Anda di halaman 1dari 5

PT.

WIJAYA KARYA (Persero) Tbk


PROCEDURE
DEPARTEMEN INDUSTRIAL PLANT

Document Number MATERIAL TAKE Rev. : 1


OFF FOR MAINLINE Page Number
PRPP-10-MTO-0001
AND HOT BEND PIPE 1 dari 5

PROJECT END USER : PT. PERTAMINA (PERSERO)

PROJECT OWNER : PT. KERETA CEPAT INDONESIA CHINA

COMPANY : HIGH SPEED RAILWAY CONTRACTOR


CONSORTIUM PT. WIJAYA KARYA (Persero) Tbk
– DEPARTEMEN SIPIL UMUM 1

CONTRACTOR : PT. WIJAYA KARYA (Persero) Tbk –


DEPARTEMEN INDUSTRIAL PLANT

PROJECT : RELOCATION FUEL OIL PIPELINE PERTAMINA


DK 117-128 & DK 135-138

LOCATION : TOL PURBALEUNYI, BANDUNG, JAWA BARAT

CONTRACT NUMBER : TP.02.01/HSRCC.WIKA.P/96/X/2018

1 05/01/2019 IFI BGS RA GPS


0 7/12/2018 IFI BGS RA GPS
Made By Reviewed By Approved By
REV. DATE DESC
PT WIJAYA KARYA
PT. WIJAYA KARYA (Persero) Tbk
PROCEDURE
DEPARTEMEN INDUSTRIAL PLANT

Document Number MATERIAL TAKE Rev. : 1


OFF FOR MAINLINE Page Number
PRPP-10-MTO-0001
AND HOT BEND PIPE 2 dari 5

TABLE OF CONTENS
1. GENERAL
2. DEFINITIONS DOCUMENT
3. DEFINITION
4. ABBREVIATION
5. REFERENCE

EXHIBIT I MTO MAIN LINE


EXHIBIT II MTO HOT BEND PIPE
PT. WIJAYA KARYA (Persero) Tbk
PROCEDURE
DEPARTEMEN INDUSTRIAL PLANT

Document Number MATERIAL TAKE Rev. : 1


OFF FOR MAINLINE Page Number
PRPP-10-MTO-0001
AND HOT BEND PIPE 3 dari 5

1. GENERAL
This procedure explains the Material Take Off for Main Line and Hot
Bend pipe are used to Project Relocation of Fuel oil Pipeline Pertamina DK 117-
128 and DK 135-138.

2. DEFINITION DOCUMENT
This Material Take Off document aims to define requirements to supply material for
12” for this project.

3. DEFINITIONS
PROJECT END USER : PT. PERTAMINA (PERSERO)

PROJECT OWNER : PT. KERETA CEPAT INDONESIA CHINA

COMPANY : HIGH SPEED RAILWAY CONTRACTOR


CONSORTIUM PT. WIJAYA KARYA (Persero) Tbk
– DEPARTEMEN SIPIL UMUM 1

CONTRACTOR : PT. WIJAYA KARYA (Persero) Tbk –


DEPARTEMEN INDUSTRIAL PLANT

4. Abbreviations
3LPE Three Layer Polyethylene
API American Petroleum Institute
ASME American Society of Mechanical Engineers
HFERW High-Frequency Electric Resistance Welding
MTO Material Take Off
PT. WIJAYA KARYA (Persero) Tbk
PROCEDURE
DEPARTEMEN INDUSTRIAL PLANT

Document Number MATERIAL TAKE Rev. : 1


OFF FOR MAINLINE Page Number
PRPP-10-MTO-0001
AND HOT BEND PIPE 4 dari 5

5. REFERENCES
a. Indonesian Legislation and Regulations
[1] KEPMENTAMBEN 300.K/38/M.PE/1997 : Keselamatan Kerja Pipa
Penyalur Minyak dan Gas Bumi
[2] SNI 3474 : Sistem Penyaluran dan Distribusi
Pipa Gas
b. International Codes & Standards
[3] ASME B31.4 : Pipeline Transportation Systems for
Liquid and Slurries
[4] API 5L : Specification for Line Pipe
c. Project Documents
[5] KCIC-FPR-5304-000-JSD-3200-001 : Pipeline Design Basis
[6] KCIC-FPR-5304-000-RT-3200-001 : Wall Thickness Verification Calculation
[7] KCIC-FPR-5304-000-NM-3200-004 : Cathodic Protection Data Sheet
[8] KCIC-FPR-5304-000-SP-3200-007 : Cathodic Protection Specification
[9] KCIC-FPR-5304-000-DW-3200-005 : Pipeline Alignment Sheet Drawing
[10] PRPP-10-TBE-0001 : TBE FOR MAIN PIPELINE
[11] PRPP-30-RFQ-0001 : RFQ Main Pipeline
[12] KCIC-FPR-5304-000-SP-3200-002 : Welded Bend Specification
[13] KCIC-FPR-5304-000-NM-3200-002 :Data Sheet of Hot Bends for Carbon
Steel Pipe
PT. WIJAYA KARYA (Persero) Tbk
PROCEDURE
DEPARTEMEN INDUSTRIAL PLANT

Document Number MATERIAL TAKE Rev. : 1


OFF FOR MAINLINE Page Number
PRPP-10-MTO-0001
AND HOT BEND PIPE 5 dari 5

MTO FOR HOT BEND

NO BOQ BOQ BOQ


CODE DESCRIPTION DEVIASI
TENDER REV 0 REV 1
Hot bend Elbow
Hot bend Elbow 11 Ø 12 6 10 15 -5
1 11
Hot bend Elbow
Hot bend Elbow 30 Ø 12 3 12 6+6 6
2 30
Hot bend Elbow
Hot bend Elbow 45 Ø 12 47 29 36 -7
3 45
Hot bend Elbow
Hot bend Elbow 60 Ø 12 11 14 14 0
4 60
Hot bend Elbow
Hot bend Elbow 90 Ø 12 4 6 7 -1
5 90

Note: For the Spare 30” 6 each