a) Direct Wages
1.0 Welder 4.00 Lot 1.00 500.00 2,000.00
2.0 laborer 4.00 Lot 2.00 350.00 2,800.00
Sub-total Labor Cost 4,800.00
Estimated Activity Duration Total Direct Cost 27,886.20
4.00 working days Indirect Costs:
4.00 calendar days Supervision 5,771.55
Average Output Overhead 5,577.24
4.00 unit per working day Contingencies / Miscellaneous 7,847.00
4.00 unit per calendar day VAT / Taxes Fees 7,556.69 26,752.48
Sequence of Operations
Total Estimated Item Cost 54,638.68
Unit Cost = 54,638.68
say 54,639.00 unit
54,639.00
Prepared By:
Alfie Sailog
Admin Engineer
a) Direct Wages
1.0 Welder 20.00 Lot 2.00 500.00
2.0 laborer 20.00 Lot 4.00 350.00
EstimatedSub-total Labor Cost
20.00 working days Total Direct Cost
20.00 calendar days Indirect Costs:
Supervision 39,025.87
Average Output Overhead 40,820.70
20.00 unit per working day Contingencies / Miscellaneous 56,790.01
20.00 unit per calendar day VAT / Taxes Fees 14,455.95
Sequence of Operations
Total Estimated Item Cost
Unit Cost = 355,196.01
say 355,197.00
Prepared By:
Alfie Sailog
Admin Engineer
1.00 Unit
ank
8,250.00 66,000.00
3,930.82 55,031.48
112.00 1,792.00
112.00 896.00
235.00 940.00
112.00 1,792.00
125.00 1,000.00
98.00 392.00
30.00 300.00
980.00 3,920.00
450.00 6,750.00
295.00 14,750.00
358.00 1,790.00
750.00 750.00
PHP 156,103.48
Unit Cost Amount
0.00
Unit Cost Amount
500.00 20,000.00
350.00 28,000.00
48,000.00
204,103.48
39,025.87
40,820.70
56,790.01
14,455.95 151,092.53
355,196.01
355,196.01
355,197.00 unit
355,197.00
Patrick C. Favoreal
EHI/CEO
Project : Re-Construction Below Adult Swimming pool
Location : Azalea Hotels and Residences Boracay
UNIT COST DERIVATION
Item No. : I Est. Qty. : 1.00 Unit
Item Description : Re-Construction Below Adult Swimming pool
a) Direct Wages
1.0 Mason 60.00 Lot 4.00 500.00 120,000.00
4.0 Labor 60.00 Lot 8.00 350.00 168,000.00
Sub-total Labor Cost 288,000.00
Estimated Activity Duration Total Direct Cost 593,663.19
60.00 working days Indirect Costs: 288,152.83
60.00 calendar days Supervision 15,283.16
Average Output Overhead 17,809.90
60.00 unit per working day Contingencies / Miscellaneous 18,802.69
60.00 unit per calendar day VAT / Taxes Fees 123,030.55 463,079.13
Sequence of Operations Total Estimated Item Cost 1,056,742.31
Unit Cost = 1,056,742.31
say 1,056,742.31 unit
1,056,742.31
Prepared By:
Alfie Sailog
Admin Engineer
3.1 Fiber cement board / hardiflex( 1/4'' x 4ft. X 8 ft.) pcs. 44.00 1,350.00 59,400.00
3.2 G.I Plain sheet ( guage # 16 x 4ft x 8 ft.) pcs. 84.00 1,288.00 108,192.00
3.3 tex screw 3/8'' x 2'' pcs 5.00 0.00
3.4 Boysen permacoat semi gloss ( DEW340- WHISPER) pail 3.00 3,136.00 9,408.00
3.5 Boysen acrytex primer- white pail 2.00 2,800.00 5,600.00
3.6 Skim coat- Mondo Brand bags 3.00 950.00 2,850.00
3.7 Black screw 1/8'' x 1 1/4'' pcs. 2,000.00 5.00 10,000.00
3.8 Metal drill bit # 1/8'' pcs. 10.00 98.00 980.00
3.9 Paint Brush 3'' pcs 10.00 85.00 850.00
3.10 Paint Roller 8'' pcs 10.00 125.00 1,250.00
3.11 Roller Pan pcs 4.00 95.00 380.00
3.12 Sand paper # 200 meters 20.00 95.00 1,900.00
Sub-total Materials Cost PHP 949,234.96
EQUIPMENT
Prepared By:
Alfie Sailog
Admin Engineer
2.8 Cutting Disc 1/16 " by 4" pcs 100.00 225.00 22,500.00
2.9 Sanding Disc 1 x 100mm x 16mm pcs 100.00 676.00 67,600.00
2.10 Automotive Primer Surfacer gal 50.00 427.25 21,362.50
2.11 Laquere Thinner gal 50.00 725.00 36,250.00
2.12 Drill Bit 3/8" by 5" (Masonry) pcs 50.00 123.00 6,150.00
2.13 Drill Bit 3/8" by 5" (Metal) pcs 50.00 149.00 7,450.00
2.14 Paint Brass 2" pcs 20.00 55.00 1,100.00
2.15 Paint Brass 3" pcs 20.00 69.00 1,380.00
2.16 Text Screw 3/8" by 1" pcs 1,500.00 2.75 4,125.00
2.17 Nylon Rope 1" dia. (150 mts/roll) roll 3.00 14,890.00 44,670.00
2.18 Automotive Paint Gray (Top Coat) gal 36.00 1,056.00 38,016.00
2.19 Concrete hollow blocks 4'' pcs 330.00 19.00 6,270.00
2.20 wash sand cu.m 2.50 1,375.00 3,437.50
2.21 fine sand cu.m 2.00 1,195.00 2,390.00
2.22 steel bars 10mm x 6 meters pcs 60.00 125.00 7,500.00
2.23 steel bar 12mm x 6meters pcs 35.00 119.00 4,165.00
2.24 portland cement bags 75.00 280.00 21,000.00
2.25 G.I wire # 16 kls 5.00 120.00 600.00
Sub-total Materials Cost PHP 1,680,812.75
Item No. Description/Cap/Model Output Unit Quantity Unit Cost Amount
EQUIPMENT
50,000.00
Item No. Designation Output Unit Quantity Unit Cost Amount
a) Direct Wages
1.0 Welder 20.00 Lot 2.00 500.00 20,000.00
DIRECT LABOR
Prepared By:
Alfie Sailog
Admin Engineer
Sub-total Materials Cost PHP 984,441.37 PHP 432,505.48 PHP 2,695,599.74 PHP 2,696,149.99
Item No. Description/Cap/Model Output Unit Quantity Unit Cost Amount Output Unit Quantity Unit Cost Amount Output Unit Quantity Unit Cost Amount Output Unit Quantity Unit Cost Amount
EQUIPMENT
1.0 Welding Machine 15.00 pcs 2.00 2,000.00 60,000.00 15.00 pcs 2.00 2,000.00 60,000.00 15.00 pcs 2.00 2,000.00 60,000.00 15.00 pcs 2.00 1,500.00 45,000.00
2.0 Chain block 1.5tons 10.00 pcs 2.00 2,000.00 40,000.00 10.00 pcs 2.00 2,000.00 40,000.00 10.00 pcs 2.00 2,000.00 40,000.00 10.00 pcs 2.00 1,500.00 30,000.00
3.0 Electric Grinder 15.00 pcs 2.00 1,000.00 30,000.00 15.00 pcs 2.00 1,000.00 30,000.00 15.00 pcs 2.00 1,000.00 30,000.00 15.00 pcs 2.00 1,000.00 30,000.00
130,000.00 130,000.00 130,000.00 105,000.00
Item No. Designation Output Unit Quantity Unit Cost Amount Output Unit Quantity Unit Cost Amount Output Unit Quantity Unit Cost Amount Output Unit Quantity Unit Cost Amount
a) Direct Wages
1.0 Welder 20.00 Lot 4.00 500.00 40,000.00 20.00 Lot 4.00 500.00 40,000.00 20.00 Lot 4.00 500.00 40,000.00 20.00 Lot 4.00 500.00 40,000.00
DIRECT LABOR
2.0 Carpenter 20.00 Lot 5.00 500.00 50,000.00 20.00 Lot 5.00 500.00 50,000.00 20.00 Lot 5.00 500.00 50,000.00 15.00 Lot 5.00 500.00 37,500.00
Mason 15.00 Lot 5.00 500.00 37,500.00
3.0 Painter 15.00 Lot 5.00 450.00 33,750.00 15.00 Lot 5.00 450.00 33,750.00 15.00 Lot 5.00 450.00 33,750.00 15.00 Lot 5.00 450.00 33,750.00
4.0 Laborer 20.00 Lot 10.00 400.00 80,000.00 20.00 Lot 10.00 400.00 80,000.00 20.00 Lot 10.00 400.00 80,000.00 20.00 Lot 10.00 400.00 80,000.00
Sub-total Labor Cost 203,750.00 203,750.00 203,750.00 228,750.00
Estimated Activity Duration Total Direct Cost 1,318,191.37 Total Direct Cost 766,255.48 Total Direct Cost 3,029,349.74 Total Direct Cost 3,029,899.99
20.0 working days Indirect Costs: 206,703.32 Indirect Costs: 204,615.01 Indirect Costs: 135,964.32 Indirect Costs: 234,142.30
20.0 calendar days Supervision 147,666.21 Supervision 43,250.55 Supervision 269,559.97 Supervision 269,615.00
Overhead 131,819.14 Overhead 38,312.77 Overhead 151,467.49 Overhead 151,495.00
Average Output Contingencies / Miscellaneous 159,767.67 Contingencies / Miscellaneous 42,390.94 Contingencies / Miscellaneous 172,518.86 Contingencies / Miscellaneous 172,550.50
20.0 unit per working day VAT / Taxes Fees 171,793.56 817,749.90 VAT / Taxes Fees 153,791.65 482,360.92 VAT / Taxes Fees 17,221.68 746,732.32 VAT / Taxes Fees 603,325.56 1,431,128.36
20.0 unit per calendar day
Total Estimated Item Cost 2,135,941.27 Total Estimated Item Cost 1,248,616.40 Total Estimated Item Cost 3,776,082.07 Total Estimated Item Cost 4,461,028.34
Sequence of Operations
Unit Cost = 2,135,941.27 Unit Cost = 1,248,616.40 Unit Cost = 3,776,082.07 Unit Cost = 4,461,028.34
say 2,135,942.00 unit say 1,248,617.00 unit say 3,776,083.00 unit say 4,461,029.00 unit
Adj Item Cost 2,135,942.00 1,248,617.00 3,776,083.00 4,461,029.00
Project : BOQ of Proposed 3 Storey Building
Location : Azalea Hotels and Residences Boracay
UNIT COST DERIVATION
Item No. : I Est. Qty. : 1.00 Unit
Item Description : BOQ of Proposed 3 Storey Building
Item No. Item Description Unit Quantity Unit Cost Amount
1.0 General Requirements
Mobilization/ Demobilization lot 1.00 277,499.50 277,499.50
2.0 Civil Works
2.1 Excavation of Footing, Backfillings, Compaction CU.M 48.38 2,000.00 96,760.00
2.2 Supply and Installation of Rebars
2.2.1 Footings KGS 409.54 28.00 11,467.12
2.2.2 Beams KGS 8,111.32 28.00 227,116.96
2.2.3 Columns KGS 5,301.46 28.00 148,440.88
2.2.4 Stairs KGS 923.82 28.00 25,866.96
2.2.5 Floor slabs KGS 3,579.04 28.00 100,213.12
2.3 Supply and Installation of 2,800 psi concrete
2.3.1 Footings CU.M 9.50 3,999.30 38,009.35
2.3.2 Beams CU.M 515.01 3,999.30 2,059,679.49
2.3.3 Columns CU.M 265.32 3,999.30 1,061,094.28
MATERIALS
3.2 Supply & Installation of granite tiles including necessary SQM 356.00 3,576.98 1,273,404.88
accessories
3.3 Painting works SQM 1,634.95 310.98 508,436.75
3.6 Electrical works roughing in LOT 1.00 315,750.00 315,750.00
3.7 Plumbing works Roughing in LOT 1.00 298,950.00 298,950.00
Sub-total Materials Cost PHP 8,076,120.76
Item No. Description/Cap/Model Output Unit Quantity Unit Cost Amount
1.0 Bar Cutter 25.00 unit 1.00 1,500.00 37,500.00
EQUIPMENT
Alfie Sailog
Admin Engineer
Item No. No. Designation Output Unit Quantity Unit Cost Amount
a) Direct Wages
1.0 Construction Engineer 180.00 Lot 1.00 800.00 144,000.00
2.0 Foreman 180.00 Lot 1.00 550.00 99,000.00
DIRECT LABOR
Prepared By:
Alfie Sailog
Admin Engineer
Alfie Sailog
Admin Engineer
Amount
49,024.65
4,788.00
2,385.00
29,610.00
7,925.00
87,400.00
7,170.00
14,550.00
675.00
1,387.50
1,800.00
3,170.00
1,995.00
180.00
220.00
130.00
30.00
892.50
780.00
1,400.00
90.00
50,000.00
PHP 265,602.65
Amount
Amount
15,000.00
9,000.00
24,000.00
289,602.65
74,794.23
364,396.88
unit
364,397.00
Project : Demolition and Re-tapping of concrete floor slab at Roof deck adult pool
Location : Azalea Hotels and Residences Boracay
UNIT COST DERIVATION
Item No. : I Est. Qty. : 1.00
Item Description : Demolition and Re-tapping of concrete floor slab at Roof deck adult pool
Item No. Item Description Unit Quantity Unit Cost
1.0 General Requirements
Mobilization/ Demobilization LOT 1.00 40,384.68
2.0 Civil Works
2.1 Demolition of dilapidated wood planks SQM. 96.75 75.00
3.0 Materials
3.1 Fine sand CU.M 10.44 2,040.00
MATERIALS
Prepared By:
Alfie Sailog
Admin Engineer
Unit
b at Roof deck adult pool
Amount
40,384.68
7,256.25
21,297.60
26,320.00
81,000.00
900.00
260.00
114.00
200.00
180.00
124.00
420.00
3,800.00
PHP 182,256.53
Amount
Amount
36,000.00
51,200.00
87,200.00
269,456.53
134,320.74
403,777.27
unit
402,894.00
Patrick C. Favoreal
EHI/CEO
Project : Construction of Proposed Lobby Annex
Location : Azalea Hotels and Residences Boracay
UNIT COST DERIVATION
1.0
2.0
Prepared By:
Alfie Sailog
Admin Engineer
Unit
bby Annex
Amount
35,000.00
45,000.00
25,000.00
75,000.00
83,187.00
2,096.50
5,600.00
36,000.00
21,780.00
250,000.00
85,000.00
105,006.85
PHP 768,670.35
Amount
0.00
Amount
30,000.00
22,750.00
7,000.00
8,400.00
38,400.00
106,550.00
875,220.35
280,932.79
1,156,153.14
unit
1,156,154.00
Patrick C. Favoreal
EHI/CEO
Project : Modification of Foyer tiles at Main lobby
Location : Azalea Hotels and Residences Boracay
UNIT COST DERIVATION
Item No. : I Est. Qty. : 1.00
Item Description : Modification of Foyer tiles at Main lobby
Item No. Item Description Unit Quantity Unit Cost
1.0 General Requirements
Mobilization/ Demobilization LOT 1.00 13,376.28
2.0 Civil Works
MATERIALS
a) Direct Wages
1.0 Mason 12.00 Lot 4.00 450.00
2.0 Laborer 12.00 Lot 8.00 320.00
Sub-total Labor Cost
Estimated Activity Duration Total Direct Cost
12.0 working days Indirect Costs: 52,452.24
12.0 calendar days Supervision 6,612.24
Overhead 7,672.12
Average Output Contingencies / Miscellaneous 8,386.34
12.0 unit per working day VAT / Taxes Fees
12.0 unit per calendar day
Total Estimated Item Cost
Sequence of Operations
Unit Cost = 228,565.32
say 228,566.00
Adj Item Cost
Prepared By:
Alfie Sailog
Admin Engineer
13,376.28
4,040.25
4,118.25
21,297.60
21,000.00
2,100.00
190.00
PHP 66,122.38
Amount
21,000.00
14,000.00
35,000.00
Amount
21,600.00
30,720.00
52,320.00
153,442.38
75,122.94
228,565.32
unit
228,566.00
Patrick C. Favoreal
EHI/CEO
Azalea Hotels and Residences Boracay
Zone 7 Road C Manggayad, Brgy. Balabag, Boracay Island, Malay, Aklan, Philippines
Malay, Aklan, Philppines 5608
Cost Comparison
Option 1: Option 2:
Item Item Description G.I plain Sheet Fiber glass 4.0 mm thick
No.
MATERIALS
Unit QTY Unit Cost Amount Unit QTY Unit Cost Amount
1 1HP Window type ACU Units 138.00 1,872.00 258,336.00 Units 138.00 3,475.00 479,550.00
2 2HP Window type ACU Units 220.00 2,528.00 556,160.00 Units 220.00 5,278.00 1,161,160.00
Permits & Utilities Requirements LOT 1.00 248,596.84 248,596.84 LOT 1.00 276,699.
3.0 Materials
3.1 Fine sand CU.M 9.11 1,998.00 18,201.78 CU.M 9.11 1,998.
3.2 Wash sand cu.m 13.66 2,040.00 27,866.40 CU.M 13.66 2,040.
3.3 Cement bags 205.00 280.00 57,400.00 bags 205.00 280.
3.4 Metal Cutting dics pcs 85.00 350.00 29,750.00 pcs 6.00 350.
3.5 Concrete nails 3'' kls 15.00 95.00 1,425.00 kls 2.00 95.
3.6 25 mm nylon string (75meters/ roll roll 2.00 125 250.00 roll 2.00 125.
3.7 1 1/2'' x 1/8'' x 20 ft angle bar pcs 150.00 4
3.8 2.5 inch diameter G.I Pipe pcs 143.00 1790 255,970.00
3.9 6013 Welding Rod kls 25.00 290 7,250.00 kls 25.00 2
3.10 Cyclone wire 6ft sets 175.00 312 54,600.00
3.11 6ft. X 32'' corrugated sheet pcs 851.00 3
3.12 Text screw 3'' x 3/16 pcs 10,212.00 3.
3.15 Automotive primer surfacer gals 70.00 1350 94,500.00 gals 70.00 13
3.16 Automotive lacquer thinner gals 70.00 970 67,900.00 gals 70.00 9
3.17 Sanding paper # 200 pcs 150.00 45 6,750.00 pcs 150.00
Sub-total Materials Cost PHP 1,077,252.97
Item No. Description/Cap/Model Output Unit QTY Unit Cost Amount Output Unit QTY Unit Cost
EQUIPMENT
1.0 Jack Hammer 35.00 pcs 2.00 1,500.00 105,000.00 35.00 unit 2.00 1,500.00
2.0 Electric Grinder 35.00 pcs 2.00 1,000.00 70,000.00 35.00 unit 2.00 1,000.00
175,000.00
Item No. Designation Output Unit QTY Unit Cost Amount Output Unit QTY Unit Cost
a) Direct Wages
DIRECT LABOR
1.0 Mason 40.00 Lot 8.00 450.00 144,000.00 40.00 Lot 8.00 450.00
2.0 welder 35.00 LOT 4.00 450.00 63,000.00 35.00 LOT 4.00 450.00
3.0 Laborer 40.00 Lot 12.00 350.00 168,000.00 40.00 Lot 12.00 350.00
DIRECT LA
Sub-total Labor Cost 375,000.00
Estimated Activity Duration Total Direct Cost 1,627,252.97 Total Direct Cost
12.0 working days Indirect Costs: 377,154.51 Indirect Costs: 377,398.06
12.0 calendar days Supervision 107,725.30 Supervision 119,903.05
Overhead 81,362.65 Overhead 87,451.53
Average Output Contingencies / Miscellaneous 90,817.05 Contingencies / Miscellaneous 97,819.26
12.0 unit per working day VAT / Taxes Fees 274,117.56 931,177.06 VAT / Taxes Fees 291,792.36
12.0 unit per calendar day
Total Estimated Item Cost 2,558,430.03 Total Estimated Item Cost
Sequence of Operations
Unit Cost = 2,558,430.03 Unit Cost = 2,723,394.79
say 2,558,431.00 unit say 2,723,395.00
Adj Item Cost 2,558,431.00
Option 2:
ed fence installation
Unit Cost Amount
45,657.00 45,657.00
175,000.00 175,000.00
276,699.35 276,699.35
1,998.00 18,201.78
2,040.00 27,866.40
280.00 57,400.00
350.00 2,100.00
95.00 190.00
125.00 250.00
435 65,250.00
0.00
290 7,250.00
0.00
380 323,380.00
3.00 30,636.00
1350 94,500.00
970 67,900.00
45 6,750.00
PHP 1,199,030.53
Unit Cost Amount
1,500.00 105,000.00
1,000.00 70,000.00
175,000.00
Unit Cost Amount
450.00 144,000.00
450.00 63,000.00
350.00 168,000.00
375,000.00
1,749,030.53
377,398.06
119,903.05
87,451.53
97,819.26
291,792.36 974,364.26
Cost 2,723,394.79
2,723,394.79
2,723,395.00 unit
2,723,395.00
Azalea Hotel and Residence Boracay
Zone 7 Road C Manggayad, Brgy. Balabag, Boracay Island, Malay, Aklan, Philippines
Malay, Aklan, Philppines 5608
Cost Comparison
Option 1: Option 2:
Item
No. Item Description Replace Floor Tile with Artificial turf Replace floor tile Installati
Unit QTY Unit Cost Amount Unit QTY Unit Cost Amount Unit
Cement
3.6 Diamond Cutting dics pcs 6.00 350.00 2,100.00 pcs 6.00 350.00 2,100.00
3.7 Concrete nails 3'' kls 2.00 95.00 190.00 kls 5.00 175.00 875.00
3.8 25 mm nylon string (75meters/ roll roll 5.00 125.00 625.00
3.9 2'' x 6'' x 1.7 Tubular bar LM
3.10 2'' x 4'' x 1.5 C- Purlins pcs
3.11 6013 Welding Rod kls
3.12 Expansion bolt 1/2'' x 4'' pcs
3.13 Cutting dics (for metal) pcs
3.14 Automotive lacquer paint (white) Gals.
3.15 Automotive lacquer paint (black) Gals.
3.16 Automotive primer surfacer pcs
3.17 Automotive lacquer thinner pcs
3.18 Sanding paper # 200 pcs
3.19 Polycarbonate 4'' x 8' x 1/4''
3.20 Tempered glass 4ft x 8ft x 12mm pcs
3.21 Clear silicon sealant
3.22 Gunther silicon sealant bottles
Sub-total Materials Cost PHP 275,661.58 PHP 80,972.25
Item No. Description Output Unit QTY Unit Cost Amount Output Unit QTY Unit Cost Amount Output
EQUIPMENT
EQUIPMENT
Total Estimated Item Cost 1,269,000.36 Total Estimated Item Cost 646,111.49
a) Direct Wages
1.0 Mason 12.00 Lot 4.00 450.00 21,600.00
2.0 Laborer 12.00 Lot 8.00 320.00 30,720.00
Sub-total Labor Cost 52,320.00
Estimated Activity Duration Total Direct Cost 362,981.58
12.0 working days Indirect Costs: 52,871.32
12.0 calendar days Supervision 27,566.16
Overhead 18,149.08
Average Output Contingencies / Miscellaneous 20,434.84
12.0 unit per working day VAT / Taxes Fees 119,021.40
12.0 unit per calendar day
Total Estimated Item Cost 482,002.98
Sequence of Operations
Unit Cost = 482,002.98
say 482,003.00 unit
Adj Item Cost 482,003.00
Azalea Hotel and Residence Boracay
Zone 7 Road C Manggayad, Brgy. Balabag, Boracay Island, Malay, Aklan, Philippines
Malay, Aklan, Philppines 5608
Option 2:
Item Item Description Replace floor tile
No.
Unit QTY Unit Cost Amount
1.0 General Requirements
Mobilization/ Demobilization / Hauling of Debris LOT 1.00 45,657.00 45,657.00
2.0 Civil Works
2.1 Demolition of existing floor tile SQM. 53.87 75.00 4,040.25
MATERIALS
a) Direct Wages
1.0 Mason 12.00 6.00 Lot 5.00 550.00 16,500.00
2.0 Laborer 12.00 6.00 Lot 10.00 450.00 27,000.00
Sub-total Labor Cost 43,500.00
Estimated Activity Duration Total Direct Cost Total Direct Cost 263,387.25
12.0 working days Indirect Costs: Indirect Costs: 43,903.77
12.0 calendar days Supervision Supervision 20,188.73
Overhead Overhead 13,169.36
Average Output Contingencies / Miscellaneous
Contingencies / Miscellan 14,837.27
12.0 unit per working day VAT / Taxes Fees VAT / Taxes Fees 92,099.13
12.0 unit per calendar day
Total Estimated Item Cost Total Estimated Item Cost 355,486.38
Sequence of Operations
Unit Cost = Unit Cost = 355,486.38
say say 355,487.00 unit
Adj Item Cost 355,487.00
Project : Ground floor Veranda Clothes Line
Location : Azalea Hotels and Residences Boracay
Prepared By:
Alfie Sailog
Admin Engineer
PHP 167,862.20
Unit Cost Amount
1,500.00 7,500.00
1,500.00 7,500.00
2,500.00 25,000.00
40,000.00
550.00 16,500.00
350.00 10,500.00
27,000.00
234,862.20
16,786.22
11,743.11
13,169.58
41,698.91
276,561.11
276,562.00 unit
st 276,562.00
Patrick C. Favoreal
EHI/CEO