Anda di halaman 1dari 1

SAURA IMPORT & EXPORT CO., INC. V.

DEVELOPMENT BANK OF THE PHILIPPINES


Apr 27 1972| Makalintal, J. | Petition for Review on Certiorari | Mutuum
PETITIONER: Saura Import and Export Co, Inc.
RESPONDENT: Devt Bank of the Philippines
SUMMARY: The RFC approved Saura Inc’s application for a P500k subject to certain conditions;
however, Saura requested changes in the terms of the agreement. While negotiations took place, the
loan documents were executed, including a deed of mortgage. Negotiations eventually came to a
standstill and Saura requested that the mortgage be cancelled, which request the RFC complied with. In
the meantime, Saura failed to pay other obligations. Almost 9 years later, Saura filed suit against the
RFC, alleging that RFC’s non-compliance with its obligation to release the loan proceeds had prevented
Saura from complying with its other commitments. The SC ruled against Saura and dismissed the
complaint.
DOCTRINE: Mutuum contracts are only perfected upon the actual delivery of the object of the contract.
Notwithstanding the fact that all the documentary requirements have been signed, mutual desistance
prior to delivery of the object, as signified by the acts of the parties, may terminate the contract

FACTS: RATIO:
1. Plaintiff Saura Import and Export Co., Inc. applied to the 1. There was perfected consensual contract as recognized
Rehabilitation Finance Corp, before its conversion into in Art 1934, CC: An accepted promise to deliver something,
DBP, for a P500k industrial loan. The application was by way of commodatum or simple loan is binding upon the
approved subject to specific terms and to be secured by a parties, but the commodatum or simple loan itself shall not
mortgage on the factory building to be constructed, land be perfected until the delivery of the object of the contract.
site, machinery and equipment to be installed. Saura was 2. There was undoubtedly offer and acceptance in this
officially notified of the resolution of approval on 9 Jan case. Saura’s application for a P500k loan was approved by
1954, but had asked the day before for modification of the defendant’s resolution, and the corresponding mortgage
terms. was executed and registered.
2. In the meantime, the loan documents were executed, 3. When the loan was approved, it was with the imposition
including the promissory note and corresponding deed of with conditions, none of which deviated from the terms of
mortgage. However, after continuous communications, the agreement; rather, they were a step in its
negotiations between Saura and the RFC eventually came implementation. Nor did the conditions contradict the
to a standstill. Saura did not pursue the matter further but terms laid down in the original RFC Resolution approving
instead rested RFC to cancel the mortgage, which RFC did. the loan.
3. It appeared that the cancellation was requested to make 4. When the RFC turned down Saura’s request asking for a
way for the registration of a mortgage contract over the change in the conditions, negotiations which had been
same property in favour of Prudential Bank and Trust Co. going on for the implementation of the agreement reached
Under which Saura had up to 31 Dec 1954 to pay its an impasse. Saura was in no position to comply with RFC’s
obligation on a trust receipt. Saura failed to pay Prudential, conditions. So instead of doing so and insisting that the
prompting the latter to sue Saura. loan be released as agreed upon, Saura asked that the
4. Almost 9 years after the mortgage in favour of RFC was mortgage be cancelled, which the RFC did on 15 June 1955.
cancelled at Saura’s request, Saura commenced the present 5. The action thus taken by both parties was in the nature
suit for damages, alleging RFC’s failure to comply with its of mutual desistance (“mutuo disenso”), which is a mode of
obligation to release the proceeds of the loan applied for extinguishing obligations. It is a concept that derives from
and approved, thereby preventing the plaintiff from the principle that since mutual agreement can create a
completing or paying contractual commitments it had contract, mutual disagreement by the parties can cause its
entered into in connection with its jute mill project. extinguishment.
5. DBP argued, among others, that there was no perfected 6. Saura’s subsequent conduct confirms this desistance. It
contract, and that assuming that there was, the plaintiff did not protest against any alleged breach of contract by
itself did not comply with the terms thereof. RFC or even point out that the latter’s stand was legally
unjustified. Its request for cancellation of the mortgage
ISSUE: WoN there was a perfected contract – YES carried no reservation of whatever rights it believed it
might have against RFC for the latter’s non-compliance,
WoN the contract was validly terminated - YES and it even later applied with DBP for another loan, which
RULING: Judgment appealed from reversed. Complaint was disapproved. It was only 8 years after the loan
dismissed. agreement had been cancelled that Saura brought this
action for damages.

Anda mungkin juga menyukai