Anda di halaman 1dari 4

ANALISIS DE PRECIOS UNITARIOS

PARTIDA: Excavación de Zanjas PRECIO: S/. 25.70


RENDIMIENTO: 10 M2/DIA

RECURSO UND CUADRILLA CANTIDAD P. UNIT PARCIAL


MANO DE OBRA
AYUDANTE HH 2.00 1.6000 S/. 15.30 S/. 24.48

EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES % - 0.05 S/. 24.48 S/. 1.22

PARTIDA: CONCRETO F'c = 210 Kg/cm2 PRECIO: S/. 301.49


RENDIMIENTO: 15 m2/dia
RECURSO UND CUADRILLA CANTIDAD P. UNIT PARCIAL
MANO DE OBRA
operario HH 3 1.6000 S/. 15.63 S/. 25.01
oficial HH 1 0.5333 S/. 13.54 S/. 7.22
ayudante HH 6 3.2000 S/. 10.42 S/. 33.34
S/. 65.57
MATERIALES
cemento BLS - 9.4 S/. 19.00 S/. 178.60
arena gruesa M3 - 0.45 S/. 45.00 S/. 20.25
piedra ch. M3 - 0.48 S/. 70.00 S/. 33.60
agua M3 - 0.3 S/. 5.00 S/. 1.50
S/. 233.95

EQUIPOS Y HERRAMIENTAS
herramientas manuales % - 0.03 S/. 65.57 S/. 1.97
S/. 1.97

PARTIDA: Acero corrugado f'y = 4200 Kg/cm2 PRECIO: S/. 4.42


RENDIMIENTO: 240 kg/dia
RECURSO UND CUADRILLA CANTIDAD P. UNIT PARCIAL
MANO DE OBRA
operario HH 1 0.0333 S/. 15.63 S/. 0.52
ayudante HH 0.5 0.0167 S/. 10.42 S/. 0.17
S/. 0.69
MATERIALES
acero corrugado kg - 1.05 S/. 2.70 S/. 2.84
alambre N° 16 kg - 0.3 S/. 2.90 S/. 0.87
S/. 3.71
EQUIPOS Y HERRAMIENTAS
herramientas manuales % - 0.03 S/. 0.69 S/. 0.02
S/. 0.02

PARTIDA: Encofrado y desencofrado PRECIO: S/. 42.90


RENDIMIENTO: 20 m2/dia
RECURSO UND CUADRILLA CANTIDAD P. UNIT PARCIAL
MANO DE OBRA
operario HH 2 0.8000 S/. 15.63 S/. 12.50
ayudante HH 1 0.4000 S/. 10.42 S/. 4.17
S/. 16.67
MATERIALES
madera tornillo p2 - 5 S/. 5.00 S/. 25.00
alambre n° 8 KG - 0.25 S/. 2.90 S/. 0.73
S/. 25.73

EQUIPOS Y HERRAMIENTAS
herramientas manuales % - 0.03 S/. 16.67 S/. 0.50
S/. 0.50

PARTIDA: Tarrajeo de muros PRECIO: S/. 13.36


RENDIMIENTO: 20 m2/dia
RECURSO UND CUADRILLA CANTIDAD P. UNIT PARCIAL
MANO DE OBRA
operario HH 1 0.4000 S/. 15.63 S/. 6.25
ayudante HH 0.5 0.2000 S/. 10.42 S/. 2.08
S/. 8.34
MATERIALES
cemento p2 - 0.18 S/. 19.00 S/. 3.42
arena fina KG - 0.03 S/. 45.00 S/. 1.35
S/. 4.77

EQUIPOS Y HERRAMIENTAS
herramientas manuales % - 0.03 S/. 8.34 S/. 0.25
S/. 0.25

PARTIDA: Asentado de ladrillos kk 18h PRECIO: S/. 39.52


RENDIMIENTO: 15 m2/dia
RECURSO UND CUADRILLA CANTIDAD P. UNIT PARCIAL
MANO DE OBRA
operario HH 1 0.5333 S/. 15.63 S/. 8.34
ayudante HH 0.5 0.2667 S/. 10.42 S/. 2.78
S/. 11.11
MATERIALES
cemento BLS - 0.23 S/. 19.00 S/. 4.37
ladrillo kk 18h M3 - 38 S/. 0.60 S/. 22.80
arena gruesa M3 - 0.02 S/. 45.00 S/. 0.90
S/. 28.07

EQUIPOS Y HERRAMIENTAS
herramientas manuales % - 0.03 S/. 11.11 S/. 0.33
S/. 0.33
PRESUPUESTO
OBRA
RESPONSABLE:

ITEM DESCRIPCION UND METRADO P. UNIT TOTAL


1 Excavación para cimentación m3 30.744 25.704 S/. 790.24
2 Eliminación de material excedente m3 39.97 25.704 S/. 1,027.32
3 Concreto para cimentación m3 20.496 S/. 301.49 S/. 6,179.35
4 Concreto para sobrecimiento m3 13.794 S/. 301.49 S/. 4,158.76
5 Concreto en columnas f'c= 210 kg/cm2 m3 2.25 S/. 301.49 S/. 678.35
6 Encofrado de Columnas m2 36 S/. 42.90 S/. 1,544.30
7 Acero en columnas f'c= 420 kg/cm2 kg 291.5808 S/. 4.42 S/. 1,288.93
8 Asentado de ladrillo kk 18 huecos de soga m2 153 S/. 39.52 S/. 6,046.27
9 Tarrajeo e=2cm m2 153 S/. 13.36 S/. 2,043.48
TOTAL CD S/. 23,757.01
GG 7.5% S/. 1,781.78
TOTAL CI
UTI 6% S/. 1,425.42
SUB TOTAL S/. 26,964.20
IGV 18% S/. 4,853.56
TOTAL S/. 31,817.76