OBRA : "MEJORAMIENTO, INSTALACIÓN DE LOS SERVICIOS AGUA POTABLE Y ALCANTARILLADO EN EL ANEXO CAMPAMENTO DEL C.P. CASCAJA
ENTIDAD : MUNICIPALIDAD PROVINCIAL DEL SANTA
SON : OCHOCIENTOS VEINTI SEIS MIL DOCIENTOS VEINTIUNO CON 32/100 NUEVOS SOLES
E DESEMBOLSOS
CASCAJAL EN EL DISTRITO DE CHIMBOTE, PROVINCIA DE SANTA - ANCASH"
QUINCENA 03: dia 31 al 45 QUINCENA 04: dia 46 al 60 QUINCENA 05: dia 61 al 75 QUINCENA 06: dia 76 al 90 TOTAL
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 S/.
01 RED DE ALCANTARILLADO
4,346.04 4,346.04 3,259.53
01.01 OBRAS PROVISIONALES 1.00
8,727.93 8,727.93 11,637.24
01.02 TRABAJOS PRELIMINARES 35.00
20,330.86 40,661.71 40,661.7
01.03 MOVIMIENTO DE TIERRAS 55.00
21,305.63 42,611.26 4
01.04 TUBERIAS 42.00
25,253.64 25,253.64
01.05 CONSTRUCCION DE CAMARAS DE INSPECCION 25.00
8,760.51 8,760.51
01.06 CONEXIONES DOMICILIARIAS 20.00
3,37
01.07 PRUEBAS HIDRAULICAS 30.00
SON : OCHOCIENTOS VEINTI SEIS MIL DOCIENTOS VEINTIUNO CON 32/100 NUEVOS SOLES
NCE DE OBRA (GANTT)
TO DEL C.P. CASCAJAL EN EL DISTRITO DE CHIMBOTE, PROVINCIA DE SANTA - ANCASH"
QUINCENA 03: dia 31 al 45 QUINCENA 04: dia 46 al 60 QUINCENA 05: dia 61 al 75 QUINCENA 06: dia 76 al 90
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
11,637.24
42,611.26 35,509.39
25,253.64 25,253.64
8,760.51 8,760.51
8,999.94
93.10
25,490.68
1,070.77
NCE DE OBRA (GANTT)
TO DEL C.P. CASCAJAL EN EL DISTRITO DE CHIMBOTE, PROVINCIA DE SANTA - ANCASH"
QUINCENA 03: dia 31 al 45 QUINCENA 04: dia 46 al 60 QUINCENA 05: dia 61 al 75 QUINCENA 06: dia 76 al 90
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
1,853.60
01 RED DE ALCANTARILLADO
4,346.04 4,346.04 3,259.53
01.01 OBRAS PROVISIONALES 1.00
8,727.93 8,727.93 11,637.24
01.02 TRABAJOS PRELIMINARES 35.00
20,330.86 40,661.71 40,661.7
01.03 MOVIMIENTO DE TIERRAS 55.00
21,305.63 42,611.26 4
01.04 TUBERIAS 42.00
25,253.64 25,253.64
01.05 CONSTRUCCION DE CAMARAS DE INSPECCION 25.00
8,760.51 8,760.51
01.06 CONEXIONES DOMICILIARIAS 20.00
3,37
01.07 PRUEBAS HIDRAULICAS 30.00
SON : OCHOCIENTOS VEINTISEIS MIL DOCIENTOS VEINTIUNO CON 32/100 NUEVOS SOLES
CE DE OBRA VALORIZADO
CASCAJAL EN EL DISTRITO DE CHIMBOTE, PROVINCIA DE SANTA - ANCASH"
QUINCENA 03: dia 31 al 45 QUINCENA 04: dia 46 al 60 QUINCENA 05: dia 61 al 75 QUINCENA 06: dia 76 al 90 TOTAL
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 S/.
11,637.24 29,093.11
8,999.94 8,999.94
93.10 93.10
25,490.68 25,490.68
1,070.77 1,070.77
CE DE OBRA VALORIZADO
CASCAJAL EN EL DISTRITO DE CHIMBOTE, PROVINCIA DE SANTA - ANCASH"
QUINCENA 03: dia 31 al 45 QUINCENA 04: dia 46 al 60 QUINCENA 05: dia 61 al 75 QUINCENA 06: dia 76 al 90 TOTAL
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 S/.
1,853.60 1,853.60
Nº MES 01: 20 al 30 DE SETIEMBRE MES 02: 01 al 31 DE OCTUBRE MES 03: 01 al 30 DE NOVIEMBRE MES 04: 01 al 18 DE DICIEMBRE TOTAL
ITEM ACTIVIDAD
DIAS 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 S/.
01 RED DE ALCANTARILLADO
4,346.04 4,346.04 3,259.53 3,259.53 3,259.53 3,259.53 ###
01.01 OBRAS PROVISIONALES 1.00
7,481.09 8,312.32 8,312.32 4,987.39 ###
01.02 TRABAJOS PRELIMINARES 35.00
29,572.16 33,268.68 44,358.23 33,268.68 36,965.19 25,875.64 ###
01.03 MOVIMIENTO DE TIERRAS 55.00
6,763.69 47,345.85 27,054.77 20,291.08 40,582.15 ###
01.04 TUBERIAS 42.00
16,162.33 28,284.08 28,284.08 28,284.08 ###
01.05 CONSTRUCCION DE CAMARAS DE INSPECCION 25.00
8,760.51 8,760.51 8,760.51 8,760.51 ###
01.06 CONEXIONES DOMICILIARIAS 20.00
3,378.46 3,378.46 1,689.23 8,446.14
01.07 PRUEBAS HIDRAULICAS 30.00
10,226.16 10,226.16 10,226.16 ###
01.07 BIODIGESTOR 18.00
COSTO DIRECTO TOTAL 64,325.31 255,639.21 0.00 205,348.20 0.00 46,037.95 571,350.66
GASTOS GENERALES 7 % 4,502.77 17,894.74 0.00 14,374.37 0.00 3,222.66 39,994.55
UTILIDADES 8 % 5,146.02 20,451.14 0.00 16,427.86 0.00 3,683.04 45,708.05
SUB TOTAL 73,974.10 293,985.09 0.00 236,150.43 0.00 52,943.64 657,053.26
I.G.V. 18 % 13,315.34 52,917.32 0.00 42,507.08 0.00 9,529.86 118,269.59
DESEMBOLSO PARCIAL PROGRAMADO S/. 87,289.44 346,902.41 0.00 278,657.50 0.00 62,473.49 775,322.85
DESEMBOLSO MENSUAL PROGRAMADO S/. 87,289.44 346,902.41 278,657.50 62,473.49 775,322.85
COSTO DIRECTO TOTAL 0.00 0.00 0.00 16,721.62 0.00 20,786.47 37,508.09
GASTOS GENERALES 7 % 0.00 0.00 0.00 1,170.51 0.00 1,455.05 2,625.57
UTILIDADES 8 % 0.00 0.00 0.00 1,337.73 0.00 1,662.92 3,000.65
SUB TOTAL 0.00 0.00 0.00 19,229.87 0.00 23,904.44 43,134.30
I.G.V. 18 % 0.00 0.00 0.00 3,461.38 0.00 4,302.80 7,764.17
DESEMBOLSO PARCIAL PROGRAMADO S/. 0.00 0.00 0.00 22,691.24 0.00 28,207.23 50,898.48
DESEMBOLSO MENSUAL PROGRAMADO S/. 0.00 0.00 22,691.24 28,207.23 50,898.48
COSTO DIRECTO TOTAL 64,325.31 255,639.21 0.00 222,069.82 0.00 66,824.41 608,858.75
GASTOS GENERALES 7 % 4,502.77 17,894.74 0.00 15,544.89 0.00 4,677.71 42,620.11
UTILIDADES 8 % 5,146.02 20,451.14 0.00 17,765.59 0.00 5,345.95 48,708.70
SUB TOTAL 73,974.10 293,985.09 0.00 255,380.29 0.00 76,848.08 700,187.56
I.G.V. 18 % 13,315.34 52,917.32 0.00 45,968.45 0.00 13,832.65 126,033.76
DESEMBOLSO PARCIAL PROGRAMADO S/. 87,289.44 346,902.41 0.00 301,348.75 0.00 90,680.73 826,221.32
DESEMBOLSO MENSUAL PROGRAMADO S/. 87,289.44 346,902.41 301,348.75 90,680.73 826,221.32
DESEMBOLSO MENSUAL ACUMULADO PROGRAMADO S/. 87,289.44 434,191.85 735,540.59 826,221.32
AVANCE DE OBRA PARCIAL % 10.56 41.99 36.47 10.98
AVANCE DE OBRA ACUMULADO % 10.56 52.55 89.02 100.00
SON : OCHOCIENTOS VEINTISEIS MIL DOCIENTOS VEINTIUNO CON 32/100 NUEVOS SOLES
CRONOGRAMA DE AVANCE DE OBRA VALORIZADO
OBRA : "MEJORAMIENTO, INSTALACIÓN DE LOS SERVICIOS AGUA POTABLE Y ALCANTARILLADO EN EL ANEXO CAMPAMENTO DEL C.P. CASCAJAL EN EL DISTRITO DE CHIMBOTE, PROVINCIA DE SANTA - ANCASH"
ENTIDAD : MUNICIPALIDAD PROVINCIAL DEL SANTA
CONTRATISTA : CONSORCIO CASCAJAL
Nº MES 01: 20 al 30 DE SETIEMBRE MES 02: 01 al 31 DE OCTUBRE MES 03: 01 al 30 DE NOVIEMBRE MES 04: 01 al 18 DE DICIEMBRE TOTAL
ITEM ACTIVIDAD
DIAS 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 S/.
01 RED DE ALCANTARILLADO
4,346.04 4,346.04 3,259.53 3,259.53 3,259.53 3,259.53 ###
01.01 OBRAS PROVISIONALES 1.00
7,481.09 8,312.32 8,312.32 4,987.39 ###
01.02 TRABAJOS PRELIMINARES 35.00
29,572.16 33,268.68 44,358.23 33,268.68 36,965.19 25,875.64 ###
01.03 MOVIMIENTO DE TIERRAS 55.00
6,763.69 47,345.85 27,054.77 20,291.08 40,582.15 ###
01.04 TUBERIAS 42.00
16,162.33 28,284.08 28,284.08 28,284.08 ###
01.05 CONSTRUCCION DE CAMARAS DE INSPECCION 25.00
8,760.51 8,760.51 8,760.51 8,760.51 ###
01.06 CONEXIONES DOMICILIARIAS 20.00
3,378.46 3,378.46 1,689.23 8,446.14
01.07 PRUEBAS HIDRAULICAS 30.00
10,226.16 10,226.16 10,226.16 ###
01.07 BIODIGESTOR 18.00
COSTO DIRECTO TOTAL 64,325.31 130,317.47 125,321.74 156,362.96 65,706.86 66,824.41 608,858.75
GASTOS GENERALES 7 % 4,502.77 9,122.22 8,772.52 10,945.41 4,599.48 4,677.71 42,620.11
UTILIDADES 8 % 5,146.02 10,425.40 10,025.74 12,509.04 5,256.55 5,345.95 48,708.70
SUB TOTAL 73,974.10 149,865.09 144,120.00 179,817.40 75,562.89 76,848.08 700,187.56
I.G.V. 18 % 13,315.34 26,975.72 25,941.60 32,367.13 13,601.32 13,832.65 126,033.76
DESEMBOLSO PARCIAL PROGRAMADO S/. 87,289.44 176,840.81 170,061.60 212,184.54 89,164.21 90,680.73 826,221.32
DESEMBOLSO MENSUAL PROGRAMADO S/. 87,289.44 346,902.41 301,348.75 90,680.73 826,221.32
DESEMBOLSO MENSUAL ACUMULADO PROGRAMADO S/. 87,289.44 434,191.85 735,540.59 826,221.32
AVANCE DE OBRA PARCIAL % 10.56 41.99 36.47 10.98
AVANCE DE OBRA ACUMULADO % 10.56 52.55 89.02 100.00
SON : OCHOCIENTOS VEINTISEIS MIL DOCIENTOS VEINTIUNO CON 32/100 NUEVOS SOLES
CRONOGRAMA DE AVANCE DE OBRA ( G A N T T)
OBRA : "MEJORAMIENTO, INSTALACIÓN DE LOS SERVICIOS AGUA POTABLE Y ALCANTARILLADO EN EL ANEXO CAMPAMENTO DEL C.P. CASCAJAL EN EL DISTRITO DE CHIMBOTE, PROVINCIA DE SANTA - ANCASH"
ENTIDAD : MUNICIPALIDAD PROVINCIAL DEL SANTA
CONTRATISTA : CONSORCIO CASCAJAL
PLAZ O D E E J E C U C I O N 9 0 D IAS CALE N DAR I O S
Nº MES 01: 20 al 30 DE SETIEMBRE MES 02: 01 al 31 DE OCTUBRE MES 03: 01 al 30 DE NOVIEMBRE MES 04: 01 al 18 DE DICIEMBRE
ITEM ACTIVIDAD
DIAS 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
8,999.94
02.01 LAGUNA PRIMARIA Y SECUNDARIA 5.00
93.10
02.02 TRABAJOS PRELIMINARES 5.00
7,647.20 17,843.48
02.03 MOVIMIENTO DE TIERRAS 10.00
1,070.77
02.04 CAMARA DE VALVULAS 10.00
1,853.60
02.05 SUM. E INST. DE VALVULAS Y ACCESORIOS 5.00
ACTIVIDAD SECUNDARIA