Anda di halaman 1dari 12

QUESTIONAIRE

FOR HIGH RISE BUILDINGS (Buildings having Height Below 15 meter)


HARYANA FIRE SERVICE

Sl
Particulars Requirements As per N.B.C. Proposed provision
No

1 Name of the Building Sunvisors India Pvt. Ltd.

2 Classification of Building as per NBC Group G 2: Industrial


Buildings with
moderate hazard
3 Address of the Building Plot no. 3&4 , Sector 18,
Electronic City ,
Gurgaon

4 Name and address of builder / promoter Kothari associates& Architects


G-65 Canuaht Place
New Delhi

5 Name and address of owners / occupiers of V. K Chanana


individual flats D-79 Gulmohar Park
New Delhi-110049

6 Plot Area 2000 Sq Meter

7 Covered area (at ground level) 1199.5sQ Meter

8 Height of the Building

a) Overall height (from grade level) 09 Meter

b) Occupied Height 08 Meter

9 Number of floors (including ground floor) 02


10 Nos. of Basement , Area & Level 01, 300 Sq Meter, G-3mtr

11 If the Basement extend beyond the building No


line . Indicate the load bearing strength of the
roof of basement.

15 Compass direction in relation to the building.

NORTH 18M wide road

SOUTH Maruti Udhyog, Indutrial

EAST Plot No.5, Industrial

WEST Plot No. 2, Industrial

16 Approach to proposed building, width of the 18 Meter Wide Road


road and connecting roads, if any

17
Please give details of water supply Huda Water Supply and 45kLt.
available exclusively for fire fighting Storage tank.

18 Has wet riser(s) been provided ? No, only one floor above
If so, please indicate the number of risers ground which is provided by
and internal dia of each hydrant and hose reel
Yard Hydrant

19.. Has any down comer been provided ? If so, No


please give details.

20 Have internal hydrants been provided. If so, Ground floor = 02 Nos


please indicate:- First Floor = 01 Nos
a) No. of hydrants on each floor
including basement(s) and terrace.

b) Have these hydrants single or twin Single outlet


outlets.

21 Have first aid hose reels been provided ? Yes

If so, please indicate:-


a) No. of hose reels on each floor Ground floor = 02
including First Floor= 01
basement (s) Outside = 01

b) Bore and length of hose-reel tubing on Tube diameter = 20 mm


each reel. Length = 30 mtr

c) Size (bore) and type of nozzle fitted to Bore = 6 mm


each hose reel. Type of Nozzle = Shut off
Nozzle
d) Is the hose reel connected directly to the Yes to the Hydrant outlet
riser or to the hydrant outlet ?
22 Has fire hose been provided near each Yes
hydrant ? If so, please indicate:-
a) the type of hoses. Fabric Hose

b) the size (bore) of hoses. 63 mm

c) the length of each hose. 15 Mtr

d) total number of hoses provided near 16 in Nos


each hydrant.

23 Have branch pipes been provided ? If so, Yes


please indicate :-

a) the type of branch pipes Short Branch Pipe

b) Size of nozzle fitted to each branch 15 mm

24 a) If the basement is used for car Yes


parking or storage, has it been sprinkled ?
b) Whether segregation/compartmentation of Wall is provided in the
the basement has been provided. If so Basement for
please detail- Compartmentization, Also Fire
Redardent door has been
provided.
25 Is the building equipped with automatic fire YES, Smoke Detcetor has
detection and alarm system ? If so, please been providedat. Provided in
indicate the type of detector used :- 22 Places which include Office
area and LT Panel,Stabaliser
room.

26 Have manual call point been installed in the YES, manual Call Points Has
building for raising an alarm in the event of Been Provided.
an outbreak of fire ? If so, please give Total 16 MCPs are provided in
details. the entire plant

27 How many staircases have been provided in 01


the building ? please indicate in each case :-

a) width of the stairway 5 feet

b) width of treads. 1 feet

c) height of risers 6" INCH

28 Have any stationary fire pump(s) been No


installed for pressurizing the wet riser ?

a) The number of pumps.

b) The output of each pump.

c) Is the pump automatic in action

29 Has any yard hydrant been provided Yes


from the
building’s fire pump ?
30 Have all exists and direction of travel to each Yes
exit been sign-posted with illuminated signs.
31 Has false ceiling been provided in any Not Provided
portion of the building ? If so, please indicate
location and also mention if the material used
for the false ceiling is combustible or non-
combustible.

32 Is the building centrally air-conditioned? If No


so, please indicate :-

a) The material used for construction of Not Applicable


ducts and its fittings.

b) The type of lining used for ducts, if any. Not Applicable

c) The type of lagging used, if any for Not Applicable


insulating any portion of the duct ; please
also indicate how the lagging is secured.

d) If false ceiling is provided, please Not Applicable


give information as at (42) above.

e) If plenum is used a return air passage Not Applicable


has it been protected with fire detectors?
please give details.

f) Has a separate A.H.U been provided for Not Applicable


each floor ?

g) Whether automatic shut dhown of Not Applicable


A.H.U. is coupled with detection system ?

h) Is the ducting for each floor effectively Not Applicable


isolated or is it continuous on more than one
floors ?
I) Is the fire dampers being provided? Not Applicable

33 Where are the switchgear and transformers


located ? If inside the building, please
indicate
a) If the switchgear and transformer(s) Yes
have been housed in separate
compartments, effectively separated from
each other and from other portions of the
buildings by a four hours’ fire resistive
wall ?

b) What precautions have been taken to Distance from Building is far


prevent a possible fire in the transformer(s) off. As per NBC
from spreading ?

34 Ventilation in basement-

a) Whether Natural ventilation is relied YES, VENT-6'X2' X10 Nos


upon? If so, give detail of the vents for the
stairwell lift lobby and lift shaft

b) Whether Mechanical ventilation has been No


proposed? If so give detail of the proposed
system indicating the no. of air changers for
the basement and upper floors.

c) Whether mechanical ventilation is coupled No


with automatic detection system ?
Please give details of the system.

35 Please indicate the number and type of fire ABC=45


extinguishers provided at various locations Foam=3
and the arrangement for the maintenance of Co2=1
the extinguishers. External Agency
Signature of the Fire Consultant Signature of the Architect
With Date & Stamps With Date & Stamps

Name............................................... Name.....................................

(In Block Letters) (In Block Letters)

Organization

Place:- Designation

Dated:- Organization
Signature of the APPLICANT/ OWNER'S

Note :- every page of questionnaire is duly signed by fire consultant, ventilation consultant, fire alarm
detection consultant, architect & owner/authorize signatory
16652
62733
149990
149990
149990
30518
1048000
25 Is the building equipped with automatic fire detection and alarm system ? If so, please indicate the type of detector used :-

26 Have manual call point been installed in the building for raising an alarm in the event of an outbreak of fire ? If so, please give details.

27 How many staircases have been provided in the building ? please indicate in each case :-

a) width of the stairway

b) width of treads.

c) height of risers

28 Have any stationary fire pump(s) been installed for pressurizing the wet riser ?

a) The number of pumps.

b) The output of each pump.

c) Is the pump automatic in action

29 Has any yard hydrant been provided from the


building’s fire pump ?

30 Have all exists and direction of travel to each exit been sign-posted with illuminated signs.

31 Has false ceiling been provided in any portion of the building ? If so, please indicate location and also mention if the material used for the false cei

32 Is the building centrally air-conditioned? If so, please indicate :-

a) The material used for construction of ducts and its fittings.

b) The type of lining used for ducts, if any.

c) The type of lagging used, if any for insulating any portion of the duct ; please also indicate how the lagging is secured.

d) If false ceiling is provided, please give information as at (42) above.

e) If plenum is used a return air passage has it been protected with fire detectors? please give details.

f) Has a separate A.H.U been provided for each floor ?


ease indicate the type of detector used :-

ent of an outbreak of fire ? If so, please give details.

e location and also mention if the material used for the false ceiling is combustible or non-combustible.

lso indicate how the lagging is secured.

? please give details.


g) Whether automatic shut dhown of A.H.U. is coupled with detection system ?

h) Is the ducting for each floor effectively isolated or is it continuous on more than one floors ?

I) Is the fire dampers being provided?

33 Where are the switchgear and transformers located ? If inside the building, please indicate

a) If the switchgear and transformer(s) have been housed in separate compartments, effectively separated from each other and from othe

b) What precautions have been taken to prevent a possible fire in the transformer(s) from spreading ?

34 Ventilation in basement-

a) Whether Natural ventilation is relied upon? If so, give detail of the vents for the stairwell lift lobby and lift shaft

b) Whether Mechanical ventilation has been proposed? If so give detail of the proposed system indicating the no. of air changers f

c) Whether mechanical ventilation is coupled with automatic detection system ? Please give details of the system.

35 Please indicate the number and type of fire extinguishers provided at various locations and the arrangement for the maintenance of the extinguish
artments, effectively separated from each other and from other portions of the buildings by a four hours’ fire resistive wall ?