Abstract: Construction of large underground caverns in Himalayas is challenging due to complex geological and
in-situ stress conditions. Understanding the behaviour of such caverns during construction stage is possible only
with extensive instrumentation. A case study of a large cavern under construction in Himalayan region in Bhutan is
considered. Results from various types of instruments are discussed in this paper. Instrumentation data shows that
Himalayan rock mass particularly with phyllitic quartzite exhibits large deformations thus requiring careful
selection of support and excavation methodology.
Keywords: Instrumentation, Large Cavern, Wall Convergence, Multipoint Borehole Extensometer, Load Cells,
Himalayas, Rock Bolt Failure.
strike of foliation. Due to folding, the angle between the long axis of powerhouse and the strike of formation
varies from 150o to 55o.
2.1. Rock Mass Parameters taken for further design calculations. The physico-
Mapping of machine hall and transformer hall was mechanical properties of phyllitic quartzite and quartzite
carried out by Tala Project geologists. were determined by National Institute of Rock
Mechanics (NIRM) (Anon, 2001). The properties are
Table 2. Properties of intact rock listed in Table 2.
zone was gougy to granular. The long axis of the contact of the wall rock. At any given time, a maximum
Machine Hall cavern is oriented along N 37oW-S37oE of 9m span was exposed. The exposed wall was
and is across the strike of foliation. immediately shotcreted with 50mm thick plane
shotcrete (M35 A10). On this surface, welded wire mesh
On completion of the Central Gullet, widening was of 100mm x 100mm x 5mm was fixed by drilling holes
taken up on downstream side initially, followed by with the jack hammer drills. This was followed by
widening on upstream side. Before widening at any installation of high strength Dywidag bolts of 12m long
location, 8m long rock bolts were installed at the central and 32mm / 26.5mm diameter (bolts of 32mm diameter
gullet, using couplings (6m and 2m rods coupled were used during initial benches) at 1.5m centre to
together by couplings), with the help of Boltec Machine. centre in a staggered manner. The Dywidag rock bolts
Concurrent supporting in the widened portion was done of 26mm diameter had yield strength of 1033MPa and
with 6m and 8m long 32mm diameter rock bolts tensile strength of 1122MPa (Singh et al, 2003). The
staggered at 1.5m centre to centre with SFRS of 50- rock bolts were end anchored with resin capsules for
70mm thickness near the face. The side slashing on the initial 4m and rest was grouted with cement slurry. The
downstream side continued for 264 days and on the Dywidag rock bolts were tensioned up to 30t / 12t
upstream side the slashing continued for 252 days. (during initial benching a pretension of 30t was given,
however, after the instrumentation observations and
During the progress of excavation work in downstream other considerations, the pre tension of Dywidag bolts
side near RD 95m, a roof collapse occurred in the was fixed at 12t). A second layer of 50mm plain
Machine Hall between RD 120m and RD 135m (Chopra shotcrete was applied after installing all the rock bolts in
et al, 2003). It was observed that the bearing plates and the exposed area. The third layer of 50mm thick
the end anchors were intact in this zone, but the rock shotcrete was provided after the setting of second layer
mass in between the bolts fell down. Subsequently, falls of shotcrete.
continued for some more time and extended from RD
135m to 160m and then 120m to 90m. It was observed In the initial stages, as 12m long Dywidag rock bolts
that in the zone between 135m and 160m, the bolts were not readily available, the Dywidag rock bolts of
sheared off from just above the bearing plate but the end 8m and 4m were coupled together for use in single hole.
anchorages were intact. From RD 120m to 90m also, the For this purpose a 76mm dia hole was drilled up to a
bolts were reported to be sheared off from 3m to 4m depth of 4.5m so that 4m long rock bolt could be
from the bottom and they fell along with large chunks of coupled with 8m long rock bolt with a coupler of 61mm
rock mass with bearing plates still intact at the end. The outer diameter. Beyond 4.5m, the hole was drilled using
shells of the end anchorage found to be open in all these standard 51mm diameter hole. During the excavation of
cases. It was noted that the height of the fall was more the first bench, consolidation grouting was carried out
on the upstream side from the central line of the up to a depth of 11m and after the grout was set, the
Machine Hall. It varied from a few meters to 7m. On the holes were re-drilled for installing the Dywidag rock
downstream side the height of the fall varied from 1 to bolts. The sequence of excavation of the benches and
3m. Subsequently, it was decided to support the crown the duration of excavation of each bench is shown in a
of the Machine Hall with steel ribs of ISMB 350m x schematic diagram in Figure 2. It may be noted that the
140mm section at 0.6m spacing and welding 12mm widths of central gullet and benches were varied to suit
thick plates on both the flanges at suitable spacing to the geological conditions. From 6th bench and
enhance the strength of steel ribs. The ribs were downwards, the benching was done between RD 60 and
installed for the entire length of Machine Hall. The RD 206.4 only. Eleven benches were excavated up to
space between the rock mass and the ribs was back EL 499.5.
filled with concrete. This was followed by grouting to
ensure proper contact with the rock mass.
After completion of the ribs and subsequent back filling,
the benching down of the Machine Hall was started.
First bench was started with excavation of central gullet
of 6.5m widths and 2.6m deep. The central gullet
excavation generally starts with opening of box cuts at
two locations by drilling using jack hammers or crawler
mounted pneumatic drill (41mm blasthole diameter).
The central gullet was advanced on either direction and
benches were formed on both upstream and downstream
side. Benches were excavated with controlled blasting
techniques and by providing the line drilling along the
steel ribs. The entire crown portion of the Transformer is shown in Figure 5. In this paper, instruments results
Hall was provided with the steel ribs. The area between in machine hall cavern are discussed.
ribs and rock surface was backfilled with concrete, and
contact grouting was done to ensure proper contact with
the rib surface. The benching operation in Transformer
Hall was started with the excavation of first bench from
EL 533 to EL 530. The second bench was excavated
from EL 530 to EL 527. The procedure of excavation in
Transformer Hall was almost similar to the procedure
adopted in Machine Hall. However, Dywidag bolts of
8m long and 32mm diameter was used in conjunction
with wire mesh and plain shotcrete as the primary
method of support on the walls.
3.3 Excavation of Bus Ducts
Bus Ducts were excavated up to 10m initially from Figure 4. Instrumentation layout at a) Machine Hall
Machine Hall side. The excavation of Bus Ducts which b) Transformer Hall Cavern
were earlier excavated up to 10m from Machine Hall
Side was continued from Transformer Hall side and
excavation was completed.
was done. Major observations of MPBX and anchor Results of Multipoint Borehole Extensometers (MPBX)
load cells are presented in the following sections. installed in the center of the crown at RD 15m, RD
80m, RD 130m and RD 150m are shown in Figure 6.
4.1.1 Multipoint Borehole Extensometer
Figure 6. Displacement versus time at RD 15m, 80m , 130m and 150m Center of the Crown, Machine Hall Cavern
At RD 15m, maximum surface displacement of 115mm Anchor load cells were installed on 8m long full cement
was observed after a period of 216 days. The grouted rock bolts at the crown portion of Machine Hall.
displacement started accelerating after a period of 46 Load cells were installed at RD 15m, 80m, 90m, 100m,
days. The separation at various horizons was found to 110m, 130m and 150m at the centre of the crown and at
initiate at the same time. The maximum rate of RD 80m on the right up side of the crown. The load
displacement was 0.37mm/day during this period. A induced on the bolts at different RD’s is shown in
separation of 41mm occurred between the surface and Figure 7.
0.7m horizon, indicating separation of shotcrete from
the rock surface. It was observed that the bed separation
took place up to a height of 8.7m above the crown,
indicating the ineffectiveness of rock bolts in controlling
the displacement, Figure 6(a). Subsequently, ribs were
put up for the entire length of the cavern.
At RD 80m crown, the separation of beds started after
48 days and the separation was occurring up to a height
of 3.8m above the crown as could be seen in Figure
6(b). The separation was of the order of 22mm. Anchors
between 4.8m and 17.5m horizons showed negative
movement indicating the closure of pre-existing cracks.
Maximum surface displacement observed was 52mm at
the time of installation of the ribs. The displacements
were however restricted after the backfilling. Figure 7. Load on Rock Bolt in the crown versus time at
At RD 130m crown, surface displacement (lowering of different RD’s, Machine Hall
crown) of 18 mm was observed before installation of
ribs and was increased to 23mm after backfilling of the
ribs as seen in Figure 6(c). The separation up to a height
of 9m above the crown was observed. At RD 150m, a
small crown surface displacement of 7mm was
observed.
Before installation of the ribs in the crown of the was a marginal increase in the load on the rock bolts
Machine Hall, the rock bolts were the primary mode of indicating some amount of deformation in the rock
Figure 8. Load on ribs on upstream and downstream side at EL 533, Machine Hall Cavern
Figure 11. Load on 12m long rock bolts on d/s & u/s wall of Machine Hall at EL -520m
Figure 12. Load on 12m long rock bolts on d/s & u/s wall of Machine Hall at EL -515m
Load Cells at EL 506: The load cells were installed at Reflective targets were fixed on a plate which was held
RD 65m, 110m and 150m on both upstream and in position by a rod grouted into the wall to a depth of
downstream walls of the Machine Hall. The load cell 0.3m to 1m. The stations were fixed opposite to each
data recorded during the excavation of machine hall on other on upstream and downstream walls. The
d/s and u/s is shown in Figure 13. cumulative convergence of two walls was computed.
Convergence observations at EL 525m, 520m, 515m
4.2.2 Wall Convergence and 506m are shown in Figure 14. It may be noted from
The wall convergence of Machine Hall Cavern was the figure that, convergence in excess of 250mm was
monitored using reflective targets with Total Station observed at EL 525, 520 and EL 525m and shows
Leica TDA 5005 with angular accuracy of 0.5s. increasing trend.
Figure 13. Load on 12m long rock bolts on the d/s & u/s wall of Machine Hall at EL -506.
The behaviour of large underground cavern in Himalaya [4] Naik, S., Nair, R., Sudhakar, K. and Nawani, P.C.
was assessed using the instrumentation data. The 2010. Need For Systematic Instrumentation In
instrumentation results reveal that rock mass consisting Hydroelectric Projects In Himalayas, International
of phyllitic quartzite exhibit excessive deformation Conference on Accelerated Development of Hydro
under high stress conditions. Although, rock bolts of Power in Bhutan – Opportunities and Challenges,
high strength are effective in controlling the Thimpu, Bhutan. 16-18.
deformations, failure of large number of bolts are
[5] Naik, S., Sudhakar, K and Nair, R. 2011
witnessed. This suggests that flexible supports like cable
Instrumentation – A Key to Stability Analysis of
bolts may work better under such geological conditions.
Large Caverns in Hydroelectric Projects,
Based on the instrumentation data and analysis during
International Conference on International
the construction of large underground cavern in
Conference on Underground Space Technology,
Himalaya, the following conclusions are drawn:
NIRM, Bangalore, India, January, 16-18,
• Instrumentation data and analysis has played vital role
[6] Chopra, V., and Gupta, A. 2003. Roof arch failure of
during the various stages of cavern excavation in
Machine Hall Cavern – Tala Hydroelectric Project,
ensuring stability to the excavation and in assessing
Bhutan. International Conference on Engineering of
the efficacy of the support system.
Dams and Appurtenance Works including
• Instrumentation data is highly useful for taking Powerhouse and Transmission Systems, New Delhi
appropriate measures in case of inadequate support
system by additional strengthening. After taking
remedial measures, instruments were further used to
assess efficacy of these measures.
• Instrumentation data aided the management in taking
appropriate decisions at right time.
• More sections in the caverns need to be instrumented
in order to correctly understand the behaviour of the
multiple caverns.
• Measurement of convergence using optical instrument
rather than using tape extensometer proved useful as
continuous data could be collected during the entire
benching period and during the post excavation period
also.
7.0 References
[1] Anon., 2001. Technical Report on Laboratory Rock
Mechanics Investigations – Tala Hydroelectric
Project, Bhutan, NIRM Unpublished Report
[2] Singh, R., Chowdhry, A.K., Sharma, B.N., Goyal,
D.P., and Khazanchi, R.N., 2002. Wall Support
System for powerhouse cavern of Tala Hydroelectric
Project in Bhutan Himalayas, INDOROCK, New
Delhi. 132-142
[3] Singh, R., Sharma, B.N., Puri, P.K., Gupta, M.,
Goyal, D.P. and Chugh, I.K., 2003 Experience of
long rock bolts in Machine Hall Cavern at Tala
Hydroelectric Project. International Conference on
Accelerated Construction of Hydropower Projects,
Gedu, Bhutan Vol.I 30-39.