING WORK

25 mm or 1" thick P.C.C. (1:2:4) work in floor with all


8.01 H1(11-1A) complete. Sqm. 414.74 476.95

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.100 Nos. 940.00 1,034.00
Labour
Unskilled 1.500 Nos. 650.00 975.00
Cement 0.090 M.T. 17,510.00 1,575.90
Materials Sand (Aurahi Khola) 0.120 Cum. 1,307.25 156.87
Aggrigate 12 mm-River bed 0.230 Cum. 1,763.75 405.66
Total 4,147.43
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 622.11
Grand Total 4,769.54

38 mm or 1½" thick P.C.C. (1:2:4) work in floor with all


8.02 H1(11-1B) complete. Sqm. 562.15 646.47

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.250 Nos. 940.00 1,175.00
Labour
Unskilled 2.000 Nos. 650.00 1,300.00
Cement 0.130 M.T. 17,510.00 2,276.30
Materials Sand (Aurahi Khola) 0.180 Cum. 1,307.25 235.30
Aggrigate 12 mm-River bed 0.360 Cum. 1,763.75 634.95
Total 5,621.55
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 843.23
Grand Total 6,464.78

50 mm or 2" thick P.C.C. (1:2:4) work in floor with all


8.03 H1(11-1C) complete. Sqm. 688.86 792.19

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.250 Nos. 940.00 1,175.00
Labour
Unskilled 2.500 Nos. 650.00 1,625.00
Cement 0.170 M.T. 17,510.00 2,976.70
Materials Sand (Aurahi Khola) 0.230 Cum. 1,307.25 300.66
Aggrigate 20 mm-River bed 0.460 Cum. 1,763.75 811.32
Total 6,888.68
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,033.30
Grand Total 7,921.98

75 mm or 3" thick P.C.C. (1:2:4) work in floor with all


8.04 H1(11-1D) complete. Sqm. 932.14 1,071.96

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.250 Nos. 940.00 1,175.00
Labour
Unskilled 3.000 Nos. 650.00 1,950.00
Cement 0.260 M.T. 17,510.00 4,552.60
Materials Sand (Aurahi Khola) 0.340 Cum. 1,307.25 444.46
Aggrigate 20 mm-River bed 0.680 Cum. 1,763.75 1,199.35
Total 9,321.41
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,398.21
Grand Total 10,719.62

25 mm thick mosaic flooring with 20 mm thick P.C.C.


8.05 H2(11-2) (1:2:4) & 5 mm thick white cement marble chips1:1 Sqm. 1,892.63 2,176.52
rubbing & polishing work with all complete.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.500 Nos. 940.00 2,350.00
Labour
Unskilled 16.000 Nos. 650.00 10,400.00
Cement 0.065 M.T. 17,510.00 1,138.15
Sand (Aurahi Khola) 0.088 Cum. 1,307.25 115.03
Aggrigate 12 mm-River bed 0.176 Cum. 1,763.75 310.42
White cement 0.061 M.T. 56,650.00 3,455.65
Materials Marble chips 3 mm 0.061 Cum. 16,222.50 989.57

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 45 of 79

Materials
Oxalic acid powder 0.365 Kg. 118.45 43.23
Main Polish 0.118 Kg. 442.90 52.26
Tarpaintain oil 0.538 Ltr. 133.90 72.03
Carborendam Stone 2.000 Nos. - - L.S. 2 Nos.
Total 18,926.34
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 2,838.95
Grand Total 21,765.29

25 mm thick mosaic flooring with 19 mm thick cement


8.06 H3(11-3) sand plaster 1:2 & 6 mm thick white cement marble Sqm. 3,390.46 3,899.03
chips1:1 rubbing & polishing work with all complete.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.500 Nos. 940.00 3,290.00
Labour
Unskilled 36.000 Nos. 650.00 23,400.00
Cement 0.121 M.T. 17,510.00 2,118.71
Sand crusher(Badahari khola) 0.165 Cum. 1,607.25 265.19
White cement 0.069 M.T. 56,650.00 3,908.85
Marble chips 3 mm 0.047 Cum. 16,222.50 762.45
Materials
Oxalic acid powder 0.340 Kg. 118.45 40.27
Main Polish 0.118 Kg. 442.90 52.26
Tarpaintain oil 0.500 Ltr. 133.90 66.95
Carborendam Stone 2.000 Nos. - - 2 Nos.
Total 33,904.68
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 5,085.70
Grand Total 38,990.38

20 mm thick mosaic flooring with 12.5mm thick cement


8.07 H4(11-4) sand plaster 1:2 & 6 mm thick white cement marble Sqm. 3,464.40 3,984.06
chips1:1 rubbing & polishing work with all complete.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.500 Nos. 940.00 3,290.00
Labour
Unskilled 36.000 Nos. 650.00 23,400.00
Cement 0.089 M.T. 17,510.00 1,558.39
Sand crusher(Badahari khola) 0.122 Cum. 1,607.25 196.08
White cement 0.089 M.T. 56,650.00 5,041.85
Marble chips 3 mm 0.061 Cum. 16,222.50 989.57
Materials
Oxalic acid powder 0.370 Kg. 118.45 43.82
Main Polish 0.118 Kg. 442.90 52.26
Tarpaintain oil 0.538 Ltr. 133.90 72.03
Carborendam Stone 2.000 Nos. - - 2 Nos.
Total 34,644.00
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 5,196.60
Grand Total 39,840.60

20 mm thick Terrazo tile paving with 20 mm thick cement


8.08 H5(11-5) sand mortar 1:4 rubbing & polishing work with all Sqm. 2,020.88 2,324.01
Level/Typecomplete. Quantity Unit Rate Amount Remarks
Resources
Skilled 2.000 Nos. 940.00 1,880.00
Labour
Unskilled 12.600 Nos. 650.00 8,190.00
Terrazo tile 20 mm thick 11.000 Sqm. 710.70 7,817.70
Cement 0.081 M.T. 17,510.00 1,418.31
Sand crusher(Badahari khola) 0.220 Cum. 1,607.25 353.59
Materials Oxalic acid powder 0.370 Kg. 118.45 43.82
Main Polish 0.118 Kg. 442.90 52.26
Tarpaintain oil 0.538 Ltr. 133.90 72.03
Carborendam Stone 2.000 Nos. 190.55 381.10 2 Nos.
Total 20,208.81
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 3,031.32
Grand Total 23,240.13

15 mm thick marble tile 600x600 mm paving with 20 mm


8.09 11-6 thick cement sand mortar 1:2 rubbing & polishing work Sqm. 5,047.36 5,804.47
with all complete.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.000 Nos. 940.00 1,880.00
Labour
Unskilled 8.000 Nos. 650.00 5,200.00
Marble tile 15mm 11.000 Sqm. 3,656.50 40,221.50
Cement 0.133 M.T. 17,510.00 2,328.83
Sand crusher(Badahari khola) 0.183 Cum. 1,607.25 294.12
Materials Oxalic acid powder 0.370 Kg. 118.45 43.82
Main Polish 0.118 Kg. 442.90 52.26
Tarpaintain oil 0.538 Ltr. 133.90 72.03
Carborendam Stone 2.000 Nos. 190.55 381.10 L.S. 2 Nos.
Total 50,473.66
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 7,571.04

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 46 of 79

Rate analysis for :10.00 Sqm.


Grand Total 58,044.70

Porcelain glazed /non glazed tile paving work in cement


8.10 H6(11-7) Sqm. 2,822.26 3,245.60
sand (1:4) mortar
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 13.000 Nos. 940.00 12,220.00
Labour
Unskilled 4.500 Nos. 650.00 2,925.00
Porecelain glazed/non glazed tile 11.000 Sqm. 1,060.90 11,669.90
Cement 0.056 M.T. 17,510.00 980.56
Materials
Sand crusher(Badahari khola) 0.152 Cum. 1,607.25 244.30
White cement 3.228 Kg. 56.65 182.86
Total 28,222.62
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 4,233.39
Grand Total 32,456.01

Spartik Non-glazed tile paving work in cement sand (1:4)


8.11 H6(11-7) Sqm. 2,765.61 3,180.45
mortar
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 13.000 Nos. 940.00 12,220.00
Labour
Unskilled 4.500 Nos. 650.00 2,925.00
Spartik non glazed tile 11.000 Sqm. 1,009.40 11,103.40
Cement 0.056 M.T. 17,510.00 980.56
Materials
Sand crusher(Badahari khola) 0.152 Cum. 1,607.25 244.30
White cement 3.228 Kg. 56.65 182.86
Total 27,656.12
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 4,148.41
Grand Total 31,804.53

Flat Brick paving in 1:6 & cement sand pointing in1:2 in


8.12 H12(11-12) Sqm. 1,068.73 1,229.04
joints
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.250 Nos. 940.00 2,115.00
Labour
Unskilled 3.250 Nos. 650.00 2,112.50
Brick chimney 340.000 Nos. 13.90 4,726.00
Materials Cement 0.078 M.T. 17,510.00 1,365.78
Sand crusher(Badahari khola) 0.229 Cum. 1,607.25 368.06
Total 10,687.34
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,603.10
Grand Total 12,290.44

Edge Brick paving in 1:6 & cement sand pointing in1:2 in


8.13 H13(11-13) joints Sqm. 1,266.04 1,455.94

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.100 Nos. 940.00 1,034.00
Labour
Unskilled 1.800 Nos. 650.00 1,170.00
Brick chimney 550.000 Nos. 13.90 7,645.00
Materials Cement 0.121 M.T. 17,510.00 2,118.71
Sand crusher(Badahari khola) 0.431 Cum. 1,607.25 692.72
Total 12,660.43
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,899.06
Grand Total 14,559.49

Dry flat Brick paving work


8.14 H15(11-15A) Sqm. 698.71 803.52

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 940.00 470.00
Labour
Unskilled 1.000 Nos. 650.00 650.00

Materials Brick chimney 340.000 Nos. 13.90 4,726.00


Sand crusher(Badahari khola) 0.710 Cum. 1,607.25 1,141.14
Total 6,987.14
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,048.07
Grand Total 8,035.21

Dry flat Brick (Brick Bat ) paving work


8.15 H15(11-15A) Sqm. 409.88 471.36

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 940.00 470.00
Labour
Unskilled 1.000 Nos. 650.00 650.00
Brick Bat 340.000 Nos. 5.41 1,837.70 50% brick rate
Materials

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 47 of 79

Materials
Sand crusher(Badahari khola) 0.710 Cum. 1,607.25 1,141.14
Total 4,098.84
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 614.82
Grand Total 4,713.66

Dry edge Brickpaving work


8.16 H15(11-15B) Sqm. 1,183.86 1,361.44

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 940.00 940.00
Labour
Unskilled 3.250 Nos. 650.00 2,112.50
Brick chimney 550.000 Nos. 13.90 7,645.00
Materials
Sand crusher(Badahari khola) 0.710 Cum. 1,607.25 1,141.14
Total 11,838.64
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,775.79
Grand Total 13,614.43

Note : 1.00 Cum Brick bat=438 Brick

Dry edge Brick (Brick Bat ) paving work


8.17 H15(11-15B) Sqm. 716.63 824.13

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 940.00 940.00
Labour
Unskilled 3.250 Nos. 650.00 2,112.50
Brick Bat 550.000 Nos. 5.41 2,972.75 50% brick rate
Materials
Sand crusher(Badahari khola) 0.710 Cum. 1,607.25 1,141.14
Total 7,166.39
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,074.95
Grand Total 8,241.34

8.18 H16( 11-16) Stone filling in floor with sand lead up to 30 mtr. Cum. 6,776.64 7,793.13
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 940.00 940.00
Labour
Unskilled 3.500 Nos. 650.00 2,275.00
Stone block 1.000 Cum. 2,420.50 2,420.50
Materials
Sand Local 0.710 Cum. 1,607.25 1,141.14
Total 6,776.64
Rate analysis for :1.00 Cum. 15 % Contractor overhead 1,016.49
Grand Total 7,793.13

Edge brick paving with sand packing in voids & cement


8.19 H17( 11-17) Sqm. 1,263.59 1,453.13
sand (1:3) flush pointing in top surface.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.000 Nos. 940.00 1,880.00
Labour
Unskilled 4.000 Nos. 650.00 2,600.00
Brick chimney 550.000 Cum. 13.90 7,645.00
Materials cement 0.020 Cum. 17,510.00 350.20
Sand crusher(Badahari khola) 0.100 Cum. 1,607.25 160.72
Total 12,635.92
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,895.38
Grand Total 14,531.30

Sand filling work


8.20 H19( 11-19A) Cum. 2,378.97 2,735.82

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Skilled 6.500 Nos. 940.00 6,110.00
Materials Sand crusher(Badahari khola) 11.000 Cum. 1,607.25 17,679.75
Total 23,789.75
Rate analysis for :10.00 Cum. 15 % Contractor overhead 3,568.46
Grand Total 27,358.21

15-15 cm. Brick bat filling work.


8.21 H19( 11-19B) Cum. 955.29 1,098.58

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Skilled 10.00 Nos. 940.00 9,400.00
Materials Brick bat 11.00 Cum. 13.90 152.90
Total 9,552.90
Rate analysis for :10.00 Cum. 15 % Contractor overhead 1,432.93
Grand Total 10,985.83

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 48 of 79

3 mm thick neat cement punning work.


8.22 H20( 11-20) Sqm. 252.15 289.97

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 940.00 940.00
Labour
Unskilled 1.000 Nos. 650.00 650.00
Materials Cement 53.200 Kg. 17.51 931.53
Total 2,521.53
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 378.22
Grand Total 2,899.75

25 mm thick Sal wood planking work with 50x75 mm sal


8.23 H21(11-21) wood frame in 600x600 mm Sqm. 9,974.61 11,470.80

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 6.500 Nos. 940.00 6,110.00
Labour
Unskilled 0.650 Nos. 650.00 422.50
Wood Sal 0.421 Cum. 220,935.00 93,013.63
Materials
Killa L.S. 200.00
Total 99,746.13
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 14,961.91
Grand Total 114,708.04

3 mm thick neat Plaster of Paris punning work.


8.24 H24( 11-20) Sqm. 274.07 315.18

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 940.00 940.00
Labour
Unskilled 1.000 Nos. 650.00 650.00
Materials Plaster of Paris 53.200 Kg. 21.63 1,150.71
Total 2,740.71
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 411.10
Grand Total 3,151.81

Clay tile(Machine Made) paving work in cement sand (1:4)


8.25 H25(11-7) Sqm. 1,674.37 1,925.53
mortar
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 13.000 Nos. 940.00 12,220.00
Labour
Unskilled 4.500 Nos. 650.00 2,925.00
clay tile(Machine Made) 11.000 Sqm. 33.99 373.89
Materials Cement 0.056 M.T. 17,510.00 980.56
Sand crusher(Badahari khola) 0.152 Cum. 1,607.25 244.30
Total 16,743.75
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 2,511.56
Grand Total 19,255.31

Granite 16mm thick paving with 20 mm thick cement sand


8.26 H26(11-6) mortar 1:2 rubbing & polishing work with all complete. Sqm. 6,083.48 6,996.00

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 2.000 Nos. 940.00 1,880.00
Labour
Unskilled 8.000 Nos. 650.00 5,200.00
Granite 16mm thick 11.000 Sqm. 3,800.70 41,807.70
Cement 0.133 M.T. 17,510.00 2,328.83
Sand crusher(Badahari khola) 0.183 Cum. 1,607.25 294.12
Materials Oxalic acid powder 0.370 Kg. 118.45 43.82
Main Polish 0.118 Kg. 442.90 52.26
Tarpaintain oil 0.538 Ltr. 133.90 72.03
Carborendam Stone 2.000
Nos. 190.55 381.10 L.S. 2 Nos.
Equipment Unskilled 13.500
Nos. 650.00 8,775.00
Total 60,834.86
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 9,125.22
Grand Total 69,960.08
I - PLASTER & POINTING WORK

9.01 I1(12-1B) 12.5 mm. thick cement sand plaster work 1:3 on wall. Sqm. 346.81 398.83
Resources Level/Type Quantity Unit Rate Amount Remarks

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 49 of 79

Skilled 12.000 Nos. 940.00 11,280.00


Labour
Unskilled 16.000 Nos. 650.00 10,400.00

Materials Cement 0.625 M.T. 17,510.00 10,943.75


Sand crusher(Badahari khola) 1.280 Cum. 1,607.25 2,057.28
Total 34,681.03
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 5,202.15
Grand Total 39,883.18

9.02 I1(12-1C) 12.5 mm. thick cement sand plaster work 1:4 on wall. Sqm. 334.46 384.64
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 12.000 Nos. 940.00 11,280.00
Labour
Unskilled 16.000 Nos. 650.00 10,400.00
Cement 0.538 M.T. 17,510.00 9,420.38
Materials
Sand crusher(Badahari khola) 1.460 Cum. 1,607.25 2,346.58
Total 33,446.96
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 5,017.04
Grand Total 38,464.00

9.03 I1(12-1D) 12.5 mm. thick cement sand plaster work 1:6 on wall. Sqm. 308.92 355.26
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 12.000 Nos. 940.00 11,280.00
Labour
Unskilled 16.000 Nos. 650.00 10,400.00
Cement 0.382 M.T. 17,510.00 6,688.82
Materials
Sand crusher(Badahari khola) 1.570 Cum. 1,607.25 2,523.38
Total 30,892.20
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,633.83
Grand Total 35,526.03

9.04 I4(12-4A) 20 mm. thick cement sand plaster work 1:3 on wall etc. Sqm. 454.53 522.71
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 14.000 Nos. 940.00 13,160.00
Labour
Unskilled 19.000 Nos. 650.00 12,350.00
Cement 0.960 M.T. 17,510.00 16,809.60
Materials
Sand crusher(Badahari khola) 1.950 Cum. 1,607.25 3,134.13
Total 45,453.73
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 6,818.05
Grand Total 52,271.78

9.05 I4(12-4B) 20 mm. thick cement sand plaster work 1:4 on wall etc. Sqm. 432.29 497.13
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 14.000 Nos. 940.00 13,160.00
Labour
Unskilled 19.000 Nos. 650.00 12,350.00
Cement 0.810 M.T. 17,510.00 14,183.10
Materials
Sand crusher(Badahari khola) 2.200 Cum. 1,607.25 3,535.95
Total 43,229.05
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 6,484.35
Grand Total 49,713.40

9.06 I4(12-4C) 20 mm. thick cement sand plaster work1:6 on wall etc. Sqm. 392.67 451.57
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 14.000 Nos. 940.00 13,160.00
Labour
Unskilled 19.000 Nos. 650.00 12,350.00
Cement 0.570 M.T. 17,510.00 9,980.70
Materials
Sand crusher(Badahari khola) 2.350 Cum. 1,607.25 3,777.03
Total 39,267.73
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 5,890.15
Grand Total 45,157.88

9.07 I5(12-5) 25 mm. thick mud plaster on wall etc. Sqm. 367.96 423.16
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 20.000 Nos. 940.00 18,800.00
Labour
Unskilled 25.000 Nos. 650.00 16,250.00
Mud 3.000 Cum. 412.00 1,236.00
Materials Bhush 10.000 Kg. 6.69 66.90
Gobar 120.000 Kg. 3.70 444.00
Total 36,796.90
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 5,519.53
Grand Total 42,316.43

9.08 I5(12-6) 12.5 mm. thick mud plaster on wall etc. Sqm. 282.74 325.15
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 15.000 Nos. 940.00 14,100.00
Labour
Unskilled 20.000 Nos. 650.00 13,000.00
Mud 1.500 Cum. 412.00 618.00
Materials

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 50 of 79

Materials Bhush 50.000 Kg. 6.69 334.50


Gobar 60.000 Kg. 3.70 222.00
Total 28,274.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,241.17
Grand Total 32,515.67

9.09 I7(12-1B) 12.5 mm. thick cement sand plaster work (1:3 ) on ceilling Sqm. 401.01 461.16

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 15.000 Nos. 940.00 14,100.00
Labour
Unskilled 20.000 Nos. 650.00 13,000.00

Materials Cement 0.625 M.T. 17,510.00 10,943.75


Sand crusher(Badahari khola) 1.280 Cum. 1,607.25 2,057.28
Total 40,101.03
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 6,015.15
Grand Total 46,116.18

9.10 I7(12-1C) 12.5 mm. thick cement sand plaster work 1:4 on ceilling Sqm. 388.66 446.97
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 15.000 Nos. 940.00 14,100.00
Labour
Unskilled 20.000 Nos. 650.00 13,000.00
Cement 0.538 M.T. 17,510.00 9,420.38
Materials
Sand crusher(Badahari khola) 1.460 Cum. 1,607.25 2,346.58
Total 38,866.96
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 5,830.04
Grand Total 44,697.00

Flush pointing works in 1:1 Cement sand mortar on Brick


9.11 I8(14-1A) masonry wall Sqm. 235.56 270.90

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 10.500 Nos. 940.00 9,870.00
Labour
Unskilled 12.000 Nos. 650.00 7,800.00
Cement 0.316 M.T. 17,510.00 5,533.16
Materials
Sand crusher(Badahari khola) 0.220 Cum. 1,607.25 353.59
Total 23,556.75
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,533.51
Grand Total 27,090.26

Flush pointing works in 1:2 Cement sand mortar on Brick


9.12 I8(14-1B) masonry work Sqm. 218.13 250.85

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 10.500 Nos. 940.00 9,870.00
Labour
Unskilled 12.000 Nos. 650.00 7,800.00
Cement 0.210 M.T. 17,510.00 3,677.10
Materials
Sand crusher(Badahari khola) 0.290 Cum. 1,607.25 466.10
Total 21,813.20
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,271.98
Grand Total 25,085.18

Flush pointing works in 1:3 Cement sand mortar on Brick


9.13 I8(14-1C) masonry wall Sqm. 208.98 240.33

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 10.500 Nos. 940.00 9,870.00
Labour
Unskilled 12.000 Nos. 650.00 7,800.00
Cement 0.155 M.T. 17,510.00 2,714.05
Materials
Sand crusher(Badahari khola) 0.320 Cum. 1,607.25 514.32
Total 20,898.37
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,134.75
Grand Total 24,033.12

Rulled pointing works in 1:1 Cement sand mortar on


9.14 I8(14-1A) Brick masonry wall Sqm. 323.91 372.50

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 15.750 Nos. 940.00 14,805.00
Labour
Unskilled 18.000 Nos. 650.00 11,700.00
Cement 0.316 M.T. 17,510.00 5,533.16
Materials
Sand crusher(Badahari khola) 0.220 Cum. 1,607.25 353.59
Total 32,391.75
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,858.76
Grand Total 37,250.51

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 51 of 79

Ruled pointing works in 1:2 Cement sand mortar on Brick


9.15 I8(14-1B) masonry work Sqm. 306.48 352.45

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 15.750 Nos. 940.00 14,805.00
Labour
Unskilled 18.000 Nos. 650.00 11,700.00
Cement 0.210 M.T. 17,510.00 3,677.10
Materials
Sand crusher(Badahari khola) 0.290 Cum. 1,607.25 466.10
Total 30,648.20
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,597.23
Grand Total 35,245.43

Ruled pointing works in 1:3 Cement sand mortar on Brick


9.16 I8(14-1C) masonry wall Sqm. 297.33 341.93

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 15.750 Nos. 940.00 14,805.00
Labour
Unskilled 18.000 Nos. 650.00 11,700.00
Cement 0.155 M.T. 17,510.00 2,714.05
Materials
Sand crusher(Badahari khola) 0.320 Cum. 1,607.25 514.32
Total 29,733.37
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,460.00
Grand Total 34,193.37

Flush/Rulled pointing works in 1:1 Cement sand mortar


9.17 I9(14-2A) Sqm. 299.07 343.93
on Stone masonry wall
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 10.000 Nos. 940.00 9,400.00
Labour
Unskilled 14.000 Nos. 650.00 9,100.00
Cement 0.612 M.T. 17,510.00 10,716.12
Materials
Sand crusher(Badahari khola) 0.430 Cum. 1,607.25 691.11
Total 29,907.23
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,486.08
Grand Total 34,393.31

Flush/Rulled pointing works in 1:2 Cement sand mortar


9.18 I9(14-2B) Sqm. 265.60 305.44
on Stone masonry work
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 10.000 Nos. 940.00 9,400.00
Labour
Unskilled 14.000 Nos. 650.00 9,100.00
Cement 0.408 M.T. 17,510.00 7,144.08
Materials
Sand crusher(Badahari khola) 0.570 Cum. 1,607.25 916.13
Total 26,560.21
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,984.03
Grand Total 30,544.24

Flush/Rulled pointing works in 1:3 Cement sand mortar


9.19 (14-2C) on Stone masonry work Sqm. 248.70 286.01

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 10.000 Nos. 940.00 9,400.00
Labour
Unskilled 14.000 Nos. 650.00 9,100.00
Cement 0.306 M.T. 17,510.00 5,358.06
Materials
Sand crusher(Badahari khola) 0.630 Cum. 1,607.25 1,012.56
Total 24,870.62
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,730.59
Grand Total 28,601.21

Flush/Rulled pointing works in 1:3 Cement sand mortar


9.20 I10(14-3) on Aslar Stone masonry work Sqm. 162.67 187.07

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 8.000 Nos. 940.00 7,520.00
Labour
Unskilled 10.000 Nos. 650.00 6,500.00
Cement 0.110 M.T. 17,510.00 1,926.10
Materials
Sand crusher(Badahari khola) 0.200 Cum. 1,607.25 321.45
Total 16,267.55
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,440.13
Grand Total 18,707.68

1:3 Cement sand pointing on 450 mm x 450 mm flat


9.21 I11(14-4) stone paving joints. Sqm. 87.33 100.43

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 5.000 Nos. 940.00 4,700.00
Labour
Unskilled 5.000 Nos. 650.00 3,250.00
Cement 0.042 M.T. 17,510.00 735.42
Materials
Sand crusher(Badahari khola) 0.030 Cum. 1,607.25 48.21

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 52 of 79

Total 8,733.63
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,310.04
Grand Total 10,043.67

1:1 Cement sand pointing on Teliya brick paving joints.


9.22 I12(14-5) Sqm. 186.87 214.90

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 10.000 Nos. 940.00 9,400.00
Labour
Unskilled 10.000 Nos. 650.00 6,500.00
Cement 0.150 M.T. 17,510.00 2,626.50
Materials
Sand crusher(Badahari khola) 0.100 Cum. 1,607.25 160.72
Total 18,687.22
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,803.08
Grand Total 21,490.30

9.23 (14-6) 3 mm thick Cement sand 1:1 flushing plaster Sqm. 221.53 254.75
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 10.000 Nos. 940.00 9,400.00
Labour
Unskilled 10.000 Nos. 650.00 6,500.00
Cement 0.336 M.T. 17,510.00 5,883.36
Materials
Sand crusher(Badahari khola) 0.230 Cum. 1,607.25 369.66
Total 22,153.02
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,322.95
Grand Total 25,475.97

9.24 I13(14-7) 3 mm thick lime flushing plaster Sqm. 159.03 182.89


Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 10.000 Nos. 940.00 9,400.00
Labour
Unskilled 10.000 Nos. 650.00 6,500.00
Materials White lime 0.160 Kg. 22.66 3.62
Total 15,903.62
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,385.54
Grand Total 18,289.16

9.25 I14(14-8) 3 mm thick Cement flushing plaster Sqm. 249.70 287.15


Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 10.000 Nos. 940.00 9,400.00
Labour
Unskilled 10.000 Nos. 650.00 6,500.00
Materials Cement 0.518 M.T. 17,510.00 9,070.18
Total 24,970.18
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,745.52
Grand Total 28,715.70

9.26 I15 20 mm thick Jhalar/pani patti making over cement plaster Sqm. 169.29 194.68
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.025 Nos. 940.00 23.50
Labour
Unskilled 0.010 Nos. 650.00 6.50
Cement 0.007 M.T. 17,510.00 122.57
Materials Sand crusher(Badahari khola) 0.004 Cum. 1,607.25 6.42
Water proofing compound 0.100 Kg. 103.00 10.30
Total 169.29
Rate analysis for :1.00 Rmtr. 15 % Contractor overhead 25.39
Grand Total 194.68

25 mm thick roofing tile butta plaster in cement sand (1:4)


9.27 I16 work Sqm. 641.69 737.94

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour
25mm thick roofing tile butta plaster 1.000 Sqm 641.69 641.69
Materials
Total 641.69
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 96.25
Grand Total 737.94

2 mm thick plane white putting plaster work in wall


9.28 I17 &ceilling Sqm. 224.75 258.46

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 940.00 940.00
Labour
Unskilled 1.000 Nos. 650.00 650.00
Materials White patti plaster 10.640 Kg. 61.80 657.55
Total 2,247.55
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 337.13
Grand Total 2,584.68

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 53 of 79

J - PAINTING WORK

Two coat white washing work on wall.


10.01 J1(13-1B) Sqm. 27.73 31.89

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.500 Nos. 940.00 1,410.00
Labour
Unskilled 1.100 Nos. 650.00 715.00
White lime 22.000 Kg. 22.66 498.52
Materials
gum 0.880 Kg. 169.95 149.55
Total 2,773.07
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 415.96
Grand Total 3,189.03

10.02 J1(13-1B) Two coat white washing work on ceilling. Sqm. 33.04 37.99
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.875 Nos. 940.00 1,762.50 25% Add for
Labour
Unskilled 1.375 Nos. 650.00 893.75 ceilling
White lime 22.000 Kg. 22.66 498.52
Materials
gum 0.880 Kg. 169.95 149.55
Total 3,304.32
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 495.64
Grand Total 3,799.96

10.03 J1(13-1C) Three coat white washing work on wall. Sqm. 55.17 63.45
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.000 Nos. 940.00 2,820.00
Labour
Unskilled 2.700 Nos. 650.00 1,755.00
White lime 32.000 Kg. 22.66 725.12
Materials
gum 1.280 Kg. 169.95 217.53
Total 5,517.65
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 827.64
Grand Total 6,345.29

10.04 J1(13-1C) Three coat white washing work on ceilling. Sqm. 66.61 76.60
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.750 Nos. 940.00 3,525.00 25% Add for
Labour
Unskilled 3.375 Nos. 650.00 2,193.75 ceilling
White lime 32.000 Kg. 22.66 725.12
Materials
gum 1.280 Kg. 169.95 217.53
Total 6,661.40
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 999.21
Grand Total 7,660.61

10.05 J2(13-2) white washing work in old surface. Sqm. 15.01 17.26
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.800 Nos. 940.00 752.00
Labour
Unskilled 0.700 Nos. 650.00 455.00
White lime 10.000 Kg. 22.66 226.60
Materials
gum 0.400 Kg. 169.95 67.98
Total 1,501.58
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 225.23
Grand Total 1,726.81

10.06 J3(13-3AB) One coat distemper painting work over primer coat. Sqm. 111.18 127.86
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 4.00 Nos. 940.00 3,760.00
Labour
Unskilled 4.00 Nos. 650.00 2,600.00
Distemper primer 8.00 Ltr. 360.50 2,884.00
Materials
Distemper Powder 6.50 Kg. 288.40 1,874.60
Total 11,118.60
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,667.79
Grand Total 12,786.39

Two coat distemper painting work over primer coat.


10.07 J3(13-3ABC) Sqm. 154.22 177.35

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 5.80 Nos. 940.00 5,452.00
Labour
Unskilled 5.80 Nos. 650.00 3,770.00
Distemper primer 8.00 Ltr. 360.50 2,884.00
Materials
Distemper Powder 11.50 Kg. 288.40 3,316.60
Total 15,422.60
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,313.39
Grand Total 17,735.99

10.08 J3(13-3B) One coat distemper painting work without primer coat. Sqm. 50.54 58.12
Resources Level/Type Quantity Unit Rate Amount Remarks

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 54 of 79

Skilled 2.00 Nos. 940.00 1,880.00


Labour
Unskilled 2.00 Nos. 650.00 1,300.00
Materials Distemper washable 6.50 Kg. 288.40 1,874.60
Total 5,054.60
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 758.19
Grand Total 5,812.79

10.09 J3(13-3BC) Two coat distemper painting work without primer coat. Sqm. 93.58 107.62
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.80 Nos. 940.00 3,572.00
Labour
Unskilled 3.80 Nos. 650.00 2,470.00
Materials Distemper washable 11.50 Kg. 288.40 3,316.60
Total 9,358.60
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,403.79
Grand Total 10,762.39

10.10 J3(13-3AB) One coat weather proof painting work over primer coat. Sqm. 156.24 179.68
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 4.00 Nos. 940.00 3,760.00
Labour
Unskilled 4.00 Nos. 650.00 2,600.00
Weather proof primer 8.00 Ltr. 463.50 3,708.00
Materials
Weather proof paint 6.50 Kg. 854.90 5,556.85
Total 15,624.85
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,343.72
Grand Total 17,968.57

Two coat weather proof painting work over primer coat.


10.11 J3(13-3ABC) Sqm. 227.61 261.75

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 5.80 Nos. 940.00 5,452.00
Labour
Unskilled 5.80 Nos. 650.00 3,770.00
Weather proof primer 8.00 Ltr. 463.50 3,708.00
Materials
Weather proof paint 11.50 Kg. 854.90 9,831.35
Total 22,761.35
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,414.20
Grand Total 26,175.55

One coat weather proof painting work without primer coat.


10.12 J3(13-3B) Sqm. 87.36 100.47

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 2.00 Nos. 940.00 1,880.00
Labour
Unskilled 2.00 Nos. 650.00 1,300.00
Materials Weather proof paint 6.50 Kg. 854.90 5,556.85
Total 8,736.85
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,310.52
Grand Total 10,047.37

Two coat weather proof painting work without primer coat.


10.13 J3(13-3BC) Sqm. 158.73 182.54

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 3.80 Nos. 940.00 3,572.00
Labour
Unskilled 3.80 Nos. 650.00 2,470.00
Materials Weather proof paint 11.50 Kg. 854.90 9,831.35
Total 15,873.35
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,381.00
Grand Total 18,254.35

One coat water proof cement paint painting work in old


10.14 J4(13-4A) surface Sqm. 53.29 61.28

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.70 Nos. 940.00 1,598.00
Labour
Unskilled 1.70 Nos. 650.00 1,105.00
Materials Water proof cement paint 30.00 Kg. 87.55 2,626.50
Total 5,329.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 799.42
Grand Total 6,128.92

Two coat water proof cement paint painting work in old


10.15 J4(13-4B) surface Sqm. 121.96 140.25

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 5.00 Nos. 940.00 4,700.00
Labour
Unskilled 5.00 Nos. 650.00 3,250.00
Materials Water proof cement paint 48.50 Kg. 87.55 4,246.17
Total 12,196.17
Rate analysis for :100.00 Sqm.

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 55 of 79

Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,829.42


Grand Total 14,025.59

10.16 J4(13-4A) One coat white cement paint painting work . Sqm. 44.02 50.62
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.70 Nos. 940.00 1,598.00
Labour
Unskilled 1.70 Nos. 650.00 1,105.00
Materials White cement 30.00 Kg. 56.65 1,699.50
Total 4,402.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 660.37
Grand Total 5,062.87

10.17 J4(13-4B) Two coat white cement paint painting work . Sqm. 106.97 123.02
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 5.00 Nos. 940.00 4,700.00
Labour
Unskilled 5.00 Nos. 650.00 3,250.00
Materials White cement 48.50 Kg. 56.65 2,747.52
Total 10,697.52
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,604.62
Grand Total 12,302.14

One coat enamel painting work over primer coat in wooden


10.18 J5(13-5AB) surface. Sqm. 190.66 219.26

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 8.00 Nos. 940.00 7,520.00
Labour
Unskilled 5.00 Nos. 650.00 3,250.00
Enamel Primer 8.10 Ltr. 360.50 2,920.05
Materials
Enamel paint 9.00 Ltr. 597.40 5,376.60
Total 19,066.65
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,859.99
Grand Total 21,926.64

Two coat enamel painting work over primer coat in wooden


10.19 J5(13-5ABC) surface. Sqm. 289.58 333.02

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 12.00 Nos. 940.00 11,280.00
Labour
Unskilled 8.00 Nos. 650.00 5,200.00
Enamel Primer 8.10 Ltr. 360.50 2,920.05
Materials
Enamel paint 16.00 Ltr. 597.40 9,558.40
Total 28,958.45
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,343.76
Grand Total 33,302.21

One coat plastic emulsion painting work over primer coat.


10.20 J5(13-5AB) Sqm. 197.15 226.72

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 8.00 Nos. 940.00 7,520.00
Labour
Unskilled 5.00 Nos. 650.00 3,250.00
Enamel Primer 8.10 Ltr. 360.50 2,920.05
Materials
Plastic emulsion paint 9.00 Ltr. 669.50 6,025.50
Total 19,715.55
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,957.33
Grand Total 22,672.88

Two coat plastic emulsion painting work over primer coat.


10.21 J5(13-5AB) Sqm. 301.12 346.28

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 12.00 Nos. 940.00 11,280.00
Labour
Unskilled 8.00 Nos. 650.00 5,200.00
Enamel Primer 8.10 Ltr. 360.50 2,920.05
Materials
Plastic emulsion paint 16.00 Ltr. 669.50 10,712.00
Total 30,112.05
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,516.80
Grand Total 34,628.85

Two coat aluminium painting work over primer coat in metal


10.22 J6(13-6) Sqm. 263.26 302.75
surface.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 10.75 Nos. 940.00 10,105.00
Labour
Unskilled 10.75 Nos. 650.00 6,987.50
Red oxide Primer 8.10 Ltr. 463.50 3,754.35
Materials Aluminium paint 10.76 Ltr. 504.70 5,430.57
Sand paper 4.00 Nos. 12.36 49.44
Total 26,326.86
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,949.02

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 56 of 79

Rate analysis for :100.00 Sqm.


Grand Total 30,275.88

10.25 J7(13-8A) One coat double boiled Linseed oil painting work . Sqm. 39.83 45.80
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.00 Nos. 940.00 1,880.00
Labour
Unskilled 2.00 Nos. 650.00 1,300.00
Materials Linseed oil paint 6.00 Ltr. 133.90 803.40
Total 3,983.40
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 597.51
Grand Total 4,580.91

10.23 J7(13-8AB) Two coat double boiled Linseed oil painting work . Sqm. 78.32 90.07
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 4.00 Nos. 940.00 3,760.00
Labour
Unskilled 4.00 Nos. 650.00 2,600.00
Materials Linseed oil paint 11.00 Ltr. 133.90 1,472.90
Total 7,832.90
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,174.93
Grand Total 9,007.83

10.24 J8(13-9A) One coat varnish painting work . Sqm. 61.28 70.47
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.00 Nos. 940.00 2,820.00
Labour
Unskilled 2.00 Nos. 650.00 1,300.00
Materials Varnish paint 6.00 Ltr. 334.75 2,008.50
Total 6,128.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 919.27
Grand Total 7,047.77

10.25(A) J8(13-9AB) Two coat varnish painting work . Sqm. 119.22 137.10
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 6.00 Nos. 940.00 5,640.00
Labour
Unskilled 4.00 Nos. 650.00 2,600.00
Materials Varnish paint 11.00 Ltr. 334.75 3,682.25
Total 11,922.25
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,788.33
Grand Total 13,710.58

10.26 J9(13-10A) One coat Bitumen painting work . Sqm. 32.13 36.95
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.50 Nos. 940.00 1,410.00
Labour
Unskilled 1.00 Nos. 650.00 650.00
Materials Bitumen paint 7.00 Ltr. 164.80 1,153.60
Total 3,213.60
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 482.04
Grand Total 3,695.64

10.27 J9(13-10B) Two coat Bitumen painting work . Sqm. 56.27 64.71
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.50 Nos. 940.00 2,350.00
Labour
Unskilled 2.00 Nos. 650.00 1,300.00
Materials Bitumen paint 12.00 Ltr. 164.80 1,977.60
Total 5,627.60
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 844.14
Grand Total 6,471.74

10.28 J10(13-11) Three coat chapra painting work . Sqm. 146.48 168.45
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 10.00 Nos. 940.00 9,400.00
Labour
Unskilled 5.00 Nos. 650.00 3,250.00
Chapra paint 2.00 Kg. 587.10 1,174.20
Materials
Sprit 10.00 Ltr. 82.40 824.00
Total 14,648.20
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,197.23
Grand Total 16,845.43

10.29 J11(13-4C) One coat RED OXIDE painting work . Sqm. 135.18 155.45
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.70 Nos. 940.00 1,598.00
Labour
Unskilled 1.70 Nos. 650.00 1,105.00
Materials Red oxide paint 30.00 Kg. 360.50 10,815.00
Total 13,518.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,027.70

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 57 of 79

Rate analysis for :100.00 Sqm.


Grand Total 15,545.70

10.30 J11(13-4C) Two coat RED OXIDE painting work . Sqm. 230.49 265.06
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.50 Nos. 940.00 3,290.00
Labour
Unskilled 3.50 Nos. 650.00 2,275.00
Materials Red oxide paint 48.50 Kg. 360.50 17,484.25
Total 23,049.25
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,457.38
Grand Total 26,506.63

One coat water proof cement paint painting work in


10.31 J12(13-12A) Sqm. 81.91 94.20
plastered surface
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.50 Nos. 940.00 3,290.00
Labour
Unskilled 3.50 Nos. 650.00 2,275.00
Materials Water proof cement paint 30.00 Kg. 87.55 2,626.50
Total 8,191.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,228.72
Grand Total 9,420.22

J12(13- Two coat water proof cement paint painting work in


10.32 plastered surface Sqm. 147.12 169.19
12AB)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 6.50 Nos. 940.00 6,110.00
Labour
Unskilled 6.50 Nos. 650.00 4,225.00
Materials Water proof cement paint 50.00 Kg. 87.55 4,377.50
Total 14,712.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,206.87
Grand Total 16,919.37

ENAMEL paint painting work over linceed oil in face brick wall
10.33 J15(5-5) Sqm. 189.16 217.53

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.538 Nos. 940.00 505.72
Labour
Unskilled 0.538 Nos. 650.00 349.70
Linseed oil paint 0.538 Ltr. 133.90 72.03
Materials
Enamel paint 1.614 Ltr. 597.40 964.20
Total 1,891.65
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 283.74
Grand Total 2,175.39

One coat enamel painting work without primer coat in wooden


10.34 J16(13-5B) surface. Sqm. 113.76 130.83

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 5.00 Nos. 940.00 4,700.00
Labour
Unskilled 2.00 Nos. 650.00 1,300.00
Materials Enamel paint 9.00 Ltr. 597.40 5,376.60
Total 11,376.60
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,706.49
Grand Total 13,083.09

Two coat enamel painting work without primer coat in wooden


10.35 J17(13-5BC) surface. Sqm. 212.68 244.58

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 9.00 Nos. 940.00 8,460.00
Labour
Unskilled 5.00 Nos. 650.00 3,250.00
Materials Enamel paint 16.00 Ltr. 597.40 9,558.40
Total 21,268.40
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,190.26
Grand Total 24,458.66

One coat plastic emulsion painting work without primer coat.


10.36 J18(13-5B) Sqm. 120.25 138.29

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 5.00 Nos. 940.00 4,700.00
Labour
Unskilled 2.00 Nos. 650.00 1,300.00
Materials Plastic emulsion paint 9.00 Ltr. 669.50 6,025.50
Total 12,025.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,803.82
Grand Total 13,829.32

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 58 of 79

Two coat plastic emulsion painting work without primer coat.


10.37 J19(13-5BC) Sqm. 224.22 257.85

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 9.00 Nos. 940.00 8,460.00
Labour
Unskilled 5.00 Nos. 650.00 3,250.00
Materials Plastic emulsion paint 16.00 Ltr. 669.50 10,712.00
Total 22,422.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,363.30
Grand Total 25,785.30

One coat aluminium painting work without primer coat in


10.38 J20(13-6) Sqm. 87.14 100.22
metal surface.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.75 Nos. 940.00 3,525.00
Labour
Unskilled 3.75 Nos. 650.00 2,437.50
Aluminium paint 5.38 Ltr. 504.70 2,715.28
Materials
Sand paper 3.00 Nos. 12.36 37.08
Total 8,714.86
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,307.22
Grand Total 10,022.08

Two coat aluminium painting work without primer coat in


10.39 J21(13-6) Sqm. 178.02 204.72
metal surface.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 7.75 Nos. 940.00 7,285.00
Labour
Unskilled 7.75 Nos. 650.00 5,037.50
Aluminium paint 10.76 Ltr. 504.70 5,430.57
Materials
Sand paper 4.00 Nos. 12.36 49.44
Total 17,802.51
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,670.37
Grand Total 20,472.88

10.40 J22(13-7) One coat RED OXIDE painting work without primer coat Sqm. 93.73 107.80
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 4.33 Nos. 940.00 4,070.20
Labour
Unskilled 4.00 Nos. 650.00 2,600.00
Materials Red oxide paint 7.50 Ltr. 360.50 2,703.75
Total 9,373.95
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,406.09
Grand Total 10,780.04

10.41 J23(13-7) Two coat RED OXIDE painting work without primer coat Sqm. 187.57 215.70
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 8.67 Nos. 940.00 8,149.80
Labour
Unskilled 8.00 Nos. 650.00 5,200.00
Materials Red oxide paint 15.00 Ltr. 360.50 5,407.50
Total 18,757.30
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,813.59
Grand Total 21,570.89

10.44 J26 Two coat washable distemper painting work over primer Sqm. 167.20 192.28
Resources Level/Type coat. Quantity Unit Rate Amount Remarks
Skilled 5.80 Nos. 940.00 5,452.00
Labour
Unskilled 5.80 Nos. 650.00 3,770.00
Distemper primer 8.00 Ltr. 360.50 2,884.00
Materials
Distemper washable 16.00 Kg. 288.40 4,614.40
Total 16,720.40
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,508.06
Grand Total 19,228.46
K - Damp proofing work

20 mm thick D.P.C. work in cement sand mortar in 1:2 with


11.01 K1(18-7) W.P.Compound. Sqm. 415.62 477.96

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.750 Nos. 940.00 705.00
Labour
Unskilled 0.800 Nos. 650.00 520.00
Cement 0.135 M.T. 17,510.00 2,363.85
Materials Sand crusher(Badahari khola) 0.180 Cum. 1,607.25 289.30
W.P.Compound 2.700 Kg. 103.00 278.10
Total 4,156.25
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 623.43
Grand Total 4,779.68

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 59 of 79

25 mm thick D.P.C. work in cement concrete in 1:1½:3


11.02 K2(18-8) Sqm. 460.16 529.19
withwith W.P.Compound.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.0000 Nos. 940.00 940.00
Labour
Unskilled 1.2500 Nos. 650.00 812.50
Cement 0.1125 M.T. 17,510.00 1,969.87
Sand crusher(Badahari khola) 0.1130 Cum. 1,607.25 181.61
Materials
Aggrigate 12 mm 0.2500 Cum. 1,863.75 465.93
W.P.Compound 2.2500 Kg. 103.00 231.75
Total 4,601.66
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 690.24
Grand Total 5,291.90

38 mm thick D.P.C. work in cement concrete in 1:2:4 with


11.03 18-9 Sqm. 554.47 637.64
with W.P.Compound.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 940.00 940.00
Labour
Unskilled 2.000 Nos. 650.00 1,300.00
Cement 0.120 M.T. 17,510.00 2,101.20
Sand crusher(Badahari khola) 0.170 Cum. 1,607.25 273.23
Materials
Aggrigate 12 mm 0.340 Cum. 1,863.75 633.67
W.P.Compound 2.880 Kg. 103.00 296.64
Total 5,544.74
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 831.71
Grand Total 6,376.45

11.05 K4(18-11) 500 gauge polythine sheet laying work Sqm. 152.05 174.85
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.600 Nos. 940.00 564.00
Labour
Unskilled 0.600 Nos. 650.00 390.00
Materials Polythine sheet 500 gauge 11.000 Sqm. 51.50 566.50
Total 1,520.50
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 228.07
Grand Total 1,748.57

11.06 K5(18-12A) One layer tarfelt laying work. Sqm. 826.68 950.68
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.100 Nos. 940.00 1,034.00
Labour
Unskilled 3.500 Nos. 650.00 2,275.00
Tarfelt 11.000 Sqm. 144.20 1,586.20
Bitumen 15.000 Kg. 123.60 1,854.00
Materials
Fire wood 60.000 Kg. 16.99 1,019.40
Sand crusher(Badahari khola) 0.310 Cum. 1,607.25 498.24
Total 8,266.84
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,240.02
Grand Total 9,506.86

11.07 K5(18-12B) Two layer tarfelt laying work. Sqm. 1,327.18 1,526.26
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.300 Nos. 940.00 2,162.00
Labour
Unskilled 4.600 Nos. 650.00 2,990.00
Tarfelt 22.000 Sqm. 144.20 3,172.40
Bitumen 25.000 Kg. 123.60 3,090.00
Materials
Fire wood 80.000 Kg. 16.99 1,359.20
Sand crusher(Badahari khola) 0.310 Cum. 1,607.25 498.24
Total 13,271.84
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,990.77
Grand Total 15,262.61

11.08 K6(18-13A) One layer damp proof grade tarfelt laying work. Sqm. 1,040.40 1,196.46
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.350 Nos. 940.00 2,209.00
Labour
Unskilled 4.600 Nos. 650.00 2,990.00
Damp proof grade tarfelt 11.000 Sqm. 144.20 1,586.20
Bitumen 17.000 Kg. 123.60 2,101.20
Materials
Fire wood 60.000 Kg. 16.99 1,019.40
Sand crusher(Badahari khola) 0.310 Cum. 1,607.25 498.24
Total 10,404.04
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,560.60
Grand Total 11,964.64

11.09 K6(18-13B) Two layer damp proof grade tarfelt laying work. Sqm. 1,926.20 2,215.13
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.500 Nos. 940.00 3,290.00
Labour
Unskilled 11.700 Nos. 650.00 7,605.00

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 60 of 79

Damp proof grade tarfelt 22.000 Sqm. 144.20 3,172.40


Bitumen 27.000 Kg. 123.60 3,337.20
Materials
Fire wood 80.000 Kg. 16.99 1,359.20
Sand crusher(Badahari khola) 0.310 Cum. 1,607.25 498.24
Total 19,262.04
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 2,889.30
Grand Total 22,151.34

Two coat elastocret cementious elastomeric water


11.10 K7 proofing work Sqm. 531.97 611.76

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.000 Nos. 940.00 -
Labour
Unskilled 0.000 Nos. 650.00 -
lastocret cementious elastomeric water
Materials
proofing 1.000 Sqm. 531.97 531.97
Total 531.97
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 79.79
Grand Total 611.76

11.11 K8(18-14) One coat rain Crystallization seal paint or equivalent paint Sqm. 139.15 160.02
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.000 Nos. 940.00 -
Labour
Unskilled 0.000 Nos. 650.00 -
Materials Crystallization seal 0.245 Sqm. 567.99 139.15
Total 139.15
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 20.87
Grand Total 160.02

Expansion Joint Works: - Chipping and laying thermocol


in the hole, masking tape on the thermocol and plaster
with mixing Perma Bond SBR or eqv. modified mortar up
11.12 0 to 40 mm wide and levelling all complete. Sqm. 6,864.95 7,894.69

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.000 Nos. 940.00 -
Labour
Unskilled 0.000 Nos. 650.00 -
Materials Expansion joint materials 1.000 sqm 6,864.95 6,864.95
Total 6,864.95
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 1,029.74
Grand Total 7,894.69

L - MAINTAINANCE & DISMANTLING WORK

Dismantling work of mud masonry wall & removing of


12.01 L1(19-1) material upto 10 mtr lead. Cum. 689.00 792.35

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 1.060 Nos. 650.00 689.00
Total 689.00
Rate analysis for :1.00 Cum. 15 % Contractor overhead 103.35
Grand Total 792.35

Dismantling work of cement masonry wall & removing of


12.02 L2(19-2) material upto 10 mtr lead. Cum. 1,378.00 1,584.70

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 2.120 Nos. 650.00 1,378.00
Total 1,378.00
Rate analysis for :1.00 Cum. 15 % Contractor overhead 206.70
Grand Total 1,584.70

Dismantling work of R.C.C. / R.B.C. & removing of material


12.03 L3(19-3) upto 10 mtr lead. Cum. 7,150.00 8,222.50

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 11.000 Nos. 650.00 7,150.00
Total 7,150.00
Rate analysis for :1.00 Cum. 15 % Contractor overhead 1,072.50
Grand Total 8,222.50

Dismantling work of P.C.C. / L.C.C. & removing of material


12.04 L4(19-4) upto 10 mtr lead. Cum. 2,600.00 2,990.00

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 4.000 Nos. 650.00 2,600.00
Total 2,600.00
Rate analysis for :1.00 Cum. 15 % Contractor overhead 390.00

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 61 of 79

Rate analysis for :1.00 Cum.


Grand Total 2,990.00

Dismantling work of cement sand / lime surkhee plaster &


12.05 L5(19-5) removing of material upto 10 mtr lead. Sqm. 70.20 80.73

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.108 Nos. 650.00 70.20
Total 70.20
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 10.53
Grand Total 80.73

Dismantling work of tile roof & removing of all material


12.06 L6(19-6) wood, tile upto 10 mtr lead. Sqm. 103.41 118.92

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.054 Nos. 940.00 50.76
Labour
Unskilled 0.081 Nos. 650.00 52.65
Total 103.41
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 15.51
Grand Total 118.92

Wood preservative paint painting work


12.07 L7 Sqm. 360.12 414.13

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.22 Nos. 940.00 206.80
Labour
Unskilled 0.100 Nos. 650.00 65.00
Wood preservative paint 0.245 Ltr. 360.50 88.32
Total 360.12
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 54.01
Grand Total 414.13

Clearance work of old existing marble floor with Oxalic


12.08 L11 acid & carborendum stone Sqm.. 240.62 276.71

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled - Nos. 940.00 -
Labour
Unskilled 3.375 Nos. 650.00 2,193.75
Oxalic acid powder 0.185 Kg. 118.45 21.91 NCN 11-6
Materials
Carborendam Stone 1.000 Nos. 190.55 190.55 L.S.
Total 2,406.21
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 360.93
Grand Total 2,767.14

Clearance work of old existing parket & polishing work


12.09 L12 Sqm.. 219.37 252.28

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled - Nos. 940.00 -
Labour
Unskilled 3.375 Nos. 650.00 2,193.75
Sand paper Kg. 12.36 - L.S.
Materials
Main polish Nos. 442.90 - L.S.
Total 2,193.75
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 329.06
Grand Total 2,522.81

Clearance work of old existing mosaic floor with Oxalic


12.10 L13 acid , main polish , terpantain oil & carborendum stone Sqm.. 255.24 293.52

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled - Nos. 940.00 -
Labour
Unskilled 3.375 Nos. 650.00 2,193.75
Oxalic acid powder 0.370 Kg. 118.45 43.82
Main Polish 0.118 Kg. 442.90 52.26
Materials
Tarpaintain oil 0.538 Ltr. 133.90 72.03
Carborendam Stone 1.000 Nos. 190.55 190.55 L.S.
Total 2,552.41
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 382.86
Grand Total 2,935.27

Clearance work of brick from mud masonry wall &


12.11 L14(A) stacking of brick for re-used Nos. 2.82 3.25

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.040 Nos. 940.00 37.60
Labour
Unskilled 3.900 Nos. 650.00 2,535.00
Equipment Pully, dori,gas cutter & gas etc 10% of Labour 257.26
Total 2,829.86
Rate analysis for : 1000.00 Nos. 15 % Contractor overhead 424.47
Grand Total 3,254.33

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 62 of 79

Clearance work of brick from cement masonry wall &


12.12 L14(C) stacking of brick for re-used Nos. 4.70 5.41

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.200 Nos. 940.00 1,128.00
Labour
Unskilled 4.850 Nos. 650.00 3,152.50
Equipment Pully, dori,gas cutter & gas etc 10% of Labour 428.05
Total 4,708.55
Rate analysis for : 1000.00 Nos. 15 % Contractor overhead 706.28
Grand Total 5,414.83

Clearance work of stone from cement masonry wall &


12.13 L15(B) stacking of stone for re-used Cum. 1,002.01 1,152.31

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.220 Nos. 940.00 206.80
Labour
Unskilled 1.150 Nos. 650.00 747.50
Equipment Pully, dori,gas cutter & gas etc 5% of Labour 47.71
Total 1,002.01
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 150.30
Grand Total 1,152.31

Clearance work of stone from mud masonry wall &


12.13a L15(B) stacking of stone for re-used Cum. 813.90 935.98

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.183 Nos. 940.00 172.33
Labour
Unskilled 0.927 Nos. 650.00 602.82
Equipment Pully, dori,gas cutter & gas etc 5% of Labour 38.75
Total 813.90
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 122.08
Grand Total 935.98

Dismantling work of R. C. C. barbed wire fencing work


12.14 L19(A) with earthwork excavation filling & leveling Sqm. 292.50 336.37

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled - Nos. 940.00 -
Labour
Unskilled 0.450 Nos. 650.00 292.50
Total 292.50
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 43.87
Grand Total 336.37

Dismantling work of IRON. barbed wire fencing work with


12.15 L19(B) earthwork excavation filling & leveling Sqm. 273.00 313.95

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled - Nos. 940.00 -
Labour
Unskilled 0.420 Nos. 650.00 273.00
Total 273.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 40.95
Grand Total 313.95

Dismantling work of WOODEN. barbed wire fencing work


12.16 L19(C) with earthwork excavation filling & leveling Sqm. 260.00 299.00

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled - Nos. 940.00 -
Labour
Unskilled 0.400 Nos. 650.00 260.00
Total 260.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 39.00
Grand Total 299.00

Dismantling work of M.S. bar from R.C.C./R.B.C.&


12.17 L19(C) stacking upto 10 mtr. Sqm. 874.00 1,005.10

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.100 Nos. 940.00 94.00
Labour
Unskilled 1.200 Nos. 650.00 780.00
Total 874.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 131.10
Grand Total 1,005.10

Dismantling work of Gavian work


12.18 L21 Sqm. 946.50 1,088.47

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 940.00 940.00
Labour

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 63 of 79

Labour
Unskilled 0.010 Nos. 650.00 6.50
Total 946.50
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 141.97
Grand Total 1,088.47

Dismantling work of cgi sheet roof & removing of all


12.19 L22 material wood, cgi sheet upto 10 mtr lead. Sqm. 51.38 59.08

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.027 Nos. 940.00 25.38
Labour
Unskilled 0.040 Nos. 650.00 26.00
Total 51.38
Rate analysis for :1.00 Sqm. 15 % Contractor overhead 7.70
Grand Total 59.08

M - METAL, FENCING & RAILING WORK

3 x 20mm Metal Grill including manufacturing, fitting, painting


13.01 M1(24-1A) with Aluminium paint, sand papering all complete Sqm. 2,472.00 2,842.80

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Skilled - Nos. 940.00 -
Material MS grill 3*20 mm (15 kg/sqm) 150.000 Kg. 164.80 24,720.00
Total 24,720.00
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 3,708.00
Grand Total 28,428.00

4 x 20mm Metal Grill including manufacturing, fitting, painting


13.02 M2(24-1B) with Aluminium paint, sand papering all complete Sqm. 3,543.20 4,074.68

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Skilled - Nos. 940.00 -
Material MS grill 4.5*20 mm (21.5 kg/sqm) 215.000 Kg. 164.80 35,432.00
Total 35,432.00
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 5,314.80
Grand Total 40,746.80

12x12 mm solid core square rod M. S. grill with 4 x 20mm


13.03 M3 Metal frame Sqm. 2,125.69 2,444.55

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.700 Nos. 940.00 658.00
Labour
Unskilled 0.600 Nos. 650.00 390.00
MS plate 4.5*20 mm 28.240 Kg. 143.17 4,043.12
Material Square rod 12 mm solid core 215.000 Kg. 75.19 16,165.85
Total 21,256.97
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 3,188.54
Grand Total 24,445.51

Fabricating, supplying & fixing of different size M.S. angle


13.04 M4 Kg. 189.77 218.24

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.687 Nos. 940.00 645.78
Labours
Unskilled 0.781 Nos. 650.00 507.65
MS angle different size 18.940 Kg. 123.60 2,340.98
Material
Primer etc L.S. 100.00
Total 3,594.41
Rate analysis for :18.94 Kg. 15 % Contractor overhead 539.16
Grand Total 4,133.57

13.05 M5 Spiral stair case 3.00 mtr height 90 cm. width Rmtr. 10,304.12 11,849.73

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled - Nos. 940.00 -
Labour
Unskilled - Nos. 650.00 -
MS Spiral Staircase Readymade 1.00 Rmtr. 10,304.12 10,304.12
Total 10,304.12
Rate analysis for : 1.00 Rmtr. 15 % Contractor overhead 1,545.61
Grand Total 11,849.73

Providing & fixing MS folded sheet rolling shutters with


13.06 M6(24-2) iron clamps, spring and axle of good quality finish with one Sqm. 3,862.50 4,441.87
coat red- oxide paint on shutter and oiling on spring and axle.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled - Nos. 940.00 -
Labour
Unskilled - Nos. 650.00 -

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 64 of 79

Rolling Shutter 1.00 Nos. 3,862.50 3,862.50


Total 3,862.50
Rate analysis for : 1.00Rmtr 15 % Contractor overhead 579.37
Grand Total 4,441.87

Collapsible shutter including manufacturing, welding, supply


13.07 M7(24-4) Sqm. 5,232.40 6,017.26
of material, painting and fixing
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Skilled - Nos. 940.00 -
Material Collapisible gate (60 kg/sqm.) 10.00 Sqm. 5,232.40 52,324.00
Total 52,324.00
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 7,848.60
Grand Total 60,172.60

Providing and fixing MS gate as per drawing with 50 mm X


50 mm X 3 mm MS angle, 25 mm X 25 mm MS square pipe,
13.08 M8(24-3) 16 gauge MS flat sheet, 12 mm X 3 mm MS flat , ready Sqm. 4,362.50 5,016.87
made pivot hing welded to 175 mm long angle hold fast
embedded in concrete and iron locking arrangement over one
coat primer .
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Fixing charge L.S. 5,000.00
Material MS grill gate 5*20 mm(35 kg/sqm) 10.00 Sqm. 3,862.50 38,625.00
Total 43,625.00
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 6,543.75
Grand Total 50,168.75

Providing and fixing MS gate as per drawing with 50 mm X


50 mm X 3 mm MS angle, 25 mm X 25 mm MS square pipe,
13.09 M8(24-3) ready made pivot hing welded to 175 mm long angle hold fast Sqm. 4,362.50 5,016.87
embedded in concrete and iron locking arrangement over one
coat primer.

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Fixing charge L.S. 5,000.00
MS grill gate 5*25 mm(40 kg/sqm) M.
Material
sheet 10.00 Sqm. 3,862.50 38,625.00
Total 43,625.00
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 6,543.75
Grand Total 50,168.75

Supplying and fixing of Barbed wire 14 gauge including


13.10 M9(24-6) Rmtr. 175.87 202.26
hooks, nails etc
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.076 Nos. 940.00 1,011.44
Labours
Unskilled 5.380 Nos. 650.00 3,497.00
Barbed wire 14 gauge 110.00 Rmtr. 118.45 13,029.50
Material
U-nail, killa etc L. S. 50.00
Total 17,587.94
Rate analysis for :100.00 Rmtr. 15 % Contractor overhead 2,638.19
Grand Total 20,226.13

Supplying and fixing of Barbed wire 12 gauge including


13.11 M10(24-7) hooks, nails etc 5 H+2D with 75x100 mm sal wood 2100 mm Rmtr. 2,379.88 2,736.86
long .
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 940.00 940.00
Labours
Unskilled 2.000 Nos. 650.00 1,300.00
Wood Sal 0.190 Cum. 220,935.00 41,977.65
Material Barbed wire 12 gauge 250.000 Rmtr. 108.15 27,037.50
U-nail 77.000 Nos. 1.84 141.35
Total 71,396.50
Rate analysis for :30.00 Rmtr. 15 % Contractor overhead 10,709.47
Grand Total 82,105.97

Fabricating, supplying & fixing of different size M.S. black


13.12 M11 pipe Truss with metal primer Kg. 169.17 194.55

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.687 Nos. 940.00 645.78
Labours
Unskilled 0.781 Nos. 650.00 507.65
MS black pipe 18.940 Kg. 103.00 1,950.82
Material
Primer etc L.S. 100.00
Total 3,204.25
Rate analysis for : 18.94 Kg. 15 % Contractor overhead 480.63
Grand Total 3,684.88

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 65 of 79

Supplying & fixing work of 50 mm Ø MS black pipe @ 2.0


mtr with 10 S.W.G.G. I. Chain Link 2"x2" mesh size fixing
13.13 M12 in 4x20x20 mm & 4x25x25 mm ms angle frame & top 3x20 Sqm. 3,172.26 3,648.10
mm MS grill 15 cm height with primer coat..

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 7.000 Nos. 940.00 6,580.00
Labours 9,830.00
Unskilled 5.000 Nos. 650.00 3,250.00
MS Black pipe 35.510 Kg. 103.00 3,657.53
Angle 4x25x25 32.060 Kg. 123.60 3,962.61
Material Angle 4x20x20 25.190 Kg. 123.60 3,113.48 19,037.06
Grill 3x20 14.760 Kg. 164.80 2,432.44
Chain Link 2"x2" mesh (10 SWG G. I.) 10.000 Kg. 587.10 5,871.00
Fabrication charge 15% of materials 2,855.56
Total 31,722.62
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 4,758.39
Grand Total 36,481.01

Supplying & fixing work of 50 mm Ø MS black pipe @ 2.0


mtr with 7 mm Ø TMT bar mesh 62x62 mm size 4x25x25
13.14 M13 mm ms angle frame & top 3x20 mm MS grill 15 cm height Sqm. 2,816.35 3,238.81
with primer coat..

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 7.000 Nos. 940.00 6,580.00
Labours 9,830.00
Unskilled 5.000 Nos. 650.00 3,250.00
MS Black pipe 35.510 Kg. 103.00 3,657.53
Angle 32.060 Kg. 123.60 3,962.61
Material 15,942.26
MS grill 14.760 Kg. 164.80 2,432.44
TMT reinforcement bar 7 mm Ø 66.490 Kg. 88.58 5,889.68
Fabrication charge 15% of materials 2,391.33
Total 28,163.59
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 4,224.53
Grand Total 32,388.12

13.15 M14 900 mm height stainless steel staircase railing work Sqm. 4,212.70 4,844.60
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled Nos. 940.00 -
Labours -
Unskilled Nos. 650.00 -

Stainless Steel 50mm dia Handrail in


2.00m.distance with 50mm dia.vertical
Material 4,212.70
post & 3 layer Horizontal 25mm
dia.stainless steel member ,2.5' to 3'
height Railing with Painting & fixing. 1.000 Rmtr. 4,212.70 4,212.70
Total 4,212.70
Rate analysis for : 1.00Rm 15 % Contractor overhead 631.90
Grand Total 4,844.60

Supplying & fixing work of 38 mm Ø stainless steel pipe


post @ 2.0 mtr , 8 mm Ø stainless steel pipe hand rail with
13.16 M15 two rows 25 mm Ø stainless steel pipe in between ground Sqm. 3,308.24 3,804.48
& hand rail.

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 7.780 Nos. 940.00 7,313.20
Labours 14,690.70
Unskilled 11.350 Nos. 650.00 7,377.50
Stainless steel pipe 38 mm Ø 15.490 Rmtr. 387.28 5,998.96
Material 11,004.76
Stainless steel pipe 25 mm Ø 20.000 Rmtr. 250.29 5,005.80
Gas welding charge 9.150 LS 500.00 4,575.00
Total 30,270.46
Rate analysis for : 9.15 Sqm. 15 % Contractor overhead 4,540.57
Grand Total 34,811.03

Supplying & fixing work of 150x150 mm size sisham wood


13.17 M16 ornamental post , 75x75 mm size bluster with 75x100 mm Sqm. - -
hand rail.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 5.720 Nos. 940.00 5,376.80
Labours 5,714.80
Unskilled 0.520 Nos. 650.00 338.00
Material Wood Sisham 0.329 Cum. 120,098.00 39,512.24 39,512.24
Ornamental work 9.000 Sqm. -
Total
Rate analysis for : 9.00 Sqm. 15 % Contractor overhead
Grand Total

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 66 of 79

Hand rail 3"x4" size sisham wood supplying & fixing work
13.18 M17 Rmtr. 1,095.76 1,260.12

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.100 Nos. 940.00 94.00 LS
Labours
Unskilled 0.100 Nos. 650.00 65.00 LS
Material Wood sisham 0.0078 Cum. 120,098.00 936.76
Total 1,095.76
Rate analysis for : 1.00 Rmtr 15 % Contractor overhead 164.36
Grand Total 1,260.12

Supplying & fixing work of 20x20 mm square pipe railing


13.19 M18 two nos. every trade 900 to 1000 mm height with 3"x4" Rmtr. 2,190.87 2,519.50
sisham wood hand rail
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.200 Nos. 940.00 188.00
Labours
Unskilled 0.200 Nos. 650.00 130.00
Material Wood sisham 0.024 Cum. 120,098.00 2,930.39
Square pipe1"x1" 16.200 Rmtr 75.19 1,218.07
MS plate 4x20 2.650 kgs 143.17 379.40
MS Black pipe 40mm dia. 6.500 kgs 103.00 669.50
Welding charge ls 400.00
Total 5,915.36
Rate analysis for : 2.70 Rmtr 15 % Contractor overhead 887.30
Grand Total 6,802.66

Supplying & fixing work of 20x20 mm square pipe railing


13.20 M19 two nos. every trade 900 to 1000 mm height with 40 mm Rmtr. 1,607.31 1,848.40
MS black pipe hand rail
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.000 Nos. 940.00 -
Labours -
Unskilled 0.000 Nos. 650.00 -
Material Square pipe1"x1" 18.200 Kg. 75.19 1,368.45
MS plate 4x20 4.600 kgs 143.17 658.58
MS Black pipe 40mm dia. 18.570 kgs 103.00 1,912.71
Welding charge ls 400.00
Total 4,339.74
Rate analysis for : 2.70 Rmtr 15 % Contractor overhead 650.96
Grand Total 4,990.70

O - ROAD WORK
Subgrade prepairing work with simple mud cutting 10
15.01 O1 Sqm. 100.42 115.48
mtr. lead
Resources Level/Type Quantity Unit Rate Amount Remarks
Labours Unskilled 0.150 Nos. 650.00 97.50
Material T&P 3 % of labour 2.92
Total 100.42
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 15.06
Grand Total 115.48

15.02 O2 Rolling work Sqm. 8.05 9.25


Resources Level/Type Quantity Unit Rate Amount Remarks
Labours Unskilled 0.500 Nos. 650.00 325.00
Equipment Road roller 8-10 M.T. 1.600 Hours 300.00 480.00
Total 805.00
Rate analysis for : 100.00 Cum. 15 % Contractor overhead 120.75
Grand Total 925.75

10 cm. compact sub base laying work with sand mixed


15.03 O3(15-9A) gravel, load unload & proper levelling. Sqm. 291.36 335.06

Resources Level/Type Quantity Unit Rate Amount Remarks


Labours Unskilled 0.150 Nos. 650.00 97.50
Material Sand mixed gravel 0.128 Cum. 1,493.50 191.16
Equipment Road roller 8-10 M.T. 0.009 Hours 300.00 2.70
Total 291.36
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 43.70
Grand Total 335.06

15 cm. compact sub base laying work with sand mixed


15.04 O3(15-9C) gravel, load unload & proper levelling. Sqm. 414.15 476.27

Resources Level/Type Quantity Unit Rate Amount Remarks


Labours Unskilled 0.190 Nos. 650.00 123.50
Material Sand mixed gravel 0.192 Cum. 1,493.50 286.75
Equipment Road roller 8-10 M.T. 0.013 Hours 300.00 3.90

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 67 of 79

Total 414.15
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 62.12
Grand Total 476.27

20 cm. compact sub base laying work with sand mixed


15.05 O3(15-9D) gravel, load unload & proper levelling. Sqm. 524.23 602.86

Resources Level/Type Quantity Unit Rate Amount Remarks


Labours Unskilled 0.210 Nos. 650.00 136.50
Material Sand mixed gravel 0.256 Cum. 1,493.50 382.33
Equipment Road roller 8-10 M.T. 0.018 Hours 300.00 5.40
Total 524.23
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 78.63
Grand Total 602.86

25 Misclenious WORK

Alluminium fixed panel window With ventilation but


25.01 without fly mesh shutter from section( 88mmx38.1mm Sqm. 6,386.00 7,343.90
x1.3mm , Glass 5mm)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.00 Nos. 940.00 -
Labour
Unskilled 0.00 Nos. 650.00 -
Alluminium fixed panel window With
ventilation but without fly mesh shutter
Materials 1.00 Sqm. 6,386.00 6,386.00
from section( 88mmx38.1mm x1.3mm ,
Glass 5mm)
Total 6,386.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 957.90
Grand Total 7,343.90

Alluminium fixed panel window With Ventilation with fly


25.02 mesh shutter from section(88mmx38.1mm x1.3mm , Glass Sqm. 6,798.00 7,817.70
5mm )
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.00 Nos. 940.00 -
Labour
Unskilled 0.00 Nos. 650.00 -
Alluminium fixed panel window With
Ventilation with fly mesh shutter from
Materials 1.00 Sqm. 6,798.00 6,798.00
section(88mmx38.1mm x1.3mm , Glass
5mm )
Total 6,798.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 1,019.70
Grand Total 7,817.70

Alluminium framed Sliding window Without ventilator


25.03 ( Aluminium :- Natural anodised 101mmx45mm x1.50mm , Sqm. 6,695.00 7,699.25
Glass 5mm clear)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.00 Nos. 940.00 -
Labour
Unskilled 0.00 Nos. 650.00 -
Alluminium framed Sliding window
Without ventilator ( Aluminium :-
Materials 1.00 Sqm. 6,695.00 6,695.00
Natural anodised 101mmx45mm
x1.50mm , Glass 5mm clear)
Total 6,695.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 1,004.25
Grand Total 7,699.25

Alluminium framed Sliding window With ventilator


25.04 ( Aluminium :- Natural anodised 101mmx45mm x1.5mm , Sqm. 7,210.00 8,291.50
Glass 5mm clear)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.00 Nos. 940.00 -
Labour
Unskilled 0.00 Nos. 650.00 -
Alluminium framed Sliding window
With ventilator ( Aluminium :- Natural
Materials 1.00 Sqm. 7,210.00 7,210.00
anodised 101mmx45mm x1.5mm ,
Glass 5mm clear)
Total 7,210.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 1,081.50
Grand Total 8,291.50

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 68 of 79

Alluminium framed Sliding Door ( Aluminium :- Natural


25.05 anodised 101mmx45mm x1.5mm ,) with sash 40*45*1.5mm Sqm. 7,622.00 8,765.30
and 5mm glass

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.00 Nos. 940.00 -
Labour
Unskilled 0.00 Nos. 650.00 -
Alluminium framed Sliding Door
( Aluminium :- Natural anodised
Materials 1.00 Sqm. 7,622.00 7,622.00
101mmx45mm x1.5mm ,) with sash
40*45*1.5mm and 5mm glass
Total 7,622.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 1,143.30
Grand Total 8,765.30

Casement double panel aluminium window With


25.06 ventilator section of ( 54mmx33mm x1.5)mm with sash Sqm. 7,210.00 8,291.50
38*34*1.5mm with Glass 5mm
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.00 Nos. 940.00 -
Labour
Unskilled 0.00 Nos. 650.00 -
Casement double panel aluminium
window With ventilator section of
Materials 1.00 Sqm. 7,210.00 7,210.00
( 54mmx33mm x1.5)mm with sash
38*34*1.5mm with Glass 5mm
Total 7,210.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 1,081.50
Grand Total 8,291.50

Alluminium Casement Door section of ( 101mmx45mm


25.07 Sqm. 12,360.00 14,214.00
x1.1)mm sash 40*45*1.1mm & Glass 5mm

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.00 Nos. 940.00 -
Labour
Unskilled 0.00 Nos. 650.00 -
Alluminium Casement Door section of
( 101mmx45mm x1.1)mm sash
Materials 1.00 Sqm. 12,360.00 12,360.00
40*45*1.1mm & Glass 5mm

Total 12,360.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 1,854.00
Grand Total 14,214.00

Alluminium framed Swing Door section of (101mmx45mm


25.08 Sqm. 7,879.50 9,061.42
x1.5)mm & Glass 5mm clear

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.00 Nos. 940.00 -
Labour
Unskilled 0.00 Nos. 650.00 -
Alluminium framed Swing Door
Materials section of (101mmx45mm x1.5)mm & 1.00 Sqm. 7,879.50 7,879.50
Glass 5mm clear
Total 7,879.50
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 1,181.92
Grand Total 9,061.42

Alluminium framed Sliding window 2 track section of


25.09 Sqm. 6,180.00 7,107.00
(88mmx38mm x1.5)mm & Glass 5mm

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.00 Nos. 940.00 -
Labour
Unskilled 0.00 Nos. 650.00 -
Alluminium framed Sliding window 2
Materials track section of (88mmx38mm 1.00 Sqm. 6,180.00 6,180.00
x1.5)mm & Glass 5mm
Total 6,180.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 927.00
Grand Total 7,107.00

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Rate_Analysis_Dhanusha_Civil_2075/076 Page 69 of 79

Alluminium fixed window and partition with fixed


25.10 ventilator from 9mm bord and section (101mmx45mm Sqm. 6,180.00 7,107.00
x1.5)mm
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.00 Nos. 940.00 -
Labour
Unskilled 0.00 Nos. 650.00 -
Alluminium fixed window and partition
with fixed ventilator from 9mm bord
Materials 1.00 Sqm. 6,180.00 6,180.00
and section (101mmx45mm x1.5)mm

Total 6,180.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 927.00
Grand Total 7,107.00

Alluminium partition with 5mm thick glass & 9mm thick


25.11 Sqm. 6,180.00 7,107.00
laminated bord of section (101mmx45mm x1.5)mm

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.00 Nos. 940.00 -
Labour
Unskilled 0.00 Nos. 650.00 -
Alluminium partition with 5mm thick
glass & 9mm thick laminated bord of
Materials 1.00 Sqm. 6,180.00 6,180.00
section (101mmx45mm x1.5)mm

Total 6,180.00
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 927.00
Grand Total 7,107.00

False ceiling by Gypsum, Gypsum board 12.5 mm With


25.12 providing,finisging og joint with compound & tape all Sqm. 906.40 1,042.36
complete
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.00 Nos. 940.00 -
Labour
Unskilled 0.00 Nos. 650.00 -

Materials
False ceiling by Gypsum ,Gypsum 1.00 Sqm. 906.40 906.40
Board : 12.5mm
Total 906.40
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 135.96
Grand Total 1,042.36

11.09 K6(18-13B) ASO Joint Tape laying Work. Rm - -


Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.100 Nos. 940.00 94.00
Labour
Unskilled 0.000 Nos. 650.00 -
ASO Joint Tape laying Work. 1.100 Rm 741.60 815.76 rm=720.00
Materials Two coat elastocret cementious
elastomeric water proofing work 0.100 sqm - -
Total -
Rate analysis for :1.00 Rm. 15 % Contractor overhead -
Grand Total -

-------------------Prepared by : -----------------Checked by : --------------------Approved by :


Aditional_Analysis Rate_Analysis_Udayapur_Civil_2074/075 Page 70 of 79

20 mm thick Sal wood planking work with 50x75 mm


8.23 H21(11-21) sal wood frame in 600x600 mm Sqm. 5,323.93 6,122.52

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 6.500 Nos. 940.00 6,110.00
Labour
Unskilled 0.650 Nos. 650.00 422.50
Wood Sal 0.211 Cum. 220,935.00 46,506.81
Materials
Killa 200.00
Total 53,239.31
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 7,985.89
Grand Total 61,225.20

Stone filling in trench with proper leveling


3.18 C10( 6-5) (Ex.Boulder Used) Cum. 975.00 1,121.25

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 1.50 Nos. 650.00 975.00
Stone block 0.00 Cum. 2,420.50 -
Materials
Stone bond 0.00 Cum. 2,060.00 -
Total 975.00
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 146.25
Grand Total 1,121.25

t= Uoflaogsf] sfd
P1 Gabion making work with wire Per Box 3,889.28 4,472.67
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.450 Nos. 940.00 423.00
Labour
Unskilled 0.200 Nos. 650.00 130.00
Unskilled 0.300 Nos. 650.00 195.00
Gavion wire commercial 30.600 kgs 87.55 2,679.03
Materials Selwage wire 9swg 3.900 kgs 90.64 353.49
Binding wire 11swg 1.200 kgs 90.64 108.76
Total 3,889.28
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 583.39
Grand Total 4,472.67

Supplying & filling of Boulder in Gabion box cum 2,745.50 3,157.32


Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled Nos. 940.00 -
Labour
Unskilled 0.500 Nos. 650.00 325.00
Materials Stone block 1.000 cum 2,420.50 2,420.50
Total 2,745.50
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 411.82

Grand Total 3,157.32

fixing of existing Barbed wire 14 gauge including


13.10 M9(24-6) Rmtr. 45.58 52.42
hooks, nails etc
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.076 Nos. 940.00 1,011.44
Labours
Unskilled 5.380 Nos. 650.00 3,497.00
Barbed wire 14 gauge Rmtr. 118.45 -
Material
U-nail, killa etc L. S. 50.00
Total 4,558.44
Rate analysis for :100.00 Rmtr. 15 % Contractor overhead 683.76
Grand Total 5,242.20
t= Uoflaogsf] sfd

Prepared By:- Checked By:- Approved By:-


Aditional_Analysis Rate_Analysis_Udayapur_Civil_2074/075 Page 71 of 79

Gabion making work with wire


cutting,weaving,Square mess size:
16.00 9-kha 150x150mm,mess wire 10 swg selwage wire Per Box 2,351.00 2,703.65
9swg,Gabion box (3.0x1.5x0.75 ) & Gabion fixing
wearing all complete work.

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 940.00 470.00
Labour
Unskilled 0.200 Nos. 650.00 130.00
Materials Gavion wire commercial 20.000 kgs 87.55 1,751.00
Total 2,351.00
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 352.65
Grand Total 2,703.65

Supplying & filling of Boulder in Gabion box


(3.0x1.5x0.75 ) & Gabion fixing wearing all complete cum 2,745.50 3,157.32
work.

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled Nos. 940.00 -
Labour
Unskilled 0.500 Nos. 650.00 325.00
Materials Stone block 1.000 cum 2,420.50 2,420.50
Total 2,745.50
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 411.82

Grand Total 3,157.32

Prepared By:- Checked By:- Approved By:-


Governmentof Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Federal Project Implementation Unit
Janakpurdham, Dhanusha
Aluminium Door and Window

DISTRICT : DHANUSHA F / Y : 2075/76


Remark
S. District Transporta
Description Unit Rate Dhanusha rate
No. Rate tion @ 3 %
code)
Alluminium fixed panel window With ventilation but without fly mesh shutter
1 Sqm. 6200.00 186.00 6386.00 199-1
from section( 88mmx38.1mm x1.3mm , Glass 5mm)
Alluminium fixed panel window With Ventilation with fly mesh shutter from
2 Sqm. 6600.00 198.00 6798.00 200-2
section(88mmx38.1mm x1.3mm , Glass 5mm )
Alluminium framed Sliding window Without ventilator ( Aluminium :- Natural
3 Sqm. 6500.00 195.00 6695.00 201-3
anodised 101mmx45mm x1.50mm , Glass 5mm clear)
Alluminium framed Sliding window With ventilator ( Aluminium :- Natural
4 Sqm. 7000.00 210.00 7210.00 202-4
anodised 101mmx45mm x1.5mm , Glass 5mm clear)
Alluminium framed Sliding Door ( Aluminium :- Natural anodised
5 Sqm. 7400.00 222.00 7622.00 203-5
101mmx45mm x1.5mm ,) with sash 40*45*1.5mm and 5mm glass

Casement double panel aluminium window With ventilator section of


6 Sqm. 7000.00 210.00 7210.00 204-6
( 54mmx33mm x1.5)mm with sash 38*34*1.5mm with Glass 5mm

Alluminium Casement Door section of ( 101mmx45mm x1.1)mm sash


7 Sqm. 12000.00 360.00 12360.00 205-7
40*45*1.1mm & Glass 5mm
Alluminium framed Swing Door section of (101mmx45mm x1.5)mm & Glass
8 Sqm. 7650.00 229.50 7879.50 206-8
5mm clear
Alluminium framed Sliding window 2 track section of (88mmx38mm x1.5)mm
9 Sqm. 6000.00 180.00 6180.00 207-9
& Glass 5mm
Alluminium fixed window and partition with fixed ventilator from 9mm bord
10 Sqm. 6000.00 180.00 6180.00 208-10
and section (101mmx45mm x1.5)mm
Alluminium partition with 5mm thick glass & 9mm thick laminated bord of
11 Sqm. 6000.00 180.00 6180.00 209-11
section (101mmx45mm x1.5)mm
Alluminium partition with 5mm thick glass & 9mm thick laminated bord of
12 Sqm. 5600.00 168.00 5768.00 210-12
section (64mmx38mm x1.1)mm

False ceiling by Gypsum, Gypsum board 12.5 mm With providing,finisging


13 Sqm. 880.00 26.40 906.40 213.00
og joint with compound & tape all complete
Governmentof Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Federal Project Implementation Unit
Janakpurdham, Dhanusha

RATE ANALYSIS
[Civil Works ]

DISTRICT : DHANUSHA
FISCAL YEAR : 2075/076

---------------- ---------------- -----------------


Prepared by Checked by Approved by
Er. Pradeep Kumar Singh
Er. Division Chief
g]kfn ;/sf/
zx/L ljsf; dGqfno
zx/L ljsf; tyf ejg lgdf{0f ljefu
;+3Lo cfof]hgf sfof{Gjog OsfO{
hgsk'/wfd, wg'if
b/ ljZn]if0f, wg'if

l;len
cf=j= @)&%÷)&^

tof/ ug]{ M–
ho s'df/ 7fs'/
r]s hfFr ug]{ M–
O{= >j0f s'df/ ofbj

k|dfl0ft ug]{ M–
cfof]hgf k|d'v – प्रददीप कक ममार सससिंह

ldlt M–
15.03 O3(15-9A) sub base laying work with sand mixed gravel, load Sqm. 2,273.50 2,614.52
Resources unload & proper levelling.
Level/Type Quantity Unit Rate Amount Remarks
Labours Unskilled 1.200 Nos. 650.00 780.00
Material Sand mixed gravel 1.000 Cum. 1,493.50 1,493.50
Total 2,273.50
Rate analysis for : 1.00Cum 15 % Contractor overhead 341.02
Grand Total 2,614.52

P.C.C. (1:2:4) Plum supply of matarials hulage


4.03 D1(7-2D) distance all complete. work in foundation, wall Cum. 10,834.15 12,459.27
(River bed)

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 940.00 470.00
Labour
Unskilled 4.000 Nos. 650.00 2,600.00
Cement 0.320 M.T. 17,510.00 5,603.20 6.4
Aggrigate 40 mm-River bed
Materials & Stone block 0.890 Cum. 1,713.75 1,525.23
Sand 0.445 Cum. 1,307.25 581.72
Water 150.000 Ltr. 0.36 54.00
Total 10,834.15
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,625.12
Grand Total 12,459.27
Governmentof Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Federal Project Implementation Unit
Janakpurdham, Dhanusha

Brick Calculation
Brick Brand : U # B Place : Gaighat,Udayapur
S.No. Length Bredth Height Remarks
1 230 110 65
2 220 105 65
3 230 110 60
Total 680 325 190
Average 226.66 108.33 63.33

Brick Brand : sathi Place : P. Pipra, Saptari


S.No. Length Bredth Height Remarks
1 225 110 60
2 230 110 60
3 215 110 60
Total 670 330 180
Average 223.33 110.00 60.00

Brick Brand : SHIVA Place :


S.No. Length Bredth Height Remarks
1 250 112 70
2 250 115 80
3 260 120 70
Total 760 347 220
Average 253.33 115.66 73.33

Brick Bbrand : NEPAL Place : Kadamaha, Saptari


S.No. Length Bredth Height Remarks
1 220 100 60
2 220 105 70
3 225 110 70
Total 665 315 200
Average 221.66 105.00 66.66

Brick Brand : S # S Place :


S.No. Length Bredth Height Remarks
1 240 115 70
2 230 110 60
3 240 120 75
Total 710 345 205
Average 236.66 115.00 68.33
DISTRICT : DHANUSHA
CALCULATION OF BRICK NUMBERS
A Analysis for brick 1.000 Cum. Number Westage 2075/2076
Size of brick with 10 mm thick Volume of number of number of
Size of brick in mm of bricks of bricks
S.No. Brick Brand Place mortar brick with bricks per bricks per Remarks
Length Breadth Height Length Breadth Height per 1 M3 per 1 M3
mortar 1 M3 brick 1 M3
1 U#B 226.66 108.33 63.33 236.66 118.33 73.33 0.00205 brick work
487.80 (Say
24.395%) 512.19 512.19
2 sathi 223.33 110.00 60.00 233.33 120.00 70.00 0.00195 512.82 25.64 538.46 538.46
3 SHIVA 253.33 115.66 73.33 263.33 125.66 83.33 0.00275 363.63 18.18 381.81 381.81
4 NEPAL 221.66 105.00 66.66 231.66 115.00 76.66 0.00204 490.19 24.5 514.69 514.69
5 S#S 236.66 115.00 68.33 246.66 125.00 78.33 0.00241 414.93 20.74 435.67 435.67
Total brick 1161.64 553.99 331.65 1211.64 603.99 381.65 Total 2382.82
Average 232.32 110.79 66.33 242.32 120.79 76.33 Average 476.56
Say 476.00

B Brick masonry work 1.000 Cum. Westage Total


Size of brick with 10 mm thick Volume of Number number of
Size of brick in mm of bricks number of
S.No. Brick mortar brick with of bricks bricks per Remarks
Length Breadth Height Length Breadth Height per 1 M bricks per
3
mortar per 1 M3 1 M3
448.43 (Say22.42
5%) 1470.85
M3
1 Average brick size 232.32 110.79 66.33 242.32 120.79 76.33 0.00223 476.00

C Flat Brick soling work 1.000 Sqm. Westage Total


Size of brick in mm Size of brick with 10 mm sand Area of Number number of
of bricks number of
S.No. Brick brick with of bricks bricks per Remarks
Length Breadth Height Length Breadth Height per 1 M 2
bricks per
sand per 1 M2 1 M2
34.17 (Say 5%) 1M 2
1 Average brick size 232.32 110.79 66.33 242.32 120.79 76.33 0.02926 1.70 35.87 34.00 0.02573
38.86514 1.94 40.81 42.00
D Edge Brick soling work 1.000 Sqm. Westage Total
Size of brick in mm Size of brick with 10 mm sand Area of Number number of
of bricks number of
S.No. Brick brick with of bricks bricks per Remarks
Length Breadth Height Length Breadth Height per 1 M bricks per
2
sand per 1 M2 1 M2
54.08 (Say 5%) 1M 2
1 Average brick size 232.32 110.79 66.33 242.32 120.79 76.33 0.01849 2.70 56.78 55.00

Anda mungkin juga menyukai