Ref : - 1) sE/Qc/Hydera bad Lr. No. SEec/HyD/eA&M p AEE3 201 5, Dt. 23-09-20 1
I / 5.
2) T'O. Lr. No. 2609 1 50009/ ENC/Adm n&QC/ DEEI AEE2 120 1 5, Dt: 29-09-20 15 to a | |
the HODs of (R&B)Department.
3) T.O. Lr' No. 2609 1 50009/ ENC/Adm n&QC/ DEEI AEE2 120 1 5, Dt: 16- 1 1-20 1 5 to a | |
the HODs of (R&B)Department.
*******
To ffit''
> The Superintending Engineers (R&B) i.e, 1) Rural Circle, Hyderabad 2) Head
euarter
circle, Hyderabad 3) Karimnagar 4) warangal 5) Medak 6) Nalgonda 7)Khammam
8) Nizambad 9) Mahabubnagar 10) Adilabadll) NH Circle, Hyderabad 12) Etectrical
Circle, Hyderabad 13) D&p wing, Hyderabad.
(Contd.,)
F Copy to
information and
1) The Engineer-in-Chief(R&B) State Roads &CRN, Hyderabad for
necessary action.
for information and
2) The chief Enginee(R&B) NH, CRF, LWE&PPP, Hyderabad
necessary action.
for information
3) The Chief Engineer(R&B) Buildings, NABARD & HUDCO, Hyderabad
and necessary action'
4) The Engineer-in-Chief(R&B) ,Cl-E & Member of CoT, Hyderabad for information
and necessary action.
> Copy to
1) The Superintending Enginee(R&B)I&QC Circle, Hyderabad
for information and
necessary action.
and
2) The Executive Engineer(R&B),QC Division, Hyderabad for information
necessary action.
3) The Executive Engineer(R&B)QC Division, warangal for
information and necessary
action.
r Copy to
Tab|e.
1) The Dy' Engineer-in-Chief(R&B) Admn. &QC, Hyderabad
Government of Telangana
Roads and Buildings Department
In this Scenario, it is imperative that the roads are built and maintained to the
standards as specified in the respective contracts. With a view to achieve the required
standards in road construction and maintenance, uniformly and consistently, it is necessary
to have all the required standards, construction methods, quality control procedures and
tests at one place in the form of a document. Therefore all the relevant information is
compiled and put in this document.
Definition of Q-A/M Plan: it is defined as all the planned and systematic activities
implemented within the quality system and demonstrated as needed to provide adequate
confidence that it will fulfill all the requirements.
The QA/M Plan consists of two main parts i.e., (i) Quality Control and (ii) Quality
Audit. The first part is very important one where in it helps in achieving a specified quality
product. The second part evaluates quality standards of the final product. This plan is
developed with main focus on Road and Bridge Projects. This plan, once implemented will
help in achieving uniform and consistent standards in all projects across the state.
The design of mix / job mix formula is to be got approved by the Engineer-in-charge
before starting of the work/According permission to start the work.
All agreements specify that the tenderer shall inspect and select the quarries of his
own choice (cl. 9 of preamble to BOQ and Cl.10.1 of conditions of contract). Cl.25.1 specifies
that the contractor shall furnish within one month from work order, a work program.
The Superintending Engineer/ Executive Engineer shall ensure that the work
program includes the source of (i) all quarried materials like (a) earth (b) aggregates (c) sand
etc.,
(ii) All manufactured materials like (a) cement, (b) Bitumen, (c) Steel etc.,
(iii) List of equipment in accordance with requirement of work program like (a)HMP
(b) Concrete Batching plant (c) Pavers (d) PTR etc.,
The Executive Engineer shall ensure that the field laboratory is established for works
costing more than Rs.2.00 Crores.
The quality assurance and quality control in work execution is best achieved by
adopting.
The field engineers shall conduct the tests as required as per the frequency specified
for each items of work. The items of work which are not within the specified limits shall be
rejected or rectified /redone as specified in the departmental circulars.
Each activity of construction shall be associated with RFI and OK card system i.e right from
setting out to final completion. The contractor shall first establish TBMs. Raise an RFI for
verification of TBMs. The Engineer-in-charge shall verify & approve the TBMs if correct. If
TBMs are not correct then redirect to establish them afresh. This methodology shall be
continued for each item like setting out, C&G, Formation, layer wise approval, wherever
construction of a particular item involves construction in layers and for Inspection of
specified plant & Machinery etc., RFIs shall be accompanied by the abstract of test results,
levels etc.,
Working BMs/TBM shall be established one per KM and at each culvert/bridge etc.
center lines, toe lines etc., shall be staked carefully. The surface of road way construction
shall be controlled carefully so as to achieve the designed profile/level. The tolerances with
reference to various stages of construction shall be as indicated.
All work done shall confirm to the lines, grades, cross sections and dimensions as shown on the
drawing or as directed Engineer subject to the permitted tolerances described below:
5
Bituminous Layers ±6
Over – machine laid WMM ±10
Machine laid ±6
Provided that the negative tolerance for wearing course shall not be permitted in conjunction with
the positive tolerance for base Course if the thickness of the former is thereby reduced by more than
the following limits.
The longitudinal profile shall be checked with a three meter long straight edge at the middle of
each traffic lane along a line parallel to the centre line of the road. The cross profile shall be checked
with a set of three camber boards at intervals of 10 meter.
6
2
Length(Meters) 300 75 300 75 300 75 300 75
No.of irregularities in
3
National Highways 15 9 2 1 40 18 4 2
No.of irregularities in
4 Road of lower category 40 18 4 2 60 27 6 3
The maximum allowable difference between the road surface and underside of 3m straight edge
when Placed parallel or right angles to the centre line of the road at points decided by Engineer shall be:
In cases where requirements of surface irregularity are not satisfied and the tolerance limits given
above are exceeded in respect of sub grade and various pavement courses, work of rectification shall
be carried out in the following manner:
A) SUBGRADE: Where the surface is high, it shall be trimmed and suitably compacting shall correct
the deficiency. Where the surface is low, adding fresh material and suitably
compacting shall correct the deficiency.
B) GRANULAR SUB-BASE: Same as at (A) above but the degree of compacting and the type of material
shall confirm to Clause 401.
C) WMM: Where the surface is high or low, the top 75 mm shall be scarified reshaped with added
material wherever necessary and re compacted as per requirement.
D) BITUMINOUS Construction:
I) Other than wearing course: where the surface is low, the deficiency shall be corrected by
adding fresh material and re-compacting to specifications. Where the surface is high, the extra
thickness in the effected layer shall be removed and replaced with fresh material and compacted to
specifications.
7
ii) Wearing Course: Where the surface is high or low, the full depth of the layer shall be
removed and replaced with fresh material and compacted to specifications.
In all cases of bituminous construction, where the removal and replacement of a bituminous
layer is involved, the area treated shall not be less than 3.5 m in width and not less than 5 meters in
length.
2) C & G Stage: (i) In this stage it requires to ensure that the C&G is done up to the widths
as specified or up to toe line/edge of excavation. (ii) Pre-levels i.e. levels prior to
commencement of C&G and after C & G are taken & verified.
Lumps/coarse material of size > 75mm shall not be allowed in embankment and >
50mm shall not be allowed in sub grade.
EMBAN 305
KMENT Plasticity 2 tests per 3000 IS:2720(pt-V) LL≤50,PI ≤25
cum
MDD and OMC --do— IS:2720(pt-VIII) Up to 3
M≥1.52kN/cum
Above
3m,≥1.6kN/cum
Free Swelling
Index --do— IS:2720(pt-40) ≤50
Natural do IS:2720(pt-II)
moisture
content
For earth work in shoulders and sub grade at least one set of ten density measurements shall be
taken for each 2000 sq. m of compacted area.
FREQUENCY RELEVANT
ITEM CLAUSE TEST REQUIRED LIMITS
(Min) IS CODE
The acceptance criteria shall be subject to condition that the mean density is not less than the
specified density plus (1.65 – 1.65/√n)*σ.
4(ii) Wet Mix Macadam sub base: Compacted thickness of a single layer shall not be less than
75mm nor more than 200mm. The material shall be graded aggregate and granular material. The
aggregate shall confirm to the limits specified in table 400-13. Which is extracted hereunder
The grading shall not vary from low limit on one sieve to the high sieve on the adjacent
sieve. Mixing, laying and compacting shall be as per the specifications in a particular contract like use
of pug mill, paver, and vibratory roller etc., without exception where ever they are provided for in
the agreement.
After final compaction WMM surface shall be allowed to dry for 24 hours.
No vehicular traffic shall be allowed on WMM surface.
Where the surface irregularity exceeds the permissible tolerance limits, or defective, the full
thickness of the layer shall be scarified over the affected area, re-shaped with added premixed
material or removed and replaced with fresh material and compacted to required density. Various
limits of quality control tests on WMM surface are as follows:
11
The acceptance criteria shall be subject to condition that the mean density is not less than
the specified density plus (1.65 – 1.65/√n)*σ.
5 Bituminous Bases/W.C.
Binder shall confirm to grades mentioned in I.S. 73 and modified binders shall confirm to
specification as IRC SP53 and IS 15462
5(i) Prime coat: Prime coat is applied on a prepared granular surface on which a bituminous layer in
going to be laid.
The characteristics of prime coat and frequency for tests shall be as follows.
5(ii) Tack coat: It is applied on a primed granular surface or on a bituminous surface which
is going to receive next layer of bituminous surface. The material shall be as specified in
agreement i.e., VG 10 or bitumen emulsion etc. The required properties, tests to be
conducted are as follows.
Mixing:
The ingredients of BM i.e. (i) Bitumen, (ii) Coarse aggregate and (iii)Fine aggregates
shall be as per relevant MORTH classes which are compiled in this QAP at relevant pages.
The mix of aggregate and binder shall be prepared in Hot Mix Plant of specified type
and capacity. The mix shall be uniform and mixed at specified temperatures as indicated in
respective clauses and extracted here in QAP.
The difference in temperature between the binder and aggregate shall not exceed
140 C. The Hot Mix Plant shall be calibrated from time to time to produce the desired mix.
Transporting:
Mix shall be transported in clean, insulated and covered vehicles. Asphalt release
agent like soap or lime water may be applied to interiors to facilitate discharge of material.
13
Laying:
Spreading/laying mix shall be avoided (i) when standing water is present (ii) when rain is
imminent, (iii) when the course on which the mix is going to be laid is damp, (iv)when the course on
which the mix is going to be laid is having temperature < 100 C for conventional bitumen and < 150 C
for modified bitumen. (v) when wind speed exceeds 40 kmph at 2m height. Spreading shall be by
specified type of paving machine. Mix soon after arrival at the site shall be supplied continuously to
the paver and laid without delay. Paver speed shall be adjusted to ensure even and uniform flow,
free from dragging, tearing and segregation. Where paver can’t reach, the material shall be spread,
raked and levelled with suitable hand tools. The bitumen mix shall be spread on surface cleaned of
all loose and extraneous matter by means of a mechanical broom and air jet. The equipment for
applying a high pressure air jet shall be available full time at the site.
Compaction:
Compaction shall commence as soon as possible after laying. Rolling shall be completed
before the temperature falls below specified temperature. Rolling of the longitudinal joints shall be
done immediately behind the paving operation. After rolling of longitudinal joint, rolling shall
commence from edges and shall progress towards centre. In super elevated or unidirectional
camber rolling shall progress from lower edge to upper edge. Rolling shall continue until all roller
makes have been removed from the surface. Rolling shall be in three stages: (i) The initial or break
down rolling with 8-10 t static weight smooth wheeled rollers (ii) The intermediate rolling with 8 -
10 t static weight or vibratory roller or with 12 to 15 t PTR with a tyre pressure of at least 0.56MPa,
(iii)Finish rolling shall be with 6 – 8 t smooth wheel tandem rollers. Each pass of roller shall overlap
with the previous pass by 1/3rd of the roller width and in case of PTR by 300mm. Roller speed shall
not be more than 5 Kmph.
Joints:
All joints shall be cut vertical to the full thickness of the previously laid mix. All loosened
material shall be discarded and the vertical face coated with a suitable viscosity grade hot bitumen.
The material/mix shall be spread along the joint with a overlap of 25mm to 50mm. The thickness of
the loose overlap shall be ~ ¼ of final compacted thickness. The overlap shall be dragged back to
hot lane and rolled to give a high density joint. Longitudinal joints shall not be in wheel tract zones.
Transverse joints in successive layers shall be with a minimum off set of 2m.
14
The requirements of grading, binder content, mix for BM, DBM & BC shall be as
detailed below.
Grading 1 2
Nominal Maximum aggregate Size* 40mm 19mm
Layer thickness 80 -100mm 50-75mm
IS Sieve size (mm) Cumulative % by weight of total aggregate passing
45 100
37.5 90-100
26.5 75-100 100
19 - 90-100
13.2 35-61 56-88
4.75 13-22 16-36
2.36 4 – 19 4 – 19
0.3 2 – 10 2 – 10
0.075 0–8 0–8
Bitumen content ** percent by mass 3.3** 3.4**
of total mix
* Nominal maximum aggregate size is the largest specified sieve size upon which any of the
aggregate material is retained.
ii) Aggregate Impact value or Los One test per 200 cu.m. of each
Angeles Abrasion Value source and whenever there is
change in the quality of aggregate.
iii) Combined Flakiness and One test per 350 cu.m for each
Elongation indices source
iv) Stripping value One test of each source and
whenever there is change in the
quality of aggregate
v) Water absorption of aggregates - do -
vi) Water sensitivity of mix - do -
vii) Grading of aggregates 2 tests per day
viii)Soundness (Magnesium One test of each source and
sulphate/Sodium sulphate) whenever there is change in the
quality of aggregate
The B.M layer shall be protected with next layer of pavement course or W.C within a
maximum period of forty eight hours. If there is any delay, it shall be covered by seal coat.
16
The thickness of single layer shall be from 50mm to 100mm. The combined grading and
bitumen content of DBM shall be as fallows.
Grading 1 2
Nominal aggregate Size* 37.5mm 26.5 mm
Layer thickness 75 -100mm 50-75 mm
IS Sieve size (mm) Cumulative % by weight of total aggregate passing
45 100
37.5 95-100 100
26.5 63- 93 90 – 100
19 - 71 – 95
13.2 55- 75 56 – 80
9.5 - -
4.75 38 – 54 38 – 54
2.36 28 – 42 28 – 42
1.18 - -
0.6 - -
0.3 7 – 21 7 – 21
0.15 - -
0.075 2–8 2–8
Bitumen content % by mass of Min. 4.0** Min. 4.5**
total mix
The nominal maximum particle size is the largest specified sieve size upon which any of the
aggregate is retained.
** Corresponds to specific gravity of aggregates being 2.7. In case aggregate have specific gravity
more than 2.7, the minimum bitumen content can be reduced proportionately. Further the
region wherein highest daily mean air temperature is 300 C or lower and lowest daily air
temperature is - 100 C or lower, the bitumen content may be increased by 0.5 percent.
17
** If the minimum retained tensile test strength falls below 80 percent, use of anti stripping agent
is recommended to meet the requirement.
Apart from grading and quality of individual ingredients, the mix of DBM shall satisfy the
following requirements.
Opening to the traffic shall be after the DBM layer is cooled to ambient temperature.
Combined 1 set of test per 400 tons IS:2386,part-II As per MOST table
gradation subjected to a minimum of
two test per plant per day
Bitumen content One test for 400 tonnes of ASTM D-2172 Min 4%by weight
mix subject min of two tests of total mix for
per plant per day Grd-1
Stability at 600C One set of test per 400 tons ASTM D1559 <9 KN
subjected to a minimum of
two test per plant per day
Flow 2-4mm
Nominal Maximum Minimum VMA, percent related to design air voids present
Particle size(mm) 3.0 4.0 5.0
26.5 11.0 12.0 13.0
Subjected to the condition that final gradation shall remain within respective gradation band
Grading 1 2
Nominal aggregate size 19mm 13.2mm
Layer thickness 50mm 30-40mm
IS Sieve (mm) Cumulative % by weight of total aggregate passing
45
37.5
26.5 100
19 90-100 100
13.2 59-79 90-100
9.5 52-72 70-88
4.75 35-55 53-71
2.36 28-44 42-58
1.18 20-34 34-48
0.6 15-27 26-38
0.3 10-20 18-28
0.15 5-13 12-20
0.075 2-8 4-10
Bitumen content % by mass of total Min 5.2* Min 5.4**
mix
Note:
The nominal maximum particle size is the largest specified sieve size up on which any of
the aggregate is retained
** Corresponding to specific gravity of aggregate being 2.7 .In case aggregate have specific
gravity more than 2.7, the minimum bitumen content can be reduced
proportionately. Further the region where highest daily mean air temperature is 300
C or lower and lowest daily air temperature is – 100 C or lower, the bitumen content
may be increased by 0.5 percent.
21
Combined One set of test per 400 tons IS:2386,part-II As per MOST
gradation/mix subjected to a minimum of two table
grading test per plant per day
For all bituminous layers the acceptance criteria with regard to density is that the mean density is
not less than the specified density plus (1.65 – 1.65/√n)*σ.
Rigid pavements are usually constructed on a sub base consisting of (a) Granular material
OR (b) stabilized soil OR(c) Semi Rigid material, usually DLC.
Below this sub base, the sub grade shall have the following properties.
The grading of aggregate (combined grading of fine and coarse aggregates) shall be as
follows
The field density achieved at edges i.e 0.5m from edges shall not be less than 96% maximum
density that is achieved during trial construction.
The minimum dry density shall not be less than 98% of maximum dry density obtained
during trial length construction.
The average compressive strength of each consecutive group of cubes shall not be less than
10mpa at 7days. The minimum individual cube strength shall not be less than 7.5mpa at
7days. OR
23
While laying the DLC, the concrete shall have the moisture content between OMC and OMC
+2%.
Time from mixing of concrete and the final finishing in any transverse section shall not be
more than 90mts if temperature is 250c to 300c and 120 minutes if temperature is < 250c (of
concrete).
The combined grading of Fine and Coarse aggregates for PQC shall be as fallows.
Water absorption ≤ 2%
Aggregate 1. Gradation IS 2386 Part 1 One test for every day’s work of
each fraction of coarse aggregate
and fine aggregate.
IS 2386 Part 2
- do -
2. Deleterious
IS 2386 part 3 Regularly as required , subject to a
3. Water absorption
minimum of 1 test / day for coarse
aggregate and two test /day for
fine aggregate.
4. Bulking of fine IS: 2386 part 3 Once for each source for moisture
aggregate content for deriving the moisture
content and bulking relationship.
25
Coarse aggregate 1. Los Angels IS 2386 Part 4 Once for each source of supply and
abrasion Value/AIV subsequently when warranted by
changes in the quality of
aggregate/monthly basis
BRIDGES
Bridge is one of the most important inventions of the human history. Bridges are not only
most difficult structures to be constructed but also the most expensive part of highway
projects.
Therefore it is all the more important that these structures are built with a proper and
detailed QAP in place.
QAP for bridges/ C.D works shall start with planning and investigation stage.
Planning stage: Planning of bridges influences the overall cost of the bridge. Hence it is
utmost important to have proper planning.
(i) For bridges up to 60m length the siting of bridges shall generally governed by the
approach alignment (straight, minimum shifting etc.)
(ii) For bridges from 60 to 300mm. The site selection shall be suitability of bridges
site and proper alignment of approaches.
(iii) For bridges of length > 300m, suitability of bridge site shall have the overriding
consideration.
Investigation stage:
(1) Hydraulic investigation: The cost of bridge and /or safety of the bridge is influenced by
this aspect to a large extent. Under estimation of maximum discharge will endanger the
bridge safety whereas over estimation of maximum discharge will increase the cost of
bridges. Hence max discharge shall be properly estimated by (i) Correctly assessing the HFL,
(ii) Selection of proper cross sections (Always at right angle to the direction of flow).(iii)
Correct estimation of bed slope.(iv) correct estimation of catchment area.(v) Adoption of
correct formula for assessing ‘Q’ i.e., max discharge. For all major bridges, it is always
advisable to obtain HFL and ‘Q’ from CWC for the site selected. Correct estimation of silt
factor which influences the type, and depth of foundations.
(2) Geological/Subsurface investigation: This investigation will greatly influence the safety
and cost of the bridges.
The subsurface investigation for bridges shall be carried out in the following three
zones:
i) Between bed level and up to anticipated maximum scour depth (below H.F.L)
iii) From founding level to a depth of about 1 ½ times the width of the foundation.
27
The data required to be obtained from each zone will cover soil classification,
particle size distribution, shear strength characteristics, compressibility and permeability as
detailed in Table 1 of Annex 2 of IRC:78 . In all cases, samples of soils shall be collected at
every 1 m to 1.5 m depth or at change of strata.
For bridge works, the investigations shall be comprehensive enough to give the following
information to the designer:
ii) The location and extent of soft layers, cavities and gas pockets, if
any, under the hard founding strata.
Structural concrete: The requirement of concrete for different exposure conditions with
20mm aggregate are as follows.
Note:
i) All three provisions given in the above table for a particular exposure condition, shall be
satisfied.
ii) The term cement for maximum w/c ratio and minimum cement content shown in Table
includes all cementitious materials mentioned in Clause 1715.2. The maximum limit of
fly ash and ground granulated blast furnace slag in the blended cement shall be as
specified in IS:1489 (Part-I) and IS: 455 respectively.
iii) For plain cement concrete, with or without surface reinforcement, the minimum grade
of concrete can be lowered by 5 MPa and maximum water/cement ratio exceeded by
0.05.
Cement content shown in the above table shall be increased by 40 kg/m3 for use of 40mm
nominal size aggregates.
Note: When the grading falls outside the limits of any particular grading zone of sieves other than 600 –
micron IS Sieve by a total amount not exceeding 5 percent, it shall be regarded as falling within that
grading zone. However for crushed stone sand, the permissible limit on 150-micron IS Sieve is
increased to 20 percent. Reference shall be made to clause: 4.3 of IS: 383.
The Flakiness index for coarse aggregate shall not be more than 35.
The Fineness modulus of Fine Aggregate shall be≥ 2 and ≤ 3.5.
29
Requirements of Consistency
Notwithstanding the optimum consistency indicated against Sl. No.1 to 3, the situation
should be property assessed to arrive at the desired workability with the adjustment of
admixture in each case, where the concrete is to be transported through transit mixer and
placed using concrete pump. Under these circumstances, the optimum consistency during
placement for the items of work of Sl. No.1 to 3, can be considered ranging from 75mm to
150mm. This is, however, subject to satisfying the other essential criteria of strength,
durability etc. and approval of the Engineer.
Maximum Nominal
Components Size of Coarse
Aggregate (mm)
i) RCC well curb 20
ii) RCC/PCC well steining 40
iii)Well cap or Pile Cap Solid type piers and abutments 40
iv) RCC work in girder, slabs wearing coat, kerb, approach slab, 20
hollow piers and abutments, pier/abutment caps, piles
v) PSC work 20
vi) Any other item As specified by the
Engineer
Maximum nominal size of aggregates shall also be restricted to the smaller of the following
values:
a) 10mm less than the minimum lateral clear distance between individual
reinforcements.
b) 10mm less than the minimum clear cover to the reinforcement
c) One quarter of minimum thickness of member.
The proportions of the various individual sizes of aggregates shall be so adjusted that
the grading produces the densest mix and the grading curve corresponds to the maximum
nominal size adopted for the concrete mix.
EQUIPMENT
a) Production of Concrete:
i) For overall bridge length of less than 200 m – batch type concrete
mixer, diesel or electric operated, with a minimum size of 200
litres automatic water measuring system and integral weigher
(hydraulic/pneumatic type)
Accuracy of measurement
The accuracy of the measuring devices shall fall within the following limits:
A random sampling procedure shall be adopted which ensures that each of the concrete
batches forming the lot under acceptance inspection has equal chance of being chosen for
taking cubes.
150mm cubes shall be made, cured and tested at the age of 28 days for compressive
strength in accordance with the IS:516. The 28 day test strength result for each cube shall
form an item of the sample. Tests at other age shall also be performed, if specified.
Where automated batching plant/Ready Mixed Concrete Plant is located away from the
place of use and the time gap between production and placement is more than the initial
setting time or where any ingredients are added subsequent to mixing, separate sets of
samples shall be collected and tested at batching plant and at location of placement. The
results shall be compared and used to make suitable adjustment at batching plants so that
properties of concrete at placement are as per the requirements.
Three test specimens shall be made from each sample for testing at 28 days. Additional
cubes may be required for various purposes such as to determine the strength of concrete
at 7 days or for any other purpose.
The test strength of the sample shall be the average of the strength of 3 cubes. The
individual variation should not be more than + 15 percent of the average. If variation is
more, the test results of the sample are invalid.
Frequency
32
Acceptance criteria
Cubes
The concrete shall be taken as having the specified compressive strength when
both the following conditions are met:
a) The mean strength determined from any group of four consecutive non-
overlapping samples exceed
b) s the specified characteristic compressive strength by 3 MPa.
c) Strength of any sample is not less than the specified characteristic compressive
strength minus 3 MPa.
The quantity of concrete represented by the test results include the batches from
which the first and last samples were taken, together with all intervening batches.
PILE FOUNDATIONS
The requirement of concrete in piles shall be as follows.
The terms ‘minimum cement content’ and ‘minimum water cement’ ratio mentioned are to
based on total cementitious material (inclusive of all mineral admixtures called additives)
mentioned in Clause 1007 of these specifications. Maximum limits for such additives shall
be as specified in Clause 1716.2 of these specifications.
Well Foundations:
Most commonly used deep foundations. These may be in brick masonry, PCC or RCC.
The tolerances are
TOLERANCES
The permissible tilt and shift shall not exceed 1 (horizontal) in 80 (vertical) and the shift at
the well base shall not be more than 150mm in any resultant direction.
For the well steining and well cap, the permissible tolerances shall be as follows:
If any well with tilt and/or shift exceeding the permissible values is accepted by the Engineer
the contractor shall be subjected to a reduction in the rates for the sinking of well as
follows:
For excessive tilt and shift, the reduction in rates shall be decided separately by the
Engineer.
Open foundations: The Open foundation shall be executed as per specifications
indicated in the drawing to the dimensions indicated there on.
TOLERANCES
Note: 1. Where ever the limits as specified above are over ruled through Government
orders/concerned HOD orders they shall be fallowed.
Enls.1. Copy of circular no.12582/Vig.I/1/2005-1 dt.17-10-2006.
2. List of Equipment for various activities communicated through circular .no.
711/ENC-QC/TS/DEE/AEE1/2014 Dt. 24-11-2014
1
START
AGREEMENT CONCLUDED
NO
IS THE WORK PROGRAMME
PROPER AND APPROVED
YES
NO
IS SETTING OUT VERIFIED
AND FOUND CORRECT
YES
START OF C&G, SUBMISSION OF PRELEVELS
NO
VERIFICATION OF PRELEVELS.
LEVELS TALLIED?
YES
C&G COMPLETED, SUBMISSION OF FINAL LEVELS
IS VERIFICATION OF FINAL
LEVELS DONE AND AGREED
2
NO
ARE THE MACHINERY AND
PLANTS AS PER
SPECIFICATIONS?
YES
NO
VERIFICATION OF MATERIAL
PROPERTIES, LIKE ATTERBERG
LIMITS,DENSITY, OMC ETC.,
RESULTS SATISFY?
YES
NO
VERIFICATION OF FIELD
DENSITY, OMC, LAYER WISE
RESULTS SATISFY?
YES
NO
VERIFICATION OF MATERIAL
PROPERTIES LIKE CBR, OMC,
DENSITY AND ATTERBERG LIMITS
RESULTS SATISFY?
YES
3
NO
VERIFICATION OF FDD,
OMC, LAYER WISE.
RESULTS SATISFY?
YES
NO
VERIFICATION OF MATERIAL PROPERTIES LIKE
CBR, OMC, DENSITY, ATTERBERG LIMITS
(THESE ARE ESSENTIAL WHEN THE GSB IS
PROVIDED WITH NATURAL MATERIAL LIKE
NATURAL GRAVEL/MORRUM) ETC.,
RESULTS SATISFY?
YES
NO
VERIFICATION OF FDD,
PROFILE ETC.,
RESULTS SATISFY?
YES
4
NO
VARIFICATION OF MATERIAL
PROPERTIES LIKE AIV, PI, PLANT &
MACHINERY ETC.,
RESULTS SATISFY?
YES
NO
RESULTS SATISFY?
YES
NO
VARIFICATION OF MATERIAL
PROPERTIES
RESULTS SATISFY?
YES
5
NO
VARIFICATION OF MATERIAL
PROPERTIES
RESULTS SATISFY?
YES
SPREADING OF TACK COAT ALONG WITH CKECKING FOR RATE OF SPREAD
NO
VARIFICATION OF MATERIAL
PROPERTIES LIKE QUALITY OF BINDER,
AGGREGATE, MIX DESIGN PLANT &
EQUIPMENT ETC.,
RESULTS SATISFY?
YES
NO
VARIFICATION OF BITUMINUS BINDER
COURSES FOR PROFILE, GRADATION,
DENSITY ,BITUMEN CONTENT ETC.,
LAYERWISE.
RESULTS SATISFY?
YES
6
NO
RESULTS SATISFY?
YES
NO
VARIFICATION OF BITUMINOUS
WEARING COURSES LIKE PROFILE
DENSITY BITUMEN CONTENT AND
GRADATION
RESULTS SATISFY?
YES
END