COMMISSIONING

LIFTING PUMP
Project: JOB No.:

Client Ref.:

Location:

Type:

Unit No.: _____________________________________ Function: _____________________________________

Model: _______________________________________

ITEM OK COMMENT

PRE-START-UP INSPECTION
PHYSICAL INSTALLATION COMPLETE
Mounting checked
Chain checked
Oil level checked
Pump(s) rotate freely
Float switches checked
MECHANICAL SERVICE CONNECTIONS
Piping & Valves Completed and Tested
Valves positioned for Start-up
ELECTRICAL SERVICE CONNECTIONS
Electrical connections completed
Disconnect switch installed
Overload relay sized correctly
Ready to start & run under control

START-UP INSPECTION
Pump rotation correct
Check valve tested
Start / Stop operation verified
Motor Amps-Rated __________ Actual _________
Motor Volts-Rated __________ Actual _________
Vibrational & noise level acceptable

Comments:

Start-up by: Verified by:


Name: _______________________________________ Name: _______________________________________

Signed: ______________________ Signed: ______________________


QA546.00 rev 1.0

Date: _______/________/_________ Date: _______/________/_________